F I L E D
United States Court of Appeals
Tenth Circuit
UNITED STATES CO URT O F APPEALS
July 12, 2007
TENTH CIRCUIT Elisabeth A. Shumaker
Clerk of Court
RAY HULL; KAREN K. HULL,
Plaintiffs-Appellants,
v. No. 06-5136
(D.C. No. 04-CV-721-HDC-PJC)
BARAN TELECOM , IN C, (N .D. Okla.)
Defendant-Appellee.
OR D ER AND JUDGM ENT *
Before M cCO NNELL, M cKA Y, and TYM KOVICH, Circuit Judges.
This negligence action was filed against Baran Telecom, Inc., the general
contractor on a cellular telephone tower construction project, after Plaintiff, the
foreman for the subcontractor tower erection crew, fell 240 feet when a cable
used to hoist tow er sections snapped. The district court aw arded summary
judgment in favor of Baran Telecom, and this appeal followed.
*
This order and judgment is not binding precedent, except under the
doctrines of law of the case, res judicata, and collateral estoppel. It may be cited,
however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th
Cir. R. 32.1.
B ACKGROUND 1
Plaintiff Ray Hull, an experienced tower construction specialist, accepted a
position with Innovative W ireless Construction (“IW C”) in an effort to resurrect
its failing cellular telephone tower construction business. M r. Hull’s first job
with IW C was the time-sensitive construction of a three-leg, 350-foot, self-
supporting cellular telephone tower in Fremont, Nebraska for Baran Telecom after
Baran’s original subcontractor defaulted.
According to the undisputed material facts, IW C accepted the job on the
express condition that Baran Telecom w ould provide a hydraulic crane and crane
operators to assist IW C with the hoisting of pre-assembled tower sections into
position. M r. Hull and his crew immediately began assembly of the tower
sections and, using the crane supplied by Baran Telecom, erected the tower to a
height of 240 feet before the crane operator refused to continue working due to
windy conditions. The next morning the crane operator disassembled his crane
and left the work site over Baran Telecom’s on-site representative’s objections
because the crane was scheduled for another job.
IW C and Baran agree that, because Baran Telecom could not secure another
crane, the job could only be completed on time with the use of a gin pole and
1
W e recount only those facts relevant to the issues before us, construing
them in the light most favorable M r. Hull, the non-movant.
-2-
hoist. 2 Although IW C offered the use of its gin pole and hoist at additional cost,
M r. Hull was unable to retrieve it from its off-site location. Baran Telecom,
concerned over meeting the project deadline, secured the use of one of its gin
poles and hoists, which M r. Hull retrieved and brought to the construction site.
M r. Hull and his crew inspected the gin pole and hoist system, erected it,
and tested its operation. M r. Hull then ascended the tower and secured his safety
rigging to the gin pole in preparation for the first hoist. Shortly after they began
the first hoist, however, the cable snapped under only seventeen percent of its
maximum load-bearing capability. This failure caused the gin pole, and M r. Hull
along with it, to fall some 240 feet to the ground. M r. Hull’s safety cable
attempted to arrest his fall after 200 feet, but snapped under the pressure, causing
him to free fall the last 40 feet.
M r. Hull and his wife sued Baran Telecom for negligence under Nebraska
law 3 , alleging Baran Telecom ow ed him a duty of care as the general contractor
and site supervisor as well as the supplier of chattel. Baran Telecom moved for
summary judgment, which the district court granted in part and denied in part.
2
A gin pole and hoist consists of a mast, pulley and tackle assembly, and
either hand- or machine-powered hoist. The mast, or gin pole, is attached to the
tower with various clasp assemblies but protrudes above its highest section. New
tower sections are then attached to the cables, or tackle, and hoisted into position
and attached. The gin pole is then slid further up the tow er and the process
repeated.
3
The parties agree that Nebraska law controls.
-3-
The district court granted Baran Telecom summary judgment with respect to the
supplier of chattel claim after concluding that Baran Telecom offered its gin pole
and hoist only as a favor. But genuine issues of material fact concerning the
precise nature of Baran Telecom’s supervision prevented the district court from
awarding Baran Telecom summary judgment on the supervisor claim.
Baran Telecom moved for summary judgment a second time on the
supervisor claim after submitting newly obtained testimony. That testimony came
from Baran Telecom’s on-site representative, an employee of a company to which
Baran Telecom frequently subcontracted non-tower-related construction such as
fencing and ground work. The representative testified that as Baran Telecom’s
liaison he merely observed and reported on IW C’s progress. The district court
found this evidence persuasive enough to aw ard Baran Telecom summary
judgment on that remaining issue. Plaintiffs’ appeal challenges both awards of
summary judgment.
A NALYSIS
A. Standard of Review
W e review summary judgment decisions de novo, taking the evidence in the
light most favorable to the non-moving party, in this case, M r. H ull’s favor. See
Zam ora v. Elite Logistics, Inc., 478 F.3d 1160, 1164 (10th Cir. 2007) (en banc).
Summary judgment is appropriate only “if the pleadings, depositions, answ ers to
-4-
interrogatories, and admissions on file, together with the affidavits, if any, show
that there is no genuine issue as to any material fact and that the moving party is
entitled to a judgment as a matter of law .” Fed. R. Civ. P. 56(c).
B. Duty O w ed by a G eneral Contractor
A general contractor’s duty of care under N ebraska law is set forth in
Parrish v. Omaha Public Power District, 496 N.W .2d 902 (Neb. 1993). That
case, which distinguished between the duties of care owed by premise owners
versus general contractors in control of the premises, stated that general
contractors owe a duty of care to those lawfully on the premises “to keep the
premises in a reasonably safe condition while the contract is in the course of
performance.” Id. at 911 (quotation omitted). Under Parrish,
to impose liability on a general contractor for injury to a
subcontractor’s employee, the general contractor must have (1)
supervised the work that caused the injury to the employee; (2) had
actual or constructive knowledge of the danger w hich ultimately
caused the injury; and (3) had the opportunity to prevent the injury,
but negligently failed to prevent the injury.
Id. at 912. “‘N ormally when a general contractor has a supervisor on the site, it
will be able to exercise control over the premises.’” Id. at 911 (quoting Farris v.
Gen. Growth Dev. Corp., 354 N.W .2d 251, 254 (Iow a Ct. App. 1984)). However,
“[i]t is not enough that [the general contractor] has merely a general right to order
the work stopped or resumed, to inspect its progress or to receive reports, to make
suggestions or recommendations w hich need not necessarily be followed, or to
-5-
prescribe alterations and deviations.” Restatement (Second) of Torts § 414, cmt.
c.
The district court analyzed Plaintiffs’ factual assertions that Baran
Telecom’s on-site liaison supervised IW C’s work, but rejected those assertions as
insufficient proof that Baran Telecom “controlled the manner and details of H ull’s
work.” (A plts.’ A pp., v. 2, at 604 (O rder at 8 [hereinafter O rder II]).)
Plaintiff argues that the district court applied the wrong law when it cited
Didier v. Ash Grove Cement Co., No. A-03-924, 2005 Neb. App. Lexis 226, at
*19-20 (N eb. Ct. App. Sept. 20, 2005), rev’d on other grounds, 718 N.W .2d 484
(Neb. 2006), in its general statement of negligence law for the proposition that
“[a] passive observer-representative of the defendant does not constitute
supervision.” (Aplts.’ App., v. 2, at 602 (Order II at 6).) Specifically, Plaintiff
contends that because Didier dealt with the duties of site owners as opposed to
general contractors, it assessed Plaintiff’s claim under the wrong standard. W e
disagree.
The district court expressly stated in its first summary judgment decision
that while Parrish explained the distinction between site owners and general
contractors, only the latter applied to M r. Hull’s claims. In its second summary
judgment decision, the district court repeated Parrish’s command that general
contractors owe a duty of care to subcontractors when exercising supervisory
control. It only cited Didier to provide an example of actions incapable of
-6-
amounting to “supervision.” W e do not believe that the district court’s reliance
on Didier in order to illustrate the nature of “supervision” is incorrect.
Additionally, Plaintiffs have presented no facts indicating that Baran
Telecom’s on-site representative did anything more than occasionally
comm unicate IW C’s progress to Baran Telecom or that Baran Telecom in any
way attempted to control M r. Hull’s actions short of urging his timely completion
of the construction. Cf. Olson v. Pennzoil Co., 943 F.2d 881, 883 (8th Cir. 1991)
(relying on North Dakota Supreme Court decision addressing amount of retained
or exercised control necessary to invoke Restatement § 414, which held that “[a]n
employer who does not retain or actually exercise any control over a project of
the employees of an independent contractor, but, instead, is concerned primarily
only with the finished product should not be held liable for the negligence of the
independent contractor or its employees,” M adler v. M cKenzie Cty., 467 N.W .2d
709, 712 (N.D. 1991) (quotation omitted)). Plaintiffs’ assertions that such
supervision is sufficient to impose a duty of care on a general contractor are
contrary to the law .
Thus, the district court’s grant of summary judgment in favor of Baran
Telecom on this issue is A FFIR M ED.
C. Duty O w ed by a Supplier of a Defective Chattel
Under Nebraska law , the supplier of a defective chattel may be held liable
-7-
for negligence in certain circumstances. In Semler v. Sears, Roebuck & Co., 689
N.W .2d 327 (Neb. 2004), the Nebraska Supreme Court adopted the negligence
standard provided by the Restatement (Second) of Torts § 392:
One who supplies to another, directly or through a third person, a
chattel to be used for the supplier’s business purposes is subject to
liability to those for whose use the chattel is supplied, or to those
whom he should expect to be endangered by its probable use, for
physical harm caused by the use of the chattel in the manner for
which and by persons for whose use the chattel is supplied
(a) if the supplier fails to exercise reasonable care to make the
chattel safe for the use for which it is supplied, or
(b) if he fails to exercise reasonable care to discover its dangerous
condition or character, and to inform those whom he should expect
to use it.
Id. at 864-65 (quoting Restatement (Second) of Torts § 392). W hen supplying
tools to another party’s employees,
[o]ne who employs another to erect a structure or to do other work,
and agrees for that purpose to supply the necessary tools and
temporary structures, supplies them to the employees of such other
for a business purpose. . . . On the other hand, if it is understood
that the person w ho is to do the work is to supply his own
instrumentalities, but the person for whom the work is to be done
permits his own tools or appliances to be used as a favor to the
person doing the w ork, the tools and appliances are supplied as a
gratuity and not for use for the supplier’s business purposes.
Id. (quoting Restatement (Second) of Torts § 392, cmt. e).
The district court determined that no duty of care arose when Baran
Telecom supplied the gin pole and hoist because Baran Telecom allowed IW C to
use the gin pole and hoist “as a favor.” (Aplts.’ App., v. 2, at 342 (Order at 9
-8-
[hereinafter Order I]).) The district court rejected Plaintiffs’ contention that
because of the project’s rapidly approaching deadline, Baran Telecom’s lending
of the equipment served its business purposes. Rather, the district court stated:
“Hull does not provide any evidence by pointing to the contract between Baran
and IW C or otherwise that there was any understanding other than that IW C was
responsible for furnishing its own tools.” (Id. at 341 (Order I at 8).)
This conclusion, however, ignores both the inclusion of the “or otherwise”
phrase as w ell as the undisputed facts of the case. According to the district court,
it is an undisputed material fact that “Hull accepted the contract on behalf of
IW C, on the express condition that a large crane would be available.” (Id. at 334
(Order I at 1) (emphasis added).) Indeed, Baran Telecom conceded the existence
of this condition at oral argument. (Oral Arg. at 21:33-37.) Despite this
concession, Baran Telecom attempts to argue that because the construction
contract stated that IW C would provide its own tools, Baran Telecom w as under
no obligation to supply either the crane or the gin pole and hoist. Baran
Telecom’s acknowledgment of IW C’s conditional acceptance, however, prevents
it from arguing to the contrary now.
This undisputed condition establishes that Baran Telecom was obligated to
supply a crane in order to permit IW C to complete the project on time. The
undisputed facts indicate that Baran Telecom, through its on-site representative,
booked the crane for only one day and failed to persuade the crane operator to
-9-
remain on-site. W hen the crane operator dismantled his crane and left due to
prior commitments, Baran Telecom was obligated to supply a suitable
replacement. The duty to supply safe equipment did not leave the job site with
the hydraulic crane. Accordingly, we REV ER SE the district court’s award of
summary judgment in favor of Baran Telecom on this issue, and REM AND to the
district court for further proceedings consistent with this opinion.
Entered for the Court
M onroe G. M cKay
Circuit Judge
-10-