COURT OF APPEALS
SECOND DISTRICT OF TEXAS
FORT WORTH
NO. 2-07-352-CV
GRAND TEXAS HOMES, INC., APPELLANTS
D/B/A GRAND HOMES, GRAND
HOMES 2003, L.P., GRAND
HOMES 2000, L.P. AND
MELANIE BRUTON
V.
SHIRLEY HILL AND JULIUS HILL APPELLEES
------------
FROM THE 17TH DISTRICT COURT OF TARRANT COUNTY
------------
MEMORANDUM OPINION 1
------------
I. Introduction
1
… See T EX. R. A PP. P. 47.4.
In this interlocutory appeal, Appellants Grand Homes and Melanie Bruton
challenge the trial court’s denial of their motion to compel arbitration. We
affirm.
II. Factual and Procedural History
On April 11, 2005, Appellees Shirley and Julius Hill entered into a
contract with Grand Homes 2003, L.P. (“Grand Homes”) for the construction
and purchase of a new home. The Hills paid Grand Homes a $5,000 deposit
upon executing the agreement. Four days later, GLG Mortgage, L.P. (“Grand
Lending”), an affiliate of Grand Homes, approved the Hills for a home loan.
Over the next two months, the Hills paid Grand Homes an additional $118,000,
which they were told would go toward paying down the total purchase price
and toward “construction upgrades.”
More than six months after receiving loan approval, the Hills were notified
by Grand Lending that they no longer qualified for their loan. Subsequently,
Grand Homes notified the Hills that it had elected to terminate their contractual
agreement due to the Hills’ failure to close. Shirley Hill called Grand Homes and
requested a refund of the $5,000 deposit and the additional payments totaling
over $118,000 that Grand Homes had retained. During this telephone call,
Shirley Hill spoke with Mike Mints, Vice President of Grand Homes, and he
refused her demand for the refund. On September 5, 2006, the Hills received
2
a letter from Mints in which he again refused Shirley’s demand for the return
of the money. On April 16, 2007, the Hills received an additional letter from
Robert Garcia, general counsel of Grand Homes, in which Grand Homes again
refused the Hills’ demands. Subsequently, the Hills discovered that Grand
Homes had sold the house to another buyer.
On June 11, 2007, the Hills filed suit against Grand Homes for breach of
contract, negligence, suit on debt, statutory fraud, negligent misrepresentation,
DTPA violations, and injunctive relief. On September 4, the Hills added Melanie
Bruton—a sales employee of Grand Homes whom the Hills dealt with when they
entered the contract—as a defendant.
On September 19, Grand Homes filed a motion to compel arbitration on
behalf of itself and Melanie Bruton, arguing that the parties’ contract requires
arbitration of the dispute. The parties’ contract contains the following
arbitration clause:
[A]ll claims and disputes arising out of or relating to this
Agreement, except only any dispute in which Seller seeks equitable
relief, shall be settled by arbitration in accordance with the rules of
The American Arbitration Association then in effect . . . .
a. If an agreement shall not have been reached within ten (10) days
after notice of a claim or dispute is delivered by either party to the
other party in accordance with the terms of this Agreement, then
either party shall have the right at any time after the expiration of
such 10-day period to refer such claim or dispute to arbitration as
3
herein provided, and both parties shall cooperate in obtaining such
arbitration.
b. Notice of any demand for arbitration shall be filed in writing by
the party seeking arbitration with both the other party to this
Agreement and with The American Arbitration Association. Any
demand for arbitration shall be made within 90 days after the
expiration of the 10-day period specified above . . . .
The trial court denied the motion to compel arbitration, and Grand Homes
and Bruton filed this interlocutory appeal as well as an application for writ of
mandamus. This court consolidated the interlocutory appeal and the original
proceeding on December 6 and denied Grand Homes’s and Bruton’s petition for
writ of mandamus on February 21, 2008.
III. Standard of Review
A trial court must consider two factors when determining whether to
compel arbitration: (1) whether a valid, enforceable arbitration agreement
exists, and (2) if so, whether the claims asserted fall within the scope of that
agreement. See Ikon Office Solutions, Inc. v. Eifert, 2 S.W.3d 688, 693 (Tex.
App.—Houston [14th Dist.] 1999, no pet.).
The party seeking arbitration has the initial burden to establish its right to
the remedy under the contract; that is, to establish that a valid, enforceable
arbitration agreement exists. See id.; Grand Homes 98, L.P. v. Ely, No. 05-00-
00925-CV, 2001 WL 869362, at *1 (Tex. App.—Dallas Aug. 2, 2001, no
4
pet.). Once a party establishes a claim within the scope of the arbitration
agreement, the trial court must compel arbitration and stay its own proceedings
unless the party opposing arbitration meets its burden of presenting evidence
that prevents enforcement of the agreement. In re H.E. Butt Grocery Co., 17
S.W.3d 360, 367 (Tex. App.—Houston [14th Dist.] 2000, no pet.).
In reviewing factual questions concerning an order denying arbitration, the
appellate courts use a “no evidence” standard. See Eifert, 2 S.W.3d at 693.
Legal conclusions, however, are reviewed de novo. Id. Because Texas public
policy favors arbitration, every reasonable presumption must be decided in favor
of arbitration. Id.
IV. Grand Homes
Because the Hills do not dispute the existence of an arbitration agreement
or that their claims fall within the scope of the arbitration clause, they have the
burden to present evidence to prevent enforcement of the agreement. See In
re H.E. Butt Grocery, 17 S.W .3d at 376. Although the Hills challenge the
enforcement of the arbitration agreement on four grounds, the dispositive issue
in this case is whether Grand Homes failed to comply with a condition
precedent in the contract to invoke the arbitration clause.2 Specifically, the
2
… In this interlocutory appeal, the Hills challenge the enforcement of the
arbitration clause on four grounds: (1) failure to satisfy an asserted condition
5
Hills contend that Grand Homes’s failure to file a demand for arbitration within
100 days of receiving notice of the Hills’ claims was a failure of a condition
precedent that was required to be met before arbitration could be compelled.
A. Substantive vs. Procedural Issue
Grand Homes first argues that the question of whether a condition
precedent was satisfied is a procedural question that must be left to the
arbitrator. See Ely, 2001 WL 869362, at *1. Thus, according to its argument,
whether Grand Homes timely demanded arbitration should not be decided by
the trial court, and any determination of this question by the trial court is error.
Grand Homes made this exact same argument in an earlier case that its
affiliate Grand Homes 98 was involved in. See id. In Ely, Grand Homes 98 had
contracted with the plaintiffs for the construction of a new home. Id. After
closing on the contract, the plaintiffs discovered that the house had been
severely damaged in a fire and had suffered substantial water damage. Id. The
plaintiffs sent a demand letter to Grand Homes 98 on January 18, 2000, and
then subsequently filed suit on April 25, 2000. Id. On May 17, Grand Homes
98 filed a motion to compel arbitration. Id. The trial court denied the motion
precedent to arbitration; (2) collateral estoppel precluding arbitration; (3) waiver;
and (4) unconscionability.
6
because it found that Grand Homes 98 had failed to comply with notice
requirements that were a condition precedent to the arbitration clause. Id. On
appeal, the reviewing court held that it was permissible for the trial
court—rather than the arbitrator—to determine whether the condition precedent
had been satisfied because the relevant facts of the case were undisputed. Id.
Thus, the question before us today is whether the facts are disputed; if
they are, then the issue of whether the condition precedent was fulfilled should
have been determined by the arbitrator, as asserted by Grand Homes. See id.
Grand Homes argues that the facts are disputed because the Hills failed to
present any evidence indicating when or if they delivered the required notice of
“a claim or dispute.”
After a careful review, we determine that the record clearly shows that
Grand Homes received notice of the Hills’ “claim or dispute,” and therefore we
determine that Grand Homes had notice as a matter of law. See Tex. Dep't of
Criminal Justice v. Simons, 140 S.W.3d 338, 347–48 (Tex. 2004) (holding
that actual notice can be determined as a matter of law). First, although Grand
Homes argues that the facts are disputed, they have offered nothing more than
their bare assertion that “there is no evidence before the [trial court] as to when
or if [notice of a claim or dispute] occurred.” In contrast, the record clearly
shows that the Hills presented affidavit testimony in which Shirley Hill stated
7
that after learning that according to Grand Homes she and her husband no
longer qualified for their loan, she called Grand Homes and spoke with Vice
President Mints and “requested a refund of the $5,000 deposit and the
additional payments totaling over $118,000.” However, Mints refused her
request as evidenced by his September 5, 2006 letter. We determine that this
evidence indicates that Grand Homes had notice that the Hills were disputing
the withholding of their approximate $123,000, and there is no conflicting
evidence in the record. See World Savings Bank, F.S.B. v. Gantt, 246 S.W.3d
299, 305 (Tex. App.—Houston [14th Dist.] 2008, no pet.) (stating that a fact
issue existed where there was conflicting evidence in the record).
However, even if it could be argued that this exchange between Shirley
Hills and Mints was insufficient to convey notice to Grand Homes that the Hills
had a claim or dispute regarding the withholding of the funds, the record further
shows that after receiving Mints’s letter, Shirley Hills continued to contact
Grand Homes to make requests for documentation as to how the $118,000
was applied. However, all such requests were denied by Grand Homes’s
representatives. The culmination of Grand Homes’s refusal to return the funds
was evidenced in the April 16, 2007 letter to the Hills in which Grand Homes
rejected “[Shirley’s] demand for the return of deposits retained by Grand
8
Homes.” Clearly, Grand Homes had notice as of April 16 that the Hills were
disputing the fact that their money had not been returned to them.
Furthermore, we are not convinced by Grand Homes’s characterization of
Shirley Hill’s multiple phone calls as “inquiries” that were insufficient to convey
notice. First, the record shows that the Hills continued to contact Grand
Homes regarding the retained funds even after Grand Homes had denied their
request by phone and by letter. The Hills’ repeated attempts to recover their
funds indicates that the Hills actually disputed Grand Homes’s decision to retain
the funds and that they were making more than a mere “inquiry,” as Grand
Homes asserts. Moreover, the very letter sent by Grand Homes on April 16
states that it is in response to “[the Hills’] demand for the return of deposits.”
The fact that Grand Homes referred to the Hills “demand” indicates that it was
more than a mere “inquiry.”
Because the record does not show any conflicting evidence regarding
whether Grand Homes had notice of the Hills’ claim or dispute, we determine
that Grand Homes had notice of the Hills’ claim or dispute. Because the facts
are undisputed, we hold that it was proper for the trial court to make the
9
determination of whether the condition precedent was satisfied.3 See Ely,
2001 WL 869362, at *2. Thus, we reject Grand Homes’s first argument.
B. Burden to Demand Arbitration
Grand Homes further contends that there is no legal or factual basis for
the Hills’ argument that the timely demand for arbitration is a condition
precedent to the right to arbitrate.
General contract principles apply to construction of an arbitration
agreement. See D. Wilson Constr. Co. v. Cris Equip. Co., 988 S.W.2d 388,
393 (Tex. App.—Corpus Christi 1999, pet. granted, judgm’t rev’d w.r.m.); Ely,
2001 WL 869362, at *2. A contract “will be enforced according to its plain
meaning unless such a reading would defeat the intention of the parties.” D.
Wilson Constr. Co., 988 S.W.2d at 393. A condition precedent in a contract
includes an event that must occur before there is a right to performance under
a contract. Id. at 395. To determine whether a condition precedent exists, the
intention of the parties must be ascertained, which requires an examination of
the entire contract. See Criswell v. European Crossroads Shopping Ctr., Ltd.,
792 S.W.2d 945, 948 (Tex. 1990). Conditional language, such as “if,” is
3
… Because we hold that the facts are undisputed, we must review the
trial court’s denial of Grand Homes’ motion to compel arbitration under a de
novo standard. See Eifert, 2 S.W.3d at 693; Ely, 2001 WL 869362, at *1.
10
indicative that a condition precedent was intended by the parties. See Belmont
Constructors, Inc. v. Lyondell Petrochemical Co., 896 S.W.2d 352, 357 (Tex.
App.—Houston [1st Dist.] 1995, no writ). Breach of a condition precedent
affects the enforceability of the provision to which the condition is attached.
City of Alamo v. Garcia, 878 S.W.2d 664, 665 (Tex. App.—Corpus Christi
1994, no writ).
Grand Homes first argues that it did not have the burden to initiate
arbitration prior to the filing of the Hills' suit. Instead, Grand Homes argues that
it was the Hills' responsibility—as claimants—to initiate arbitration proceedings
and that Grand Homes was never a party seeking arbitration under the contract.
We reject this argument because the plain language of the contract gives
“either party” the right to refer any claim or dispute to arbitration. See e.g.,
Ely, 2001 WL 869362, at *2. Thus, it is the responsibility of the party desiring
arbitration to file a demand for arbitration.
We also reject Grand Homes’s contention that the time period to demand
arbitration does not apply to Grand Homes. After reviewing the contract, we
determine that the plain language clearly expresses the parties' intent that a
timely demand for arbitration must occur before a party has a right to
arbitration. See id. Section 17 provides: “If an agreement shall not have been
reached within 10 days after notice of a claim or dispute is delivered by either
11
party to the other party . . . , then either party shall have the right at any time
after the expiration of such 10-day period to refer such claim or dispute to
arbitration as herein provided.” Id. It further provides: “Any demand for
arbitration shall be made within 90 days after the expiration of the 10-day
period specified above.” Id. We conclude that under the plain language of the
parties' agreement, a timely demand for arbitration was a condition precedent
to the enforceability of the arbitration clause. See id.
C. Whether Grand Homes Satisfied the Condition Precedent?
Grand Homes next argues that if the contract required that a demand for
arbitration be made within 100 days of receiving notice of a claim or dispute,
then it satisfied such a condition as it filed a demand for arbitration within 100
days of the filing of the underlying lawsuit. Grand Homes points to June 18,
2007—the date that it was served with the Hills’ lawsuit—as the day that it
received notice of the Hills’ claims or disputes. Grand Homes asserts that
because it actually received notice of the claims on June 18, the expiration for
the asserted time to make a demand for arbitration fell on September 25, or
100 days after June 18. Thus, Grand Homes asserts that its demand for
arbitration was timely because it filed the motion to compel arbitration on
September 19.
12
After reviewing the plain language of the arbitration agreement, we
determine that Grand Homes failed to satisfy the condition precedent. First, the
record shows that Grand Homes failed to file an adequate demand for
arbitration. Grand Homes’s attempt to rely on its September 19 motion to
compel arbitration as evidence that it complied with the arbitration agreement
is insufficient. Per the agreement, Grand Homes was required to file a demand
for arbitration with the American Arbitration Association (“AAA”) within 100
days of receiving notice of the Hills’ claims. The record is clear that Grand
Homes has never filed such a demand with the AAA.
Furthermore, even if Grand Homes’s September 19 motion to compel
arbitration was a sufficient “demand” for arbitration—which it is not—the
motion was still untimely. Our review of the record shows that Grand Homes
had notice of the Hills’ “claim or dispute” at the latest by April 11, 2007. 4
Grand Homes was required to file a demand for arbitration within 100 days, or,
at the latest, by July 20, 2007.5 However, Grand Homes did not file its motion
to compel arbitration until September 19. Thus, the record shows that Grand
4
… September 5, 2006 and April 11, 2007 are the dates that Grand
Homes sent the Hills two letters in which Grand Homes denied the return of the
Hills’ deposit and subsequent payments, totaling $123,000.
5
… See id.
13
Homes failed to demand arbitration within 100 days of receiving notice of the
Hills’ dispute as required by section 17 of the arbitration agreement.
Grand Homes did not comply with this condition precedent to its
contractual right to arbitration, and this breach affects the enforceability of the
arbitration provision to which the condition is attached. Weekley Homes, Inc.
v. Jennings, 936 S.W.2d 16, 18 (Tex. App.—San Antonio 1996, writ denied);
Ely, 2001 WL 869362, at *3. We conclude that because the Hills have
presented evidence that Grand Homes failed to satisfy a condition precedent,
Grand Homes was not entitled to an order compelling arbitration. See In re H.E.
Butts Grocery, 17 S.W.3d at 367; Ely, 2001 WL 869362, at *3.6
V. Melanie Bruton
In this appeal, the Hills allege that a Grand Homes’s sales employee,
Melanie Bruton, was not entitled to an order compelling arbitration because she
and Grand Homes failed to satisfy a condition precedent.
Although Bruton was not a signatory to the contract between Grand
Homes and the Hills, no one challenges the fact that Bruton was an agent
6
… Thus, it is unnecessary for us to consider the remaining grounds upon
which the Hills challenged the enforcement of the arbitration clause. See T EX.
R. A PP. P. 47.1.
14
acting for Grand Homes’s benefit and within the scope of her agency.7 Because
a principal—such as Grand Homes—is bound under the terms of a valid
arbitration clause, its agents, employees, and representatives are also covered
under the terms of such agreements. See In re Merrill Lynch Trust Co. FSB,
235 S.W.3d 185, 188 n.5 (Tex. 2007). Thus, the pertinent question before us
is whether Bruton satisfied the arbitration clause’s condition precedent.
The record shows that Bruton was added as a defendant in this lawsuit
on September 4, 2007, and that she received notice of the Hills’ amended
petition on September 10. On September 19, Grand Homes filed a motion to
compel arbitration on behalf of itself and Bruton. As we have previously
determined, this motion was an insufficient demand for arbitration. Per the
agreement, Bruton and Grand Homes were required to file notice of a demand
for arbitration with the AAA and with the Hills within 100 days of receiving
notice of the Hills’ claims. Bruton had notice of the Hills’ claims once she was
served with their lawsuit on September 10. However, there is no evidence in
the record to show that Bruton filed notice of a demand for arbitration with the
7
… Within Grand Homes’s motion to compel arbitration, it identified
Bruton as an employee of Grand Homes who “operates as an agent of [Grand
Homes] when she is acting within the scope of her employment.”
15
AAA within the 100 days, or by December 19, 2007, as required by the
arbitration clause.
Although Bruton asserts that the function of officially noticing an
intention to arbitrate with the AAA was fulfilled by the filing of the motion to
compel arbitration, we disagree. Under the plain language of the arbitration
agreement, the party seeking arbitration was required to give written “notice
of any demand for arbitration” with “both the other party to this agreement and
with the American Arbitration Association.” The agreement provides a very
specific method for referring a claim to arbitration, and we will not disregard the
plain language of the contract as Bruton’s position would require us to do. See
D. Wilson Constr. Co., 988 S.W.2d at 393 (holding that general contract
principles apply to construction of an arbitration agreement and the contract
should be enforced according to its plain meaning).
Because Bruton did not comply with the contractual requirements which
entitle her to arbitration, she did not comply with the condition precedent to her
contractual right to arbitration. See Garcia, 878 S.W.2d at 666 (holding that
where the notice given did not meet the requisites established by the parties in
their agreement, the trial court properly refused to refer the dispute to
arbitration). This breach affects the enforceability of the arbitration provision
to which the condition is attached. Jennings, 936 S.W.2d at 18; Ely, 2001 WL
16
869362, at *3. Accordingly, we determine that the trial court properly refused
to refer the dispute to arbitration. See Garcia, 878 S.W.2d at 666.
VI. Conclusion
Accordingly, we hold that the trial court did not err in denying the motion
to compel arbitration. We affirm the trial court’s order.
BOB MCCOY
JUSTICE
PANEL B: LIVINGSTON, WALKER, and MCCOY, JJ.
DELIVERED: May 22, 2008
17