State of New York
Supreme Court, Appellate Division
Third Judicial Department
Decided and Entered: December 17, 2015 520624
________________________________
GRANGER CONSTRUCTION COMPANY,
INC.,
Plaintiff,
v
TJ, LLC,
Defendant
and Third-
Party MEMORANDUM AND ORDER
Plaintiff-
Appellant,
et al.,
Defendant;
LIBERTY MUTUAL GROUP INC.,
Doing Business as LIBERTY
MUTUAL INSURANCE COMPANY,
Third-Party
Defendant-
Respondent.
________________________________
Calendar Date: October 22, 2015
Before: Peters, P.J., Garry, Rose and Clark, JJ.
__________
Hinman, Howard & Kattell, LLP, East Greenbush (Michael
Keenan of counsel), for defendant and third-party plaintiff-
appellant.
Alario & Fischer, PC, East Syracuse (Linda E. Alario of
counsel), for third-party defendant-respondent.
__________
-2- 520624
Clark, J.
Appeal from an order of the Supreme Court (Lebous, J.),
entered November 26, 2014 in Broome County, which, among other
things, granted third-party defendant's motion for summary
judgment dismissing the third-party complaint.
In 2011, defendant TJ, LLC entered into a contract with
plaintiff for the construction of a hotel in the Town of Vestal,
Broome County. The contract was insured by a performance bond
with third-party defendant, Liberty Mutual Group Inc., acting as
surety. Although construction continued through early 2013, the
hotel opened in April 2012. When the fire alarm system began to
malfunction in January 2013, TJ was forced to temporarily close
the hotel. TJ informed plaintiff of the need for repairs, but
plaintiff refused to perform the repairs, citing TJ's alleged
failure to keep its payments current. Upon undertaking the
repairs itself, TJ discovered other problems with the
construction of the hotel and, by April 2013, TJ had hired
contractors other than plaintiff to complete all needed repairs.
In June 2013, TJ sent Liberty Mutual a letter stating that it
intended to file for contractor default under the terms of the
performance bond and that it had fully complied with paragraph 3
of the bond. Liberty Mutual then scheduled a conference between
plaintiff and TJ in an attempt to resolve their issues pursuant
to the terms of the bond. A resolution having not been achieved,
TJ sent a formal notice of contractor default to Liberty Mutual
in July 2013.1
Plaintiff thereafter commenced this action against TJ and
defendant Thomas Bedosky, TJ's owner, alleging breach of
contract, among other things. TJ then commenced a third-party
action against Liberty Mutual to compel it to perform under the
bond. After answering, Liberty Mutual moved for summary judgment
dismissing the third-party complaint. Supreme Court granted
1
Both Liberty Mutual and plaintiff, as well as counsel for
plaintiff, claim that they did not receive this notice.
-3- 520624
Liberty Mutual's motion for summary judgment and TJ appeals.2
We affirm. In determining whether a party is relieved of
its duty to perform under a surety bond, courts interpret the
bond, like any other contract, according to its terms (see Walter
Concrete Constr. Corp. v Lederle Labs. 99 NY2d 603, 605 [2003];
General Phoenix Corp. v Cabot, 300 NY 87, 92 [1949]). As
relevant herein, "a contractual duty ordinarily will not be
construed as a condition precedent absent clear language showing
that the parties intended to make it a condition" (Mullany v
Munchkin Enters., Ltd., 69 AD3d 1271, 1274 [2010] [internal
quotation marks, brackets and citations omitted]; see Unigard
Sec. Ins. Co. v North Riv. Ins. Co. 79 NY2d 576, 581 [1992]).
"Notably, it is for the court to decide, as a matter of law,
whether an express condition precedent to performance exists
under the terms of a contract" (Rooney v Slomowitz, 11 AD3d 864,
865 [2004] [citations omitted]).
Liberty Mutual contends that TJ failed to meet one or more
express conditions precedent under the bond, thus rendering the
bond null and void. Pursuant to paragraph 3 of the bond, Liberty
Mutual's obligation arose after three conditions were met, namely
(1) TJ notified plaintiff and Liberty Mutual that it was
considering declaring a contractor default and was requesting a
conference with the parties, (2) TJ formally declared a
contractor default and terminated plaintiff's right to complete
the contract, which could not occur earlier than 20 days after
the parties received notice under section 3.1, and (3) TJ agreed
to pay the balance of the contract price to Liberty Mutual or to
a contractor selected to perform the rest of the construction
contract. As relevant here, sections 4.2 and 4.4 of the bond,
respectively, state that when TJ has satisfied the conditions of
paragraph 3, Liberty Mutual shall promptly, and at its own
2
TJ also cross-moved to strike Liberty Mutual's second
affirmative defense. Such motion was denied by Supreme Court.
To the extent that TJ does not take issue with this portion of
Supreme Court's order, any argument with respect thereto has been
abandoned (see Salzer v Benderson Dev. Co., LLC, 130 AD3d 1226,
1229 n 1 [2015]).
-4- 520624
expense, undertake performance of the construction contract
through independent contractors or, alternatively, waive this
right and either tender payment to TJ or deny liability.
Paragraph 5 states that, should Liberty Mutual have failed to
proceed under paragraph 4 within a reasonable time, it would be
deemed to be in default on the bond 15 days after receiving
additional written notice from TJ demanding performance.
However, if Liberty Mutual tendered payment and then TJ refused
the payment, or if Liberty Mutual denied liability, then TJ was
entitled to enforce any remedy available to it against Liberty
Mutual without providing further notice.
Inasmuch as paragraph 3 clearly states that Liberty
Mutual's obligation under the bond "shall arise" only after TJ
had performed the three conditions detailed in sections 3.1 to
3.3, this language unambiguously created conditions precedent to
be performed in the order that they are listed (see Archstone v
Tocci Bldg. Corp. of N.J., Inc., 119 AD3d 497, 498 [2014], lv
dismissed 24 NY3d 1037 [2014]; see also 120 Greenwich Dev.
Assocs., LLC v Reliance Ins. Co., 2004 WL 1277998, *11-12, 2004
US Dist LEXIS 10514, *34-37 [SD NY, June 8, 2004, No. 01 Civ 8219
(PKL)]). Therefore, TJ must have strictly complied with each
condition precedent before Liberty Mutual could be held liable
under the bond.
Viewing the facts in the light most favorable to TJ, as the
nonmovant (see U.W. Marx, Inc. v Koko Contr., Inc., 97 AD3d 893,
894 [2012]), Liberty Mutual met its burden of demonstrating the
absence of a material question of fact (see JMD Holding Corp. v
Congress Fin. Corp., 4 NY3d 373, 384 [2005]).3 The record before
us demonstrates that TJ failed to comply with at least one of the
express conditions precedent in paragraph 3 of the bond.
Specifically, plaintiff affirms that it never received the notice
from TJ, allegedly sent in June 2013, saying that TJ was
considering declaring a contractor default, as required by
section 3.1. This, by itself, would preclude Liberty Mutual's
liability under the express terms of the performance bond (see
3
We note that Supreme Court issued a bench decision
immediately following oral argument on Liberty Mutual's motion.
-5- 520624
153 Hudson Dev., LLC v DiNunno, 8 AD3d 77, 78 [2004]). Further,
the evidence establishes that TJ paid outside contractors under
section 3.3 prior to sending notice to plaintiff and Liberty
Mutual pursuant to section 3.1 or 3.2, which also would serve to
preclude Liberty Mutual's liability. Finally, TJ also admits
that it failed to provide additional notice demanding performance
before bringing suit as set forth in paragraph 5, which also
operates to release Liberty Mutual of its obligations under the
bond to the extent that the conditions precedent set forth in
paragraph 3 had not been complied with. Thus, inasmuch as the
record demonstrates that TJ failed to comply with the conditions
precedent of paragraph 3, Liberty Mutual adequately shifted the
burden to TJ to demonstrate a material question of fact (see
Alvarez v Prospect Hosp., 68 NY2d 320, 324 [1986]).
In this regard, we are unpersuaded by TJ's contentions that
the loss of profits and economic hardship of temporarily closing
the hotel in order to comply with the terms set forth in
paragraph 3 of the bond rise to the level to warrant excusing
performance of the bond's conditions under the rarely imposed
theory of impossibility of performance (see Kel Kim Corp. v
Central Mkts., 70 NY2d 900, 902 [1987]; 407 E. 61st Garage v
Savoy Fifth Ave. Corp., 23 NY2d 275, 281 [1968]; Lagarenne v
Ingber, 273 AD2d 735, 737 [2000]). Nor are we persuaded that the
plain language of the bond should be construed so as to reflect
the "commercial reality" facing TJ. Accordingly, TJ failed to
meet its shifted burden and summary judgment was properly granted
to Liberty Mutual (see Roel Partnership v Amwest Sur. Ins. Co.,
258 AD2d 780, 781-782 [1999]).
TJ's remaining contentions are found to be lacking in
merit.
Peters, P.J., Garry and Rose, JJ., concur.
-6- 520624
ORDERED that the order is affirmed, with costs.
ENTER:
Robert D. Mayberger
Clerk of the Court