IN THE COURT OF APPEALS OF IOWA
No. 18-1186
Filed September 25, 2019
OLMSTEAD CONSTRUCTION, INC.,
Plaintiff-Appellee/Cross-Appellant,
vs.
OTTER CREEK INVESTMENTS, LLC,
Defendant-Appellant/Cross-Appellee.
________________________________________________________________
Appeal from the Iowa District Court for Linn County, Kevin McKeever,
Judge.
Olmstead Construction, Inc. and Otter Creek Investments, L.L.C. both
appeal following resolution of their contract dispute. AFFIRMED IN PART AND
REVERSED IN PART ON APPEAL; CONDITIONALLY AFFIRMED ON CROSS-
APPEAL; AND REMANDED.
Dana L. Oxley and Kevin J. Caster of Shuttleworth & Ingersoll, P.L.C.,
Cedar Rapids, for appellant Otter Creek Investments, LLC.
Jeffrey A. Stone and Chad D. Brakhahn of Simmons Perrine Moyer
Bergman PLC, Cedar Rapids, for appellee Olmstead Construction, Inc.
Heard by Doyle, P.J., Blane, S.J.* and Lloyd, S.J.*
*Senior judges assigned by order pursuant to Iowa Code section 602.9206 (2019).
2
DOYLE, Presiding Judge.
The parties to a dispute over a construction contract ask us to review the
district court’s determination of various contract terms that affect the damages,
attorney fees, and interest awarded in a breach-of-contract claim. We must also
determine whether the district court erred by refusing to foreclose on a mechanic’s
lien.
We affirm the judgment entered in favor of Olmstead Construction, Inc.
(Olmstead Construction) on its breach-of-contract claim but reverse the awards of
$48,150 in damages for electrical costs and $47,787.73 in attorney fees. We
conditionally affirm the denial of Olmstead Construction’s petition to foreclose on
its mechanic’s lien and affirm the district court in all other respects. We remand
the case for further proceedings in conformance with this opinion.
I. Background Facts and Proceedings.
Brothers Don and Joe Burd decided to open a convenience store and gas
station in Robins and formed Otter Creek Investments, LLC (Otter Creek) for that
purpose. Otter Creek hired Olmstead Construction to build the store. In May 2014,
the parties entered a cost-plus contract, which requires the owner to pay the
contractor for construction costs plus a percentage markup. Otter Creek agreed
to reimburse Olmstead Construction for its construction costs and pay a seven-
percent markup on those costs. The contract also required Olmstead Construction
to act as the project manager, which entailed obtaining subcontractor bids,
supervising their subcontractor work, and processing and paying subcontractor
invoices. Olmstead Construction would then bill Otter Creek for the subcontractor
costs plus the seven-percent markup on those costs.
3
In July 2014, Olmstead Construction provided Otter Creek an initial estimate
of the total cost of construction, which it projected to be $1,204,774. Construction
began. During 2014, Olmstead Construction billed Otter Creek for work totaling
$81,093.16. Otter Creek paid Olmstead Construction this amount in December
2014.
By the end of the year, Otter Creek realized it needed to scale back the cost
of the project due to financing issues. As a result, it redesigned the construction
plans between December 2014 and May 2015 with Olmstead Construction’s help.
Based on Otter Creek’s changes to the plans, Olmstead Construction submitted a
revised estimate of the total cost of construction on April 5, 2015, which it projected
to be $962,535. Two days later, Olmstead Construction submitted a new estimate,
this time projecting a total cost of $948,132.
One way in which Otter Creek tried to reduce the cost of the project was to
contract directly with some subcontractors, eliminating the seven-percent markup
Olmstead Construction would otherwise receive for that subcontracted work. One
subcontractor Otter Creek opted to contract with directly was Streff Electric, the
electrical subcontractor. The parties agreed that Otter Creek would pay Streff
Electric directly for the portion of the electrical work running to the gas pumps while
Olmstead Construction would oversee the work Streff Electric performed inside the
store. Olmstead Construction’s revised estimates reflect this change.1
Olmstead Construction received invoices from the subcontractors it
supervised, while those contracting directly with Otter Creek submitted invoices to
1
The revised estimates include a line for electrical work but list it as “Electrical (No
electrical at Gas Pumps).”
4
Don Burd. Daniel Olmstead, the owner and president of Olmstead Construction,
testified, “We pay strictly off whatever invoices are sent to us.” So when Olmstead
Construction received invoices from Streff Electric for work on the gas pumps,
Daniel Olmstead assumed Otter Creek was adding that expense back into their
contract despite Otter Creek’s silence on the matter. Because it received the
invoice, Olmstead Construction paid Streff Electric for that work and added the
expense to its invoice to Otter Creek. Unbeknown to Olmstead Construction, Otter
Creek also paid Streff Electric for the electrical work on the gas pumps.
During 2015, Olmstead Construction billed Otter Creek for work totaling
$778,432.84 in 2015. Don Burd noted some items listed as completed in an
October 2015 invoice were for work that had not yet begun and asked for
documentation of the costs. He never received the requested documentation.
When Olmstead Construction sent a new invoice in December without
documentation, Don Burd again asked for documents to verify the costs. Although
Olmstead Construction never provided documentation, Otter Creek paid the total
amount due in December 2015.
In February 2016, Olmstead Construction sent Otter Creek three invoices
listing different amounts owed. An invoice dated February 9 shows a total project
cost of $999,850 and an amount due of $102,930.84. An invoice dated February
12 shows a total project cost of $962,535 and an amount due of $102,928. Another
invoice dated February 12 also shows a total project cost of $962,535 but an
amount due of $35,483.16. When Otter Creek asked about the invoices, Olmstead
Construction stated it had revised the invoices and would invoice for “extras” later.
5
Olmstead Construction sent a final invoice to Otter Creek on March 22,
2016. That invoice shows a total project cost of $1,058,869.82 and an amount due
of $199,343.82. Confused about what the additional charges were for, Don Burd
decided to wait to pay it until Olmstead Construction provided explanation or
documentation of the costs. Olmstead Construction informed Otter Creek that it
would file a mechanic’s lien if Otter Creek failed to pay the invoice within thirty
days. Olmstead Construction filed a mechanic’s lien on April 12, 2016.
In June 2016, Olmstead Construction petitioned to foreclose the mechanic’s
lien for the remaining $199,343.82. Otter Creek counterclaimed for breach of
contract and defective construction. Olmstead Construction amended its petition
to add a claim for breach of contract, seeking prejudgment interest and attorney
fees.
Following a bench trial, the district court found Olmstead Construction
proved its breach-of-contract claim. It entered a $217,121.19 judgment for
Olmstead Construction, which included $48,150 in damages attributable to work
on the gas pumps.2 Although the court found Olmstead Construction proved a
valid mechanic’s lien, it denied the petition to foreclose on it. It also found Otter
Creek failed to prove its counterclaim. After both parties moved the court to
reconsider its ruling, the court reduced the judgment entered against Otter Creek
to $163,395.84, based on an error in its damage calculation.3 The court awarded
Olmstead Construction $47,787.73 in attorney fees and assessed interest from the
2
This figure reflects the amount Olmstead Construction paid to Streff Electric for the work
($45,000) plus Olmstead Construction’s seven-percent markup of that cost ($3150).
3
Otter Creek has since paid Olmstead Construction $115,000 in partial satisfaction of the
judgment.
6
date of judgment. Otter Creek appeals and Olmstead Construction cross-
appeals.4
II. Breach of Contract.
We review breach-of-contract claims for errors at law. See Postell v. Am.
Family Mut. Ins. Co., 823 N.W.2d 35, 41 (Iowa 2012) (stating the court reviews
contract interpretation and construction for errors at law). Under this review, the
district court’s factual findings are binding on us if supported by substantial
evidence. See Metro. Prop. & Cas. Ins. Co. v. Auto-Owners Mut. Ins. Co., 924
N.W.2d 833, 839 (Iowa 2019). That said, the district court’s legal determinations
do not bind us. See Westhoff v. Am. Interins. Exch., 250 N.W.2d 404, 408 (Iowa
1977).
To establish breach of contract, a party must show:
(1) the existence of a contract; (2) the terms and conditions of the
contract; (3) that it has performed all the terms and conditions
required under the contract; (4) the defendant’s breach of the
contract in some particular way; and (5) that plaintiff has suffered
damages as a result of the breach.
Iowa Arboretum, Inc. v. Iowa 4-H Found., 886 N.W.2d 695, 706 (Iowa 2016)
(citation omitted). The parties stipulated to the existence of a contract, and the
district court found that Otter Creek breached the terms of the contract by failing
to provide prompt payment to Olmstead Construction for completion of the
contracted work. On appeal, the parties challenge the district court’s interpretation
4
The table of contents in the parties’ appendix lists trial exhibits but fails to provide
descriptors of the exhibits. Iowa Rule of Appellate Procedure 6.905(4)(c) requires that if
exhibits are included in the appendix “the table of contents shall . . . give a concise
description of [each] exhibit (e.g., ‘warranty deed dated . . . ’; ‘photograph of construction
site’; ‘Last Will and Testament executed on . . . ’).”
7
of various terms of the contract, which affect the amount of damages and the award
of attorney fees.
A. Payment for Electrical Work.
Otter Creek first challenges the portion of the district court’s order awarding
damages to Olmstead Construction to reimburse payments it made to Streff
Electric for the work Streff Electric performed on the gas pumps. The court
determined that the $45,000 Streff Electric billed for this work was “related to
material, labor, or services provided for the purpose of the construction project.”
Because the contract required Otter Creek to pay Olmstead Construction costs
plus seven percent, the court held Olmstead Construction had a right to recover
$48,150 for the this work.
Otter Creek challenges the evidence that Olmstead Construction paid the
$45,000 invoiced by Streff Electric for the work on the gas pumps. In the
alternative, it argues that Olmstead Construction cannot recover payments to Streff
Electric for the work on the gas pumps because this work is not a cost under the
contract.
Assuming Olmstead Construction paid Streff Electric for wiring the gas
pumps, Olmstead Construction cannot recover that amount from Otter Creek
because the work is not a cost of construction under the contract. The contract
states that Olmstead Construction proposes to furnish all labor, materials, and
equipment to complete a list of items.5 One of the items listed is “Electrical.” The
5
Some categories in the list have sub-lists that provide more information on Olmstead
Construction’s responsibilities. For instance, under the category of “General Conditions,”
it states that Olmstead Construction would coordinate all subcontractors on the project.
8
contract provides no further detail on the electrical work. But when asked to
explain his understanding of Olmstead Construction’s obligations under the
contract, Daniel Olmstead testified:
Electrical was all—mainly all we did on—or I guess what I’d say is
the main thing we ever did on this building was the building only.
There was a lot of other work that was completed around this project
that was not included in our contract or in our proposal. So the
electrical included everything that pertained to the building itself,
which would have been the lights, the wiring, everything like that.
Likewise, Don Burd testified:
A. On our initial meeting, we—I laid out the—what I needed him
to perform. And it would be to construct the building, to manage the
construction of the building, managing the subcontractors, obtaining
all the bid work for the different particulars of the job, and submitting
all that and—
Q. Did you discuss whether or not the contract would include
the fueling station, the pumps and so on? A. No. I told him that we
had another contract for that portion of work.
Q. So you discussed it but you told him you had another
contractor? A. Yes, it was going to be the building only.
Olmstead Construction’s July 2014 estimate also reflects that the scope of
its work was limited to construction of the building. The estimate includes a more
detailed list of Olmstead Construction’s responsibilities, listing five categories of
electrical work: (1) building, (2) paging and sound, (3) security system, (4) IP based
CCTV, and (5) network cabling. Under the category of “Items furnished by owner,”
the estimate lists “Fuel tanks and pumping equipment” as item 11. Daniel
Olmstead testified that the work Streff Electric performed on the gas pumps is the
same work that the July 2014 estimate lists as “furnished by owner.”
Daniel Olmstead testified he did not know that Otter Creek contracted
directly with Streff Electric for the work performed on the gas pumps. Don Burd
disputed this claim in the following testimony:
9
Q. Did you at any time tell Olmstead Construction that you
were contracting directly with Streff Electric with respect to the fuel
pumps? A. Yes, I would have. That is not in the scope of Olmstead’s
work that we had discussed.
Q. Did you have conversations at the very beginning of your
relationship with Olmstead Construction about the scope of the work
excluding the fuel pumps? A. Yes, we did.
....
Q. Do you have reason to believe that Olmstead Construction
at all times knew that you had contracted independently and
separately with Streff Electric to provide services to the fuel pumps?
A. Yes.
Q. And is there any reason to think that that changed at any
point in time during the course of the construction? A. No.
Q. Would Olmstead have any reason to believe that they had
suddenly taken off the obligation to provide electrical or any other
construction services related to the fuel pumps? A. No.
The estimates Olmstead Construction provided in April 2015 further show
that the electrical work on the gas pumps was not a cost by stating “(No electrical
at Gas Pumps)” next to the line for the cost of electrical work. Olmstead admitted
that when he prepared the April 2015 estimates, the scope of the contract did not
include electrical wiring to the gas pumps. He also admitted that the final invoice
Olmstead Construction sent to Otter Creek in March 2016 does not purport to
include the electrical work to the gas pumps, instead listing as item 21, “Electrical
(No gas Pumps).”
Daniel Olmstead assumed Otter Creek added the electrical work to the gas
pumps back into the contract based solely on Olmstead Construction’s receipt of
invoices for that work from Streff Electric. He admitted he never received a change
order from Streff Electric for the gas pump work. Olmstead also admitted that no
one told him to add the cost of the electric work to the gas pumps back into the
contract. When asked if it was a mistake for Olmstead Construction to charge or
pay Streff Electric for the invoices on the electrical work performed on the gas
10
pumps, Olmstead testified, “I guess you can look at it any way you want to look at
it. When an invoice comes to our office, the office girl automatically puts that in
our system as a bill against that project. That’s how it got put in here.”6
It is true that an executory contract may be modified by one party with the
consent of the other, even by implied acts and conduct. See Tindell v. Apple Lines,
Inc., 478 N.W.2d 428, 430 (Iowa Ct. App. 1991). But the district court never found
the parties agreed to modify the contract. Rather, the court determined that Otter
Creek was liable for Olmstead Construction’s costs, and the mere fact that
Olmstead Construction received an invoice from Streff Electric qualified that work
as a cost of Olmstead Construction. The record does not support that finding.
Because the cost of the electrical work to the gas pumps is not a cost of the
contract, Olmstead Construction is not entitled to the $48,150 awarded by the
district court for that cost plus the seven-percent markup. Reducing the amount of
the judgment awarded to Olmstead Construction on its breach-of-contract claim by
this amount, we revise the judgment to award Olmstead Construction $115,245.84.
B. Payment for Equipment Costs.
On cross-appeal, Olmstead Construction challenges the court’s refusal to
award reasonable costs for using its own equipment on the project. Based on the
equipment rates provided by the Iowa Department of Transportation (IDOT),
Olmstead Construction seeks an $83,342.34 increase in its award to compensate
6
The three invoices in question were directed “To: Otter Creek Investments” with a
descriptor of “Project: Otter Creek Outpost Pumps.” Otter Creek received and paid these
invoices before Olmstead paid on the same invoices. Although the president of Streff
Electric testified at trial, he gave no explanation as to why the invoices in question were
sent to both Otter Creek and Olmstead Construction. All other invoices Omstead received
from Streff Electric were directed “To: Olmstead Construction” with a descriptor of “Otter
Creek Outpost Station.”
11
it for the cost of using a skid loader, a large forklift, several small tools, a delivery
truck, insulated blankets, and concrete forms that it owns.
Olmstead Construction bought the equipment and used it on several
projects before entering the contract with Otter Creek. Because the equipment is
self-owned, Olmstead Construction cannot produce receipts for the cost of its use
on the Otter Creek project. To calculate the “cost” of using this equipment, it
presented testimony from Matt Olmstead, who has been working in the
construction industry for twenty years and is the current president of Olmstead
Construction. He provided two methods for calculating the reasonable cost of self-
owned equipment. The first method allocates the equipment cost “as part of the
wage rate for the project,” which he testified was $60 per hour. Using this method,
Olmstead Construction invoiced Otter Creek $33,130.98 for use of the equipment.
The second method involves the equipment rate schedules provided by the IDOT,
which Olmstead Construction sometimes use to determine the rates to charge for
use of its own equipment or to rent its equipment to others. Using the IDOT
equipment rate schedules, Matt Olmstead testified that Olmstead Construction
could charge Otter Creek $83,342.34 for use of its equipment.
The district court determined that Olmstead Construction had no right to
compensation for the use of its equipment, noting “the language to the contract
indicated that [Olmstead Construction] would be paid cost plus seven percent.”
Because Olmstead Construction failed to prove “what its cost of providing the
equipment actually was,” the court “conclude[d] that to award damages for the
provided equipment would amount to little more than speculation.” In its expanded
ruling, the court clarified that it “intended to afford [Olmstead Construction] the
12
amount of $0 for the rental equipment simply because [Olmstead Construction]
failed to prove any cost associated therewith. Since the contract was for cost plus
7%, [Olmstead Construction] is entitled to recover $0 for the rental equipment.”
Olmstead Construction argues the court erred by declining to award
damages for its use of self-owned equipment because the cost was too
speculative. It claims that Iowa has recognized that the cost of self-owned
equipment is reimbursable under cost-plus contracts, citing our opinion in
Constructive Consultants, Inc. v. Banwart, No. 12-1011, 2013 WL 988637, at *4
n.2 (Iowa Ct. App. Mar. 13, 2013). There, we quoted the following treatise
language:
It is important to carefully define which construction costs incurred by
the contractor are to be reimbursed. It is typical to provide
reimbursement for wages paid for labor and taxes; benefits;
insurance costs based on those wages; rented equipment;
subcontract costs; insurance costs; bonding costs; building permit
costs; costs of contractor-owned equipment (which can be
controversial to determine); and costs of material.
Constructive Consultants, 2013 WL 988637, at *4 n.2 (emphasis added) (quoting
Philip L. Bruner & Patrick J. O’Connor, Jr., 2 Bruner & O’Connor on Construction
Law § 6:81). The same treatise notes that computing the cost of self-owned
equipment “is extraordinarily complex and poses difficult cost accounting problems
that few beyond experienced construction cost accountants and equipment
dealers truly understand.” 6 Bruner & O’Connor on Construction Law § 19:104,
Westlaw (database updated June 2018) (footnotes omitted). However, the method
used to calculate charges for contractor-owned equipment is less important than
the parties’ agreement as to the method. See Stephen A. Hess, Construction
Contract Pricing, Construction Briefings No. 2008-7 (July 2008). For this reason,
13
the “traditional and accepted method” for determining actual costs of contractor-
owned equipment is to include with the contract a schedule of the rates the
contractor is entitled to bill for use of its own equipment. See id. “In the absence
of such a schedule, the attribution of ‘cost’ to contractor-owner equipment can be
a contentious and frustrating process for both parties.” Id. Other ways to
determine actual costs of contractor-owned equipment is by using equipment rate
manuals and expert testimony if there is an “absence of accurate and complete
accounting records from which actual costs may be determined.” 6 Bruner &
O’Connor on Construction Law § 19:104.
Olmstead Construction claims that it can recover the reasonable charge for
renting its equipment in the area, citing Olberding Construction Co., Inc. v. Ruden,
243 N.W.2d 872, 877 (Iowa 1976). But that case involved an implied contract, not
a cost-plus contract. Olberding Constr., 243 N.W.2d at 875 (“There is no claim
that an express contract existed as to the amount of compensation to be paid.”).
The supreme court noted that “where there is no agreement as to the amount of
compensation, the law implies a promise to pay reasonable compensation.” Id.
Because another contractor who was knowledgeable with the amount charged for
rental equipment in the area testified that the contractor’s charges for rental
equipment were reasonable, the court found substantial evidence to support the
contractor’s bill. See id. at 877.
The district court noted that Olmstead Construction “provided evidence that
the equipment charges would have been reasonable” but failed to show the actual
cost of the equipment’s use. In other words, although it may have been reasonable
for Olmstead Construction to charge an owner for the use of its equipment based
14
on either of the two calculations it provided at trial, there was no evidence that
either figure related to the actual cost of using the equipment.
We agree that the IDOT rate schedules do not reflect the actual cost of
using Olmstead Construction’s equipment. Matt Olmstead testified that the IDOT’s
rate schedules provided an appropriate hourly rental rate to charge for construction
equipment, not a rate for equipment that one owned. And the rates relate to
highway construction rather than building construction. We also note that
Olmstead Construction did not use this schedule when it initially billed Otter Creek
for the use of its equipment. Using the IDOT rate schedules results in a charge
more than $50,000 higher than the amount Olmstead Construction invoiced to
Otter Creek. There is insufficient evidence to justify use of the IDOT rate schedules
to calculate the cost of the equipment use.
The evidence regarding the so-called labor rate charged by Olmstead
Construction is unavailing. Olmstead Construction provided two exhibits to
illustrate its calculations for labor. An exhibit titled “Otter Creek Outpost Employee
Breakdown” lists each laborer who worked on the project, the number of hours
each worked, and the “raw cost” of employing each laborer based on the salary,
benefits, and taxes Olmstead Construction paid. Next to the “raw cost” column is
a column titled “other expenses,” which Daniel Olmstead testified represents the
hourly cost7 for the use of its equipment by each laborer. A column combining
“raw cost” and “other expenses” shows a final hourly rate for each laborer,8
7
The hourly cost for the equipment used by each laborer, whether it was small tools or a
skid loader, ranges from $7.36 to $8.92 per hour.
8
This figure ranges from $51.94 to $62.89 per hour.
15
followed by a column showing the total project cost for each by multiplying that
final hourly rate by the number of hours worked. Adding these amounts together,
the exhibit shows a total cost of $233,640, the same amount Olmstead
Construction shows as the total cost of labor for the project in its final invoice.
An exhibit titled “Billing Itemization” also shows the final labor cost of
$233,640 based on a labor rate of $60 per hour, with labor expenses itemized:
Union Wages, Benefits,
Insurance, Medicare &
Unemployment Taxes $ 200,509.02
Skid Loader $ 13,580.00
Large fork lift $ 10,000.00
Large truck $ 2,000.00
Small Tools $ 3,000.98
Insulated Blankets $ 550.00
Concrete forms $ 4,000.00
3,894 Man hours @ 60.00/HR $ 233,640.00
To justify its labor rate, Daniel Olmstead testified that the $60 per hour
charge for labor is “very reasonable” in his experience. Matt Olmstead testified
that Olmstead Construction uses a similar rate on about 80% of contracts involving
reimbursable costs. When asked about the “other expenses” column listing
equipment charges by laborer in the exhibit showing a breakdown of expenses by
employee, Daniel Olmstead testified:
What we end up doing—we do a lot of projects with a labor rate.
Factories, other jobs we’ve done before, they want you to include
everything. They don’t want you to itemize out you’re using the skid
loader for two hours, you’re using this for whatever amount of
hours. This is included in our labor rate. We give somebody a labor
rate, that’s the labor rate. It includes the equipment.
However, nothing in the record indicates how Olmstead Construction calculated
the hourly labor rate.
16
Because Olmstead Construction failed to prove the actual costs associated
with use of its equipment, we affirm on this issue.
C. Attorney Fees.
The parties’ contract states that
any credit granted shall be paid promptly, in accordance with terms
and agreements (net 30 days), that the credit grantor may add one
and one half percent (1 1/2%) per month (18% per annum) to any
balance owed over 30 days, and in event of default, to pay
reasonable collection charges and/or attorney fees.
After the district court entered judgment in its favor on its breach-of-contract claim,
Olmstead Construction asked the district court to award it $94,575.45 in attorney
fees. The district court found it was reasonable to award Olmstead Construction
$47,787.73 in attorney fees, one-half the amount requested.
On appeal, Otter Creek does not dispute that the contract allows recovery
of attorney fees in the event of default. Nor does it dispute the reasonableness of
Olmstead Construction’s attorney fees. Instead, Otter Creek contends that
Olmstead Construction is not entitled to an award of attorney fees because
Olmstead Construction failed to perform under the implied terms of the contract.
Otter Creek argues that the contract required Olmstead Construction to
substantiate its costs as a condition precedent to payment and so Olmstead
Construction’s failure to do so excused Otter Creek from paying the final invoice.
On this basis, Otter Creek claims it did not default under the contract and Olmstead
Construction is not entitled to an award of its attorney fees.
The district court rejected Otter Creek’s claim that the implied terms of the
contract required Olmstead Construction to provide it with an accounting of the
costs it was charging. The court determined:
17
Element 3 requires that [Olmstead Construction] fulfill all of
the terms of the contract. [Olmstead Construction] argues that [it]
has completed the terms of the contract and therefore satisfied
element 3 of [its] breach of contract claim. [Otter Creek] claims that
[Olmstead Construction] has not satisfied element 3. [Otter Creek]
argues that [it] requested to know the specific items that constituted
the costs that were being claimed. [It] further argues that [Olmstead
Construction] failed to provide [it] with such costs and that such
failure constitutes a material breach of the contract. [Olmstead
Construction] argues that [it] provided all services required under the
agreement in accordance with industry standards and completed
construction of the project on February 26, 2016. The Court agrees
with [Olmstead Construction]. The Court finds that the overwhelming
evidence shows that [Olmstead Construction] was required to
complete certain construction tasks that were part of the overall
project. The Court further finds that [Olmstead Construction]
completed each and every task according to the agreement and in
accordance with industry standards. Therefore, the Court finds that
[Olmstead Construction] has proven element 3.
Otter Creek argues that Daniel Olmstead’s testimony supports its claim that
the implied terms of the contract required Olmstead Construction to confirm its
costs. On cross-examination, he testified:
Q. At the time that you signed this contract, May 14, 2014,
was Olmstead Construction willing to show documentation to support
the costs that it would incur? A. Yes.
Q. And would that documentation include invoices that you
paid from your sub and suppliers as well as evidence of what you
paid your employees? A. Yes.
Q. So do you agree that this contract at least assumed that
you would supply that documentation? A. Yes.
Q. And that gives your customer protection from a contractor
that might try to overcharge them for things that were not actually
incurred? A. That is correct.
Q. And it’s fair for a customer to ask to see those records to
find out whether or not they are being overcharged? A. Yes.
The evidence also suggests that Olmstead Construction’s common practice was
to include documentation of its costs with every invoice.
But Olmstead Construction never provided Otter Creek with the requested
documentation of its costs. Don Burd testified that Olmstead Construction did not
18
provide documentation of its costs until “way after the lawsuit was filed” and did
not document its labor costs or equipment rental costs until a month before trial.
Don Burd testified that he “didn’t really understand” the change in final cost listed
in the February 2016 and March 2016 invoices because he did not know what extra
costs Olmstead Construction was billing and it provided no documentation of these
costs. He also testified that when he learned that the total price of the contract
had risen nearly $200,000 from the last estimate, it stunned him and he “had no
idea that the costs were getting this out of whack.” Don Burd explained why he
did not pay the final invoice, testifying:
I was trying to decipher what the costs were. I
didn’t . . . understand what the extra costs were for which items, and
things had gotten mixed up here and there was no explanation, and
I had never received any explanation or invoices documenting the
cost through the whole project. So . . . until I figured this out of what
the costs were for, the extras from the original 962,535, . . . I didn’t
know really how to go about figuring this out. I was trying to figure it
out.
Q. What happened next? A. Let’s see. I believe Jenny [works
in office at Olmstead Construction] sent an email that she included
with this that if I had any questions to contact her or Dan [owner of
Olmstead Construction].
Q. What happened after that? A. . . . I was reviewing it so I
sent her back an email that said I would be reviewing this and I’d get
back with her.
Q. Okay. What happened next? A. I believe she sent me an
email that indicated that Dan was going to file a mechanic’s lien on
April 21st, I believe.
Q. I’ve put on the overhead what was attached to the
amended petition as Exhibit 1, and the Court can find that in the court
records. It looks like this mechanic’s lien was posted on April 12th,
2016. Does that comport with your recollection? A. Yeah, that looks
like it.
Q. What happened next? A. I was trying to figure out how to
go about getting these costs for these items on these invoices. I
hadn’t received any supplement cost or anything on the entire
project. The invoices were now no longer in the same categories as
the original documentation so it made it impossible for me to track
where my costs were, whether on the original one, whether concrete
19
was . . . what we agreed upon or whether it was less or whether it
was more, I didn’t know, high or low, . . . or what had gotten deleted.
There was no accounting of it.
Although the court rejected Otter Creek’s claim that Olmstead Construction
had to provide documentation of its costs, its ruling notes the problem with
Olmstead Construction’s billing practices:
One of the major problems to [Olmstead Construction] being paid in
accordance with the invoices has been [Olmstead Construction]’s
seeming inability to provide accurate invoices to [Otter Creek] in a
timely manner. At trial, [Olmstead Construction] has been able to
prove [its] expenses. However, there has been considerable
confusion regarding the invoices. Although communication
problems can rarely be attributed to one party, the confusion in the
instant case has overwhelmingly been due to the fault of [Olmstead
Construction]. Olmstead [Construction] submitted its first “final
invoice” to Otter Creek on or around February 9, 2016. This invoice
was withdrawn and revised. Olmstead [Construction] submitted its
second final invoice on February 12, 2016 (Exhibit 19). The e-mail
communication submitted with this invoice reflects that Don Burd
wanted all extras accounted for at the time of final payment. After
revising the final invoice a second time, another invoice dated March
1, 2016 was submitted (Exhibit 20). The total amount Olmstead
[Construction] alleged due on this invoice was $199,343.82. Don
Burd received this invoice Tuesday, March 22, via e-mail (Exhibit M).
At trial, [Olmstead Construction] claimed that the total amount owed
by [Otter Creek] was $252,572.14. It is no mystery that [Otter Creek]
was concerned about the accuracy of [Olmstead Construction]’s
billing practices given this level of confusion.
This observation highlights the problem with awarding Olmstead Construction
attorney fees. Is it fair to require Otter Creek to pay the final invoice without any
documentation as to the costs listed? Did Otter Creek’s desire to have an
accounting of those costs before paying cause it to default on the contract? And
if so, should it be required to pay Olmstead Construction’s attorney fees when
proper documentation could have revealed any errors in in the bill (such as the
20
double payment made to Streff Electric) and the parties could have addressed it
without resorting to legal action?
No Iowa case has addressed whether a cost-plus contract requires the
contractor to justify the expenses billed on a project. However, a cost-plus
contract, by nature, demands that the contractor maintain accurate and detailed
expense records. See, e.g., Joe Bonura, Inc. v. Hiern, 419 So. 2d 25, 29 (La. Ct.
App. 1982) (requiring a contractor to “itemize each and every expenditure made”);
Shaw v. Bula Cannon Shops, 38 So. 2d 916, 918 (Miss. 1949) (stating contractor
who agrees to perform on a cost-plus basis has a “duty to keep accurate and
correct accounts of all material used and labor performed”); Hitt v. Smallwood, 133
S.E. 503, 506 (Va. 1926) (same); 17A Am. Jur. 2d Contracts § 484 (“Under a cost-
plus contract, a contractor has the duty of itemizing expenditures made by him or
her on the job . . . .”); Albert Hamilton Dib, 1 Forms and Agreements for Architects,
Engineers and Contractors § 8:4, Westlaw FA-ARCHTCT (database updated June
2019) (“The cost-plus contractor is obliged to keep a detailed and accurate record
for audit purposes.”); Benjamin F. Sturgeon, Fiduciary Duties in Cost-Plus
Contracts for Construction, 34 Construction Law. 24, 28 (Winter 2014)
(“Contractors are held to an implied covenant of good faith and fair dealing and
must keep clear and accurate records that account for all of the supplies and labor
expended in each project.”); Paul J. Walstad, Sr. & Camille Williams, Contracting
on a Cost-Plus Basis: The Owner’s Relationship of Trust with the Contractor,
Construction Briefings No. 2000-12 (Dec. 2000) (noting most cases “impose upon
the contractor the obligation to keep accurate and detailed records of its
expenditures”). Contractors who fail to keep “meticulous cost records” may find
21
their expenses are not reimbursable. Walstad & Williams, supra. Likewise, costs
based on estimates or approximations of expenses are insufficient. See id.; see
also Arc Elec. Co. v. Esslinger-Lefler, Inc., 591 P.2d 989, 992 (Ariz. Ct. App. 1979)
(“The meaning of ‘costs’ is plain and definite in the sense that it denotes actual as
opposed to average costs. The party performing under a cost-plus contract must
keep a record of who worked on a given job and of his hourly wage.
Approximations and averages are insufficient.”); Freeman & Co. v. Bolt, 968 P.2d
247, 254 (Idaho Ct. App. 1998) (same). Rather, a contractor may only recover the
costs actually incurred. See Shaw, 38 So. 2d at 918 (requiring that a contractor
show the claimed expenditures “were necessarily paid for materials and work upon
the job” to recover). Therefore, a contractor may be required to present invoices
and statements of accounts accompanied by proof of payment. See M. Carbine
Restoration, Ltd. v. Sutherlin, 544 So. 2d 455, 458–59 (La. Ct. App. 1989), writ
denied, 547 So. 2d 355 (La. 1989); 17A Am. Jur. 2d Contracts § 484.
Keeping detailed records allows the owner to check on the contractor’s
expenditures. See Shaw, 38 So. 2d at 918; William Garth Snider, Defamation
Claims in Construction Litigation, Construction Briefings No. 2000-7 (July 2000)
(noting an owner can always challenge the reasonableness of costs incurred).
Therefore, any contract requiring an owner to reimburse a contractor’s costs
implicitly allows the owner to approve the contractor’s accounting system and audit
contract costs and pricing data. See 1 Bruner & O’Connor on Construction Law
§ 2:26; see also Dib, 1 Forms and Agreements for Architects, Engineers and
Contractors § 8:4 (“An owner who lets out a cost-plus job normally requires the
contractor to use owner’s approved accounting system or ‘chart of accounts,’ so
22
that contractor’s records may be readily audited.”). And if the owner disputes the
billing, the burden is on the contractor to prove “each and every item of expense.”
Joe Bonura, Inc., 419 So. 2d at 29; see also 17A Am. Jur. 2d Contracts § 484.
In Sherwood Distilling Co. v. Ryan, 190 F.2d 314, 321 (Emer. Ct. App.
1951), a government contractor asked the court to review the Department of
Commerce’s orders and regulations governing its cost-plus contract for the
production of ethyl alcohol. In rejecting the contractor’s argument about the
department’s audits of its costs, the court noted that such audits were “obviously
necessary” if the department was to pay based on the contractor’s own statement
of cost. Sherwood Distilling, 190 F.2d at 319. The court observed “that it is the
duty of a contractor under a contract on a cost-plus basis to keep adequate records
to justify the actual costs reported and further to keep the usual documents to
substantiate its claims for reimbursement.” Id. at 321. The court then noted the
contractor’s failure to keep such documents “is the cause of much of the
controversy in this case.” Id. The same is true here. Had Olmstead Construction
provided the explanation of costs Otter Creek requested, it would have eliminated
much of the confusion regarding the Streff Electric invoices and, perhaps, the
litigation in its entirety.
Otter Creek was not required to make final payment until Olmstead
Construction provided the requested documentation of its costs. Because Otter
Creek did not default under the agreement, Olmstead Construction is not entitled
to an award of its attorney fees under the contract, and we reverse the award of
$47,787.73 in attorney fees.
23
D. Prejudgment Interest.
Olmstead Construction contends it is entitled to prejudgment interest on its
contract damages. It argues that interest should begin when damages are
complete—here, thirty days after it issued the final invoice. In the alternative, it
requested interest begin to run on the day it filed the action.
Generally, interest on unliquidated damages becomes due and payable on
the date of judgment. See Brenton Nat’l Bank of Des Moines v. Ross, 492 N.W.2d
441, 443 (Iowa Ct. App. 1992). An exception occurs when damages are complete
at a specific time, in which case interest runs from that time. See id. That
exception is inapplicable, however, when a genuine dispute exists between the
parties as to the amount of damages. See id; 13 Am. Jur. 2d Building and
Construction Contracts § 88 (“[P]rejudgment interest will not be allowed on such
claims . . . where a serious and substantial controversy exists as to the amount
due under the contract.”).
The district court determined that interest did not become recoverable until
it entered final judgment because “damages were not complete at any specified
time before the trial” and “the amount remained in controversy until the Court
issued its final judgment.” Under these circumstances, prejudgment interest is
inappropriate. We therefore affirm on this issue.
III. Mechanic’s Lien.
Olmstead Construction also appeals the denial of its petition to enforce the
mechanic’s lien. It contends it met all the statutory requirements for foreclosure
and it is therefore entitled to foreclose on the lien. We review actions to enforce a
mechanic’s liens de novo. See Flynn Builders, L.C. v. Lande, 814 N.W.2d 542,
24
545 (Iowa 2012). On de novo review, we give weight to the district court’s factual
findings although they are not binding. See id.
In denying Olmstead Construction’s petition to enforce its mechanic’s lien,
the district court again observed that Olmstead Construction’s billing led to a
genuine dispute over how much Otter Creek owed it. Rather than clarifying its
invoice to Otter Creek, Olmstead Construction filed a mechanic’s lien and initiated
proceedings to foreclose on the lien. The court determined that “nothing in the
statute . . . requires that the parties reach an agreement regarding the amount of
money in dispute prior to filing a mechanic’s lien.” However, it denied Olmstead
Construction’s petition on equitable principles, concluding that “a plaintiff should
not be permitted to invoice a defendant for an unsubstantiated amount of money
and then subsequently foreclose on the defendant’s property without providing the
defendant with proof that the amount invoiced is actually valid.” In denying
Olmstead Construction’s motion to reconsider on this issue, the court reiterated its
conclusion, stating, “[Olmstead Construction] is largely responsible for creating this
dispute due to their confusing and inaccurate billing. [Olmstead Construction]
proposes foreclosure on the mechanic’s lien. If the Court granted such
foreclosure, it would amount to an extremely inequitable solution to a problem that
is largely of [Olmstead Construction]’s own making.”
Our mechanic’s lien statute allows one who contracts with a landowner and
furnishes material or performs labor to improve the land to place a lien on that land
to secure payment. Iowa Code § 572.2 (2016). To perfect the lien, one must post
a verified statement of account to the mechanics’ notice and lien registry within two
years and ninety days of the date on which material was last furnished or labor
25
was last performed. Id. §§ 572.8, .9. Once the mechanic’s lien is perfected, a
party may initiate an action to enforce it. Id. § 572.24.
The purpose of a mechanic’s lien
is to protect persons who have supplied labor or material for the
improvement of real property by giving the lienholder security
independent of their contractual remedies against the owner of the
land. The principle underlying the mechanic’s lien statute is that a
party who materially increases the value of the owner’s property is
entitled to look to the improved property as security for the effort.
Winger Contracting Co. v. Cargill, Inc., 926 N.W.2d 526, 535 (Iowa 2019) (cleaned
up) (citing Roger W. Stone, Mechanic’s Liens in Iowa, 30 Drake L. Rev. 39, 41
(1980)). We liberally construe the mechanic’s lien statute “with a view to promote
its objects and assist the parties in obtaining justice.” Iowa Code § 4.2. We also
allow set-offs and counterclaims “to permit complete determination of the rights of
the parties arising from a single transaction in the same action.” Capitol City
Drywall Corp. v. C. G. Smith Const. Co., 270 N.W.2d 608, 611 (Iowa 1978).
Olmstead Construction has met the statutory requirements to foreclose on
its mechanic’s lien. However, we have flexibility in determining an equitable
remedy. See Hosteng Concrete & Gravel, Inc. v. Tullar, 524 N.W.2d 445, 448
(Iowa Ct. App. 1994). “In questions of equity, the court has broad discretion to
consider the hardship its orders would cause the defendant. Under the relative
hardship doctrine, a court of equity should not grant an award that would be
disproportionate in its harm to the defendant and its assistance to the plaintiff.”
27A Am. Jur. 2d Equity § 102.
The record shows Otter Creek has paid $115,000 in satisfaction of
judgment. Because we reduced the amount of the judgment entered in Olmstead
26
Construction’s favor to $115,245.84, foreclosing on the mechanic’s lien would
disproportionately harm Otter Creek by forcing it to sell property that cost in excess
of $1,000,000 in satisfaction of a $245.84 judgment. Noting that the delay in Otter
Creek’s payment is due largely to Olmstead Construction’s billing practices, we
grant Otter Creek thirty days from the date we file this opinion to satisfy the
remaining judgment due of $245.84. If Otter Creek satisfies the judgment in this
time, there is nothing owed on the contract, and Olmstead Construction is not
entitled to foreclose on the mechanic’s lien. See Bidwell v. Midwest Solariums,
Inc., 543 N.W.2d 293, 297 (Iowa Ct. App. 1995) (holding that when owner’s
damages exceeded that of the contractor such that the contractor is “in a negative
position,” “[i]t goes without saying” that the contractor is not entitled to foreclose on
its mechanic’s lien). If Otter Creek fails to satisfy the judgment in full within thirty
days, the court shall grant Olmstead Construction’s petition to foreclose on the
mechanic’s lien.
IV. Conclusion.
We affirm the entry of judgment in favor of Olmstead Construction but
reverse the award of $48,150 in damages and $47,787.73 in attorney fees to
Olmstead Construction. We conditionally affirm the denial of Olmstead
Construction’s petition to foreclose on its mechanic’s lien, and we affirm the district
court in all other respects. Finally, we remand the case for further proceedings in
conformance with this opinion. Costs of the appeal are taxed to Olmstead
Construction.
AFFIRMED IN PART AND REVERSED IN PART ON APPEAL;
CONDITIONALLY AFFIRMED ON CROSS-APPEAL; AND REMANDED.