C. H. Heist Ohio Corp. v. Bethlehem Steel Co.

Per Curiam.

This, is an appeal by C. H. Heist Ohio Corporation, hereinafter called “ Heist ”, from an order which granted summary judgment in favor of Bethlehem Steel Company, hereinafter called “Bethlehem” and from a judgment based upon the order.

Allied Material Supply Company, hereinafter called ‘ ‘ Allied ’ ’, entered into a prime contract for certain construction with “ Bethlehem ” on September 27, 1961. Article Sixth of that agreement reads as follows: “The Contractor shall promptly pay all just claims for labor, material, or otherwise in and about the performance of the Work and the Contractor expressly covenants and agrees that no liens .shall be filed either by the Contractor or by any subcontractor, workman or materialman, against the property of the Company or the property of any other of the Bethlehem Companies (as that term is hereinafter defined in Clause Seventh hereof) for any work done or materials furnished in or for the performance of the *203Work. The Contractor further agrees that if, notwithstanding the foregoing covenant, any liens should be filed by any subcontractor, workman or materialman against the property of the Company or of any other of the Bethlehem Companies or any part thereof or in case any attachment, mesne or otherwise, should be levied by any such subcontractor, workman or materialman against any moneys then due or to become due to the Contractor from the Company under this Agreement, it, the Contractor, will promptly discharge by bond or otherwise ■such lien or attachment and indemnify and protect each of the Bethlehem Companies against any loss or expense in connection therewith, including in .such expense counsel fees which any of the Bethlehem Companies may reasonably incur for its protection. And as further protection to each of the Bethlehem Companies, the Contractor agrees that in case the Company shall at any time have reason to believe that the Contractor has not paid or is not paying all proper claims for labor and material done or furnished in or about the performance of the Work, which claims might under any law or statute form the basis of a lien against the property of the Company or of any other of the Bethlehem Companies, the Company may at its option withhold all or any part of any moneys then or thereafter due the Contractor hereunder until it shall have been furnished with a certificate from the proper public officials that there are no such liens undischarged of record and reasonably convincing proof that there are no unsettled claims which may become liens. In case the Contractor fails to pay such claims within thirty (30) days after payment of the same shall be due, the Company may at its option pay out of the moneys so retained the amount of such claims and the amount so paid shall be considered as payment on account of moneys due or to become due the Contractor hereunder.”

“Heist” entered into a subcontract with “Allied” on October 17, 1961. Article 5 of that subcontract provided as follows: “All terms and conditions of the Owner’s Standard Contract 2500 with the Contractor will become a part of this agreement.”

Special Term found that article Sixth of the prime contract was incorporated in the subcontract and that this constituted the express waiver by “ Heist ” to file a mechanic’s lien required by section 34 of the Lien Law.

With this we disagree. Section 34 of the Lien Law reads as follows: “ A contractor, subcontractor, material man or laborer may not waive his lien, except by an express agreement in writing specifically to that effect, signed by him or his agent.”

*204Without question the pertinent provisions of the prime contract were by reference incorporated in the subcontract. (4 Williston, Contracts [Jaeger ed.], § 628; Matter of Board of Comrs. of Washington Park of City of Albany, 52 K Y. 131.)

Before the adoption of section 34 of the Lien Law in 1929 there had existed some confusion as to' the effect of various types of clauses and contracts whereby owners required potential lienors to waive their right to file a notice of lien. This section has settled these questions and sets forth clearly and distinctly the only manner in which the class favored by the Lien Law may waive the right to file a lien. (Blanc, Mechanics Liens, §§ 10-a, 10-b.)

By incorporating article Sixth of the prime contract in the subcontract in hcec verba, we have in the subcontract an express covenant of the contractor (Allied) that no lien will be filed by it or any subcontractor. “ Allied ” cannot deprive “ Heist ” of its right to file a lien by an agreement with Bethlehem (North American Iron Works v. De Kimpe, Inc., 232 App. Div. 579.)

Section 34 requires in order that the right to file a lien be waived, an express agreement in writing specifically to that effect. The intention to waive that right must by the agreement be clear and unequivocal. (Cieri Constr. Co. v. Gramercy Constr. Corp., 13 A D 2d 901.)

Reading article Sixth of the prime contract in its entirety makes it clear that it was only “ Allied ” agreeing to various things as to the filing of liens including its obligation to Bethlehem ” in the event liens were filed by subcontractors. By the terms of this article, it is apparent that Bethlehem ” was looking to Allied ” for protection. This article when incorporated in the subcontract does not constitute an express agreement showing a clear and unequivocal intent on the part of 1 ‘ Heist ’ ’ to waive the right to file a lien which is required.

The judgment and order should be reversed and the motion denied.