OPINION
CAFFREY, District Judge.This matter came before the Court on petitioner’s motion for summary judgment, which motion was briefed and orally argued by the parties. After hearing I rule as follows:
This is a civil action. Jurisdiction of this court is invoked on the basis of 40 U.S.C.A. § 270b(b) and 9 U.S.C.A. § 4. On June 15, 1966, the United States, acting by the Department of the Navy, entered into a contract with respondent Edward R. Marden Corp., under the terms of which Marden agreed to furnish all labor and materials required for the construction of an aircraft maintenance facility at the United States Naval Air Station, South Weymouth, Massachusetts, for $2,169,600. Respondents Marden, Planet Insurance Company, a corporation organized under the laws of Wisconsin, and American Re-Insurance Company, a corporation organized under the laws of New York, executed standard form payment bonds to the United States whereby Marden, as principal, and Planet and American, as sureties, bound themselves jointly and severally in the sum of $867,840, for the prompt payment of all persons supplying labor and materials in the prosecution of the work called for in the prime contract and any and all duly authorized modifications thereof. The sureties waived notice of any such modifications. *142Thereafter, during the months of August through December 1966, the plaintiff, Wrecking Corporation of America, a corporation organized under the laws of Ohio, performed certain work and labor at an agreed price of $235,000 on the basis of a subcontract between it and Marden. The complaint recites that plaintiff was a subcontractor of Marden and that the work done by it was work required to be done by Marden under its prime contract with the United States. It further recites that Marden has failed and refused to pay the plaintiff the sum of $52,673, despite plaintiff’s completion of the work and timely demand for payment. Finally, the complaint recites that Article 21 of its subcontract with Marden provides for arbitration of any dispute with reference to the subcontract. Wherefore, plaintiff seeks an order compelling Marden to arbitrate their differences over the performance of and the amounts due under the subcontract, and an order that respondents Planet and American pay whatever sum is established as due from Marden to plaintiff.
(1) Plaintiff’s motion for summary judgment must be denied as against respondents Planet and American, because the Miller Act, 40 U.S.C.A. § 270b (b), places a one-year limitation on actions against sureties, after which their contingent liability ceases. No action may be maintained against them unless commenced within one year from the completion of the work on the contract. In this case the work was completed, according to the allegations of the complaint, in December 1966 and, thus, one year therefrom expired in December 1967. The complaint was not filed until April 8, 1968, several months after the statute of limitations had run as to respondents Planet and American.
The Court of Appeals for the Eighth Circuit ruled, over fifty years ago, that the one-year statute of limitations “is not merely a limitation on the remedy but on the liability itself.” United States, to Use of Gibson Lumber Co. v. Boomer, 183 F. 726 (1910). This ruling has been followed by the Court of Appeals for the Sixth Circuit, in United States, f/u/b/o Statham Instruments, Inc. v. Western Casualty & Surety Co., 359 F.2d 521 (1966), and by the Court of Appeals for the Third Circuit in United States, f/u/b/o Soda v. Montgomery, 253 F.2d 509 (1958). See, also, United States f/u/b/o M. A. Hartnett, Inc. v. Enterprise Engineering & Construction Co., 169 F.Supp. 131 (D.Del.1958); United States, f/u/b/o B. Katchen Iron Works, Inc. v. Standard Accident Insurance Co., 158 F.Supp. 616 (D.N.J.1958), aff'd 257 F.2d 78.
The cases relied on by plaintiff, such as United States, f/u/b/o Industrial Engineering & Metal Fabricators v. Eric Elevator Corp., 214 F.Supp. 947 (D.Mass.1963), and Agostini Brothers Building Corp. v. United States on Behalf of and For Use of Virginia-Carolina Electrical Works, 142 F.2d 854 (4th Cir. 1944), establish only that there is no inconsistency between the provisions of Title 9, U.S.C.A. secs. 1-14, and Title 40, U.S.C.A. §§ 270a-270e. No case cited by plaintiff is authority for the proposition that invocation of arbitration under 9 U.S.C.A. §§ 2 and 4 dispenses with the operation of the statute of limitations contained in the Miller Act, 40 U. S.C.A. § 270b(b), and nothing in those cases indicates that the actions therein were filed subsequent to the expiration of the one-year period of limitation.
It should be added that there is nothing contained in the waiver by the sureties of notice of “all duly authorized modifications of said contract that may hereafter be made” that operates as a waiver by the sureties of the provisions of 40 U.S.C.A. § 270b (b), nor is there any suggestion that the contract was ever modified in such a way as to include a waiver of said section.
(2) It appearing that there is diversity of citizenship as between petitioner and respondent Marden, and that more than $10,000 is involved, the motion for summary judgment is allowed as to Marden and an order will be entered directing Marden to proceed forth*143with with arbitration of its controversy with Wrecking Corporation of America in accordance with the terms of the subcontract, and dismissing the complaint as against respondents Planet and American.