FILED
Dec 27 2023, 8:52 am
CLERK
Indiana Supreme Court
Court of Appeals
and Tax Court
ATTORNEYS FOR APPELLANTS ATTORNEYS FOR APPELLEE
Maggie L. Smith David L. Guevara
Joshua N. Kutch James R. A. Dawson
Indianapolis, Indiana Indianapolis, Indiana
Heather M. Hawkins
Cincinnati, Ohio
IN THE
COURT OF APPEALS OF INDIANA
Professional Construction, Inc., December 27, 2023
and West Bend Mutual Court of Appeals Case No.
Insurance Company, 23A-PL-654
Appellants-Defendants, Appeal from the Marion Superior
Court
v. The Honorable Heather A. Welch,
Judge
Historic Walnut Square, LLC, Trial Court Cause No.
Appellee-Plaintiff 49D01-2206-PL-21757
Opinion by Chief Judge Altice
Judges May and Foley concur.
Altice, Chief Judge.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 1 of 20
Case Summary
[1] Professional Construction, Inc. (Contractor) and West Bend Mutual Insurance
Company (Surety) (collectively, Appellants) bring this interlocutory appeal of
the trial court’s denial of their motion to enforce arbitration agreement and stay
litigation in a lawsuit brought by Historic Walnut Square, LLC (Owner).
Appellants present the following restated issues for review:
1. Did the trial court properly determine that Contractor waived
its contractual right to demand arbitration by filing suit
against Owner in Wisconsin?
2. Did the trial court err by determining that Surety had no right
to enforce the arbitration provision in the construction
contract?
3. Where is the proper venue for arbitration?
[2] We reverse and remand.
Facts & Procedural History
[3] In 2020, Owner solicited bids for a construction project for the development of
a forty-unit, multi-family housing project in Terre Haute and ultimately selected
Contractor as general contractor for the project. On August 6, 2020, they
executed two standard form American Institute of Architects (AIA)
agreements, A101-2017 and A201-2017 (collectively, the Construction
Contract). Additionally, Contractor obtained a Payment Bond and a
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 2 of 20
Performance Bond (collectively, the Bonds), also AIA standard form
agreements, through Surety in the amount of the Construction Contract.
[4] The Construction Contract provides for binding arbitration, pursuant to § 15.4
of AIA Document A201-2017, of any claim subject to or not resolved by
mediation and expressly indicates that the Federal Arbitration Act (the FAA)
shall govern. § 15.4.1 provides in relevant part:
[A]ny claim subject to, but not resolved by, mediation shall be
subject to arbitration which, unless the parties mutually agree
otherwise, shall be administered by the American Arbitration
Association in accordance with its Construction Industry
Arbitration Rules in effect on the date of the Agreement. The
Arbitration shall be conducted in Fond du Lac County,
Wisconsin unless expressly prohibited by law, in which case
mediation [sic] shall be held in the place where the Project is
located, unless another location is mutually agreed upon. A
demand for arbitration shall be made in writing, delivered to the
other party to the Contract, and filed with the person or entity
administering the arbitration.
Appellants’ Appendix Vol. 2 at 111. Further, pursuant to § 15.4.3, the agreement
to arbitrate “shall be specifically enforceable under applicable law in any court
having jurisdiction thereof.” Id.
[5] Certain contractual disputes arose between Contractor and Owner and came to
a head in the beginning of 2022. The details of the disputes are not particularly
relevant here; our focus is on the parties’ attempts to resolve them. Contractor
initially communicated its claim to the architect (Architect) – the project’s
initial decision maker under the Construction Contract. Unsatisfied with
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 3 of 20
Architect’s decision and anticipating a breach of the Construction Contract by
Owner, Contractor stopped work on the project on February 11, 2022. Owner
then declared Contractor in default and made a claim against Surety on the
Performance Bond.
[6] On February 14, 2022, Contractor (by email and certified mail) sent a written
demand for mediation/arbitration to Owner and Architect. After setting out
Contractor’s position in detail, the letter concluded with the following:
Demand for Mediation/ Arbitration
Given the Owner’s position, and the Architect’s decision to affirm the
Owner’s position, concerning the substantial completion date, pursuant to §§ 15.3
and 15.4 of the Construction Contract, PCI hereby demands mediation and
arbitration of the current dispute between the parties.
Pertinent sections dealing with mediation and arbitration in the
Construction Contract, call for mediation to be administered by the American
Arbitration Association ("AAA"). We are not opposed to this prescription,
however, due to the likely urgency of the matter, PCI would consider using an
alternate mediation agency or mediator. Please advise on your position on this as
soon as possible. If we do not hear back from you by February 17, 2022, we will
assume the Owner’s preference is to have the matter handled by an AAA
mediator, and we will file the mediation/ arbitration demand with the AAA.
Appellants’ Appendix Vol. 3 at 46 (emphases in original).
[7] Surety quickly followed Contractor’s demand for mediation/arbitration with a
letter to Owner requesting a meeting in Wisconsin with decision makers for all
parties present, along with Architect. On February 23, Owner responded and
proposed “a meeting that does not involve the Contractor or the sideshow of
topics, such as liquidated damages, which are unrelated to the immediate goal
of performing and completing the Construction Contract.” Id. at 22.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 4 of 20
[8] On February 27, Surety wrote Owner again and emphasized that there were
issues between Owner and Contractor that were “worth mediating” and that
resolving these issues was “critical” to Surety’s decision regarding the claim on
the Performance Bond. Id. at 25, 26. Surety proposed that all parties meet on
March 4 and agree to prompt mediation of any issues not resolved at that
meeting.
[9] On March 1, Owner responded that it would not entertain Contractor’s input in
the matter between Owner and Surety, explaining in part:
Right now, and while the Owner attempts to recover the Project
from the Contractor’s defective, untimely performance, there is
nothing to mediate. The Owner is open to negotiations and
engaging a third party mediator to resolve any remaining claims,
but only after the Owner and Surety have all of the relevant
information, the Surety performs its obligations under the
Performance Bond, and the Work is complete. It is only then
that the parties may be able to bring this matter to a full, final
resolution. Mediation efforts now would be premature and waste
precious time.
Id. at 30.
[10] On April 17, 2022, Surety denied Owner’s claims on the Bonds and provided a
detailed explanation of its denial. In summary, Surety claimed that Owner had
repudiated the Construction Contract prior to Contractor justifiably stopping
work and that Owner’s subsequent refusal to mediate or arbitrate the dispute
between Contractor and Owner also constituted a breach of the Construction
Contract.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 5 of 20
[11] Two days after Surety’s denial of Owner’s claims, Contractor filed a four-count
complaint against Owner in Waukesha County, Wisconsin 1 (the Wisconsin
Action), and named Surety as an involuntary plaintiff. Relevant here, the
complaint alleged that Owner had refused Contractor’s written demand for
mediation/arbitration of the claims and disputes arising out of the Construction
Contract and that “[b]ecause of [Owner’s] contractual breaches and refusal to
mediate or arbitrate, [Contractor] has been left with no recourse except
litigation to seek resolution of the claims.” Appellants’ Appendix Vol. 2 at 176.
Among its specific requests for relief, Contractor asked the Wisconsin court for:
“Order compelling [Owner] to comply with the Contract’s mediation and
arbitration clauses as it relates to all claims arising of the contract.” Id. at 179.
[12] Two months after the Wisconsin Action was filed, Owner filed the instant
complaint in Marion County, Indiana, on June 29, 2022, against Contractor
and Surety (the Indiana Action). Owner asserted breach of contract and other
associated claims and argued that Indiana was the proper venue for litigation
related to the Construction Contract and the Bonds. Owner’s complaint for
damages made no mention of the dispute resolution provisions in the
Construction Contract.
[13] On July 1, 2022, in the Wisconsin Action, Owner filed a motion to stay or, in
the alternative, dismiss without prejudice. Owner argued that Indiana was the
1
Contractor, Owner, and Surety are each organized under the laws of Wisconsin with their principal places
of business there.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 6 of 20
more convenient forum to address the parties’ claims that all “relate to disputes
concerning the interpretation and enforcement of the Construction Contract
and Bonds, which relate to the Project in Indiana.” Id. at 196.
[14] Contractor responded in both pending actions to Owner’s attempt to litigate the
contractual disputes in Indiana. First, in the Wisconsin Action, Contractor
filed a motion to compel arbitration. Second, in the Indiana Action, it filed
jointly with Surety a motion to enforce arbitration agreement and stay litigation
pending arbitration. Owner opposed both motions on two bases: 1) Contractor
did not satisfy the mandatory conditions precedent to trigger arbitration under
the Construction Contract and 2) Contractor waived its right to enforce the
arbitration provision by filing the Wisconsin Action. 2
[15] The Wisconsin court was the first to hold a hearing and decide the motions
pending before it. At the conclusion of the hearing on February 10, 2023, the
Wisconsin court ordered Owner and Contractor to arbitration in Wisconsin.
This order was based on three conclusions by the court: 1) Contractor did not
waive its right to arbitration by filing its complaint, which was “in essence, a
suit to enforce the arbitration clause”; 2) matters of procedural arbitrability,
such as whether conditions precedent have been satisfied, are for the arbitrator
2
In the Indiana Action, Owner additionally argued that Surety did not have a contractual right to compel
arbitration of Owner’s claims under the Bonds.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 7 of 20
to decide; and 3) the proper venue for the arbitration is Wisconsin. 3 Appellants’
Appendix Vol. 3 at 112. Owner did not appeal the Wisconsin court’s arbitration
ruling, which was reduced to written order on March 6, 2023.
[16] In the meantime, a hearing was held in the Indiana Action on February 23,
2023, to address Appellants’ motion to enforce arbitration agreement and stay
litigation pending arbitration. The trial court denied the motion and issued a
written order that same day. Specifically, the trial court determined that
Contractor waived its contractual right to arbitration by initiating the
Wisconsin Action rather than filing for mediation or arbitration with the AAA.
Further, the court determined that Appellants could not “get around”
Contractor’s waiver by arguing that Surety had a right to enforce the arbitration
provision in the Construction Contract. Appellants’ Appendix Vol. 2 at 24. The
trial court denied Appellants’ subsequent request to reconsider its ruling
regarding arbitration.
[17] Appellants now appeal the trial court’s February 23, 2023 interlocutory order as
a matter of right pursuant to Ind. Appellate Rule 14(D) and Ind. Code § 34-57-
2-19(a)(1). 4 Additional information will be provided below as needed.
3
The parties agreed that the arbitration order would not extend to Surety. However, Surety acknowledged
that it would be bound by any contractual determinations made by the arbitrator regarding the Construction
Contract.
4
During the pendency of this appeal, the arbitration process began in Wisconsin. On July 28, 2023, Owner
filed with the arbitrator a motion to stay the arbitration pending resolution of this appeal. The arbitrator
denied this request on October 25, 2023, and directed the arbitration to proceed expeditiously.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 8 of 20
Standard of Review
[18] Our Supreme Court has made clear that we do not defer to a trial court’s
decision on a motion to compel but rather review it de novo. Decker v. Star Fin.
Grp., Inc., 204 N.E.3d 918, 921 (Ind. 2023); Doe v. Carmel Operator, LLC, 160
N.E.3d 518, 521 (Ind. 2021). And we have applied this standard of review
when determining whether a party waived its contractual right to request
arbitration. 5 Welty Bldg. Co. v. Indy Fedreau Co., LLC, 985 N.E.2d 792, 798 (Ind.
Ct. App. 2013) (observing that although waiver is generally a question of fact,
we review de novo a trial court’s ruling on a motion to compel arbitration).
This is especially true where, as here, “to the extent the trial court had to
resolve a ‘factual’ issue regarding waiver, it did so based entirely upon a paper
record.” Id.
Discussion & Decision
1. Waiver of Contractual Right to Demand Arbitration
[19] The parties do not dispute that the traditional threshold issues of arbitrability
have been met in this case. That is, Owner and Contractor agreed in the
Construction Contract to arbitrate, and their agreement covers the particular
5
We reject Owner’s invitation to adopt a different standard of review, a clear error standard. Moreover,
contrary to Owner’s apparent suggestion on appeal, the Seventh Circuit does not review a district court’s
ultimate waiver determination in this context for clear error. See Cooper v. Asset Acceptance, LLC, 532 F. App’x
639, 641 (7th Cir. 2013) (“While the factual findings that led to the district court’s conclusion are reviewed
for clear error, ‘the question of whether [Asset’s] conduct amounts to waiver is reviewed de novo.’”) (quoting
Kawasaki Heavy Indus., Ltd. v. Bombardier Recreational Prods., Inc., 660 F.3d 988, 994 (7th Cir. 2011)).
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 9 of 20
controversy at issue. Their disagreement is focused on whether Contractor
waived its right to demand arbitration by pursuing the Wisconsin Action.
1.1 Is Waiver by Litigation Conduct an Issue for the Court to Decide?
[20] Directing us to the following language by the U.S. Supreme Court, Contractor
argues that the waiver determination must be made by the arbitrator, not the
court:
The Arbitration Act establishes that, as a matter of federal law,
any doubts concerning the scope of arbitrable issues should be
resolved in favor of arbitration, whether the problem at hand is
the construction of the contract language itself or an allegation
of waiver, delay, or a like defense to arbitrability.
Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983)
(emphasis added); see also BG Grp., PLC v. Republic of Argentina, 572 U.S. 25, 34-
35 (2014) (explaining that courts presume that parties intend for arbitrators, not
courts, to decide “procedural matters includ[ing] waiver, delay, or a like defense
to arbitrability”) (internal quotations omitted); Howsam v. Dean Witter Reynolds,
Inc., 537 U.S. 79, 84 (2002) (recognizing the presumption that “the arbitrator
should decide allegations of waiver, delay, or a like defense to arbitrability”)
(internal quotations and brackets omitted); Lumbermens Mut. Cas. Co. v.
Broadspire Mgmt. Servs., Inc., 623 F.3d 476, 480 (7th Cir. 2010) (“Under Howsam,
questions such as whether prerequisites to arbitration have been met, or
questions of waiver, delay, or other defenses to arbitrability, should be
determined by the arbitrator.”).
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 10 of 20
[21] The flaw with Contractor’s argument is that it improperly lumps waiver by
litigation conduct in the same bucket as waiver in the contractual sense. The
United States District Court for the Northern District of Illinois thoroughly
addressed the two distinct meanings of the word “waiver” and rejected the
same argument asserted by Contractor:
The pertinent meaning here concerns waiver through litigation
conduct or delay. The second meaning refers to a doctrine of
contract law under which “the conduct of the party” shows an
“intentional relinquishment of a known right.” Ryder v. Bank of
Hickory Hills, 585 N.E.2d 46, 49 (Ill. 1991); see also Abellan v.
Lavelo Prop. Mgmt., LLC, 948 F.3d 820, 830 (7th Cir. 2020)
(explaining that the waiver defense “admits the alleged breach
but can defeat a remedy”). Closely related to this second
meaning of waiver is the equitable defense of laches, which the
Supreme Court of Illinois has defined as “a neglect or omission
to assert a right, taken in conjunction with a lapse of time of
more or less duration, and other circumstances causing prejudice
to an adverse party.” Sundance Homes, Inc. v. Cnty. of DuPage, 746
N.E.2d 254, 262 (Ill. 2001). Like the contractual doctrine of
waiver, laches “bars the remedy but does not discharge the
right.” Halcon Int’l, Inc. v. Monsanto Austl. Ltd., 446 F.2d 156, 159
(7th Cir. 1971).
Moses Cone concerned the contractual meaning of waiver, not the
litigation conduct meaning. Although the Seventh Circuit has
not expressly so held, it has continued after Moses Cone and
Howsam to address whether a party invoking an arbitration clause
has waived arbitration through litigation conduct or delay. See,
e.g., Brickstructures, Inc. v. Coiaster Dynamix, Inc., 952 F.3d 887,
891 (7th Cir. 2020); Smith v. GC Servs. Ltd. P’ship, 907 F.3d 495,
499 (7th Cir. 2018); Kawasaki Heavy Indus., Ltd. v. Bombardier
Recreational Prods., Inc., 660 F.3d 988, 994 (7th Cir. 2011)…. In
fact, years before Moses Cone was decided, the Seventh Circuit
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 11 of 20
expressly distinguished between “‘[w]aiver’ in the laches or
estoppel sense, rather than in the default sense or participating in
judicial proceedings.” Halcon, 446 F.2d at 161. Anticipating
Moses Cone, the Seventh Circuit held that laches or estoppel issues
were for the arbitrator, id. at 159 (holding that “[t]he defense of
laches [is] a matter for the determination of the arbitrators”), but
made clear that waiver through litigation conduct is reserved for
the court, id. at 161 (“Section 3 [of the FAA] expressly gives the
courts jurisdiction to determine the existence of a default.”).
The circuits to have addressed the issue overwhelmingly agree
that Moses Cone and Howsam concern only the contractual sense
of waiver. See Martin v. Yasuda, 829 F.3d 1118, 1123 (9th Cir.
2016) (“[U]nder Howsam, the question [of waiver through
litigation conduct or delay] is presumptively for a court and not
an arbitrator to decide. Every circuit that has addressed this
issue—whether a district court or an arbitrator should decide if a
party waived its right to arbitrate through litigation conducted
before the district court—has reached the same conclusion.”)
(citation omitted); Grigsby & Assocs., Inc. v. M Sec. Inv., 664 F.3d
1350, 1353 (11th Cir. 2011) (“[I]t is presumptively for the courts
to adjudicate disputes about whether a party, by earlier litigating
in court, has waived the right to arbitrate.”); JPD, Inc. v.
Chronimed Holdings, Inc., 539 F.3d 388, 394 (6th Cir. 2008)
(“Unlike contractually-based waiver, courts have long decided
whether conduct inconsistent with reliance on an arbitration
agreement waives a defendant’s ability to seek an arbitration
referral ....”); Ehleiter v. Grapetree Shores, Inc., 482 F.3d 207, 219
(3d Cir. 2007) (“Properly considered within the context of the
entire opinion ... the [Howsam] Court was referring only to
waiver, delay, or like defenses arising from non-compliance with
contractual conditions precedent to arbitration ... and not to
claims of waiver based on active litigation in court.”); Marie v.
Allied Home Mortg. Corp., 402 F.3d 1, 11-13 (1st Cir. 2005)
(distinguishing a “contractual time limit clause,” which is
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 12 of 20
“presumed to be for the arbitrator” under Howsam, from waiver
“due to litigation-related activity,” which courts decide).
Lukis v. Whitepages Inc., 535 F. Supp. 3d 775, 786-87 (N.D. Ill. 2021) (citations
altered to omit parallel citations and to include full citations as needed).
[22] We fully agree with the district court’s assessment in Lukis. Moreover, we
would add that the U.S. Supreme Court has recently addressed the standard
courts should apply when determining waiver through litigation conduct:
When a party who has agreed to arbitrate a dispute instead brings
a lawsuit, the Federal Arbitration Act (FAA) entitles the
defendant to file an application to stay the litigation. See 9
U.S.C. § 3. But defendants do not always seek that relief right
away. Sometimes, they engage in months, or even years, of
litigation—filing motions to dismiss, answering complaints, and
discussing settlement—before deciding they would fare better in
arbitration. When that happens, the court faces a question: Has the
defendant’s request to switch to arbitration come too late?
Most Courts of Appeals have answered that question by applying
a rule of waiver specific to the arbitration context. Usually, a
federal court deciding whether a litigant has waived a right does
not ask if its actions caused harm. But when the right concerns
arbitration, courts have held, a finding of harm is essential: A
party can waive its arbitration right by litigating only when its
conduct has prejudiced the other side. That special rule, the
courts say, derives from the FAA’s “policy favoring arbitration.”
We granted certiorari to decide whether the FAA authorizes
federal courts to create such an arbitration-specific procedural
rule. We hold it does not.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 13 of 20
Morgan v. Sundance, Inc., 596 U.S. 411, 413-14 (2022) (emphasis supplied). Of
course, if waiver of any type is only a question for the arbitrator, as Contractor
suggests, the Supreme Court would have had no need to determine that “the
Eighth Circuit was wrong to condition a waiver of the right to arbitrate on a
showing of prejudice” and would not have remanded so that the Eighth Circuit
could apply the appropriate waiver inquiry. Id. at 417.
[23] We hold that, at least in the context of the FAA, courts are the proper arbiters
of whether a party has waived its right to arbitrate by litigation-related conduct.
Matters related to whether a party complied with time limits or other
procedural conditions precedent to arbitration, however, remain presumptively
reserved for the arbitrator. See BG Grp., 572 U.S. at 34 (“[C]ourts presume that
the parties intend arbitrators, not courts, to decide disputes about the meaning
and application of particular procedural preconditions for the use of arbitration”
such as “time limits, notice, laches, estoppel, and other conditions precedent to
an obligation to arbitrate.”) (internal quotations omitted).
1.2 Did Contractor’s Filing of the Wisconsin Action Amount to Waiver?
[24] Satisfied that we have the authority to decide the waiver issue at hand, we turn
to Contractor’s litigation conduct. Here, the trial court based its waiver
determination solely on the fact that Contractor filed the Wisconsin Action
without filing for mediation or arbitration with the AAA. We believe the
waiver determination required a deeper analysis and consideration of the
specific facts of this case.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 14 of 20
[25] Whether a party has waived the right to arbitration depends primarily on
whether that party has acted inconsistently with its right to arbitrate. MPACT
Const. Grp., LLC v. Superior Concrete Constructors, Inc., 802 N.E.2d 901, 910 (Ind.
2004) (citing, among other cases, Welborn Clinic v. MedQuist, Inc., 301 F.3d 634,
637 (7th Cir. 2002)). “This requires an analysis of the specific facts in each
case.” Id.; see also Cooper, 532 F. App’x at 641 (“We must determine whether,
considering the totality of the circumstances, a party acted inconsistently with
the right to arbitrate.”) (internal quotations omitted).
[26] In considering if waiver has occurred, courts look to a variety of factors, such
as: whether the party attempting to invoke its right to arbitrate acted diligently
in doing so, substantially delayed its request, filed dispositive motions, or
participated in litigation or discovery; the degree of prejudice that would be
suffered by the other party; and whether the litigant is unfairly manipulating the
system by attempting to obtain a second bite at the apple. See Cooper, 532 F.
App’x at 641; Fin. Ctr. First Credit Union v. Rivera, 178 N.E.3d 1245, 1251 (Ind.
Ct. App. 2021).
[27] To be sure, “an election to proceed before a nonarbitral tribunal for the
resolution of a contractual dispute is a presumptive waiver of the right to
arbitrate.” Cabinetree of Wisconsin, Inc. v. Kraftmaid Cabinetry, Inc., 50 F.3d 388,
390 (7th Cir. 1995). But this presumption may be rebutted where the facts
indicate that the invocation of the judicial process does not signify an intention
to proceed in a court to the exclusion of arbitration. Id. at 391.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 15 of 20
[28] Here, Contractor and Surety each urged Owner to mediate the contractual
dispute, and Contractor sent a clear written demand for mediation/arbitration
to Owner and Architect on February 14, 2022. These demands were rebuffed
by Owner, who wanted to deal only with Surety.
[29] A mere two days after Surety denied Owner’s claim on the Bonds, Contractor
filed the Wisconsin Action. The complaint recounted Contractor’s contractual
right to demand mediation and arbitration, Contractor’s demand for such, and
Owner’s express refusal to do so. Contractor claimed that Owner’s refusal to
mediate/arbitrate constituted a breach of the Construction Contract and “left
[Contractor] with no recourse except for litigation to seek resolution of the
claims.” Appellants’ Appendix Vol. 2 at 176. And among the requests for relief
listed in the complaint, Contractor expressly asked the Wisconsin court for an
order compelling Owner to comply with the Construction Contract’s mediation
and arbitration clauses.
[30] After initiating the Wisconsin Action, Contractor did not attempt to litigate the
contractual dispute; rather Contractor filed a motion to compel arbitration.
Indeed, even Owner recognized that the Wisconsin Action had not proceeded
along the usual litigation route, as there had been “no disclosures, discovery,
schedules, or any activity other than the motion practice surrounding dismissal
or stay of the case.” Appellants’ Appendix Vol. 3 at 143.
[31] Owner complains that Contractor “jumped straight to litigation” instead of
following “the clear dispute resolution steps in the Construction Contract.”
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 16 of 20
Appellee’s Brief at 28-29. But this argument confuses the separate concepts of
waiver through litigation conduct and failure to satisfy conditions precedent to
enforcing arbitration. The latter determination is for the arbitrator, not us.
[32] Further, we find no merit in Owner’s suggestion that the timing of Contractor’s
motion to compel arbitration was “particularly egregious” and represented
“Contractor’s new-found desire to arbitrate.” Id. at 29. And this case is not on
par with Cabinetree, in which the Seventh Circuit found waiver where the
defendant “dropped a bombshell into the proceedings” and sought arbitration
in the middle of the litigation, after plaintiff had provided extensive discovery to
defendant, a trial date had been set six months prior, and the defendant offered
no reason for its delay in requesting a stay besides needing time to weigh its
options. 50 F.3d at 389. Unlike the defendant in Crabtree, there was no hiding
the ball. Contractor’s desire to arbitrate was clear, despite any alleged
procedural stumbles.
[33] We agree with the Wisconsin court’s assessment of the situation. Contractor
filed the Wisconsin Action to enforce the arbitration clause and did not act
inconsistently with its right to arbitrate. Accordingly, the trial court erred in
determining that Contractor waived its right to demand arbitration and in
refusing to stay the proceedings pending arbitration.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 17 of 20
2. Surety’s Right to Enforce the Arbitration Clause in the
Construction Contract
[34] The parties disagree about whether Surety can demand arbitration under the
Construction Contract, where Surety was a non-signatory to the Construction
Contract but the Bonds expressly incorporated the Construction Contract by
reference. 6 They also cannot agree on whether this court has a say in the
matter, with Owner asking us to decide whether there is an agreement to
arbitrate between it and Surety, and Appellants arguing that this determination
is for the arbitrator.
[35] We need not reach the complex arguments presented by the parties, as Surety’s
purported right to demand arbitration was offered by Appellants only as an
alternative basis to reach arbitration. Indeed, Owner indicates in its appellate
brief: “Surety is attempting to rehabilitate Contractor’s waiver and backdoor
Owner into arbitration when the clear language in the Bonds state otherwise.”
Appellee’s Brief at 34. We, however, have found that Contractor can go through
the front door.
6
§1 of the Performance Bond provides: “The Contractor and Surety, jointly and severally, bind themselves
… to the Owner for the performance of the Construction Contract, which is incorporated herein by
reference.” Appellants’ Appendix Vol. 2 at 114. § 1 of the Payment Bond similarly provides: “The Contractor
and Surety, jointly and severally, bind themselves … to the Owner to pay for labor, materials and equipment
furnished for use in the performance of the Construction Contract, which is incorporated by reference,
subject to the following terms.” Id. at 122.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 18 of 20
3. Proper Venue for Arbitration
[36] The Construction Contract provides that arbitration “shall be conducted in
Fond du Lac County, Wisconsin unless expressly prohibited by law, in which
case mediation [sic] shall be held in the place where the Project is located.”
Appellants’ Appendix Vol. 2 at 111.
[37] Owner argues that Ind. Code § 32-28-3-17 expressly prohibits arbitration in
Wisconsin and thus Indiana is the proper venue for the arbitration. This statute
provides: “A provision in a contract for the improvement of real estate in
Indiana is void if the provision … requires litigation, arbitration, or other
dispute resolution process on the contract occur in another state.”
[38] Appellants acknowledge the statute but note that where the FAA applies, as in
this case, courts have consistently found such state statutes preempted by
federal law. See LaSalle Grp., Inc. v. Electromation of Delaware Cnty., Inc., 880
N.E.2d 330, 332 (Ind. Ct. App. 2008) (holding that I.C. § 32-28-3-17 is
preempted by the FAA because it “presents an obstacle” to “congressional
intent to ‘foreclose state legislative attempts to undercut the enforceability of
arbitration agreements’”) (quoting Southland Corp. v. Keating, 465 U.S. 1, 16
(1984)); see also OPE Int’l LP v. Chet Morrison Contractors, Inc., 258 F.3d 443, 447
(5th Cir. 2001) (similar statute found preempted by FAA “because the
Louisiana statute conditions the enforceability of arbitration agreements on
selection of a Louisiana forum; a requirement not applicable to contracts
generally”); Sterling Const. Corp. v. SOS Const. & Roofing, Inc., 2015 WL 2189588,
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 19 of 20
at *3 (N.D. Ind. May 11, 2015) (“As the Supreme Court has made clear, the
[FAA] preempts any state law that is geared towards invalidating arbitration
agreements.”).
[39] Owner attempts to distinguish the cases finding preemption by noting that the
Construction Contract here provided for a venue alternative if arbitration in
Wisconsin was prohibited by law. But Owner unsuccessfully made this same
argument in the Wisconsin Action and then did not appeal that court’s order
compelling arbitration. As a result, arbitration is currently proceeding in
Wisconsin. We will leave it to the arbitrator to decide if the matter should be
transferred to an arbitrator in Indiana.
[40] We reverse and remand with instructions for the trial court to stay the litigation
pending arbitration.
May, J. and Foley, J., concur.
Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 20 of 20