RECOMMENDED FOR FULL-TEXT PUBLICATION
Pursuant to Sixth Circuit I.O.P. 32.1(b)
File Name: 13a0233p.06
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
_________________
X
Plaintiff-Appellee, -
ROCKIES EXPRESS PIPELINE LLC,
-
-
-
No. 12-3069
v.
,
>
-
Defendants, -
4.895 ACRES OF LAND, MORE OR LESS, et al.,
-
-
-
-
MURRAY ENERGY CORPORATION;
-
CONSOLIDATED LAND COMPANY; AMERICAN
Defendants-Appellants. -
ENERGY CORPORATION,
N
Appeal from the United States District Court
for the Southern District of Ohio at Columbus.
No. 2:08-cv-554—Gregory L. Frost, District Judge.
Argued: January 17, 2013
Decided and Filed: August 15, 2013
Before: SILER, GRIFFIN, and STRANCH, Circuit Judges.
_________________
COUNSEL
ARGUED: Mark S. Stemm, PORTER, WRIGHT, MORRIS & ARTHUR, LLP,
Columbus, Ohio, for Appellants. Gregory D. Brunton, REMINGER CO., L.P.A.,
Columbus, Ohio, for Appellee. ON BRIEF: Mark S. Stemm, Alvin J. McKenna, Bryan
R. Faller, PORTER, WRIGHT, MORRIS & ARTHUR, LLP, Columbus, Ohio, John E.
Jevicky, DINSMORE & SHOHL, LLP, Cincinnati, Ohio, for Appellants. Gregory D.
Brunton, Paul N. Garinger, REMINGER CO., L.P.A., Columbus, Ohio, for Appellee.
1
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 2
_________________
OPINION
_________________
GRIFFIN, Circuit Judge. Plaintiff Rockies Express Pipeline LLC (“REX”) was
unsuccessful in privately obtaining from Ohio landowners easements along the right-of-
way for an interstate natural-gas pipeline that the Federal Energy Regulatory
Commission (“FERC”) had authorized the gas company to build and operate. REX
therefore took the next available step and filed the instant action in federal court seeking
the necessary easements through eminent domain. The complaint named as interested
parties defendants Murray Energy Corporation, Consolidated Land Company, and
American Energy Corporation (collectively the “Murray Companies” or the “coal
companies”), which own or are associated with a coal mine in Ohio. That mine lies
beneath a tract of land over which REX intended to run its pipeline and on which it
sought an easement. Following discovery and pretrial motions, the district court
determined that the Murray Companies suffered no compensable damages to its coal-
mining operations as a result of the pipeline. We affirm.
I.
A.
Robert Murray is part owner of defendant Murray Energy Corporation, which in
turn wholly owns subsidiary co-defendants Consolidated Land Company and American
Energy Corporation. Between 1999 and 2003, the Murray Companies spent $450
million to purchase the necessary subsurface mineral rights and open their Century
Mine, which is in Ohio. The companies have contracts with purchasers of the coal they
extract from the Century Mine that extend to 2021. They negotiated the contracts on the
assumption that they would remove all of the mine’s coal, including a portion known as
the 6 West Panel.
The Murray Companies use a mining technique called “longwall mining.” With
this technique, they can extract coal panels of up to 18,000 feet in length. Planned land
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 3
subsidence is a necessary consequence of longwall mining. Due in part to the machinery
involved, longwall mining requires extensive planning in order to ensure maximum coal
recovery and economic viability. Unplanned disruptions have significant financial
consequences.
The Murray Companies own expansive rights to subside the surface estate: they
are free of any obligation to provide subjacent support to the land and are absolved of
any liability for damage their mining causes to the surface estate.
B.
REX is a natural gas company that built and now operates the REX-East
Pipeline, the easternmost portion of a high-speed pipeline transporting natural gas from
supply basins in the Rocky Mountains to eastern Ohio.
In 2007, REX filed an application seeking from FERC a “certificate of public
convenience and necessity” authorizing the construction and operation of the REX-East
Pipeline. Notice of the application and a request for public comment were published in
the Federal Register.
The Murray Companies intervened in the proceeding and proposed a different
route for the pipeline, one that did not traverse their mine. They were concerned that the
land subsidence incident to longwall mining would place excessive stress on the
pipeline, creating a potential for rupture. REX responded that it would take measures
to mitigate the effects of subsidence and claimed that changing the route would impact
nearly 350 additional acres of mostly forested land and increase costs by approximately
$40 million.
On May 30, 2008, FERC approved REX’s application. See Rockies Express
Pipeline LLC, Nos. CP07-208-000, CP07-208-001, 123 FERC ¶ 61234, 2008 WL
2224961 (2008) (“FERC Certificate”). FERC concluded that it was unnecessary to
reroute the pipeline around the Century Mine because REX had proposed an adequate
framework for a subsidence mitigation plan and had agreed to cover all costs associated
with “monitoring or mitigation of the pipeline should mining advance in close proximity
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 4
to the pipeline,” including the cost of moving the pipeline to avoid damage from mining.
Id. ¶¶ 93, 96. FERC also concluded that REX’s proposal was “adequate to ensure
safety” and would not “compromise longwall coal mining operations in the area.” Id.
¶ 93.
However, FERC made its approval of the pipeline subject to Environmental
Condition 147, which required REX, before laying any pipe over the Century Mine, to
file with FERC, “for review and written approval,” a “construction and operations plan,
developed in collaboration with the Murray Companies, for the segment of the pipeline
that traverses the coal mining reserves held by the Murray Companies.” FERC
Certificate app. E ¶ 147. FERC ordered REX to address “the primary concern of
maintaining pipeline integrity and operation while not impeding the mining operation.”
Id. If a plan could not be achieved, REX was to propose “an alternative pipeline route”
that avoided the coal reserves. Id.
Over the next few months, REX and the Murray Companies discussed pipeline
construction. Representatives of the companies met to discuss REX’s construction and
operations plan. The Murray Companies expressed concerns, and REX directed its
experts to refine their studies and reports to address those concerns. On December 23,
2008, REX filed its plan with FERC. In it, REX explained the measures it would take
to build a pipeline that would maintain structural integrity during mining. REX agreed
to measure stress on the pipeline and to reduce the pressure or, if necessary, shut down
the pipeline during mining.
The Murray Companies filed objections to the plan, claiming that REX had failed
to consider their views in drafting it. The Chief of Gas Branch 2 in FERC’s Office of
Energy Projects disagreed and concluded that REX had satisfied the collaboration
requirement, had proposed an acceptable plan, and did not have to reroute around the
Century Mine. FERC itself later ratified that decision. See Rockies Express Pipeline,
LLC, No. CP07-208-005, 128 FERC ¶ 61045, 2009 WL 2049170, at ¶ 23 (2009) (“FERC
Rehearing Order”). The Murray Companies petitioned for judicial review in the U.S.
Court of Appeals for the D.C. Circuit. That court concluded that substantial evidence
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 5
supported FERC’s decisions and denied the petition. Murray Energy Corp. v. FERC,
629 F.3d 231 (D.C. Cir. 2011). REX began building the pipeline over the Century Mine
in May 2009, and construction ended four months later. Gas began flowing in
November 2009.
C.
Meanwhile, citing safety concerns and a business judgment that extensive
regulatory delay sure to be caused by mining under the pipeline would destroy its
business, the Murray Companies accelerated by several years their efforts to mine the
Century Mine’s 6 West Panel. The companies believed they would be unable to procure
without undue delay the permits needed to mine the panel so long as the pipeline was
energized. Any unanticipated delay, they believed, would have caused them to breach
their supply contracts, eventually driving them into bankruptcy. Their decision to mine
early resulted in previously unanticipated costs associated with inefficient mining
techniques they were forced to use as a result of mining early. The 6 West Panel was
extracted before natural gas began to flow in the pipeline in November 2009.
D.
A certificate of public convenience and necessity grants its holder the right to
acquire through the power of eminent domain any portion of the necessary right-of-way
that the holder cannot obtain by contract. 15 U.S.C. § 717f(h). In June 2008, REX filed
the instant action seeking easements along the pipeline’s right-of-way through Ohio.
The Murray Companies were joined as interested parties because they claimed an
interest in the subsurface coal rights in their Century Mine, over which REX had
proposed running its pipeline.
The district court appointed a fact-finding commission to determine the proper
value of the easements REX sought. See Fed. R. Civ. P. 71.1(h)(2). The Murray
Companies sought to recover from REX the costs incurred in mining the 6 West Panel
earlier than anticipated. REX later moved for summary judgment on this claim. The
decision to mine early, REX maintained, was based entirely upon a belief that FERC had
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 6
already rejected: that coal mining and the pipeline could not co-exist. According to
REX, the Murray Companies were barred from relitigating that determination.
The district court granted REX’s motion in part and denied it in part. It agreed
that FERC had “settled” whether the Murray Companies could “continue to mine even
with the pipeline in place.” FERC had not prohibited mining underneath the pipeline,
the court reasoned, so the coal companies could not claim that REX had wholly
prevented them from mining. Yet the court did not foreclose the companies’ request
entirely. If “REX’s easement rights for the pipeline damage Murray’s efforts to obtain
coal by increasing the costs of mining,” the court ruled, “it would unquestionably be a
compensable injury properly before the Commission.” The court instructed the
commission to ignore “any argument or evidence that the Murray Companies cannot
safely mine underneath the pipeline,” but to consider “damages that are an outgrowth of
safe mining underneath the pipeline,” such as the cost of “necessary modifications to
Murray’s mining technique or practices.”
As the case progressed, the issues narrowed, and it became clear that the Murray
Companies sought to recover only the costs incurred in mining the 6 West Panel on an
expedited basis. Because REX thought such damages were outside the scope of the
district court’s earlier ruling, the parties sought clarification from the district court. The
court clarified that costs incurred from mining early did not fall within the parameters
of what it ruled was recoverable. It deemed these costs “self-inflicted,” incurred wholly
as a result of “wary speculation” as to what mining regulators would do. The court
concluded that the companies had no damages if they did not suffer “pipeline-related
damages arising from how [they] mined 6 West by necessity.” It instructed the
commission to exclude evidence of costs incurred due to early mining.
At a pre-hearing conference two weeks later, the Murray Companies made a
proffer of its evidence of damages, which consisted solely of the costs it incurred mining
ahead of schedule. The commission’s chairperson excluded the evidence, explaining
that “the only admissible evidence as to 6 West are modifications Murray made in its
mining technique to accommodate actual conditions existing at the time caused by the
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 7
actual construction of the pipeline itself,” and that “none of the evidence proffered fits
that definition.” The commission found that the Murray Companies offered no evidence
of injury to its mining operations due to the REX-East Pipeline. The district court
adopted that finding and awarded the coal companies no damages.
The coal companies timely appealed.
II.
We first consider the appropriate standard of review. The Murray Companies
assert that our review is de novo inasmuch as they challenge the district court’s decision
that they could not, as a matter of law, recover damages incurred because of early
mining. See Cutter v. Wilkinson, 423 F.3d 579, 584 (6th Cir. 2005) (legal questions are
reviewed de novo). They further contend that they challenge the district court’s
summary-judgment decision and its order adopting the commission’s report, matters that
are typically reviewed de novo. See Donald v. Sybra, Inc., 667 F.3d 757, 760 (6th Cir.
2012); Fed. R. Civ. P. 71.1(h)(2)(D); Fed. R. Civ. P. 53(f)(4).
REX responds that abuse-of-discretion review applies. It views the coal
companies as challenging the instruction to the commission not to consider evidence of
damages caused by expedited mining. These rulings, REX claims, are similar to jury
instructions and evidentiary rulings, which are both reviewed for an abuse of discretion.
See Harris v. J.B. Robinson Jewelers, 627 F.3d 235, 240 (6th Cir. 2010) (evidentiary
rulings); United States v. Beaty, 245 F.3d 617, 621 (6th Cir. 2001) (word choice in a jury
instruction).
The Murray Companies have the better argument. The ultimate question the
district court answered was whether the coal companies are legally entitled to the costs
incurred because of early mining. In our view, that is a legal conclusion. And even if
the district court’s rulings are favorably compared to jury instructions or evidentiary
rulings, the rulings rested entirely on a legal conclusion regarding the scope of damages
the companies could recover. We review de novo the legal conclusions that underlie a
district court’s evidentiary ruling or are contained in its jury instructions. See Harris,
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 8
627 F.3d at 240 (evidentiary ruling); Bridgeport Music, Inc. v. UMG Recordings, Inc.,
585 F.3d 267, 273–74 (6th Cir. 2009) (jury instruction). Review here is de novo.
III.
FERC issued REX a certificate of public convenience and necessity authorizing
the construction and operation of the REX-East Pipeline. As a certificate holder, REX
had the authority to use eminent domain to obtain easements along the pipeline’s
proposed right-of-way. See 15 U.S.C. § 717f(h). While condemnation under the Natural
Gas Act is a federal matter, courts conducting such proceedings must apply “the law of
the state in which the condemned property is located in determining the amount of
compensation due.” Columbia Gas Transmission Corp. v. Exclusive Natural Gas
Storage Easement, 962 F.2d 1192, 1199 (6th Cir. 1992). Here, Ohio’s law applies
because the Century Mine is located in Ohio.
We recently had occasion in a related case to set out the relevant Ohio law:
Under Ohio law, the landowner in an eminent domain action is entitled
both to the value of the taken land and to “damages” to the “residue” of
the property. City of Norwood v. Forest Converting Co., 476 N.E.2d
695, 700 (Ohio Ct. App. 1984). Damages to the residue compensate for
“any injury that may result to the remaining lands by reason of the
construction of the proposed improvement,” measured by the difference
in the residue’s fair market value before and after the taking. Id. A court
determining fair market value should take into consideration “every
element that can fairly enter into the question of value.” Sowers v.
Schaeffer, 99 N.E.2d 313, 317 (Ohio 1951).
Am. Energy Corp. v. Rockies Express Pipeline LLC, 622 F.3d 602, 606–07 (6th Cir.
2010). As this passage makes clear, Ohio law distinguishes between “compensation”
(the fair market value of the land actually taken) and “damages” to the residue (loss of
value to the remaining land). REX sought to actually take only the surface estate above
the Murray Companies’ mineral estate; it did not seek to take the mineral estate itself.
Therefore, only “damages” to the Century Mine—as “the remaining land”—are
presently at issue. Specifically, the coal companies can recover damages to its mine that
are “reasonably foreseeable” and that “might reasonably be expected to occur” by reason
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 9
of the pipeline’s construction or existence. Masheter v. Blaisdell, 282 N.E.2d 42, 45
(Ohio 1972).
Applying these principles, the district court concluded that the Murray
Companies could recover “damages in the form of necessary and additional costs
incurred due to any complications the pipeline caused,” such as “having to work around
REX’s equipment, safe mining techniques, or lost mining days due to pipeline
construction delays.” See State ex rel. Goeglein v. Wray, No. 00AP-424, 2000 WL
1678031, at *4 (Ohio Ct. App. Nov. 9, 2000). But because the companies mined the
6 West Panel without obstruction from the pipeline, they did not suffer complications
of this kind. The companies instead sought recovery for the costs they incurred because
they mined the panel ahead of schedule, contending that they did so because of concerns
that regulators either would have taken too long to approve the necessary permits or
would not have approved them at all. The district court disagreed, reasoning that if the
coal companies mined early to avoid regulatory uncertainty, they acted “prematurely,”
and that REX was not responsible for the companies’ “wary speculation” as to what
would happen. We agree with the district court.
The Murray Companies are correct to point out that the primary limit Ohio law
places on damages in condemnation matters is that they be neither “speculative [n]or
contingent.” Blaisdell, 282 N.E.2d at 45. Damages must be “reasonably foreseeable”
and “expected to occur” in the course of the normal use of the property. Id. But the
entire basis for the companies’ claim—their belief that the regulatory delays that would
accompany mining under a pipeline would cause the companies to default on their
supply contracts and drive them into bankruptcy—is not “reasonably foreseeable.” The
companies only speculate that this course of events would follow; they offer no evidence
that could reasonably convince a fact finder to credit the theory. In addition, the theory
is built upon a series of contingencies that are, at best, speculative. Although we can
accept the premise that the pipeline’s existence “triggered multiple layers of federal and
state regulatory oversight” that apparently did not exist before, we cannot accept the
conclusion that the additional oversight “diminished [the companies’] property right to
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 10
subside.” Murray Br. 29–30. And though it might be, as the companies contend, that
regulators would have to “conduct independent reviews and make safety determinations”
before mining, the Murray Companies have offered no evidence that regulators would
have prohibited mining outright, or would have delayed it for such a period that it would
no longer be economically viable. Id. at 30. The opinion of Robert Murray, the
companies’ principal, that regulators would have delayed mining for long periods of
time, unsupported by specific and tangible facts within his knowledge, fails to move the
Murray Companies’ theory beyond speculation. Cf. Masheter v. Wood, 305 N.E.2d 785,
787 (Ohio 1973) (holding that an expert witness in a condemnation proceeding may not
offer an opinion as to the likelihood of a zoning change because it constitutes
speculation).
The coal companies respond that they cannot be faulted for the lack of specific
evidence in the record concerning damages. They argue that by deeming “inadmissible
all evidence in any manner relating back to mine safety,” the district court effectively
barred them from introducing evidence of the operational and financial demands that
forced them to mine early. Murray Br. 32. But the reason the court barred such a
presentation was because the companies failed to come forward during the clarification
stage with evidence that their damages were not speculative. In the court’s words, the
Murray Companies “apparently made [the] anticipatory modifications to [their] plan and
practices based on subjective beliefs, interpretation, and speculation.” If there is
evidence showing otherwise, the Murray Companies would have been well advised to
bring it before the district court when the parties sought clarification.
Essentially, the Murray Companies contend that “[t]he mining the district court
characterized as ‘inefficient’ actually was [their] only viable option as of the 2008 date
of take to assure a precisely orchestrated sequencing of mine advancement and
investment and avoidance of unplanned stoppages of the longwall miner.” Murray Br.
34 (emphasis added). Operational constraints of longwall mining apparently mandated
avoidance of “the complex web of added regulation and corresponding delays and risks”
caused by the pipeline. Id. But again, the companies offer no evidence in support.
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 11
We do not read the district court’s decisions as categorically prohibiting, as a
matter of Ohio law, damages of the sort the Murray Companies request. Rather, we read
it as preventing such damages in part because the companies utterly failed to
demonstrate, as a matter of proof, that they rested upon more than speculation. See, e.g.,
Preston v. Stover Leslie Flying Serv., Inc., 190 N.E.2d 446, 451 (Ohio 1963) (qualifying
the general rule that prohibits recovery of lost future profits by noting that “courts look
to the evidence to determine whether it is of such a character as to take the determination
of damages out of the field of speculation” and that “[n]one of the cases purport to deny
absolutely the right to recover for loss of future profits, if proved with reasonable
exactitude”); see also Columbia Gas Transmission, 962 F.2d at 1199. The Murray
Companies failed to bring their claim out of the speculative realm. For this reason, the
district court was correct to award no damages.
IV.
The Murray Companies’ claim for damages also fails because it is a collateral
attack on the essential factual findings made by FERC in its decision to approve the
REX-East Pipeline.
Ostensibly, the Murray Companies disclaim any intent to challenge FERC’s
decision to issue the certificate or the D.C. Circuit’s judgment denying their petition for
review. See Reply Br. 17 (“FERC’s decision in permitting the construction of the REX
pipeline is both clear and unchallenged.”); id. at 18 (“MEC’s damages case is not a
collateral attack on FERC’s order.”). Moreover, the coal companies seek relief from the
district court that FERC could not provide: the Natural Gas Act allows the courts, not
FERC, to entertain eminent domain actions brought by certificate holders. However, the
basis of the companies’ damage claims requires ignoring or attacking the essential fact
findings made by the FERC. That we may not allow. See Astoria Fed. Sav. & Loan
Ass’n v. Solimino, 501 U.S. 104, 107–08 (1991) (explaining that the doctrine of
collateral estoppel prevents re-litigation of factual issues resolved by an administrative
agency acting in a judicial capacity).
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 12
FERC was tasked with deciding whether the public interest supported the REX-
East Pipeline. See FERC Certificate ¶ 26 (“[I]n deciding whether to authorize the
construction of major new pipeline facilities, we balance the public benefits against the
potential adverse consequences.”); see generally 15 U.S.C. § 717f(e). In doing so,
FERC fully considered the public comments it received, including the Murray
Companies’ contention that REX’s proposal “present[ed] numerous dangers to the
pipeline’s integrity and that construction of the pipeline will interfere with the ongoing
and future extraction of hundreds of millions of tons of coal.” FERC Certificate ¶ 91
(emphasis added). But after reviewing the evidence, FERC concluded that REX’s
“proposed [safety] measures are adequate to ensure safety and will not compromise
longwall coal mining operations in the area.” Id. ¶ 93. Also, as a condition of approval,
FERC required REX to collaborate with the Murray Companies and submit a
construction and operations plan addressing the “primary concern of maintaining
pipeline integrity and operation while not impeding the mining operation.” Id. app. E
¶ 147 (emphasis added). FERC approved REX’s plan and found that “the pipeline can
be safely constructed and operated across Murray’s coal reserves.” FERC Rehearing
Order ¶ 86.
The Murray Companies’ damages theory necessarily challenges these factual
findings. Specifically, their theory rests upon a factual finding that REX’s proposed
safety measures would compromise longwall coal mining to such an extent that it would
result in the companies’ financial ruin. However, FERC found as a matter of fact that
the pipeline would not compromise mining and that the two operations could co-exist.
Likewise, FERC’s decision to later approve REX’s proposed construction and operations
plan rested upon a factual finding that the pipeline would not “imped[e]” local mining
operations; had FERC determined otherwise, it would have ordered a reroute, but
declined to do so. Because the Murray Companies may not collaterally attack these
factual findings, their decision to mine the 6 West Panel ahead of schedule was, in the
words of the district court, “self-inflicted.” The companies cannot recover damages of
their own making. See City of Norwood, 476 N.E.2d at 700 (damages compensate for
“any injury that may result to the remaining lands by reason of the construction of the
No. 12-3069 Rockies Express Pipeline v. 4.895 Acres of Land, et al. Page 13
proposed improvement” (citation and internal quotation marks omitted) (emphasis
added)).
V.
For these reasons, we affirm the judgment of the district court.