PRESENT: Koontz, Kinser, Lemons, Goodwyn, and Millette, JJ.,
and Carrico and Russell, S.JJ.
COMMONWEALTH OF VIRGINIA, ET AL.
v. Record No. 091430
AMEC CIVIL, LLC OPINION BY
JUSTICE LEROY F. MILLETTE, JR.
AMEC CIVIL, LLC September 16, 2010
v. Record No. 091662
COMMONWEALTH OF VIRGINIA, ET AL.
FROM THE COURT OF APPEALS OF VIRGINIA
This appeal concerns the performance of a construction
contract between AMEC Civil, LLC (AMEC) 1 and the Commonwealth of
Virginia, and the Department of Transportation (collectively,
VDOT). In addressing AMEC’s twenty-two assignments of error
and VDOT’s two assignments of error and seven assignments of
cross-error in the consolidated cases, we narrow the dispute to
five primary issues: (1) whether AMEC gave timely notice of
its claims to VDOT; (2) whether sustained elevated lake water
levels constitute a differing site condition under the
contract; (3) whether AMEC established its entitlement to home
office overhead damages; (4) whether the “Rental Rate Blue
Book” was properly used to calculate AMEC’s actual costs as a
basis for its award of damages; and (5) whether AMEC is
entitled to pre-judgment interest as an element of its damages.
We do not address those issues rendered moot by our holdings in
this opinion. We affirm the judgment of the Court of Appeals
in part, reverse in part, and remand for the circuit court to
recalculate damages awarded to AMEC.
BACKGROUND
In May 2000, VDOT awarded AMEC a $72,479,999.49 contract
for the construction of the Route 58 Clarksville Bypass in
Mecklenburg County. 2 The central element of the construction
project was a bridge (Bridge 616) spanning the John H. Kerr
Reservoir (Kerr Lake), which required work to be performed by
equipment floating on the water. The project also included ten
smaller bridges and several miles of roadway. The time
allotted to the project was 41 months, with a projected
completion date of November 1, 2003. However, the project was
not substantially completed until June 2005. Delays arose
primarily from difficulties in the construction of concrete-
filled drilled shafts that form the foundation of Bridge 616,
and sustained elevated water levels in Kerr Lake.
1
Morse Diesel Civil, LLC changed its name to AMEC Civil,
LLC on or about January 1, 2001, and assigned its interests in
the contract to AMEC.
2
In this opinion, we cite VDOT’s Metric Road and Bridge
Specifications (Jan. 1997) (the Specifications), which are
incorporated into the contract. We refer to individual
sections as “Specification § ___.” In addition to the
2
In May 2006, AMEC submitted an administrative claim to
VDOT pursuant to Specification § 105.16, seeking $24,792,823.43
in additional compensation. 3 AMEC’s claim submission outlined
what it deemed major impacts, consisting of the 2003-04 winter
period, and differing site conditions, including unanticipated,
sustained high water levels, and other alleged impacts delaying
its performance of the contract. By letter, VDOT denied AMEC’s
claim.
AMEC then filed its breach of contract action against VDOT
in the circuit court, under Code § 33.1-387. Code § 33.1-387
provides in part that “[t]he submission of the claim to the
Department of Transportation within the time and as set out in
§ 33.1-386 shall be a condition precedent to bringing an action
under this chapter.” 4 The trial was conducted by the circuit
Specifications, special provisions were also included in the
contract.
3
According to Specification § 105.16, in pertinent part,
a written statement describing the act of
omission or commission by the Department or
its agents that allegedly caused damage to
the Contractor and the nature of the
claimed damage shall be submitted to the
Engineer at the time of occurrence or
beginning of the work upon which the claim
and subsequent action are based.
4
Code § 33.1-386 provides that upon the completion of any
contract for the construction of any state highway project
awarded by the Commonwealth Transportation Board or by the
Commonwealth Transportation Commissioner, a contractor may
submit a claim for payment under the contract of costs and
3
court without a jury. During litigation of the case, the
circuit court issued two letter opinions.
The first letter opinion was issued before trial
commenced, and addressed VDOT’s argument that AMEC failed to
satisfy the mandatory requirement for timely written notice, at
the time of the occurrence or beginning of the work, of an
intent to file claims under Code § 33.1-386 and Specification
§ 105.16. The circuit court held that “any writing that
memorializes the fact the VDOT had actual notice of a claim
could be sufficient” to satisfy the notice requirement of
Specification § 105.16.
The circuit court also held that “strict compliance with
legal form,” through the requirement in Code § 33.1-386 that
AMEC provide VDOT with written notice of its intention to bring
claims when such claims first arise, “must yield to achievement
of the law’s primary purpose” of giving VDOT the opportunity to
investigate such claims. The court determined that “AMEC’s
claim should not be dismissed since the public policy function
of the written notice provision was achieved through actual
notice” and, furthermore, that VDOT suffered no prejudice from
expenses caused by VDOT’s acts or omissions. Code § 33.1-386
states, in part, that “[t]he claim shall set forth the facts
upon which the claim is based, provided that written notice of
the contractor’s intention to file such claim shall have been
given to [VDOT] at the time of the occurrence or beginning of
the work upon which the claim and subsequent action is based.”
4
AMEC’s failure to abide by the statute’s written notice
provision.
After the trial concluded, the circuit court issued its
second letter opinion. The circuit court rendered a “general
verdict” and awarded AMEC $21,181,941.00, without interest or
attorney’s fees. The circuit court revisited the issue of
notice, finding that VDOT had written notice through minutes of
meetings and memoranda addressing the issues, exchanged between
the parties, and concluded that every factual assumption made
in its first letter opinion was established by the evidence at
trial. VDOT and AMEC each appealed the circuit court’s
judgment to the Court of Appeals, which reversed in part,
affirmed in part, and remanded the case for further
proceedings. Commonwealth v. AMEC Civil, LLC, 54 Va. App. 240,
246, 677 S.E.2d 633, 636 (2009). We awarded these appeals.
ANALYSIS
Although AMEC’s amended complaint segregated its claim
into 12 separate allegations of damages, the Court of Appeals
grouped the dispute into four principal issues, which we
analyze as we address the issues presented in this appeal.
I. Notice
The Court of Appeals determined that the following claims
were barred due to AMEC’s failure to fulfill the notice
requirement of Code § 33.1-386(A): drilled shaft work; defects
5
in the drilled shaft concrete specification; concrete formwork
for foundation caps, piers, and columns; pier 17 foundation cap
repair; and work authorized by work orders 4, 6, 7, and 16.
AMEC Civil, LLC, 54 Va. App. at 257-60, 677 S.E.2d at 642-43.
The Court of Appeals held that, with respect to these claims,
the circuit court erred as a matter of law by concluding that
AMEC gave timely written notice of its intention to file a
claim, because the court dispensed with the statutory
requirement of written notice. Id. at 262-63, 677 S.E.2d at
644. The Court of Appeals also held that the circuit court’s
alternate ruling that written notice had been given from
minutes of meetings and memoranda exchanged between the parties
is unsupported by the evidence. Id.
AMEC also made a claim for acceleration damages because on
some aspects of the contract, AMEC accelerated its efforts to
keep on track with expected timelines and claimed damages for
its acceleration efforts. The Court of Appeals held that the
notice given to VDOT was untimely as to AMEC’s claim for
acceleration damages incurred before April 2004, but was timely
as to acceleration damages incurred after April 2004. Id. at
260-62, 677 S.E.2d at 643-44.
Included in AMEC’s complaint was a claim for damages due
to a delay over two winter periods. In addressing AMEC’s claim
of damages, the Court of Appeals concluded that AMEC’s notice
6
as to the first winter period was timely. Id. at 261-62, 677
S.E.2d at 643-44. Notice of a claim as to the second winter
period was not addressed and is, therefore, not at issue.
AMEC, however, contends that VDOT had timely written
notice of all of AMEC’s claims, that the evidence supported the
circuit court’s ruling, and that the Court of Appeals erred
when it reversed the circuit court’s findings of proper notice.
AMEC contends that the Court of Appeals erred by failing to
consider that notice is timely when given at the time of the
occurrence, which can properly be regarded as when a dispute
over payment actually arises between the parties. AMEC argues
that the Court of Appeals erred by not considering the adequacy
of the written notice in context of the fact that VDOT had
actual knowledge and suffered no prejudice, that actual notice
followed by written notice may be timely, and that the writings
exchanged by the parties documenting the various problems
giving rise to the claims, the written requests for additional
compensation, and the administrative claim package are
sufficient to satisfy Code § 33.1-386.
A. Notice Under Code § 33.1-386(A)
Code § 33.1-387 gives government contractors the right to
file a civil action for any claim “under the contract” that has
previously been submitted to and denied by VDOT. We have
stated that this statute must be “strictly construed.” XL
7
Specialty Ins. Co. v. Commonwealth, 269 Va. 362, 371, 611
S.E.2d 356, 361 (2005). Code § 33.1-387 further provides that
“[t]he submission of the claim to the Department of
Transportation within the time and as set out in § 33.1-386
shall be a condition precedent to bringing an action under this
chapter.” By using the language “condition precedent,” Code
§ 33.1-387 makes notice under Code § 33.1-386 a mandatory
prerequisite to filing suit against the Commonwealth.
In Sabre Construction Corp. v. County of Fairfax, 256 Va.
68, 71, 501 S.E.2d 144, 146 (1998), we addressed language in
the Public Procurement Act that allowed bidders to institute a
legal action within ten days of an adverse decision of a public
body. We held that when a statute imposes such a “condition
precedent” to maintaining a cause of action against the
Commonwealth, such limitation is “not merely a procedural
requirement, but a part of the newly created substantive cause
of action.” Id. at 72, 501 S.E.2d at 147. Thus, notice given
in accordance with Code § 33.1-386 is an element of AMEC’s
prima facie case.
Code § 33.1-386(A) details the proper form and procedure
for submitting a claim “under the contract.” Code § 33.1-
386(A) requires that the administrative claim “set forth the
facts upon which the claim is based, provided that written
notice of the contractor’s intention to file such claim shall
8
have been given to the Department at the time of the occurrence
or beginning of the work upon which the claim and subsequent
action is based.” (Emphasis added.) Compliance with this
notice requirement is mandatory, and part of the substantive
cause of action authorized by Code § 33.1-387.
In its first letter opinion, the circuit court ruled that
“AMEC did not provide VDOT with written notice of its claims as
required by Va. Code Ann. § 33.1-386.” Nevertheless, the
circuit court held that AMEC had actual notice of AMEC’s
claims, and concluded that “AMEC’s actual notice was a valid
substitute for written notice since it effectively accomplished
the purpose of the written notice requirement.” The circuit
court also noted that “although AMEC did not fully comply with
the written notice requirement of Va. Code Ann. § 33.1-386,
every purpose of the notice provision has been achieved and
VDOT has not suffered any prejudice since it is aware of every
fact and circumstance ‘essential to a just determination of the
plaintiff’s claim.’ ”
In its post-trial ruling, the circuit court reaffirmed its
ruling that actual notice is an acceptable substitute for
written notice under Code § 33.1-386(A). The circuit court
also stated:
The evidence presented at trial proves that the
Commonwealth had actual notice of the
plaintiff’s claims, ab initio, that the parties
9
met on several occasions to discuss the issues
before the action was filed, that minutes of
those meetings were kept, and that memoranda
addressing the issues were exchanged between the
parties. It is clear, then, that [VDOT] also
had written notice of the plaintiff’s claims.
In neither of its letter opinions nor in its final order did
the circuit court identify the documents that supported its
conclusion that the written notice requirement for AMEC’s
various claims was satisfied, so we must consider whether the
record supports the circuit court’s blanket endorsement that
AMEC complied with the requirement of written notice or whether
the Court of Appeals correctly determined that proper written
notice was lacking as to certain claims.
B. Actual Notice
The Court of Appeals, in addressing the circuit court’s
ruling regarding actual notice, held that the “circuit court
erred in finding that anything other than written notice would
suffice” under Code § 33.1-386(A). AMEC Civil, LLC, 54 Va.
App. at 254, 677 S.E.2d at 640. The Court of Appeals stated
that “[t]o permit actual notice to suffice when the governing
statute requires written notice would create an exemption that
has no basis in the text of the statute.” Id. at 255, 677
S.E.2d at 640 (internal quotation marks omitted). We agree
with the Court of Appeals that written notice is required.
10
Code § 33.1-386(A) is to be strictly construed, and is
clear and unambiguous, stating that contractors “shall” provide
“written notice” to VDOT. We hold that actual notice cannot
satisfy the written notice requirement in Code § 33.1-386(A),
and that written notice is required. See also BBF, Inc. v.
Alstom Power, Inc., 274 Va. 326, 331, 645 S.E.2d 467, 469
(2007) (“In construing a statute, we must apply its plain
meaning, and we are not free to add [to] language, nor to
ignore language, contained in statutes.” (internal quotation
marks omitted)).
C. Timely Written Notice
Having concluded that notice under Code § 33.1-386(A) must
be written, the issue becomes what constitutes “written notice”
under the statute. Code § 33.1-386(A) provides that the
“written notice” must announce the contractor’s “intention to
file [a] claim.” The statute also requires that such notice be
given at one of two times: 1) “at the time of the occurrence”
of the claim; or 2) at the “beginning of the work upon which
the claim . . . is based.” Code § 33.1-386(A).
Written notice under Code § 33.1-386(A) must be a written
document delivered to VDOT clearly stating the contractor’s
intention to file a claim. We reject AMEC’s argument that
minutes of meetings constitute written notice under Code
§ 33.1-386(A). To the extent such minutes may reflect a record
11
of a contractor’s stated intent to file a claim, they still do
not meet the written notice requirement of Code § 33.1-386(A),
because they are merely a recorded summary of what was said at
meetings. At a minimum, to satisfy the written notice
requirement, the written document at issue must clearly give
notice of the contractor’s intent to file its claim and must be
“given to [VDOT]” by letter or equivalent communication
directed to VDOT at the appropriate time.
In Flory Small Business Development Center v.
Commonwealth, 261 Va. 230, 237, 541 S.E.2d 915, 919 (2001),
this Court interpreted a notice requirement in the Virginia
Public Procurement Act (former Code §§ 11-35 through –80),
which required parties making claims under the Act to submit a
written notice of intent to file a claim given “at the time of
the occurrence or beginning of the work upon which the claim is
based.” The relevant language in the Code section at issue in
Flory is, for purposes of this case, identical to the notice
language in Code § 33.1-386(A). In interpreting the notice
provisions of the Procurement Act, this Court stated that the
Act
does not specifically require that the notice of
intent be separate and distinct from the claim
itself in time or in form. By identifying more
than one event that triggers the filing of an
intent to file a claim, the statute acknowledges
that not all claims will arise under the same
circumstances. For example, a dispute over
12
payment under the contract may not arise until
the work is completed, preventing a contractor
from giving notice of an intent to file a claim
for such payment at the “beginning of the work
upon which the claim is based.” Thus, the
timing and form of an alleged notice of intent
pursuant to Code § 11-69(A) requires an
examination of the circumstances of each case.
Id. at 238, 541 S.E.2d 919 (emphasis added).
In determining whether AMEC has met its statutory
obligation to provide VDOT with written notice, we must examine
the documents sent by AMEC to VDOT regarding the various claims
alleged. Guided by the principles stated in Flory and the
plain language of Code § 33.1-386(A), we will examine the
circumstances of each particular claim at issue to determine
whether notice is timely and clearly shows AMEC’s intention to
file a claim.
1. Claim Involving Drilled Shaft Work
AMEC’s claim for drilled shaft work stemmed from problems
it encountered during construction of Bridge 616. The Court of
Appeals held that AMEC’s notice was untimely because it was
given in 2003, two years after the beginning of the work on the
drilled shafts. AMEC Civil, LLC, 54 Va. App. at 257-58, 677
S.E.2d at 642. We agree with the Court of Appeals that AMEC’s
notice for this claim was untimely.
The record contains letters and minutes from meetings
exchanged between AMEC and VDOT which show that the parties
13
were aware of problems with the drilled shaft work on Bridge
616 as early as 2000. However, it was not until 2003 that AMEC
sent VDOT a letter stating its intention to file a claim for
additional compensation due to the problems associated with the
drilled shafts. Clearly this notice was not given at the
“beginning of the work” on this claim because it was given two
years after work began. Code § 33.1-386. The notice was also
given long after a legitimate dispute regarding the problems
with the drilled shafts arose between the parties, as evinced
by the correspondence in the record. Therefore, the notice was
also given after the “time of the occurrence” of this claim,
rendering it untimely under Code § 33.1-386.
2. Claim for Defects in the Drilled
Shaft Concrete Specification
During construction of the drilled shafts, AMEC
encountered problems with the concrete mix specification
established by VDOT pursuant to the contract, requiring AMEC to
expend significant amounts of additional time and money. These
problems began in 2000, and persisted for more than a year.
AMEC claimed that VDOT was responsible for its loss in
productivity regarding concrete placement from 2000 until 2002,
when VDOT allowed the concrete mix specification to be changed,
which solved the problems AMEC was experiencing in laying the
concrete.
14
The Court of Appeals held that there was no evidence
presented at trial that AMEC provided VDOT with written notice
of its intention to file a claim for damages resulting from the
concrete mix specification. AMEC Civil, LLC, 54 Va. App. at
258, 677 S.E.2d at 642. We agree with the Court of Appeals
that although the record contains letters exchanged between
AMEC and VDOT discussing the concrete mix specification and
problems associated with it, there is no evidence that AMEC
provided VDOT written notice of its intention to file a claim
for damages caused by the concrete mix specification.
3. Claim for Concrete Formwork for Foundation
Caps, Piers, and Columns
In its administrative claim, AMEC alleged that it suffered
damages for problems associated with certain foundation caps,
piers, and columns. With regard to these claims, the Court of
Appeals held that there was no evidence that AMEC provided
written notice of its intention to file independent claims for
these additional costs. Id. at 259, 677 S.E.2d at 642.
As part of its administrative claim, AMEC asserted a claim
for damages resulting from a plan error regarding the
construction of concrete shafts for pier 18 on Bridge 616. In
May 2004, AMEC sent VDOT a letter in response to VDOT’s denial
of AMEC’s request for additional compensation resulting from
this plan error. This letter affirmatively states that it
15
shall serve as notice that AMEC will file a claim for damages
resulting from this plan error. Therefore, we hold that AMEC
did provide VDOT with sufficient written notice for its claim
for damages resulting from the plan error for construction of
pier 18 on Bridge 616. AMEC’s letter clearly stated its
intention to file a claim, and it was timely because it was
made shortly after VDOT’s denial of AMEC’s request for
additional compensation, which was the “time of the
occurrence.”
With regard to AMEC’s claims for problems associated with
other foundation caps, piers, and columns, we agree with the
Court of Appeals that the record does not contain evidence that
AMEC provided VDOT with written notice of such claims.
4. Claim for Pier 17 Foundation Cap Repair
AMEC experienced problems constructing the pier 17
foundation cap on Bridge 616 because fluctuating lake levels
caused leakage around the seals of the foundation cap. This
leakage continued during placement of the concrete, which
ultimately rendered the foundation cap defective. VDOT
rejected the foundation cap, and AMEC had to construct a new
foundation cap for pier 17.
The Court of Appeals held that the record contained no
written notice from AMEC to VDOT indicating its intention to
file a claim for work on the pier 17 foundation cap. Id. at
16
259, 677 S.E.2d at 643. We agree with the Court of Appeals
that the record contains no evidence of such notice from AMEC
to VDOT.
5. Claim for Work Authorized by Work
Orders 4, 6, 7, and 16
Work Orders 4, 6, 7, and 16 were authorized by VDOT for
additional work that was required during construction, but not
provided for in the contract. These work orders extended the
contract end date by a total of 41 days. In its administrative
claim, AMEC alleged that VDOT failed to compensate AMEC for
delay costs associated with these work orders. In addressing
this issue, the Court of Appeals held that notice was not
timely because AMEC provided such notice in July 2004, which
was “after commencement of the work authorized by Work Orders
4, 6, 7, and 16.” Id. at 260, 677 S.E.2d at 643.
We agree that AMEC did not provide timely written notice
for its claim regarding Work Orders 4, 6, 7, and 16. AMEC’s
notice was not timely under Code § 33.1-386 because it was made
after “beginning of the work” on which the claim was based, and
after the parties developed a legitimate dispute on this claim,
which served as the “time of the occurrence” of this claim.
6. Claim for Acceleration Damages
In its administrative claim, AMEC alleged that it is
entitled to acceleration damages resulting from its accelerated
17
effort to meet contractual timelines. The Court of Appeals
held that AMEC filed a written notice evincing its intention to
file a claim in April 2004. Id. at 260-61, 667 S.E.2d at 643.
The Court of Appeals held that this “notice was untimely as to
acceleration efforts prior to April 2004 but timely as to
acceleration efforts after April 2004 to the extent they were
reasonably attributable to contractually compensable delays not
‘correctly and fully addressed by Work Order No. 39.’ ” 5 Id. at
262, 677 S.E.2d at 644. The Court of Appeals directed the
circuit court on remand to “determine whether any such post-
notice efforts existed consistent with our views of the
contractual compensability of AMEC’s claims.” Id.
As an initial matter, we agree with the Court of Appeals
that AMEC first provided VDOT with written notice of its
intention to file a claim for its acceleration efforts in April
2004. However, this notice was not timely for all of AMEC’s
acceleration efforts during the contractual period. The notice
was not timely for AMEC’s acceleration efforts prior to April
2004 because the notice was given after the work that comprised
the acceleration began, and after the occurrence of the claim
because the parties’ dispute regarding the compensability of
AMEC’s acceleration efforts arose before April 2004.
5
Work Order 39 extended the contract end date to September
3, 2004 “due to the high lake elevations.”
18
Nevertheless, AMEC’s notice is timely for its claim for
acceleration efforts after April 2004 because the notice was
given prior to acceleration efforts made after that time.
Therefore, AMEC’s notice was timely under Code § 33.1-386 for
acceleration efforts after April 2004 because it was given at
the beginning of the work upon which AMEC’s claim was based.
7. Claim for Damages During the First Winter Period
The contract originally provided for three winter periods.
However, the contract contemplated the possibility of an
extension that would push the completion date into later winter
periods. Specification § 108.09(b) provides, in pertinent
part:
If there is a delay in the progress of the work
due to unforeseen causes . . . and the delay
extends the contract time limit into the period
between November 30 of one year and April 1 of
the following year and working conditions during
such period are unsuitable for completion of the
work, then consideration may be given to
granting an extension of time that will
encompass a suitable period during which such
work can be expeditiously and acceptably
performed.
In March 2003, AMEC sent a letter to VDOT stating its
intention to file a claim for damages resulting from extending
the contract from November 30, 2003 to April 1, 2004. AMEC
contended that this winter period extension was necessary
because work orders 6, 7, 12, and 16 extended the contractual
19
period into the winter period, a time when working conditions
were unsuitable under Specification § 108.09(b). The Court of
Appeals held that this was adequate written notice under Code
§ 33.1-386(A). AMEC Civil, LLC, 54 Va. App. at 262, 677 S.E.2d
at 644. We agree with the Court of Appeals. AMEC’s notice was
timely because it was given when the parties’ dispute regarding
the extension for the first winter period arose, which was the
time of the occurrence of the claim under Code § 33.1-386.
In summary, we agree with the Court of Appeals that AMEC
provided VDOT with timely written notice regarding its claims
for damages arising during the first winter period. We also
agree with the Court of Appeals that AMEC provided VDOT with
timely written notice regarding its acceleration claim as
applied to AMEC’s acceleration efforts after April 2004. On
remand, the circuit court should determine the amount of
compensation to which AMEC has proved it is entitled for
damages arising during the first winter period and for its
acceleration efforts from April 2004 to completion of the
contract.
Unlike the Court of Appeals, we hold that AMEC provided
VDOT timely written notice of its intention to file a claim for
damages resulting from the plan error regarding the
construction of concrete shafts on pier 18 on Bridge 616. On
20
remand, the circuit court should award AMEC damages that it
incurred regarding this claim.
With respect to the remaining claims discussed above, we
agree with the Court of Appeals that AMEC did not provide VDOT
with timely written notice of its intention to file a claim.
II. Elevated Lake Water Levels
A. Issue
The key feature of the contract was the construction of
Bridge 616 across Kerr Lake, a dam-controlled reservoir, which
is managed by the United States Army Corps of Engineers (the
U.S. Army Corps) in part to prevent flooding downstream on the
Roanoke River. The U.S. Army Corps regulates Kerr Lake’s water
level, usually maintaining a “normal level” of 300 feet. When
the water level rises to 305 feet, the U.S. Army Corps begins
releasing water at a certain rate and increases that rate as
the water continues to rise. The lake water level was critical
to the construction of Bridge 616 because AMEC could not access
the lake and complete the columns that hold up the bridge when
the water level was too high.
The contract contemplated routine fluctuations in the
water level of Kerr Lake. Specifically, the Site Information
section of the Special Provisions for Drilled Shafts states, in
pertinent part, that
21
due to the method of operating the John H. Kerr
Reservoir and other factors beyond the control
of the Department, the power pool elevation in
the reservoir routinely fluctuates by several
feet. These fluctuations can take place within
a few days. It is the responsibility of the
Contractor to avail himself of the historical
records of the water levels maintained by the
U.S. Army Corps of Engineers, Wilmington
District and determine the impacts possible
fluctuations may have on planned construction
methods and operation.
At trial, Grant Ralston, AMEC’s estimate and engineering
manager, testified that AMEC knew that the lake water level
fluctuated and looked at the historical average lake water
levels before determining that AMEC could complete the project
even if it had to shut down construction for a while due to
high water. Ralston acknowledged that he “knew [Kerr Lake]
fluctuated over a long period of time” and that “[t]here was no
doubt in [his] mind that the water had been up and down for a
long period of time,” but asserted that he took into
consideration the U.S. Army Corps’ information regarding lake
water levels while preparing the estimate for the project.
Ralston testified that while creating the project schedule,
“[they] were aware that [they] would have to deal with this
[sic] fluctuating lake elevations, so [they] would have to
adjust the amount of time [they were] out there to reflect
that.” Essentially, AMEC planned to do other tasks during the
time periods when the lake water level fluctuated to a higher
22
level. According to Ralston, AMEC also properly planned at bid
time for the usual high water period between February and June
of each year.
However, in 2003, the lake water level remained high for
six months, thereby substantially delaying AMEC’s work,
primarily the construction of Bridge 616. Charlie H. Guerrant,
VDOT’s construction manager, who lived in the area of the
project his entire life, testified that Kerr Lake had been at
higher levels than those encountered in 2003, “but not for that
long of a period.” Guerrant described the duration of the
elevated lake water levels as unusual and stated that when he
began the project, he did not expect the water level to remain
as high as it did for the length of time that it did in 2003.
Dale V. Goodman, VDOT’s resident administrator, also testified
that the duration of the high water at Kerr Lake was an unusual
circumstance. In March 2003, AMEC’s project manager, Peter
Buchardt, wrote a letter to VDOT informing it that “[c]ontrary
to the information provided [on the U.S. Army Corps’ website],
the levels actually encountered during the past month exceed
307.71 [feet],” and that “[t]hese conditions ha[d] stopped
[AMEC’s] critical path operations,” and advised VDOT that an
overall claim for the delays would be submitted.
A year later, as a result of the sustained elevated lake
water levels, VDOT issued two work orders extending the project
23
completion date from December 31, 2003 to October 14, 2004. In
an August 2004 letter to AMEC, VDOT asserted that the time
extension was granted because “the period of time from
approximately March 1, 2003 through July 27, 2003 represented
an unusual period of high water levels (148 days),” but VDOT
did not award AMEC compensation for the delays.
B. Discussion
Specification § 104.03 of the contract, titled “Differing
Site Conditions,” provided for relief in the form of additional
compensation to AMEC when either (1) “subsurface or latent
physical conditions” encountered during the work “differ[ed]
materially from those indicated in the Contract,” (Type I
condition) or (2) “unknown physical conditions of an unusual
nature, differing materially from those ordinarily encountered
and generally recognized as inherent in the work provided for
in the Contract” are encountered (Type II condition).
The Court of Appeals held that AMEC’s “high-water”
differing site condition claim was defeated by the contract as
a matter of law. AMEC Civil, LLC, 54 Va. App. at 264, 677
S.E.2d at 645. The Court of Appeals concluded that no Type I
condition existed because the elevated lake water levels did
not differ from any condition indicated in the contract, as the
contract established neither a baseline nor even a range of
fluctuations, but instead advised AMEC that the water level of
24
the lake routinely fluctuates by several feet and directed AMEC
to review the historical records to take into account non-
routine possible fluctuations. Id. at 265, 677 S.E.2d at 646.
The Court of Appeals also held that no Type II condition
existed. Id. at 266, 677 S.E.2d at 646. The Court of Appeals
reasoned that only an unknown, unforeseeable and unusual
physical condition can be a Type II condition under
Specification § 104.03. Id. In the Court of Appeals’ opinion,
routine and non-routine water level fluctuations presented
known conditional risks associated with the worksite, and such
known conditional risks, “whether of an unusual nature or not,”
should have been factored into AMEC’s risk assessment. Id.
On appeal to this Court, AMEC argues that the sustained
periods of elevated lake water levels constituted a differing
site condition, because they were sustained high water levels
beyond anything recorded by the U.S. Army Corps and unusual and
unexpected by everyone, including VDOT representatives.
According to AMEC, the Court of Appeals applied an improper
standard of review to the circuit court’s findings of fact, in
reviewing the circuit court’s findings de novo.
VDOT responds that the Court of Appeals correctly held
that the elevated water levels were neither a Type I or Type II
differing site condition. VDOT maintains that the sustained
water levels were not a Type I differing site condition because
25
they did not differ materially from any indication in the
contract, as the contract did not establish a baseline or even
a range of fluctuations and did not make any binding
representations on the subject. VDOT argues that the sustained
water levels also were not a Type II differing site condition
because they were a known, predicable condition, and AMEC knew
that there had previously been sustained periods of high water.
In Asphalt Roads & Materials Company, Inc. v.
Commonwealth, 257 Va. 452, 457, 512 S.E.2d 804, 806 (1999),
this Court stated, when interpreting a similar differing site
condition clause, that
[t]he purpose of the differing site
conditions clause and similar clauses, described
in a number of cases as the “changed conditions
clause,” has been stated in several cases. The
North Carolina Court of Appeals, for example,
has stated that its purpose is “[t]o encourage
low, competent bids,” Ray D. Lowder, Inc., v.
North Carolina State Highway Comm’n, 217 S.E.2d
682, 696, (N.C. Ct. App.) cert. denied, 218
S.E.2d 467 (N.C. 1975).
Similarly, the Court of Claims stated that
the purpose of the clause was:
[T]o take at least some of the gamble
on subsurface conditions out of bidding.
Bidders need not weigh the cost and ease of
making their own borings against the risk
of encountering an adverse subsurface, and
they need not consider how large a
contingency should be added to the bid to
cover the risk. They will have no
windfalls and no disasters. The Government
benefits from more accurate bidding,
without inflation for risks which may not
26
eventuate. It pays for difficult
subsurface work only when it is encountered
and was not indicated in the logs.
Foster Constr. C. A. & Williams Bros. Co. v.
United States, 435 F.2d 873, 887 (Ct. Cl. 1970).
The differing site conditions clause is intended to “shift
the risk of adverse subsurface or latent physical conditions
from the contractor, who normally bears such risk under a
fixed-price contract, to the government.” Olympus Corp. v.
United States, 98 F.3d 1314, 1316 (Fed. Cir. 1996). The
differing site conditions clause is designed to ensure low,
competent bids. Asphalt Roads & Mat’ls Co., 257 Va. at 457,
512 S.E.2d at 806.
To determine whether a Type I differing site condition
existed requires the court first to interpret the contract,
which is a legal inquiry reviewed de novo on appeal, and then
to engage in a factual inquiry. Randa/Madison Joint Venture
III v. Dahlberg, 239 F.3d 1264, 1274 (Fed. Cir. 2001); Turnkey
Enterprises, Inc. v. United States, 597 F.2d 750, 755 n.12 (Ct.
Cl. 1979). For a contractor to show the existence of a Type I
differing site condition, “the contractor must prove, by a
preponderance of the evidence, that the conditions indicated in
the contract differ materially from those it encounters during
performance.” Randa/Madison Joint Venture III, 239 F.3d at
1274 (quoting H.B. Mac, Inc. v. United States, 153 F.3d 1338,
27
1345 (Fed. Cir. 1998))(internal quotation marks omitted). The
contract must contain a “reasonably plain or positive
indication that the conditions to be encountered would be other
than those actually encountered at the time of performance,”
Turnkey Enterprises, Inc., 597 F.2d at 754-55, and “[t]he
conditions actually encountered must have been reasonably
unforeseeable based on all the information available to the
contractor at the time of bidding.” Meyers Cos., Inc. v.
United States, 41 Fed. Cl. 303, 309 (1998) (quoting Stuyvesant
Dredging Co. v. United States, 834 F.2d 1576, 1581 (Fed. Cir.
1987)) (internal quotation marks omitted).
Analysis of whether a Type II differing site condition
exists does not require contract interpretation, and is a
factual determination. Randa/Madison Joint Venture III, 239
F.3d at 1277; Turnkey Enterprises, Inc., 597 F.2d at 758. In
order to qualify as a Type II differing site condition, “the
unknown physical condition must be one that could not be
reasonably anticipated by the contractor from his [or her]
study of the contract documents, his [or her] inspection of the
site, and his [or her] general experience[,] if any, as a
contractor in the area.” Randa/Madison Joint Venture III, 239
F.3d at 1276 (quoting Perini Corp. v. United States, 381 F.2d
403, 410 (Ct. Cl. 1967)) (internal quotation marks omitted).
The contractor must show that “it did not [know] about the
28
physical condition, that it could not have anticipated the
condition from inspection or general experience, and that the
condition varied from the norm in similar contracting work.”
Walser v. United States, 23 Cl. Ct. 591, 593 (1991).
We hold that under the plain language of the
Specifications, the sustained elevated water levels did not
constitute a Type I differing site condition, as the water
levels were not a subsurface or latent physical condition in
existence at the time that the contract was executed. We
therefore do not need to engage in an interpretation of the
Site Information section of the Special Provisions for Drilled
Shafts or to determine if the sustained elevated water levels
differed materially from what was represented in the contract.
We conclude, however, that the sustained elevated water
levels formed a Type II differing site condition under
Specification § 104.03, as they were an unknown physical
condition of an unusual nature, which differed materially from
those ordinarily encountered and generally recognized as
inherent in the work provided for in the contract. The Court
of Appeals erred by deciding this issue as a matter of law, as
an inquiry into whether a Type II differing site condition
existed presents a question of fact. Randa/Madison Joint
Venture III, 239 F.3d at 1277; Turnkey Enterprises, Inc., 597
F.2d at 758.
29
We stated in Asphalt Roads & Materials Company, Inc. that
“in the absence of clear evidence to the contrary in the
record, we presume that [the circuit court] correctly applied
the provisions of [Specification] § 104.03 to the facts and
that, in doing so, it resolved any conflict in the facts in
favor of the contractor.” 257 Va. at 458 n.6, 512 S.E.2d at
807 n.6. This presumption is bolstered by ample evidence in
the record, from both AMEC’s and VDOT’s witnesses, that the
sustained elevated water levels were of an “unusual duration,”
presenting an “unusual circumstance,” and not ordinarily
encountered as inherent in the construction work provided for
in the contract. Moreover, the unknown physical condition was
not one that could be reasonably anticipated by AMEC from its
study of the contract, inspection of the site, or general
experience as a contractor in the area. Randa/Madison Joint
Venture III, 239 F.3d at 1276.
The risk of sustained high water in Kerr Lake was unusual,
and not one that AMEC was charged with the responsibility of
including in its bid. AMEC properly incorporated only the
costs associated with routine fluctuations after consulting the
U.S. Army Corps’ website and reviewing historical water level
information. VDOT benefited from more accurate bidding,
without inflation for a risk that might not have eventuated,
but now must bear the costs associated with a risk that came to
30
fruition and adversely impacted AMEC’s ability to complete
construction as scheduled.
Additionally, we disagree with VDOT’s assertion that the
sustained elevated water levels were a natural event and
therefore an act of God. It is undisputed that Kerr Lake is a
dam-controlled reservoir and that its water level is managed by
the U.S. Army Corps, partly to prevent flooding downstream on
the Roanoke River. The sustained elevated water levels were
not a natural event, as they resulted from the U.S. Army Corps’
exercise of its control over the dam, which dictated the water
level of Kerr Lake. Thus, VDOT’s contention that the sustained
elevated water levels are barred from consideration as a
differing site condition on this basis is unsupported by the
evidence.
C. Calculation of Damages
With regard to calculation of AMEC’s additional
compensation, AMEC argues that it is entitled to compensation
on a force account basis per Specification § 109.05 for damages
it sustained from the elevated lake water levels. AMEC
contends that Specification § 109.05 provides that contractors
will be paid on a force account basis for extra work caused by
a differing site condition when the parties cannot agree on a
price for such extra work.
31
VDOT argues that AMEC is not entitled to damages as
calculated under Specification § 109.05 because VDOT did not
require AMEC to perform work on a force account basis.
Additionally, VDOT asserts that “AMEC did not seek recovery
based on work VDOT ordered AMEC to perform on a force account
basis.”
Specification § 109.05, titled “Extra and Force Account
Work,” provides cost mark-ups for “extra work” and “force
account work” performed by contractors. Under Specification
101.02, “Extra work” is defined as an “item of work that is not
provided for in the Contract as awarded but that is found to be
essential to the satisfactory fulfillment of the Contract
within its intended scope.” Although the sustained elevated
water levels caused construction delays and problems, the work
performed, namely the construction of Bridge 616, was work
provided for in the contract. Thus, AMEC’s claim for damages
caused by the sustained elevated lake water levels is not a
claim for “extra work” because the work at issue was provided
by the contract.
“Force account work,” under Specification § 101.02, is
defined as “[p]rescribed work of a contractual status performed
by the Contractor and compensated for as specified in Section
109.05.” Specification § 109.05, in pertinent part, provides:
32
Extra work performed in accordance with the
requirements of Section 104.03 will be paid for
at the unit prices or lump sum specified in the
work order. In lieu of such agreement, the
Department may require the Contractor to do such
work on a force account basis . . . .
The work performed by AMEC, which was required by the contract
but complicated due to the elevated lake water level, was also
not “force account work” because it was neither additional work
prescribed by VDOT, nor work that VDOT ordered be done on a
“force account basis.” Therefore, AMEC is not entitled to
compensation under Specification § 109.05 for damages caused by
the elevated lake water level.
Specification § 104.03, however, provides relief to
contractors when differing site conditions impede performance
of the contract. This Specification contains a clause that
allows for an adjustment to the contract for additional costs
resulting from differing site conditions, which states:
Upon written notification, the Engineer will
investigate the conditions, and if it is
determined that the conditions materially differ
and cause an increase or decrease in the cost or
time required for the performance of any work
under the Contract, an adjustment, excluding
anticipated profits, will be made and the
Contract modified in writing accordingly.
Therefore, Specification § 104.03 provides that “an adjustment,
excluding anticipated profits” is the proper measure of damages
for increased cost or time for performance of work caused by a
differing site condition.
33
Upon remand, the circuit court shall calculate the
appropriate adjustment to the contract, excluding any profit,
based on costs incurred by AMEC through increased time required
to perform the contract, as a result of sustained elevated lake
water levels.
III. Home Office Overhead
The Court of Appeals held that AMEC failed to prove that
it could not recoup home office overhead costs from other
revenue-producing work. AMEC Civil, LLC, 54 Va. App. at 275,
677 S.E.2d at 651.
AMEC argues that the Court of Appeals improperly created
an unreasonable standard of proof concerning home office
overhead, and should have examined whether the circuit court’s
findings were plainly wrong or unsupported by the evidence.
AMEC asserts that because it kept its labor and equipment on
site and performing non-critical and less productive work, the
evidence showed that AMEC could not recoup the project’s pro
rata share of home office overhead elsewhere.
VDOT contends that AMEC failed to prove it could not
reasonably recoup its home office overhead from other revenue-
producing work during the periods of delay and therefore was
not entitled to an award of those expenses. According to VDOT,
the circuit court made no findings of fact or conclusions of
law on AMEC’s entitlement to home office overhead, and the
34
circuit court’s general verdict was contrary to the evidence
and to the contract.
This Court explained in Fairfax County Redevelopment and
Housing Authority v. Worcester Bros. Co., Inc., that
[h]ome office expenses, commonly called
overhead, include those costs that a contractor
must expend for the benefit of its business as a
whole. These expenses include, for example, the
salaries of office staff, accounting expenses,
dues and subscriptions, equipment costs, and
utility services. Unabsorbed home office
expenses comprise “those overhead costs
needlessly consumed by a partially or totally
idle contractor. A contractor continues to
incur overhead costs during periods of reduced
activity or delay on a particular contract.
When this occurs, the ‘reduced activity’
contract no longer ‘absorbs’ its share of
overhead costs.”
257 Va. 382, 387-88, 514 S.E.2d 147, 150 (1999) (quoting
Michael W. Kauffman and Craig A. Holman, The Eichleay Formula:
A Resilient Means for Recovering Unabsorbed Overhead, 24 Pub.
Contr. L.J. 319, 321 (1995)). Entitlement to home office
overhead is a question of fact. Id. at 388, 391, 514 S.E.2d at
151-52.
To prove that it suffered unabsorbed overhead damages, a
contractor is not required to show that its overhead was
increased due to the delay, “but only that it could not
otherwise reasonably recoup its pro rata home office expenses
incurred while its workforce was idled by the delay.” Id. at
388, 514 S.E.2d at 151.
35
We agree with the Court of Appeals that AMEC did not meet
its burden of proving that it could not reasonably recoup its
home office overhead from other revenue-producing work. The
record contains no evidence addressing this issue. The
evidence presented by AMEC consisted of a mathematical model
that assumed that AMEC could not have directed employees to
other revenue-producing work, including other work under this
contract. AMEC’s expert merely calculated a per diem rate of
delay and multiplied the rate by the number of days of delay.
Neither AMEC’s expert or any fact witnesses presented any
evidence that AMEC could not have recouped its home office
overhead from other revenue-producing work. Lockheed Info.
Mgmt. Systems Co., Inc. v. Maximus, Inc., 259 Va. 92, 116, 524
S.E.2d 420, 433 (2000). Therefore, AMEC is not entitled to home
office overhead expenses.
IV. Calculation of Actual Costs
The equipment costs included in AMEC’s claim were priced
according to the “Rental Rate Blue Book” (the Blue Book),
utilizing specific portfolios of equipment for all the elements
of work that were performed. AMEC based its use of the Blue
Book on Specification § 109.05. Pursuant to Specification
§ 109.05(d),
Equipment: . . . The Contractor will be
paid hourly rental rates for pieces of
machinery, equipment, and attachments necessary
36
for prosecution of the work that are approved
for use by the Engineer. Hourly rental rates
will not exceed 1/176 of the monthly rates of
the schedule shown in the Rental Rate Blue Book
modified in accordance with the Blue Book rate
adjustment tables that are current at the time
the force account is authorized. Adjustment
factors or rate modifications indicated on area
maps in the Blue Book will not be considered
when acceptable rates are determined. . . .
AMEC made no adjustments to the Blue Book rates for age or
region of the equipment.
The Court of Appeals held that the circuit court was not
plainly wrong in accepting the Blue Book as a standard used in
the profession to estimate actual costs for owner-furnished
equipment. AMEC Civil, LLC, 54 Va. App. at 277 n.32, 677
S.E.2d at 652 n.32. Therefore, the Court of Appeals held that,
on remand, the Blue Book estimates could be relied upon by the
circuit court as a basis to determine owner-furnished equipment
costs. 6 Id.
It is undisputed that the measure of damages in this case
is actual cost. However, the parties dispute whether the Blue
Book is an appropriate method of proving actual cost.
VDOT contends that AMEC did not make out a prima facie
case of damages because AMEC did not prove actual cost. VDOT
argues that the Blue Book provides only an estimate of costs
6
The Court of Appeals remanded to the circuit court to
determine whether the evidence provides a reasonable basis to
37
and does not prove actual cost, which is the measure of damages
required by Specification § 105.16. 7 Additionally, VDOT argues
that if it intended to allow AMEC to use the Blue Book to
calculate costs for claims under Specification § 105.16, VDOT
would have included a provision allowing the use of the Blue
Book.
Lastly, VDOT asserts that, assuming AMEC’s use of the Blue
Book was appropriate, AMEC failed to make adjustments to the
Blue Book’s estimated base equipment rental rates taking into
account such factors as the age of the equipment, the region
where the equipment was used, and purchase price. According to
VDOT, these adjustments would generally reduce the rental rates
to more closely approximate actual costs.
AMEC contends that, even if Specification § 109.05 is
inapplicable, the Blue Book was properly used to establish
AMEC’s actual damages for owner-furnished equipment under
establish the actual costs AMEC incurred. AMEC Civil, LLC, 54
Va. App. at 277, 677 S.E.2d at 652.
7
Specification § 105.16, “Submission and Disposition of
Claims,” provides, in pertinent part, that “[a]t the time of
occurrence or prior to beginning the work, the Contractor shall
furnish the Engineer an itemized list of materials, equipment,
and labor for which additional compensation will be claimed.
Only actual cost for materials, labor, and equipment will be
considered.” It further provides that, “[u]pon completion of
the Contract, the Contractor may, within 60 days from the time
the final estimate is paid, submit to the Department a written
claim . . . for the amount he deems he is entitled to under the
Contract. . . . Only actual cost for materials, labor, and
equipment will be considered.”
38
Specification § 105.16. AMEC asserts that the Blue Book rates
incorporate ownership and operating costs, including
depreciation costs, insurance, property taxes, costs of
facilities capital, repairs, and fuel. AMEC maintains that
expert testimony established that the Blue Book is accepted as
a standard used in the profession for determining owner-
furnished equipment costs. AMEC argues that the evidence at
trial also supported the circuit court’s finding that the Blue
Book rates accurately represented AMEC’s actual equipment
costs.
Theodore E. NeSmith testified as AMEC’s expert on
construction cost accounting and construction damage
calculations. NeSmith is a certified public accountant and a
certified valuation analyst for a certified public accounting
firm that specializes in forensic accounting and business
valuation, primarily in two areas: business damages and
construction damages. AMEC hired NeSmith to “review, assess,
and to the degree necessary, modify the damage claim that AMEC
had already prepared relating to [the] project.”
NeSmith testified as an expert that he has used the Blue
Book to calculate costs incurred by a contractor on multiple
occasions. With regard to the integrity of utilizing the Blue
Book, NeSmith stated, “if the objective is to get to the true
cost number of operating owned equipment, clearly Blue Book is
39
the most reflective of that.” When VDOT objected to NeSmith’s
testimony about the integrity of the Blue Book, the circuit
court stated, “It seems to me it’s been established thus far
that this Blue Book is a standard used in the profession for
estimating these costs, and I don’t think you need to go
further than that unless the validity is challenged by the
defense.” VDOT did not respond. NeSmith testified that the
equipment costs claimed by AMEC were “equivalent to and
represent[] the damages that were experienced by AMEC.”
The record supports the circuit court’s conclusion that
the Blue Book represents an industry standard for determining
the cost of operating owned equipment. According to the
unchallenged expert testimony, use of the Blue Book is an
accepted method to prove actual costs. Thus, the expert
testimony has established that the Blue Book is an appropriate
methodology of calculation so that VDOT’s challenge is a
challenge to the weight of the evidence rather than to its
admissibility. Because the Blue Book is recognized as an
appropriate tool for determining owner-furnished equipment
costs for purposes of proving actual costs, we hold that the
Court of Appeals properly affirmed the circuit court’s
acceptance of the Blue Book for the purpose of calculating such
costs.
40
V. Pre-Judgment Interest
The circuit court did not award AMEC pre-judgment interest
“because it [could] find no authority giving it jurisdiction to
do so.” The Court of Appeals held the circuit court properly
denied AMEC’s request for pre-judgment interest, as Code
§ 33.1-386(A) says nothing about an allowance of pre-judgment
interest on contractually recoverable costs and expenses. AMEC
Civil, LLC, 54 Va. App. at 279-80, 677 S.E.2d at 652-53.
AMEC argues that the Court of Appeals erred by determining
that VDOT was not liable for pre-judgment interest and that a
separate and distinct waiver of sovereign immunity was required
before AMEC could recover pre-judgment interest. AMEC
maintains that the Commonwealth is like any other citizen and
is liable for interest on contractual debts.
VDOT contends that it is not liable for pre-judgment
interest, as the Commonwealth is not liable for interest absent
express statutory authority or a contract provision explicitly
imposing such liability, and neither Code § 8.01-382 nor the
contract make VDOT liable for pre-judgment interest. According
to VDOT, the Commonwealth does not waive its immunity simply by
entering into a contract.
We have previously held that the Commonwealth is “as
liable for its contractual debts as any citizen would be.”
Wiecking v. Allied Medical Supply Corp., 239 Va. 548, 553, 391
41
S.E.2d 258, 261 (1990). However, in order for the Commonwealth
to be liable for pre-judgment interest, there must be a
statutory or contractual waiver of sovereign immunity with
respect to this distinct item of damages.
Nearly a century ago, this Court stated, “it has never
been held by this court that a claim asserted against the State
or a county bears interest where there is no provision in the
statute or authorized agreement creating the liability for the
payment of interest.” City of Lynchburg v. Amherst County, 115
Va. 600, 608, 80 S.E. 117, 120 (1913). We continue to adhere
to this long-standing rule. Thus, in the absence of a
statutory or contractual waiver, the Commonwealth and its
agencies have sovereign immunity from liability for pre-
judgment interest on contract claims. In this case, there has
been no statutory or contractual waiver of VDOT’s sovereign
immunity and, therefore, the Court of Appeals correctly
affirmed the circuit court’s denial of pre-judgment interest
sought by AMEC.
CONCLUSION
For the reasons stated, we will affirm in part and reverse
in part the judgment of the Court of Appeals. We will affirm
the Court of Appeals’ judgment on all but two issues.
Specifically, we will reverse the Court of Appeals’ judgment
that the sustained elevated lake water levels did not
42
constitute a differing site condition, and that AMEC did not
provide timely written notice of its claim for plan error
regarding the construction of concrete shafts for pier 18 on
Bridge 616.
We will remand the case to the Court of Appeals with
instructions to remand the case to the circuit court for
further proceedings consistent with this opinion. On remand,
in deciding the issues addressed by this Court, the circuit
court shall review the evidence already presented in the case
and calculate damages to which AMEC is entitled for the
following claims: plan error regarding the construction of
concrete shafts for pier 18 on Bridge 616; acceleration damages
incurred after April 2004; and delay damages resulting from the
sustained elevated lake water levels, as calculated per
Specification § 104.03, which shall constitute actual costs
incurred by AMEC, excluding profit. Additionally, in computing
owned equipment costs, the circuit court shall calculate a
damage award based upon Blue Book estimates, as testified by
expert witnesses, which reflect actual costs.
On remand, the circuit court shall also consider the Court
of Appeals’ holdings that were not challenged on appeal to this
Court. Specifically, the circuit court shall follow the Court
of Appeals’ direction to: review the record and make findings
on whether AMEC is entitled to damages for conditions during
43
either or both of the winter periods, and if the court finds in
favor of AMEC, identify the contractual basis of such award and
make factual findings as to any damages awarded; review the
record and make findings on whether AMEC proved its entitlement
to damages resulting from the boulders at bridge B640; and
award damages associated with AMEC’s bond premium. Finally, on
remand, the circuit court shall apply actual costs as the
measure of damages for the claims surviving appeal.
Affirmed in part,
reversed in part,
and remanded.
44