Legal Research AI

Upper Occoquan Sewage Authority v. Blake Construction Co.

Court: Supreme Court of Virginia
Date filed: 2003-10-31
Citations: 587 S.E.2d 721, 266 Va. 582
Copy Citations
25 Citing Cases

PRESENT: HASSELL, C.J., KEENAN, KOONTZ, KINSER, LEMONS, and
AGEE, JJ., and CARRICO, S.J.

UPPER OCCOQUAN SEWAGE AUTHORITY
                                            OPINION BY
v.   Record No. 022528                JUSTICE G. STEVEN AGEE
                                         OCTOBER 31, 2003
BLAKE CONSTRUCTION CO., INC./
POOLE & KENT

             FROM THE CIRCUIT COURT OF FAIRFAX COUNTY
                     Hon. Jane M. Roush, Judge

      Upper Occoquan Sewage Authority ("UOSA") appeals rulings of

the Circuit Court of Fairfax County in proceedings which arose

out of a construction contract between UOSA and Blake

Construction Company/Poole & Kent ("the Joint Venture").    On

appeal, UOSA's multiple assignments of error essentially assert

the trial court erred by: (1) denying UOSA's application for

costs under Code § 2.2—4335(A); (2) denying UOSA's motion to

strike certain Joint Venture claims on the basis of filing

appeals more than six months after UOSA's final written

decisions denying the claims; and (3) denying UOSA's motion to

strike and motion for judgment notwithstanding the verdict on

the basis that certain Joint Venture notices of claim or time

impact analyses either were not filed or were filed late.

      For the following reasons, we will affirm in part and

reverse in part the judgment of the trial court.

                          I.    BACKGROUND

      This litigation involves multiple disputes arising out of a

contract for construction of a waste water treatment facility
located in Fairfax County (the "Project").   UOSA, the owner of

the facility, is a public authority created pursuant to the

Virginia Waste and Water Authorities Act, Code § 15.2-5100

through -5158, to provide waste water reclamation for its member

jurisdictions, the counties of Fairfax and Prince William and

the cities of Manassas and Manassas Park.    As a public

authority, UOSA is subject to the Virginia Public Procurement

Act, Code § 2.2-4300 through -4377 1 (the "VPPA").

     Blake Construction Co., Inc. and Poole & Kent Corporation

formed the Joint Venture in order to submit a bid for the

Project.   The Joint Venture's bid was successful, and the Joint

Venture agreed to furnish all labor, materials, and equipment

for the Project in a contract dated December 10, 1996 (the

"Contract").   The Contract allows the Joint Venture to obtain an

increase in the contract price and/or an extension of time to

complete certain work upon written application to UOSA pursuant

to procedures set forth in the Contract.

     The Joint Venture began work on the Project in January 1997

which is ongoing at the time of this appeal.   During the course

of the work, numerous changes were made to the original




     1
       At the time the claims at issue in this appeal arose in
the trial court, the VPPA was codified at Code § 11-35 et seq.,
but was recodified at Code § 2.2-4300 et seq. by the General
Assembly in 2001. We will refer to the corresponding provisions
of the current Code of Virginia in this opinion.

                                 2
contract, some of which are in dispute and resulted in the

proceedings now at bar.

     Procedures set forth in the Contract allow the Joint

Venture to obtain an increase in the contract price and/or an

extension of time to complete certain work upon written

application to UOSA.     If UOSA issues an adverse final decision

on the claim (i.e. denies the claim), the VPPA allows the Joint

Venture to appeal that final decision to the circuit court

"within six months of the date of the final decision on the

claim by the public body" for a de novo determination of its

claim.     See Code § 2.2-4363(D). 2   As the Project remains ongoing,

this has engendered litigation by the parties while their

contractual relationship continues.

     The Joint Venture filed six lawsuits appealing adverse

claim decisions by UOSA which were eventually consolidated by

order of the trial court (collectively, the "consolidated

cases").     UOSA filed a plea in bar to approximately sixty of the

claims pled by the Joint Venture in the consolidated cases.       The

plea in bar alleged that the Joint Venture failed to comply in a

     2
         Code § 2.2-4363(D) provides:
            The decision of the public body shall be
            final and conclusive unless the contractor
            appeals within six months of the date of the
            final decision on the claim by the public
            body by invoking administrative procedures
            meeting the standards of § 2.2-4365, if
            available, or in the alternative by
            instituting legal action as provided in
            § 2.2-4364.
                                  3
timely manner with various contractual and statutory procedural

requirements.

     On September 28, 2001, the jury returned a verdict in the

plea in bar proceeding on a special verdict form noting separate

adjudications for each claim. 3   Pursuant to that verdict, the

trial judge, Judge Roush, entered an order on October 24, 2001

("the October 24th order"), denying UOSA's plea in bar on

twenty-nine of the Joint Venture's claims.    The October 24th

order also included this stipulation: "The parties also

stipulate that the Amended Motion for Judgment and Declaratory

Judgment filed in Law 193766 contains no claim for unspecified

delays or manipulation of schedule other than as may be included

in any specific claim itemized therein." 4

     Both parties made post-trial motions to set aside portions

of the verdict, which the trial court denied.    The remaining

issues in the consolidated cases were set for a trial on the

merits to begin June 17, 2002.

     While the plea in bar trial primarily dealt with the notice

and timely filing procedural requirements of certain claims,

separate issues were raised by the Joint Venture through the

amended motion for judgment and declaratory judgment in Law



     3
       During the trial, the Joint Venture withdrew some claims
as premature and non-suited others.
     4
         Law #193766 is one of the consolidated cases.

                                  4
#193766.   The Joint Venture asserted, in part, a violation of

the VPPA regarding a bar on damages for unreasonable delay,

which is the subject of the companion appeal, Blake Construction

Co., Inc./Poole & Kent v. Upper Occoquan Sewage Authority, 266

Va. ___, ___ S.E.2d ___ (2003) (today decided).   The declaratory

judgment action also requested a declaration that UOSA

materially breached the Contract and the Joint Venture was thus

entitled to "[r]ecover the reasonable value of its services

performed to the date of termination, plus a reasonable

allowance for overhead and profit."

     In supplemental responses to interrogatories prior to the

scheduled trial date, the Joint Venture calculated its damages

"[b]ecause UOSA is in material breach of the Contract."    The

Joint Venture's measure of damages was "its reasonable costs

incurred in prosecuting the work plus the Joint Venture's

[General & Administrative] overhead less that which has already

been paid."   As of February 28, 2002, the Joint Venture

represented its material breach damages to be $63,258,497.

     UOSA filed a motion to strike damages for material breach

on January 25, 2002.   After a hearing on February 8, 2002, Judge

Roush denied the motion.   Ruling from the bench, she said the

Joint Venture's declaratory judgment pleading "is a classic use

of a declaratory judgment action, I think it's appropriate."

That same day, Judge Roush entered an order ("the February 8th

order"), memorializing the bench ruling which provides in
                                5
pertinent part:    "[i]t appearing that the motion to strike the

Joint Venture's damages for material breach should be denied, it

is therefore ORDERED that UOSA's motion to strike the Joint

Venture's damages for material breach be and hereby is denied."

        Judge Finch, substituting for Judge Roush, opined from the

bench during a May 23, 2002, pretrial hearing that "material

breach is no longer an issue . . . therefore, the effect is that

all damages regarding material breach are to be excluded from

the trial of these consolidated cases."       No order appears in the

record to implement or explain Judge Finch's remarks from the

bench.    The Joint Venture non-suited the material breach claim

and all remaining claims in the consolidated cases on May 29,

2002.

        UOSA subsequently filed an application for costs pursuant

to Code § 2.2-4335(C) seeking $2,962,715.13.      The trial court

held an evidentiary hearing on UOSA's application for costs and

subsequently granted the Joint Venture's motion to strike.

        We granted UOSA this appeal.

                             II.   ANALYSIS

                   A.   UOSA's Application for Costs

        Code § 2.2-4335(C) provides protection to a public body for

delay claims made by contractors which are false or without

factual or legal basis.     The mechanism chosen by the General

Assembly is the in terrorem effect of recovering litigation


                                    6
costs from the contractor which are attributable to a frivolous

delay claim.   The statute provides in pertinent part:

     A contractor making a claim against a public body
     for costs or damages due to the alleged delaying
     of the contractor in the performance of its work
     under any public construction contract shall be
     liable to the public body and shall pay it for a
     percentage of all costs incurred by the public
     body in investigating, analyzing, negotiating,
     litigating and arbitrating the claim, which
     percentage shall be equal to the percentage of
     the contractor's total delay claim that is
     determined through litigation or arbitration to
     be false or to have no basis in law or in fact.

Code § 2.2-4335(C) (emphasis added).

     The trial court denied UOSA's application for costs under

the statute finding insufficient evidence of "a determination

within the meaning of the statute or to show that the delay

claims had no basis in law or fact."   For the following reasons,

we will affirm the judgment of the trial court.

     UOSA contends that the Joint Venture's claim for material

breach damages of $63,000,000 was, in actuality, a claim for

delay damages.   The Joint Venture responds that its damages lay

in quantum meruit and thus its claim was not one for delay

damages.

     UOSA argues the material breach claim was really a delay

damages claim that was effectively stipulated out of the case

through the October 24th order and verified by Judge Finch's

later bench ruling.   UOSA reasons that the continued litigation

of the material breach claim by the Joint Venture thereafter was

                                 7
essentially a de facto "determination" under the statute that

the material breach claim was a false act not based on law or

fact.       UOSA thus concludes it is entitled to a percentage of its

litigation costs incurred in opposing the material breach claim. 5

However, UOSA's argument runs into an immediate roadblock.

        Nothing in the October 24th order addresses the material

breach claim as set out in Law #193766.      More importantly, UOSA

cannot avoid the unmistakable clarity of the record which

contains the uncontradicted, succeeding and specific February

8th order finding material breach damages were in the

consolidated cases to be tried.

        As we noted in Hill v. Hill, 227 Va. 569, 578, 318 S.E.2d

292, 297 (1984), it is fundamental that "a court of record

speaks only through its written orders."      UOSA has not assigned

error to the February 8th order which specifically denied UOSA's

motion to strike material breach damages.      Accordingly, the

February 8th order is the law of the case.       See Searles v.

Gordon, 156 Va. 289, 294-96, 157 S.E. 759, 761 (1931).

        5
       As a tangential matter, we note the voluminous
documentation regarding UOSA's application for costs is
difficult to decipher and may well contain costs for non-delay
items. We also note UOSA offered no evidence at the hearing on
its application for costs except to introduce its cost records
and refer to the existing record in the case as evidence that a
"determination" within the meaning of the statute had already
occurred. Although we have reservations about UOSA's ability to
carry its initial burden under Code § 2.2-4335(C) with this
evidence alone, the trial court made no finding in that regard
so we will assume, for purposes of appeal, that UOSA's claimed

                                     8
     As in Hill, no order appears in the record to modify or

vacate the February 8th order.   For whatever purpose Judge Finch

may have remarked on material breach damages from the bench on

May 23, 2002, those remarks do not change the law of the case

and the binding effect of the February 8th order.    Hill, 227 Va.

at 578, 318 S.E.2d. at 297.

     It strains credulity that UOSA would ask the trial court to

clarify that it had already ruled the material breach claim was

stipulated out of the case over three months earlier in the

October 24th order, but not make that argument to the court at

the February 8th hearing or in its written motion.   That

invitation, if extended outside the record, was unequivocally

rejected by the trial judge through the plain and unmistakable

language of the February 8th order.

     The law of the case thus directs the finding that material

breach damages were very much in the consolidated cases until

the filing of the May 29, 2002, nonsuit.   Accordingly, UOSA's

argument that the material breach claim was out of the case

fails.   There is thus no evidence in the record of a false or

statutorily baseless delay damages claim upon which UOSA can

anchor its application for statutory costs.   The trial court's

judgment denying UOSA's cost application was therefore correct.




litigation costs were limited to the items it alleged were
related to delay damages claims.
                                 9
          B.   Special Verdicts on the Individual Claims

     The trial court conducted a plea in bar hearing from

September 17-28, 2001, at the conclusion of which forty-six

claims relating to time extensions were submitted to the jury.

The jury recorded its verdict on a special verdict form and

found that the Joint Venture was prohibited from pursuing

seventeen of its claims because it had either not complied with

the requirements for submitting claims under the Contract or had

failed to file suit within six months.   The jury found that

twenty-nine of the Joint Venture's claims were not procedurally

or time barred.   UOSA filed motions to strike and a motion

notwithstanding the verdict challenging the jury's findings.

The trial court denied those motions and entered an order

confirming the jury's verdict.

     UOSA assigns error to the denial of its motions to strike

and motion for judgment notwithstanding the verdict.

Specifically, UOSA asserts the trial court erred in:

     (1) denying its motion to strike and motion for judgment

     notwithstanding the verdict with respect to Work Orders 12,

     30, 39, 41, 64, 70, 71, 76, 106, 152, Claim 18, and PCO 115

     because the evidence showed the Joint Venture failed to

     file appeals of these claims within six months as required;

     (2) denying its motion to strike and motion for judgment

     notwithstanding the verdict with respect to Work Orders 113


                                 10
     and 175 because the Joint Venture expressly waived these

     claims by signing a change order;

     (3) denying its motion for judgment notwithstanding the

     verdict with respect to Work Orders 88, 106, 127, 193, and

     Claim 252 for lack of evidence that the Joint Venture

     timely submitted a time impact analysis as required; and

     (4) denying its motion for judgment notwithstanding the

     verdict with respect to Claims 240 and 280 for lack of

     evidence that the Joint Venture submitted a timely notice

     of claim as required.

     Under familiar principles of appellate review, we review

the evidence and all reasonable inferences flowing therefrom in

a light most favorable to the Joint Venture, which prevailed in

the trial court on the claims UOSA now contests.   WJLA-TV v.

Levin, 264 Va. 140, 146, 564 S.E.2d 383, 386 (2002) (citing RF&P

Railroad v. Metropolitan Wash. Airports Auth., 251 Va. 201, 208,

468 S.E.2d 90, 94 (1996)).   We will uphold the judgment of the

trial court unless it appears from the evidence that the




                                11
judgment is plainly wrong or without evidence to support it. 6

Code § 8.01-680; Nationwide Mut. Ins. Co. v. St. John, 259 Va.

71, 76, 524 S.E.2d 649, 651 (2000) (citing RF&P Corporation v.

Little, 247 Va. 309, 319, 440 S.E.2d 908, 915 (1994)).

     During the plea in bar trial the jury was asked to decide

whether the Joint Venture appealed certain claims within six

months, waived certain claims, submitted time impact analyses

for certain claims, and timely submitted a notice of claim for

other claims.   The jury determined the Joint Venture complied

with the Contract's requirements in each of the claims now

before us on appeal.   The jury's verdicts, in all but one




     6
          The standard under which a trial court
should review the evidence adduced at trial before
granting a motion to strike the case at the end of a
plaintiff's evidence is well settled under prior
decisions of this Court. That standard requires the
trial court to accept as true all the evidence
favorable to the plaintiff as well as any reasonable
inference a jury might draw therefrom which would
sustain the plaintiff's cause of action. The trial
court is not to judge the weight and credibility of
the evidence, and may not reject any inference from
the evidence favorable to the plaintiff unless it
would defy logic and common sense.

Austin v. Shoney's, Inc., 254 Va. 134, 138, 486 S.E.2d 285, 287
(1997).

                                12
instance, find evidentiary support in the record and cannot be

said to be plainly wrong. 7

     UOSA's proposed verdict form for Work Orders 12, 30, 39,

41, 64, 70, 71, 76, 106, 152, Claim 18, and PCO 115 asked the

jury to decide whether the Joint Venture filed suit within six

months of "UOSA's written decision on this claim challenging

such decision." (Emphasis added).    The verdict form submitted to

the jury substituted the word "final" for the word "written" but

otherwise mirrored UOSA's proposed language.    The record

reflects that the jury had sufficient evidence before it to

determine when the Joint Venture's claims began to accrue for

purposes of calculating the six-month period.   The jury's

findings on these issues cannot be said to be plainly wrong or

without evidentiary support.   Accordingly, we will affirm the

trial court's denial of UOSA's motion to strike and motion for

judgment notwithstanding the verdict for Work Orders 12, 30, 39,

41, 64, 70, 71, 76, 106, 152, Claim 18, and PCO 115.

     UOSA's proposed verdict form with respect to Work Orders

113 and 175 was adopted verbatim by the trial court.   In both

instances the jury found that the Joint Venture did not waive


     7
       In response to UOSA's assignments of error regarding the
individual "special verdict" claims the Joint Venture asserts
that UOSA did not "move to strike Work Orders 12, 41, 64, 70,
71, 106, Claim 18 or PCO 115." (BIO at 31). Because we find
that the jury's verdict with respect to these claims is not
plainly wrong or without evidence to support it, we do not
address the Joint Venture's contentions in this regard.

                                13
any claim by signing Change Order 79.   Given the evidence in the

record these findings cannot be said to be plainly wrong.     As

such, we will affirm the trial court's denial of UOSA's motion

to strike and motion for judgment notwithstanding the verdict

for Work Orders 113 and 175.

     The jury was asked to decide, with respect to Work Orders

88, 106, 127, 193 and Claim 252, whether the Joint Venture

timely submitted a time impact analysis as required by the

Contract.   The trial court adopted wholesale UOSA's proposed

instructions.   In each instance, the jury found that the Joint

Venture timely submitted a time impact analysis.   The evidence

in the record supports the jury's finding as to Work Orders 88,

106, 193 and Claim 252 which are thus not plainly wrong.

However, the verdict on Work Order 127 is without support in the

record.

     Work Order 127 was issued on August 16, 1999.   The only

evidence in the record as to a time impact analysis from the

Joint Venture is dated October 3, 2001, obviously long past the

Contract's seven day filing requirement.   During oral argument

before this Court the Joint Venture referenced a document that

would support the jury's finding with respect to Work Order 127.

However, the Joint Venture has since acknowledged this document

does not appear in the record and cannot be relied upon for

purposes of appeal.   Accordingly, there was no evidence to

support the jury's finding that the Joint Venture timely
                                14
submitted a time impact analysis regarding Work Order 127.       The

jury's verdict was therefore plainly wrong.

     We will affirm the trial court's denial of UOSA's motion

for judgment notwithstanding the verdict for Work Orders 88,

106, 193 and Claim 252, but will reverse the trial court with

respect to Work Order 127.

     Finally, with respect to Claims 240 and 280, the jury found

that the Joint Venture timely filed a notice of claim.     The

jury's decision is supported by the evidence in the record and

cannot be said to be plainly wrong.    We will affirm the trial

court's denial of UOSA's motion for judgment notwithstanding the

verdict for Claims 240 and 280.

                         III.   CONCLUSION

     For the foregoing reasons, we will affirm the trial court's

judgment denying UOSA's application for costs pursuant to Code

§ 2.2-4335(C).   We will affirm the judgment of the trial court

in denying UOSA's motion to strike and motion for judgment

notwithstanding the verdict as to Work Orders 12, 30, 39, 41,

64, 70, 71, 76, 88, 106, 113, 152, 175, 193, Claim 18, Claim

240, Claim 280, Claim 252, and PCO 115.      We will reverse the

judgment of the trial court in denying UOSA's motion for

judgment notwithstanding the verdict as to Work Order 127 and

enter final judgment.

                                                    Affirmed in part,
                                                    reversed in part,
                                                  and final judgment.
                                  15