IN THE COURT OF APPEALS OF TENNESSEE
AT NASHVILLE
August 6, 2003 Session
TRINITY INDUSTRIES, INC. v. McKINNON BRIDGE COMPANY, INC.
A Direct Appeal from the Chancery Court for Davidson County
No. 99-3454-I The Honorable Irvin H. Kilcrease, Jr., Chancellor
No. M2002-02713-COA-R3-CV - Filed September 22, 2003
In this case, appellant-contractor for construction of a bridge entered into a contract with
appellee-subcontractor for the fabrication and delivery of structural steel. By virtue of an indemnity
clause in the contract, the trial court held the contractor liable to the subcontractor for the amounts
expended by the subcontractor in settlement of a lawsuit filed against it and for the expenses incurred
in the defense of the lawsuit. Contractor appeals. We affirm.
Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Chancery Court Affirmed
W. FRANK CRAWFORD , P.J., W.S., delivered the opinion of the court, in which ALAN E. HIGHERS,
J. and HOLLY M. KIRBY, J., joined.
David J. Sneed, Cynthia B. Ferguson, Brentwood, For Appellant, McKinnon Bridge Company, Inc.
Hugh C. Howser, Jr., Mary Ellen Morris, David L. Johnson, Nashville, For Appellee, Trinity
Industries, Inc.
OPINION
In April 1994, Trinity Industries, Inc. (“Trinity,” “Plaintiff,” or “Appellee”) and McKinnon
Bridge Company, Inc. (“McKinnon,” “Defendant,” or “Appellant”) entered into a written Agreement
(the “Agreement”) wherein Trinity agreed to fabricate and deliver structural steel for the building
of a bridge over the Tennessee River near Clifton, Tennessee. McKinnon was the general contractor
for the Tennessee Department of Transportation (“TDOT”) on the bridge project and Trinity was
McKinnon’s steel fabrication subcontractor. McKinnon also subcontracted with ABC Contractors,
Inc. (“ABC”) to install the structural steel furnished by Trinity. The Agreement between Trinity and
McKinnon fully incorporated the terms of the bid quotation submitted by Trinity on September 3,
1993 (the “Quotation”). Regarding the incorporation of the Quotation, the Agreement reads, in
relevant part as follows:
Trinity Quotation No. B77-M93 dated 9/3/93 is incorporated herein
and forms a binding part of this agreement. B77-M93 shall prevail
over any conflicts, additions, modifications or omissions contained
herein, except as noted.
Paragraph Eighteen of the Quotation, as incorporated by the Agreement, reads as follows concerning
McKinnon’s obligation to indemnify Trinity:
...As between you [McKinnon] and us [Trinity], you [McKinnon]
assume all liability for injury to persons and damage to property
resulting from any handling of the steel from the time the truck
reaches the jobsite, and you agree to hold us [Trinity] and our
[Trinity’s] insurer harmless from any such liability. We [Trinity]
agree to indemnify and hold you [McKinnon] harmless from claims
and liens by any of our [Trinity’s] suppliers or subcontractors because
of our [Trinity’s] failure to discharge all obligations to them. You
[McKinnon] shall indemnify and hold us [Trinity] harmless and
defend us [Trinity] from any claim or litigations occasioned by
deficiencies in Design, Drawings, and Specifications provided to us
[Trinity] by you [McKinnon], and from any loss or liability resulting
from the failure, action or inaction of any party over which we
[Trinity] have no control.
On May 16, 1995, one ABC worker died and two others were injured when a segment of the
bridge being constructed by McKinnon collapsed, resulting in several suits for the losses and
damages: William M. Robinson and David Robinson v. Trinity Industries, Inc., No. 97-1093, Carres
Kennedy v. Trinity Industries, Inc., No. 97-1094, and Charles T. White v. Trinity Industries, Inc., No.
97-1118. The suits were originally filed in state court but were later removed to federal court where
they were consolidated. (for purposes of this opinion, these cases are collectively referred to as the
“Federal Suits”).1 In addition to the Federal Suits, Trinity Industries, Inc. v. McKinnon Bridge
Company, Inc., Safeco Insurance Company, J. Bruce Saltsman, Sr., Commissioner, Department of
Transportation, State of Tennessee, No. 95-3587-III-II, was filed in the Chancery Court of Davidson
County, Tennessee, seeking damages for breach of contract (hereinafter referred to as “Trinity I”).2
1
Fidelity Casualty Company and AB C Contractors, Inc. were intervening plaintiffs in the first two actions and
the third action was brought by Fidelity Casualty Company and ABC Contractors, Inc. in the name of Charles W hite as
a subrogation claim for workers compensation benefits paid to him as a result of the bridge collapse.
2
In addition to th e Federal Suits and Trinity I, McK innon also brought suit against ABC in an action styled
McKinnon Bridge Company, Inc. v. ABC Co ntractors, Inc., No. 99-1329 -II, in the Chancery Co urt of D avidson C ounty,
Tennessee.
-2-
The suit from which this appeal arises (hereinafter “Trinity II”) was filed on November 30,
1999, by Trinity against McKinnon, in the Chancery Court of Davidson County, Tennessee.
Trinity’s Complaint, reads, in relevant part, as follows:
9. As a result of the collapse of the bridge, Trinity has been sued in
three separate lawsuits that have been consolidated for trial and are
presently pending in the United States District Court for the Western
District of Tennessee at Jackson [the Federal Suits]...
* * *
11. Trinity has incurred reasonable attorneys fees, expenses and
charges for expert witnesses in defending the federal court cases to
date and will continue to incur additional expenses through trial
preparation and trial.
12. From September 13 through September 28, 1999, Trinity,
McKinnon and Safeco tried the case [Trinity I]. At the conclusion of
all the proof in that case, Chancellor McCoy found that “the only
cause for the collapse of the bridge was the removal of cross-frame
FG4, to the exclusion of any fabrication errors in the steel structures.”
An Order granting Trinity a judgment against McKinnon and Safeco
Insurance Company was entered in that case on October 27, 1999.
13. Robert Carl Smith, the supervisor for ABC, made the decision on
May 16, 1995, to remove cross-frame FG4.
14. Removing cross-frame FG4 left a 150 ft. length of girder G1 of
the bridge without lateral support.
15. It was the duty and responsibility of McKinnon and its erection
subcontractor, ABC, to develop and implement an erection plan or
procedure for the erection of the bridge.
16. It was the duty and responsibility of McKinnon and its erection
subcontractor, ABC, to erect the bridge safely and maintain the
stability of the structure during the entire erection process.
17. Trinity had no duty or responsibility to erect the bridge.
18. Trinity had no contractual relationship with ABC and no control
over the work performed by ABC.
-3-
19. In the case styled McKinnon Bridge Company, Inc. v. ABC
Contractors, Inc., in the Chancery Court for Davidson County,
Tennessee, No. 99-1329-II, McKinnon has alleged that the collapse
of the bridge was directly and proximately caused by the “acts and/or
omissions of ABC while erecting the structural steel for the Project.”
In that case McKinnon seeks a judgment against ABC for damages
resulting from ABC’s negligence and breach of contract, and for
indemnity for the amount of any judgment in favor of Trinity against
McKinnon.
20. Trinity has demanded that McKinnon and Safeco perform their
contractual indemnity and hold harmless obligations. To date, they
have failed and/or refused to do so. Wherefore, plaintiff prays as
follows:
1. That plaintiff be indemnified and held harmless by the defendants
and awarded a judgment against the defendants for any and all loss or
liability incurred by it, including but not limited to attorney’s fees and
defense costs, resulting from the federal court cases.
On January 11, 2000, McKinnon filed its Answer denying the claims asserted by Trinity.
McKinnon’s Answer reads, in relevant part, as follows:
20. McKinnon admits that on or about September 30, 1999, Trinity
demanded that McKinnon and/or Safeco indemnify and hold Trinity
harmless in the federal court actions alleged in paragraph 9 of the
Complaint. McKinnon further admits that it has refused to accept
Trinity’s tender of its defense, but denies that it has any contractual
obligation to do so.
21. McKinnon Bridge denies that Trinity is entitled to the relief
prayed for in the Complaint.
* * *
23. For further plea, McKinnon Bridge alleges upon information and
belief that the plaintiffs in the federal court action alleged in
paragraph 9 of the Complaint seek to recover damages from Trinity
that were caused by the negligence of Trinity. McKinnon Bridge
denies that its contract with Trinity requires that it indemnify and/or
hold harmless Trinity for any claims arising out of the negligence of
Trinity.
-4-
On March 7, 2000, Trinity filed a Motion for Partial Summary Judgment, along with a Statement of
Undisputed Material Facts. In its Motion, Trinity asserts that:
...it [Trinity] is entitled to partial summary judgment as a matter of
law because there is no genuine issue of material fact that defendants,
McKinnon Bridge Company, Inc. and Safeco Insurance Company of
America, are collaterally estopped from disputing that the indemnity
provision of the contract entered into between the parties requires
McKinnon to indemnify Trinity for all claims brought by third parties
against Trinity arising out of the collapse of the bridge at issue.
On April 10, 2000, McKinnon filed a Motion for Summary Judgment, along with a response to
Trinity’s statement of undisputed facts. McKinnon’s Motion for Summary Judgment reads, in
pertinent part, as follows:
...In support of this Motion, McKinnon Bridge would show that the
contract of indemnity sought to be enforced by the Plaintiff does not
encompass the claims for which indemnification is sought; that there
is no genuine issue as to any material fact; and, that McKinnon
Bridge is entitled to summary judgment in this cause as a matter of
law.
The trial court conducted a hearing on Trinity’s Motion on April 19, 2000. Trinity’s
Motion was denied by Order dated May 4, 2000 because the trial court found the Motion to be
“premature.”
On May 30, 2000, Trinity filed a Renewed Motion for Summary Judgment. On May 31,
2000, Trinity filed a response to McKinnon’s statement of additional material facts. On July 12,
2002, the trial court conducted a hearing on both Trinity’s Renewed Motion for Summary Judgment
and the Motion for Summary Judgment filed by McKinnon. By Order entered July 26, 2002, the trial
court denied McKinnon’s Motion for Summary Judgment and granted Trinity’s Renewed Motion
for Summary Judgment. The Order reads, in relevant part, as follows:
This matter came on to be heard on July 12, 2002, upon cross
Motions for Summary Judgment by plaintiff, Trinity Industries, Inc.,
and defendant McKinnon Bridge Company, Inc. Upon consideration
of the motions, legal memoranda and other materials filed in support
of the motions, statement of counsel and the entire record, this Court
finds that there is no genuine issue of material fact existing between
the parties and that plaintiff, Trinity Industries, Inc., is entitled to a
judgment against the defendant McKinnon Bridge Company, Inc., for
all amounts it incurred in defending the cases in the United States
District Court for the Western District of Tennessee at Jackson...,
-5-
which shall include attorneys fees, expert witness fees, expenses for
court reporters and other litigation related expenses and the amount
paid by Trinity Industries, Inc. to settle the above referenced federal
cases. In addition, this Court finds Trinity Industries, Inc. is entitled
to an award of pre-judgment interest at the statutory rate of 10% per
annum from June 16, 2000, the date of the settlement of the federal
court cases, to the date of the entry of this Order.
In support of its motion for summary judgment, Trinity
Industries, Inc. submitted proof that it paid $250,000.00 in settlement
of the federal cases, and that it paid $704,719.30 in attorneys fees,
expert witness fees, court reporter fees and other litigation expenses
in defending the federal court cases. Prejudgment interest at 10% on
the entire amount from June 16, 2000, to the date of the entry of this
order is another $190,943.86. The Court hereby allows defendant
McKinnon Bridge Company, Inc. Thirty (30) days from the entry of
this Order to review the billing records and other documents
previously produced by plaintiff, to give notice to Trinity Industries,
Inc. and the Court of any objection it had to any of the amounts stated
herein, and to set the objection for further hearing by this Court.
If McKinnon Bridge Company, Inc. does not make objection
to the amounts stated above within thirty (30) days of the entry of this
Order, this Order shall be a final judgment from which execution may
issue for Trinity Industries, Inc. against McKinnon Bridge Company,
Inc. in the amount of $1,145,663.16.
Pursuant to this Order, McKinnon filed an “Objection to Plaintiff’s Statement of Damages
Set Forth in Order Entered July 26, 2002 and Motion to Set Hearing on Damages,” on August 26,
2002. Following a hearing on September 27, 2002, the trial court entered an Order awarding a
judgment in favor of Trinity in the amount of $1,030,692.00. McKinnon appeals from the Order of
the trial court, granting Trinity’s Motion for Summary Judgment and denying McKinnon’s.
McKinnon raises the following issues for our review, as stated in its brief:
I. Did the trial court err in granting Trinity Industries, Inc.’s Motion
for Summary Judgment?
II. Did the trial court err in denying McKinnon Bridge Company,
Inc.’s Motion for Summary Judgment?
The issues will be considered together.
A motion for summary judgment should be granted when the movant demonstrates that there
are no genuine issues of material fact and that the moving party is entitled to a judgment as a matter
-6-
of law. Tenn. R. Civ.P. 56.04. The party moving for summary judgment bears the burden of
demonstrating that no genuine issue of material fact exists. See Bain v. Wells, 936 S.W.2d 618, 622
(Tenn. 1997). On a motion for summary judgment, the court must take the strongest legitimate view
of the evidence in favor of the nonmoving party, allow all reasonable inferences in favor of that
party, and discard all countervailing evidence. Summary judgment is a preferred vehicle for
disposing of purely legal issues. See Byrd v. Hall, 847 S.W.2d 208 (Tenn. 1993); Bellamy v.
Federal Express Corp., 749 S.W.2d 31 (Tenn. 1988). Since the construction of a written contract
involves legal issues, construction of the contract is particularly suited to disposition by summary
judgment. Browder v. Logistics Management, Inc., 1996 LEXIS Tenn. App. 227 (Tenn. Ct. App.
1996); see also Rainey, at 119. Since only questions of law are involved here, there is no
presumption of correctness regarding the trial court’s grant of summary judgment. Bain at 622.
Therefore, our review of the trial court’s grant of summary judgment is de novo on the record before
this Court. Warren v. Estate of Kirk, 954 S.W.2d 722, 723 (Tenn. 1997).
McKinnon concedes in its brief that there is no conflict as to any material fact. It further
states in the reply brief: “Trinity clearly incurred a loss in the form of attorney’s fees, litigation
expenses and settlement costs in connection with the federal court lawsuits.” There is no issue
presented by McKinnon concerning the reasonableness of the settlement and the expenses incurred
by Trinity. Primarily, McKinnon asserts that the indemnity clause in the agreement does not provide
indemnification to Trinity for expenditures “traceable to allegations of its own negligence.” We first
must construe the contractual provisions upon which this action is premised:
You [McKinnon] shall indemnify and hold us [Trinity] harmless and
defend us from any claim or litigations occasioned by deficiencies in
Design, Drawings and Specifications provided to us by you, and from
any loss or liability resulting from the failure, action or inaction of
any party over which we [Trinity] have no control.
According to the plain language of the Agreement, McKinnon is required to indemnify
Trinity if Trinity can establish (1) that it has suffered a loss or incurred a liability and (2) that such
loss or liability is the result of some failure, action or inaction of any party over which it had no
control. Although McKinnon does not dispute the fact that Trinity incurred losses and expenses in
connection with the Federal Suits, McKinnon contends that those losses were not predicated upon
the acts or failure to act of any party over which Trinity had no control. Rather, McKinnon insists
that Trinity is seeking indemnification for its own negligence. Specifically, McKinnon asserts that
the losses Trinity incurred in the Federal Suits were the result of defending, and settling, allegations
that Trinity was guilty of negligence that directly caused the collapse of the bridge and the resulting
injuries suffered by the plaintiffs in the Federal Suits.3 McKinnon relies primarily upon two cases
decided in the Court of Appeals: McClain v. Illinois Central Gulf Railraod v. Distribution and
3
The law favors settlement of disputes by compromise. See Third Nat. Bank v. Scribner, 212 Tenn. 400, 370
S.W.2d 482 (1963); settlements of litigation are no t contrary to public policy and are to be encouraged. Alexander v.
Rhodes, 63 Tenn. Ct. App. 452 , 474 S.W .2d 655 (19 71).
-7-
Transportation Services, Inc., 1991 WL 193845, 4 (Tenn. Ct. App. 1991) and Power Equipment
Co. v. J. A. Jones Construction Co., 1989 WL 9544 (Tenn. Ct. App. 1989)(affirmed by the
Tennessee Supreme Court, 1990 WL 81992 (Tenn. 1990). We have reviewed both of these cases,
which turn on contract interpretation. The particular contracts involved in the cases were interpreted
by the Court to provide indemnification for the indemnitee’s own negligence, without complying
with the particularity requirement for an express intention as required to make such an
indemnification. We do not have that situation in the case before us. Mere allegations of negligence,
as in the case before us, are not sufficient to trigger interpretation of the clause before the Court, as
asserted by McKinnon.
The indemnification clause of the Agreement, as set out supra, clearly anticipates
McKinnon’s obligations to Trinity as arising after Trinity has incurred loss and after that loss has
been shown to be the result of negligent acts committed by some entity over which Trinity had no
control. To make this clause applicable before termination of the Federal Suits (i.e. to base
applicability only on the allegations of Trinity’s negligence found in the federal plaintiffs’
complaints) would be an exercise in conjecture. The above contractual provision provides for
indemnity to Trinity in two situations. The first situation requires that McKinnon indemnify and
hold Trinity harmless and defend Trinity from any claim or litigation because of deficiency of the
material furnished by McKinnon to Trinity. We do not have this situation in the case before us. The
second part of the indemnity agreement is that McKinnon “shall indemnify and hold us [Trinity]
harmless . . . from any loss or liability resulting from the failure, action or inaction of any party over
which we [Trinity] have no control.”
Under the indemnity agreement, Trinity must prove that it sustained loss or liability because
of action or inaction of a party over which it had no control. As heretofore noted, it is conceded that
Trinity sustained loss and the amount thereof is not in dispute. Therefore, the only prerequisite to
recovery by Trinity is proof that the loss was occasioned by a party over which it had no control. To
sustain this element, Trinity relies upon the finding of the chancery court of Trinity I that the bridge
collapsed as a result of the action of ABC in removing the FG4 cross-frame. The trial court’s
findings of fact and conclusions of law in the Trinity I case clearly found that “the only cause of the
collapse of the bridge was the removal of cross-frame FG4 by the erector ABC, to the exclusion of
any fabrication errors.” The trial court entered judgment for Trinity industries against the McKinnon
Bridge Company and entered judgment for Trinity on McKinnon’s counter-claim. McKinnon
appealed to this Court and argued on appeal, among other things, that the issue of the bridge collapse
was not tried or actually tried in the court below. However, this Court noted:
McKinnon alleged as an affirmative defense that the defective steel
furnished by Trinity caused the bridge to collapse. McKinnon also
filed a counterclaim against Trinity for breach of contract and for
negligently fabricating the steel, as well as third party actions against
TDOT, E.L.Conwell & Co., and Tensor alleging that their negligence
contributed to the problems with the steel. By the time of the trial in
September of 1999, McKinnon’s counterclaim and its third party
-8-
claims had been dismissed, but the trial went forward on the original
claim by Trinity and McKinnon’s affirmative defenses.
Trinity Industries v. McKinnon Bridge Co., 77 S.W.3d 159, 177 (Tenn. Ct. App. 2001).
This Court pointed out that Trinity offered testimony from an expert witness “who gave his
opinion that the bridge collapse, not because of any fabrication defects in the steel, but because a
cross brace had been removed by the erection contractor.” Id. at 179.
After its review, this Court concluded “that what caused the bridge to collapse was triable
and was actually tried in the September 1999 trial.” Id. at 179. The judgment of the trial court was
affirmed.
To satisfy its burden of proof that the cause of the bridge disaster was the negligent act of a
party over which Trinity had no control, Trinity relies upon the Trinity I decision under the doctrine
of collateral estoppel. In Beaty v. McGraw, 15 S.W.2d 819 (Tenn. Ct. App. 1998), this Court,
through Judge Koch, extensively discussed the doctrine and the use of collateral estoppel:
Collateral estoppel is an issue preclusion doctrine devised by
the courts. See Dickerson v. Godfrey, 825 S.W.2d 692, 694 (Tenn.
1992); Goeke v. Woods, 777 S.W.2d 347, 349 (Tenn. 1989); Morris
v. Esmark Apparel, Inc., 832 S.W.2d 563, 565 (Tenn. Ct. App.
1991). Like other preclusion doctrines, its purposes are to conserve
judicial resources, to relieve litigants from the cost and vexation of
multiple lawsuits, and to encourage reliance on judicial decisions by
preventing inconsistent decisions. See Allen v. McCurry, 449 U.S.
90, 94, 101 S. Ct. 411, 414-15 (1980); Disimone v. Browner, 121
F.3d 1262, 1267 (9th Cir. 1997).
Judge Friendly succinctly explained issue preclusion when he
observed over thirty years ago that “[w]here the litigants have once
battled for the court’s decision, they should neither be required, nor
without good reason permitted, to battle for it again.” Zdanok v.
Glidden Co., 327 F.2d 944, 953 (2d Cir. 1964). Thus, as our courts
have construed the collateral estoppel doctrine, it bars the same
parties or their privies from relitigating in a second suit issues that
were actually raised and determined in an earlier suit. See Massengill
v. Scott, 738 S.W.2d 629, 631 (Tenn. 1987); Collins v. Greene
County Bank, 916 S.W.2d 941, 945 (Tenn. Ct. App. 1995). Stated
another way, when an issue has been actually and necessarily
determined in a former action between the parties, that determination
is conclusive against them in subsequent litigation. See King v.
-9-
Brooks, 562 S.W.2d 422, 424 (Tenn. 1978); Allied Sound, Inc. v.
Neely, 909 S.W.2d 815, 820 (Tenn. Ct. App. 1995).
The party seeking to rely on the doctrine of collateral estoppel
has the burden of proof. See Dickerson v. Godfrey, 825 S.W.2d at
695. To invoke the doctrine successfully, the party must demonstrate:
1. that the issue sought to be precluded is identical to the issue
decided in the earlier suit;
2. that the issue sought to be precluded was actually litigated and
decided on its merits in the earlier suit;
3. that the judgment in the earlier suit has become final;
4. that the party against whom collateral estoppel is asserted was
a party or is in privity with a party to the earlier suit; and
5. that the party against whom collateral estoppel is asserted had
a full and fair opportunity in the earlier suit to litigate the
issue now sought to be precluded.
15 S.W.3d at 825 (footnotes omitted).
The Beaty Court then noted that at common law collateral estoppel doctrine can only be used
defensively; thus, preventing a defendant from relitigating a claim that a plaintiff had previously
litigated against the defendant and lost. Id. at 825. The Court stated:
At common law, the collateral estoppel doctrine required
mutuality of the parties and could only be used defensively. Thus, a
defendant traditionally employed the doctrine to prevent a plaintiff
from relitigating a claim that the plaintiff has previously litigated
against the defendant and lost. The United States Supreme Court
expanded the application of the collateral estoppel doctrine in federal
courts when it discarded the common-law mutuality of parties
requirement. See Parklane Hosiery Co. v. Shore, 439 U.S. 322, 326-
333, 99 S. Ct. 646, 649-653(1979).
Id at 825.
Judge Koch noted that while Tennessee courts have declined to approve the use of nonmutual
offensive collateral estoppel, there apparently are no decisions in Tennessee concerning the use of
mutual offensive collateral estoppel.
-10-
[There are no decisions] in which an appellate court of this state has
addressed the propriety of mutual offensive collateral estoppel – that
is, permitting the plaintiff to foreclose a defendant from relitigating
an issue that the defendant had previously litigated unsuccessfully in
another action against the same plaintiff.4 On the face of it,
permitting the use of mutual offensive collateral estoppel seems to
provide all the benefits of the issue preclusion doctrine without any
of the perceived undesirable consequences of nonmutual offensive
collateral estoppel. Recognizing the doctrine will not increase the
total amount of litigation, and it will not necessarily be unfair to the
defendant.
Id. at 825 (citations omitted).
The Court then held that within its discretion the trial court may permit the use of mutual
offensive collateral estoppel. The Court said:
In exercising its discretion, the trial court may consider (1) whether
the plaintiff could have joined the former suit but decided instead to
adopt a “wait and see” attitude, (2) whether the defendant had an
incentive to defend the former suit vigorously, and (3) whether the
judgment on which the plaintiff seeks to rely is itself inconsistent
with previous judgments against the defendant. See Parklane
Hosiery Co. v. Shore, 439 U.S. at 330-31, 99 S. Ct. at 651-52;
Winters v. Diamond Shamrock Chem. Co., 149 F.3d at 391.
Id. at 826.
In the instant case, the trial court properly allowed Trinity to utilize the doctrine of collateral
estoppel in proving the cause of the bridge collapse.
Had Trinity been found negligent in the Federal Suits or in the Trinity I suit, then clearly the
indemnification clause at issue would not be applicable. However, the negligence that caused the
bridge collapse was found to be on the part of ABC. ABC was a subcontractor of McKinnon’s and
was under no control or direction of Trinity. As a direct result of the negligent acts of ABC, a “party
over which [Trinity had] no control,” Trinity was embroiled in the Federal Suits and forced to defend
itself. And it is undisputed that Trinity incurred losses in this defense.
4
This court may have applied mutual offensive collateral estoppel in a case involving the construction of a will
where the parties in the two proceed ings were in privity with each o ther. See Aclin v. Speight, 611 S.W.2d 54, 55 (T enn.
Ct. Ap p. 19 80).
-11-
Although McKinnon would have us read the plain language of this Agreement so as to
release McKinnon from its obligations merely because the plaintiffs in the Federal Suits alleged that
Trinity was negligent, we cannot read the indemnification clause so expansively. A contract is not
ambiguous merely because the parties have different interpretations of the contract’s various
provisions, Cookeville Gynecology & Obstetrics, P.C. v. Southeastern Data Sys., Inc., 884 S.W.2d
at 462 (citing Oman Constr. Co. v. Tennessee Valley Auth., 486 F.Supp. 375, 382 (M
.D.Tenn.1979)), nor can this Court create an ambiguity where none exists in the contract. Cookeville
P.C., 884 S.W.2d at 462 (citing Edwards v. Travelers Indem. Co., 300 S.W.2d 615, 617-18
(Tenn.1957)). The language of the indemnification clause is clear and unambiguous. Where the
language of a written instrument is unambiguous, the Court must interpret it as written rather than
according to the unexpressed intention of one of the parties. Sutton v. First Nat. Bank of Crossville,
620 S .W.2d 526 (Tenn.Ct.App.1981). Applying this standard, we find that the trial court did not
err in granting Trinity’s Motion for Summary Judgment and denying McKinnon’s motion.
The Order of the trial court granting Trinity’s Motion for Summary Judgment and denying
McKinnon’s Motion for Summary Judgment is affirmed. Costs of this appeal are assessed to the
Appellant, McKinnon Bridge Company, Inc., and its surety.
__________________________________________
W. FRANK CRAWFORD, PRESIDING JUDGE, W.S.
-12-