WAYNICK CONSTRUCTION, INC.
v.
Marion Franklin YORK and wife, Harris Wylie York.
No. 8319SC736.
Court of Appeals of North Carolina.
September 4, 1984.*305 Wilson & Kastner by James L. Wilson, Liberty, for defendants-appellants.
Douglas, Ravenel, Hardy, Crihfield & Lung by John W. Hardy, Greensboro, for plaintiff-appellee.
JOHNSON, Judge.
I
Plaintiff contends that defendants have not excepted to the findings of fact of the court, but only to the entry of the order, and that therefore defendants' assignments of error are not properly before this Court. See App.R. 10(b); 1 Strong's N.C. Index 3d Appeal and Error § 28 (1976). It is well established that defendants' broadside exception presents on appeal the question of whether the findings, established by the failure to make specific exceptions, support the conclusions of law and in turn the judgment. Anderson Chevrolet/Olds v. Higgins, 57 N.C.App. 650, 292 S.E.2d 159 (1982). It also presents conclusions of law denominated as findings of fact. Clark v. Richardson, 24 N.C.App. 556, 211 S.E.2d 530 (1975) (reviewing unexcepted "findings").
II
In the present case the court sat as finder of fact and entered written judgment. Its duties as trier of fact were to "find the facts specially and state separately its conclusions of law thereon." G.S. 1A-1, Rule 52(a)(1). The requirements of *306 Rule 52 are not simply rules of "empty ritual." Coble v. Coble, 300 N.C. 708, 712, 268 S.E.2d 185, 189 (1980). The purpose of detailed findings of specific facts is to allow a reviewing court to determine from the record whether the judgment and the underlying legal conclusions represent a correct application of the law. Id. The purpose for requiring conclusions of law to be stated separately is to enable the reviewing court to determine what law the court applied to the facts found. Hinson v. Jefferson, 287 N.C. 422, 429, 215 S.E.2d 102, 107 (1975).
The trial court failed to make any conclusions of law in the present case. Our ensuing difficulty in determining the theory of law applied is compounded by the paucity of relevant findings of fact. Other than detailing the procedural facts that plaintiff had filed a claim of lien and that the parties had stipulated that the judgment might be entered out of district and out of term, the court made only three findings of fact. Two of these simply recited the terms of the contract, the payments actually made thereunder and the outstanding balance which defendants refused to pay. None of these findings resolved any matters in dispute.
The third and critical finding was simply that plaintiff had "substantially complied" with the contract. This is the only finding in the judgment resolving any matter in dispute. Even when we accept this finding as established, it does not provide a basis for conclusively resolving all the issues of the case.
III
Under the law of construction contracts, a party is entitled to receive what he contracted for or its equivalent. Robbins v. Trading Post, 251 N.C. 663, 666, 111 S.E.2d 884, 887 (1960). "Substantial compliance" is not the same as full compliance. Moss v. Knitting Mills, 190 N.C. 644, 648, 130 S.E. 635, 637 (1925). Substantial compliance requires only ordinary care and skill, and damages for the repair of defects may still be recovered. Id. More recently, our Supreme Court has held that performance of a construction contract in substantial accordance with the specifications does not preclude an action for defects not readily apparent upon completion, such as those contested here. Realty Co. v. Batson, 256 N.C. 298, 123 S.E.2d 744 (1962); see Restatement (Second) of Contracts § 246 Comment d, illustration 6 (1981).
Defendants had counterclaimed for such damages but that counterclaim was involuntarily dismissed by the court. If that ruling was correct, no claim for damages lay before the court at the time it entered the final judgment and we might affirm. Here again, however, the court failed to make any findings of fact despite the clear mandate of the Rules of Civil Procedure. G.S. 1A-1, Rule 41(b); G.S. 1A-1, Rule 52; see Graphics, Inc. v. Hamby, 48 N.C.App. 82, 89, 268 S.E.2d 567, 571-72 (1980) (failure is reversible error). The only reason apparent on the record for the dismissal is that defendants failed to show any amount of damages. This Court has recently reiterated the applicable rules governing damages in cases such as this:
"The fundamental principle which underlies the decisions regarding the measure of damages for defects or omissions in the performance of a building or construction contract is that a party is entitled to have what he contracts for or its equivalent. What the equivalent is depends upon the circumstances of the case. In a majority of jurisdictions, where the defects are such that they may be remedied without the destruction of any substantial part of the benefit which the owner's property has received by reason of the contractor's work, the equivalent to which the owner is entitled is the cost of making the work conform to the contract. But where, in order to conform the work to the contract requirements, a substantial part of what has been done must be undone, and the contractor has acted in good faith, or the owner has taken possession, the latter is not permitted to recover the cost of making *307 the change, but may recover the difference in value." [Citations omitted.] The difference referred to is the difference between the value of the house contracted for and the value of the house builtthe values to be determined as of the date of tender or delivery of possession to owner.
LaGasse v. Gardner, 60 N.C.App. 165, 168-69, 298 S.E.2d 393, 396 (1982), quoting Robbins v. Trading Post, supra, 251 N.C. at 666, 111 S.E.2d at 887.
It is unclear which of these theories the court applied in dismissing the counterclaim. Plaintiff contends that all the evidence showed that the existing floors would first have to be destroyed to achieve compliance, and that defendants put on no evidence as to relative value, and that dismissal was accordingly proper. Defendants contend that their evidence concerned repairs to bring the work into conformity, and that no destruction was required; since their evidence as to the cost of repair was excluded, to which they also assign error, they could not show damages. If the evidence was improperly excluded, they argue, the dismissal was also improper. Nothing in the evidence affirmatively indicates that existing work need be destroyed or substantially undone to achieve conformity. We held in LaGasse that in cases such as this the court must specifically rule which theory applies. Again, the court erred failing to make such findings.
IV
The principal reason that defendants did not present evidence of damages supporting their theory is because the court excluded such evidence. Defendants attempted to put on "cost of repair" testimony through opinion testimony of an architect, but it was excluded by the court on hearsay grounds, i.e., that the architect did not have personal knowledge of the dimensions of the house and therefore could not estimate the cost of repair.
A
We note first that defendants failed to offer the architect to the court as an expert. Under the circumstances of the case, however, the lack of a formal offer does not prevent review. The architect's qualifications were presented at length and defendants' intent to offer him as an expert was clear. Defendants repeatedly asked for the architect's opinions on technical issues and asked him to describe his calculations. The adverse rulings of the court were expressly stated with the grounds therefor. On identical facts our Supreme Court has held that a formal tender is not an essential prerequisite to eliciting an opinion. Dickens v. Everhart, 284 N.C. 95, 103, 199 S.E.2d 440, 444 (1973) (to require formal offer "exalts form over substance").
B
The facts upon which the architect intended to rely in answering the question were already in evidence through defendants' other technical witness. As such, personal knowledge was not a prerequisite for him to give an opinion. State v. Grady, 38 N.C.App. 152, 247 S.E.2d 624 (1982); see 1 H. Brandis, N.C. Evidence § 137 at 546 (1982); G.S. § 8C-1, Rule 703 (Supp.1983). Accordingly, the court erred in excluding the architect's opinion as to cost of repair, especially in view of the fact that the trial took place before the court, not a jury. See 1 H. Brandis, N.C. Evidence § 4A (1982) (rules more relaxed).
C
Nevertheless, argues plaintiff, the error is not properly before this Court since defendants did not put an offer of proof into the record. Ordinarily, such an offer is necessary to appellate review of rulings excluding evidence; however, it is not absolutely essential if the record plainly discloses the significance of the evidence. Currence v. Hardin, 296 N.C. 95, 249 S.E.2d 387 (1978). Here it is clear that the significance of the excluded evidence was only the dollar amount of the architect's estimate. The architect did present testimony, although subsequently stricken, *308 that removal of some studs to effect the repair would cost $250. This appears to be as much a part of the whole record as excluded evidence offered outside the record of testimony. Furthermore, we can safely say that the remaining work which the architect testified was necessary would not be done for free. It is well established that once breach of a contract has been shown, the claimant is entitled to at least nominal damages. See 3 Strong's N.C. Index 3d Contracts § 29 (1976). The only significance of the excluded testimony would be to increase the dollar amount of alleged damages. It would not affect basic questions of liability. Compare Currence v. Hardin, supra (no offer of proof of medical diagnosis of plaintiff, not reviewable). Accordingly, we hold that the failure to make a formal offer does not preclude appellate review in this case, and we again find error in the exclusion of the evidence.
V
Having found numerous errors, the proper disposition of the case now must be determined. Ordinarily, where the court fails to make some findings necessary to support the judgment, we may remand for further proceedings to supply the few deficiencies. See Henderson v. Henderson, 307 N.C. 401, 409-10, 298 S.E.2d 345, 351 (1983) (remand for findings solely on willfulness). On the other hand, the appellate courts may also order a new trial where findings are clearly inadequate, as we believe they are here. Quick v. Quick, 305 N.C. 446, 458-59, 290 S.E.2d 653, 661-62 (1982). The failure of the court to make any findings in dismissing the counterclaim reinforces our conclusion, Graphics, Inc. v. Hamby, supra (new trial), as do the erroneous evidentiary rulings. Accordingly, the judgment is vacated and the cause remanded for a new trial.
New trial.
WELLS and BECTON, JJ., concur.