Wallich Lumber Co. v. Golds

375 Mich. 323 (1965) 134 N.W.2d 722

WALLICH LUMBER COMPANY
v.
GOLDS.

Calendar No. 50, Docket No. 50,466.

Supreme Court of Michigan.

Decided May 10, 1965.

Schuur & Keating (Patrick J. Keating, of counsel), for plaintiff.

Glassen, Parr, Rhead & McLean (Neil A. McLean, of counsel), for defendants Golds.

Jesse W. Bollinger, for defendant Bank of Dearborn.

*325 ADAMS, J.

This is a suit to determine the validity and priority of a materialman's lien. On October 5, 1959, plaintiff began delivery of materials to the homesite of defendants Golds. On December 14, 1959, defendants Golds executed a mortgage with the Bank of Dearborn. The trial judge found that some time after April 20, 1960, plaintiff and defendants Golds entered into a written contract for the purchase of the materials which were being and had been supplied. The contract was predated "October 2, 1959."

The last delivery of materials was on August 23, 1960. On August 31, 1960, plaintiff filed a claim of lien for $6,250.90. The trial judge found that this was the value of the materials and that they had been used in the Golds' home. Plaintiff filed its bill of complaint and all defendants were served within one year after filing of the claim of lien. Plaintiff did not, however, file notice of lis pendens. Because of failure to do so, the trial judge ruled that plaintiff had no cause of action.

I.

The portions of the mechanics' lien law which prompted that decision read as follows:

"Sec. 9. The several liens herein provided for shall continue for 1 year after such statement or account is recorded in the office of the register of deeds, and no longer unless proceedings are begun to enforce the same as hereinafter provided." CLS 1961, § 570.9 (Stat Ann 1963 Cum Supp § 26.289).

"Sec. 10. Proceedings to enforce such lien shall be by bill in chancery, under oath, and notice of lis pendens recorded in the office of the register of deeds, shall have the effect to continue such lien pending such proceedings." CLS 1961, § 570.10 (Stat Ann 1963 Cum Supp § 26.290).

*326 Once a lien attaches, a liberal construction should be made of the statute because of its remedial character. CL 1948, § 570.27 (Stat Ann 1953 Rev § 26.307); Burman v. Ewald, 192 Mich. 293, 295. A liberal construction is achieved by holding that the lis pendens need not be filed as to those who have actual notice of suit. To hold otherwise would exalt constructive notice over actual notice. See the extensive discussion on this point in Whitehead & Kales Co. v. Taan, 233 Mich. 597, 603-605. Also, see Vander Horst v. Kalamazoo Apartments Corporation, 239 Mich. 593, 603-605; Hart v. Reid, 243 Mich. 175, 183. The trial judge was in error. The filing of a lis pendens was unnecessary as to defendants who had notice of the lien and were sued and served within the one year period.

II.

The next question is whether the plaintiff acquired a lien. Defendants Golds' property was held by the entireties. Liens upon such property must meet the requirements of section 2 of the mechanics' lien statute which reads:

"In case the title to such lands upon which improvements are made is held by husband and wife jointly * * * the lien given by this act shall attach to such lands and improvements if the improvements be made in pursuance of a contract in writing signed by both the husband and wife." CL 1948, § 570.2 (Stat Ann 1953 Rev § 26.282). (Emphasis supplied.)

The plain requirement of this statute is that the lien shall not attach if the improvements are not made in pursuance of the written contract. As to those materials which were delivered prior to the execution of the contract, no lien was created. To hold otherwise would permit a waiver of the statute contrary to the holding of this Court in McMillan v. *327 Schneider, 147 Mich. 258, and F.M. Sibley Lumber Co. v. Letterman, 234 Mich. 32, 35. Upon remand, the trial court shall determine the date when the contract was executed and allow a lien for only such materials as were furnished from that date.

III.

The final question is whether the plaintiff's lien has priority over the bank's mortgage. Section 9 of the mechanics' lien law establishes priority for the entire act. That portion of section 9 relative to the priority question involved here was construed in Kay v. Towsley, 113 Mich. 281, as follows (p 283):

"Subdivision 3 * * * provides that mechanics' liens `shall be preferred to all other titles, liens, or incumbrances which may attach to or upon such building, machinery, structure, or improvement, or to or upon the land upon which they are situated, subsequent to the commencement of said building, erection, structure, or improvement.' This provision has been passed upon frequently by the courts, and it has been uniformly held that the lien has priority over a mortgage executed upon the lands or premises after the actual commencement of the building, though no part of the labor performed or materials furnished for which the lien is claimed was done or performed until after the execution and recording of the mortgage." (Emphasis supplied.)

See, also, Kerr-Murray Manufacturing Co. v. Kalamazoo Heat, Light & Power Co., 124 Mich. 111; River Rouge Savings Bank v. S & M Building Company, 359 Mich. 189 (91 ALR2d 409).

In this case the mortgage was executed after the commencement of construction and the lien did not come into being until after the execution of the mortgage. Under Kay v. Towsley, supra, the lien would relate back to the commencement of construction and *328 take priority. However, Kay v. Towsley involved property which was not held by the entireties, and was unaffected by section 2. The question then is whether section 2 requires a different construction of the priority section.

It seems obvious that the different treatment of entireties property was for the protection of a spouse, so as to prevent a husband or wife from affecting their unitary ownership without the written consent of the other. In this respect section 2 is consistent with other branches of the law dealing with entireties property. See 13 MLP, Husband and Wife, §§ 4, 5. This policy prevents the alienation of entireties property and has no relevance to priorities which deal with property already encumbered. There is nothing in section 2, or the policy that section seeks to effectuate, to warrant a different interpretation of section 9, the priorities section, as to property under section 2 from the interpretation given section 9 as to property affected only by section 1.

Section 1 (CLS 1961, § 570.1 [Stat Ann 1963 Cum Supp § 26.281]) requires a subcontractor, laborer, or materialman who deals with the original or principal contractor or any subcontractor to serve notice to the owner, et cetera, of the premises if he intends to assert a lien. Notice is required whether or not the property is held by the entireties. Hartwick Lumber Co. v. Chonoski, 216 Mich. 424; Saginaw Lumber Co. v. Stirling, 305 Mich. 473. Notice is not required of a person who contracts directly with the owner. Mielis v. Everts, 264 Mich. 363, 364.

The reason for the notice requirement and the distinction between one who deals directly with the owner and a subcontractor, materialman, or laborer who does not, is that in the first situation the owner knows there is a claim against him, but in the second case he may be unaware of a claim without such *329 notice. The notice is for the purpose of protecting the owner. CLS 1961, § 570.4 (Stat Ann 1963 Cum Supp § 26.284). Relative to the purpose of section 1, see Hartwick Lumber Co. v. Chonoski, supra, p 428. This policy of protecting the owner is operative whether or not entireties property is involved. Hartwick Lumber Co. v. Chonoski, supra; Saginaw Lumber Co. v. Stirling, supra.

It must be concluded that there is nothing in either section 1 or section 2 to demand a different construction of the priority section as to entireties property than would follow if section 2 were not involved. This places a great burden of diligence upon a mortgagee, as opposed to those accorded a lien under the mechanics' lien law, but this is a matter for legislative decision in the ordainment of liens and priorities.

Reversed and remanded for further proceedings in accordance with this opinion. No costs, neither party having prevailed in full.

T.M. KAVANAGH, C.J., and DETHMERS, KELLY, BLACK, SOURIS, SMITH, and O'HARA, JJ., concurred.