F I L E D
United States Court of Appeals
Tenth Circuit
PUBLISH
April 30, 2007
UNITED STATES CO URT O F APPEALS Elisabeth A. Shumaker
Clerk of Court
TENTH CIRCUIT
H U TTO N CO N TR AC TIN G
COM PANY, IN C.,
Plaintiff - Appellant,
v. No. 05-3223
CITY O F COFFEYVILLE,
Defendant - Appellee.
A PPE AL FR OM T HE UNITED STATES DISTRICT COURT
FOR T HE DISTRICT OF KANSAS
(D .C . NO. 02-CV-4130-JAR)
Bryan W . Smith, Cavanaugh, Smith & Lemon, P.A., Topeka, Kansas, for Plaintiff
- Appellant
Justice B. King (Richard Petersen-Klein with him on the brief), of Fisher,
Patterson, Sayler & Smith, LLP, Topeka, Kansas, for Defendant - Appellee
Before HA RTZ, EBEL, and O’BRIEN, Circuit Judges.
HA RTZ, Circuit Judge.
Hutton Contracting Company, Inc., a North Dakota corporation based in
Colorado, contracted to construct a power line and a fiber-optic line for the City
of Coffeyville, Kansas. Upon completion of the project the City refused to pay
the final $110,159.47 out of the contract price of $1,131,947.12, claiming that it
was entitled to these funds as liquidated damages because of Hutton’s delays.
Hutton sued the City in the United States District Court for the District of Kansas
to obtain the unpaid amount of the contract price. See 28 U.S.C. § 1332
(diversity jurisdiction). After a jury trial the court ordered the City to pay Hutton
$24,659.47— the retainage of $110,159.47 minus $85,500.00 in liquidated
damages to which the City was entitled.
Hutton appeals from this judgment, challenging four holdings by the
district court: (1) that the contract’s force-majeure clause did not excuse Hutton
for delays caused by late deliveries from its pole supplier; (2) that the contract’s
liquidated-damages provision was enforceable; (3) that the liquidated-damages
provision allowed the court to apportion delays between Hutton and the City; and
(4) that H utton was not entitled to prejudgment interest on its damages. Hutton
also challenges (5) a special interrogatory asking the jury whether the parties had
modified their contract and (6) the court’s responses to questions from the jury.
W e have jurisdiction under 28 U.S.C. § 1291 and affirm.
I. B ACKGR OU N D
A. Contract and Performance
The contract between Hutton and the City is dated M arch 28, 2000. The
engineer designated for the project was Allgeier, M artin & Associates, Inc. (the
-2-
Engineer). Rather than specifying when construction was to begin, the contract
contained the following provision:
[Hutton] agrees to commence construction on the Project on a date
(hereinafter called the “Commencement Date”) which shall be
determined by the Engineer after notice in writing of approval of the
Contract by the [City] and notice in writing from [Hutton] that
[Hutton] has sufficient materials to warrant commencement and
continuation of construction, but in no event will the Commencement
Date be later than * (See Special Conditions) calendar days after
date of approval of the C ontract by the [City].
Aplt. A pp. Vol. IV at 933. (The cross-referenced Special Conditions provide that
“[t]he starting date shall be no later than M ay 1, 2000,” id. at 969, but this date
never figures explicitly in the parties’ arguments.) The contract contemplated
completion of construction within 45 days of commencement (excluding
Sundays), with flexibility for bad weather:
[Hutton agrees] to prosecute diligently and to complete construction
phases as described in strict accordance w ith the Plans,
Specifications and Construction Drawings within Forty-five (45)
calendar days (excluding Sundays) after Commencement Date;
Provided, however, that [Hutton] will not be required to perform any
construction on such days when in the judgment of the Engineer
snow, rain, or wind or the results of snow, rain or frost make it
impracticable to perform any operation of construction and to extent
of the time lost due to the conditions described herein and approved
in writing by the Engineer, the time of completion set out above will
be extended if [Hutton] makes a written request therefor to the
[City] . . . .
Id. at 933. A provision that both parties call a force-majeure clause gave Hutton
more time to complete the project in exceptional circumstances, provided that it
submitted requests for extensions in writing:
-3-
The time for Completion of Construction shall be extended for the
period of any reasonable delay which is due exclusively to causes
beyond the control and without the fault of [Hutton], including Acts
of God, fires, floods and acts or omissions of the [City] with respect
to matters for which the [City] is solely responsible: Provided,
however, that no extension of time for completion shall be granted
[Hutton] unless within ten (10) days after the happening of any event
relied upon by [Hutton] for such an extension of time [Hutton] shall
have made a request therefor in writing to the [City], and provided
further that no delay in such time of completion or in the progress of
the work which results from any of the above causes or from any
changes in construction which may be made pursuant to Subsection
“d” of this Section 1 [which allowed the City to modify the
construction plans and provide extensions therefor] shall result in
any liability on the part of the [City]. Time extensions due to
weather will be considered only when [Hutton] is on site.
Id.
The contract required the C ity to pay Hutton within 90 days of the project’s
completion:
Upon completion by [Hutton] of the construction of the project, the
Engineer will prepare an inventory of the Project showing the total
number and character of Construction Units and, after checking such
Inventory with [Hutton], will certify it to the [City] together with a
certificate of the total cost of the construction performed. Upon the
approval of such certificates by the Engineer, the [City] shall make
payment to [Hutton] of all amounts to which [Hutton] shall be
entitled thereunder which shall not have been paid, provided,
however, that such final payment shall be made not later than ninety
(90) days after the date of Completion of Construction of the Project
as specified in the Certificate of Completion, unless w ithheld
because of the fault of [Hutton].
Id. at 936. But the amount owed would be reduced by $500 in liquidated damages
for each day by which the completion of the project was late:
-4-
The time of the Completion of Construction of the Project is of the
essence of the Contract. Should [Hutton] neglect, refuse or fail to
complete the construction within the time herein agreed upon, after
giving effect to extensions of time, if any, herein provided, then, in
that event and in view of the difficulty of estimating with exactness
damages caused by such delay, the [City] shall have the right to
deduct from and retain out of such monies which may be then due, or
which may become due and payable to [Hutton], the sum of FIVE
H UNDRED DO LLARS ($500.00) per day for each and every day
that such construction is delayed on its completion beyond the
specified time, as liquidated damages and not as a penalty.
Id. at 943.
The parties have disputed the contractual comm encement date, the
completion date, and the number of days of excused delay. Both agree that a
comm encement date of August 9, 2000, was set at a preconstruction conference
on August 4, 2000. But Hutton asserts that the City set the date “arbitrarily,”
Aplt. Br. at 4, and therefore contrary to the contract. In any event, Hutton began
clearing the construction site— the first step in the construction process— on
August 10, 2000.
Four days later Hutton sent a letter to the Engineer stating that some utility
poles would not be available before late October. The letter requested “that the
comm encement date be adjusted to October 23, 2000, due to the insufficient
material being on hand. The delivery of steel poles has been the cause of this
delay.” Aplt. App. Vol. IV at 1066.
-5-
The Engineer eventually responded to this letter on October 10, 2000,
agreeing to the proposed start date on condition that the project be completed
within 45 days:
You have requested to begin construction on October 23, 2000.
W e will arrange to have an inspector there on that day. You have
further requested the contract commencement day be moved to
October 23, 2000. W e have discussed this with M r. Jeff Tullis at the
City of Coffeyville and reiterate their position stated during the
preconstruction conference and again with you by telephone. The
City of Coffeyville is willing to forgo liquidated damages provided
that the project is entirely completed within 45 days as defined in the
contract, with construction beginning on October 23, 2000. Should
the project not be completed within that time, each day that the
project extends past the 45 day construction period would be subject
to liquidated damages. Days used for clearing [i.e., those during
which Hutton performed its original clearing work, before the new
“commencement” date of October 23] would also then be included in
the liquidated period.
Id. at 1069. Hutton commenced construction on October 23.
Hutton noticed in November that some of the poles that had been delivered
w ere defective. (D elivery of poles had started in mid-September.) On
December 7 it requested another extension— this time for 30 days— because of the
late delivery of the remaining poles. It also submitted several requests for
extensions due to weather conditions.
The lines were ready for use by M arch 22, 2001. But for more than a year
the parties disputed whether the project had been completed. In a fax on
April 20, 2001, the Engineer sent Hutton a list of clean-up tasks that it needed to
perform. Hutton responded on M ay 4, 2001, asserting that all tasks had been
-6-
accomplished. A November 28, 2001, fax from the City to Hutton stated that
cleanup was not yet complete. Finally, on August 5, 2002, the City sent Hutton a
notice that it was retaining the balance due of $110,159.47. It attached a letter
from the Engineer asserting that work was just completed on July 9, 2002, and
claimed that it was entitled to further liquidated damages for delay; but it offered
to settle by paying $34,159.47 of the retainage.
B. Court Proceedings
Seeking the full retainage, Hutton filed its suit on August 21, 2002. It
claimed that it had performed all its duties under the contract and was entitled to
the full contract price. It contended that the construction’s commencement date
under the contract was O ctober 23, 2000, that construction was substantially
complete by M arch 22, 2001, that the City either approved or was obliged under
the contract to have approved extensions of time, and that the contract excused it
from responsibility for delays caused by its suppliers. Hutton also alleged that
the City had violated its duty of good faith and fair dealing under the contract by
not granting extensions of time, requesting unneeded repairs, and failing to
facilitate the completion of cleanup-related tasks. The City countered that the
project was not complete until July 9, 2002, and that it had not improperly denied
extensions of time. The parties also disputed whether the Engineer’s letter of
October 10, 2000, modified any terms of the contract.
-7-
The district court resolved several issues before sending the case to the
jury. It held that the contract’s force-majeure clause did not excuse H utton’s
delay caused by late delivery of poles, because the supplier’s tardiness did “not
qualify as . . . extraordinary, beyond the control or fault of the bidder,” as the
clause contemplated. Aplt. App. Vol. II at 778. It stated that “problems with the
supplier were not totally without the fault of [Hutton] . . . because [it] made the
conscious choice to contract with this supplier and assumed the risk that that
supplier would perform so that [it] could, in fact, perform on its contract with the
city.” Id. at 779. The court also held that the contract’s liquidated-damages
provision was enforceable.
The district court submitted several special interrogatories to the jury. One
asked whether the parties had modified their contract in accordance with the
terms described in the Engineer’s October 10 letter to Hutton. Another asked
how many days’ worth of liquidated damages should be denied the City because
of its breach of the duty of good faith and fair dealing. During deliberations the
jury requested that the court explain how damages would be computed based on
the number of days of delay, but the court responded that the monetary amount
was not for the jury to decide. In response to the special interrogatories, the jury
found that the parties had agreed to a construction comm encement date of
October 23, 2000; that construction had been completed on M ay 4, 2001
(significantly more than 45 days after commencement); that 20 days of delay were
-8-
excusable because of weather; and that the City had breached its contractual duty
of good faith and fair dealing and therefore should not recover liquidated damages
for 23 days of delay.
In entering judgment the district court held that the City was “entitled to
liquidated damages due to Hutton’s untimely completion of the project . . . [for
days that are] unrelated to the City’s breach of the duty of good faith.” A plt.
App. Vol. I at 152. The court also denied prejudgment interest on its award to
Hutton, explaining that the amount of the damages was not liquidated until the
jury reached a verdict and that under K ansas law trial judges have discretion to
deny prejudgment interest. The final judgment incorporated liquidated damages
against Hutton for 194 days of delay attributable to Hutton minus 23 “days for
which liquidated damages should not be recovered [by the City] because of [its]
breach of its duty of good faith and fair dealing.” Id. at 154. The liquidated
damages for 171 days (194 minus 23) was $85,500. The court subtracted that
amount from the retainage of $110,159.47 to determine that the City owed Hutton
$24,659.47.
II. D ISC USSIO N
K ansas law governs the substantive issues in this diversity case, and we
review de novo the district court’s determinations of state law. See Boyd Rosene
& Assocs., Inc. v. Kan. M un. Gas Agency, 174 F.3d 1115, 1118 (10th Cir. 1999).
W e review for clear error the district court’s findings of fact. Id.
-9-
A. Force-M ajeure Clause
The contract’s force-majeure clause contains the following language:
The time for Completion of Construction shall be extended for the
period of any reasonable delay which is due exclusively to causes
beyond the control and without the fault of [Hutton], including Acts
of God, fires, floods, and acts or omissions of [the City] with respect
to matters for which [the City] is solely responsible.
Aplt. App. Vol. IV at 933. Hutton argues that late delivery of utility poles was
“beyond the control and without the fault of [Hutton].” Id. In essence it contends
that it should be excused for all delays caused by its suppliers or subcontractors,
at least when those delays arise without its fault and are beyond its control. The
district court rejected this contention on the ground that Hutton could be charged
with fault in selecting the supplier.
In our view , the district court essentially got it right. The most reasonable
interpretation of “fault of [Hutton]” in the force-majeure clause is “fault of
Hutton and those to whom it delegates its responsibilities under the contract.”
The contract did not specify a source of the poles. The City was concerned only
with the ultimate performance, not w hom Hutton employed to reach the result.
Under H utton’s interpretation of the force-majeure clause, it could protect itself
from liability arising from a particular type of delay simply by arranging that a
contractual partner assume responsibility for that type of delay. In other words,
delays could be excused or not depending solely on whether H utton chose to
outsource a particular operation or line of supply. It would be absurd to assume
-10-
that the City was concerned about delay only when caused by Hutton, and not by
a supplier or subcontractor that Hutton decided to employ. Not only would
Hutton’s interpretation provide a perverse incentive for contractors to outsource
work and supplies needlessly, but it also ignores the potential legal remedies of
the contracting parties. Under Hutton’s view the supplier, the one ultimately
responsible for the delay, would be immune from paying damages. Because
Hutton would have no liability to the City arising from the supplier’s delay, the
supplier would owe nothing to Hutton on that account. And it is unclear how the
City could have a contractual cause of action against the supplier, whose contract
is only with Hutton. See M elvin A. Eisenberg, Third-Party Beneficiaries, 92
Colum. L. Rev. 1358, 1402–06 (1992) (owner should ordinarily not have cause of
action against subcontractor unless contractor becomes insolvent). If, however,
Hutton is liable to the City for the delay, it could seek relief from its supplier. In
particular, if Hutton is concerned about paying damages caused by a supplier’s
delay, it can protect itself by paying the supplier a higher price and obtaining a
delay-damages clause in its contract with the supplier.
W e do not suggest that Hutton was at fault in its choice of supplier, only
that it is responsible to the City for its supplier’s delays when those delays are not
themselves excused by a force majeure. Hutton does not suggest that the
supplier’s failure was caused by a natural catastrophe or the like. In short, a
delay by a subcontractor or supplier is not itself a force majeure.
-11-
In so holding, w e are not stating a new rule of contract law. Although w e
have not found a Kansas case in point, courts have treated contractors as
responsible for the performance of their suppliers and subcontractors. See, e.g.,
Johnson M gmt. Group CFC, Inc. v. M artinez, 308 F.3d 1245, 1252 (Fed. Cir.
2002) (“A contractor is responsible for the unexcused performance failures of its
subcontractor”); Olson Plumbing & Heating Co. v. United States, 602 F.2d 950,
957 (Ct. Cl. 1979) (“The contractor alone is responsible for the deficiencies of its
suppliers and its subcontractors absent a showing of impossibility. Plaintiff’s
failure to produce a leak-free system was due to the deficient design of [its]
supplier [and was not] the fault of the Government.”). Accordingly, a contractor
assumes the risk that its subcontractor or supplier w ill fail, at least w hen its
contract with the owner does not call for a specific supplier or subcontractor to
complete a task. Decisions to this effect generally arise in cases analyzing the
contract doctrines of impossibility and impracticability, but the lesson from such
cases is nevertheless helpful in interpreting a force-majeure clause. As one
treatise puts it:
W hen a promised performance is known by both parties to be
impossible unless some third party performs, it may be a reasonable
interpretation that the promise is conditional upon performance by
the third party. The performance would then be discharged if the
third party does not do its part. This will usually not be the
interpretation, however, if nothing is said about the third party’s
contract or involvement in the contemplated performance. In this
context, a division among courts has developed in the so-called
“middleman” cases, in which a seller agrees to supply a good to a
-12-
buyer but then contracts with another party to manufacture the
good. . . . Courts have been more inclined to bind the middleman to
the contract if the contract is silent on the source of supply, and more
likely to release the middleman if the source is referenced in the
agreement. . . . The originating source was more likely to be a basic
assumption on which the contract was made (a so-called “sole source
of supply” contract) if the source is mentioned in the agreement.
14-75 Corbin on Contracts § 75.6 (2006) (footnotes omitted). See also M orin
Bldg. Prods. Co. v. Volk Constr., Inc., 500 F. Supp. 82, 89 (D. M ont. 1980) (“In
this case, M orin assumed the risk of performance; it assumed the risk that
delivery of the metal siding would be delayed by problems with its subcontractors
and suppliers. There is nothing in the contract between the parties which excuses
M orin for delays caused by its subcontractors or suppliers. Thus M orin had an
obligation to timely deliver . . . .”).
W e should add that our holding is a limited one. The sole concern here is
damages for delay when time is of the essence of the contract. W e are not
deciding whether the City could have declared Hutton in default, sought another
contractor, and recovered from Hutton for the increased cost. Cf. United States v.
Wegematic Corp., 360 F.2d 674, 675, 677 (2d Cir. 1966) (Friendly, J.) (rejecting
an argument that performance was impossible and upholding liquidated damages
for delay, but noting that it was not deciding whether “the Government could
have . . . recover[ed] not merely [liquidated] damages for delay but also the
higher cost of replacement equipment”).
-13-
Hutton suggests that the commencement-date clause of the contract
supports its interpretation of the force-majeure clause. It contends that the
contract must contemplate that Hutton would be excused upon the late delivery of
essential materials because the commencement date w as to be set after “notice in
writing from [Hutton] that [Hutton] has sufficient materials to warrant
comm encement and continuation of construction,” Aplt. App. Vol. IV at 933. But
we draw the contrary inference. Because Hutton is to provide notice that it has
sufficient material before the commencement date is set, one would infer that it is
responsible if its notice turns out to be erroneous. In other words, its notice
constitutes a representation that the supply of necessary material w ill be adequate
to complete the project on time; delay caused by lack of material is then its
responsibility. W e note that the force-majeure clause itself makes no reference to
the availability of materials.
Hutton also argues that the City is partly responsible for the poles’ delay
because of the City’s ow n delay in approving specifications. But even if this
contention were correct, partial responsibility does not matter under the force-
majeure clause, which makes the City’s delays relevant only “with respect to
matters for which [it] is solely responsible.” Aplt. App. Vol. IV at 933. The
City’s contributions to delays could, however, affect the amount of damages to
w hich it is entitled; w e take up that question below.
-14-
Hutton’s final argument on this issue is that it “qualified its bid based upon
the supply of the poles.” Aplt. Br. at 23. Hutton’s bid included the following
letter dated M arch 21, 2000, which Hutton argues was adopted as part of the
contract: “Please be advised that this bid proposal is being submitted with
material deliveries as follows: . . . Steel Poles — Sixteen (16) weeks after receipt
of order.” Aplt. App. Vol. IV at 946. But Hutton does not explain the relevance
of this notice. The City asserts that all specifications for the poles were resolved
by July 27, 2000, and that receipt of the poles 16 weeks later, on November 15,
2000, would have been “well within the completion time frame under the
modified commencement date of October 23, 2000.” Aplee. Br. at 25. Hutton
offers no argument in response.
For the above reasons, we affirm the district court’s determination that the
force-majeure clause does not assist Hutton.
B. Liquidated Damages
Hutton challenges two rulings of the district court concerning the contract’s
liquidated-damages provision. First, Hutton argues that the provision is not
enforceable because it is a penalty. Second, it argues that even if the clause is
enforceable, the City’s breach precluded its recovery of any liquidated damages,
so apportionment of delay between Hutton and the C ity was improper.
1. Enforceability
-15-
Under Kansas law, “[t]he burden of proving that a liquidated damages
clause constitutes an unenforceable penalty rests with the party challenging the
provision.” IPC Retail Props., L.L.C. v. Oriental Gardens, Inc., 86 P.3d 543, 548
(K an. Ct. A pp. 2004). In other words, “[t]he use of the terms ‘penalty’ or
‘liquidated damages’ in the [contract] . . . is given weight and is ordinarily
accepted as controlling unless the facts and circumstances impel a contrary
holding.” White Lakes Shopping Ctr., Inc. v. Jefferson Standard Life Ins. Co.,
490 P.2d 609, 613 (Kan. 1971) (internal quotation marks omitted). Kansas courts
distinguish unenforceable penalties from enforceable liquidated damages using
“two considerations”: first, whether the amount is “conscionable,” that is,
whether it is “reasonable in view of the value of the subject matter of the contract
and of the probable or presumptive loss in case of breach”; second, whether the
“nature of the transaction is such that the amount of actual damage resulting from
default would not be easily and readily determinable.” Id. (internal quotation
marks omitted). Kansas law echoes traditional common-law principles in this
respect. See Restatement (Second) of Contracts § 356(1) & cmt. b (1981)
(R estatement).
There is some doubt, however, about the temporal perspective from which
Kansas law evaluates the reasonableness of the liquidated-damages provision. In
other jurisdictions some courts consider only the reasonableness of the provision
at the time of contract formation. That is, only future damages, as conceived
-16-
prospectively when the contract is made, are relevant in evaluating the
reasonableness of a liquidated-damages provision. See, e.g., Kelly v. M arx, 705
N.E.2d 1114, 1117 (M ass. 1999) (“In addition to meeting the parties’
expectations, the ‘single look’ approach helps resolve disputes efficiently by
making it unnecessary to wait until actual damages from a breach are proved. By
reducing challenges to a liquidated damages clause, the ‘single look’ approach
eliminates uncertainty and tends to prevent costly future litigation.”). Other
courts additionally compare the amount that would be awarded under the
liquidated-damages provision with the actual damages a promisee suffered; that
is, they take an additional “retrospective” look at actual damages. See Yockey v.
Horn, 880 F.2d 945, 953 (7th Cir. 1989) (“If the nonbreaching party has suffered
no damages w hatsoever from the breach, the Restatement suggests that the clause
will be unenforceable, no matter how reasonable the estimate of damages was at
the time of contracting.”) (interpreting Restatement, supra, § 356 and applying
Illinois law ).
Although in White Lakes the Kansas Supreme Court evaluated damages
only in prospective terms, our review of Kansas cases finds no definitive
discussion of whether Kansas courts would also apply a supplemental
retrospective analysis. Accord K elly v. M arx, 694 N.E.2d 869, 874 (M ass. App.
Ct. 1998) (conducting a state-by-state review of liquidated-damages rules and
concluding, based on White Lakes, that Kansas is one of only a few states in
-17-
which the choice between a “single look” or “second look” analysis is unclear),
rev’d, 705 N.E.2d 1114. (M ass. 1999). The City argues that Kansas requires only
a single, prospective look at reasonableness. Hutton, however, contends that we
also need to take a second (retrospective) look at the City’s actual damages to
determine whether the liquidated-damages provision was reasonable. The City
may be correct; but we can assume, without deciding, that Hutton’s view is
K ansas law.
W e summarily dispose of Hutton’s argument on appeal that the liquidated-
damages clause was not prospectively reasonable. Its appellate briefs fail to cite
any occasion when it made this argument in district court, and we have found
none. Absent special circumstances, we will not reverse on a ground not raised
below. See Wilson v. M errell Dow Pharms., Inc., 160 F.3d 625, 628 (10th Cir.
1998). Therefore, we need not address the issue.
W e reject Hutton’s retrospective-analysis argument on the m erits. Under a
retrospective analysis, we compare the liquidated damages with the actual loss the
City sustained from the construction’s delay. Hutton argues that the City suffered
no damages because it suffered no loss in revenue from delay in energizing the
power line. To make this argument, Hutton cites a letter from the director of
Coffeyville M unicipal Light & Power:
Bottom line, the City was not losing revenue or suffering in any way
from the project being late other than the inconvenience of having a
few more loose ends to keep track of than necessary.
-18-
Although we could ask for more, I propose to withhold
$76,000 from the $110,159.47 final payment request by the contract
to reimburse the City for the estimated $75,932.50 in additional
engineering/inspection costs resulting from the extremely long
construction period.
Aplt. App. Vol. IV at 1085. Hutton would have us read this letter as an admission
by the City that it suffered no damages at all from the delay. But in addition to
noting that no revenue was lost, the letter also alleges that the City suffered
approximately $76,000 in damages from the delay through increased engineering
and inspection costs. Nothing limits liquidated-damages provisions to
compensating for lost revenue. A reasonable liquidated-damages provision may
well accommodate increased engineering and administrative costs. Because the
award of liquidated damages ($85,500) was near the $76,000 figure, the
liquidated-damages provision in this case was retrospectively reasonable.
2. Apportionment
Hutton also challenges the district court’s decision to apportion delays
between Hutton and the City rather than denying the City liquidated damages
altogether. The jury’s answers to special interrogatories regarding the
comm encement date and the completion date established that the project was
delayed by 194 days. The court subtracted 23 days for which the jury found that
the City should not recover liquidated damages because of its breach of the duty
of good faith and fair dealing. In other words, the court adjusted the amount of
-19-
liquidated damages on the ground that Hutton was responsible for only some of
the days of construction delay.
Hutton argues that because the jury found that the City breached its duty of
good faith and fair dealing, the City may not seek any liquidated damages under
the contract. Hutton relies on several old Kansas cases, although it admitted at
oral argument that these cases are not decisive and that the issue is essentially one
of first impression under Kansas law. The City for its part cites no cases
supporting the contrary position.
W e agree with Hutton that Kansas decisions do not resolve whether a party
in breach may recover liquidated damages for the portion of a divisible delay not
caused by its own breach. Two decisions are somew hat supportive of H utton’s
argument against apportionment. In Ritchie v. City of Topeka, 138 P. 618 (Kan.
1914), the principal case relied on by Hutton, the K ansas Supreme Court
considered a per-day liquidated-damages provision. The court held that an owner
could not collect liquidated damages for a construction delay because the owner
“occasioned delay [and] in effect notified [the other party] that it did not regard
the forfeiture clause of the contract to be binding upon him”; the owner “was
estopped thereafter to insist on a provision in the contract where it had prevented
the performance”; and “to compel the payment of damages for which the [owner]
was in a large part responsible would be unjust and inequitable.” Id. at 620.
Ritchie, however, does not appear to have considered the possibility that the delay
-20-
was divisible into delays caused by the contractor and delays caused by the
owner. A more recent, although unpublished, Kansas Supreme Court decision
cited by Hutton, Busch v. M cGinnis, No. 59,647, Kan. LEXIS 377, *9 (Kan.
June 12, 1987), holds that “when [one] contracting party makes it impossible for
the other party to perform [or] fails to perform a condition precedent, the first
party cannot recover damages when the second party breaches the contract.” But
Busch is inapposite because the City did not make it impossible for Hutton to
perform, at least with respect to those days for which the City received liquidated
damages, and it did not fail to perform a condition precedent.
On the other hand, Luminous Neon, Inc. v. Parscale, 836 P.2d 1201 (Kan.
Ct. App. 1992), provides some support for apportionment. It cited favorably in
dictum a W ashington case that apportioned liquidated damages, Baldwin v.
National Safe Depository Corp., 697 P.2d 587, 590 (W ash. Ct. App. 1985).
Lum inous described Baldwin as follows: “In an action by lessor of signs to
recover rental payments from lessee, provision in lease specifying liquidated
damages of all unpaid past due rentals plus 80 percent of all future rentals was
properly used as basis for apportionment of damage, notwithstanding plaintiff’s
partial breach.” Lum inous Neon, 836 P.2d at 1203. Yet this favorable reference
to another jurisdiction’s case is far from a clear holding on the question before us.
Hutton also cites two old cases from jurisdictions other than Kansas as
standing for the proposition that when a party breaches, it necessarily becomes
-21-
ineligible to seek any liquidated damages under a contract. See Bauman v. Peters,
231 N.W . 613 (M inn. 1930); Smith v. City of Tahlequah, 245 P. 994 (Okla. 1926).
W e note that these cases may never have represented a consensus among
jurisdictions, even in their era. See, e.g., Wallis v. Wenham, 90 N.E. 396, 398
(M ass. 1910) (apportioning liquidated damages for delay); Bedford–Carthage
Stone Co. v. Ramey, 34 S.W .2d 387, 391 (Tex. App. 1930) (same). But even if
they did, they are now unpersuasive for two reasons. First, they appear to reflect
a hostility to liquidated damages that arose from an outdated view that while
parties could determine their own contractual obligations, damages were the
province of the courts. See E.C. Ernst, Inc. v. M anhattan Constr. Co., 551 F.2d
1026, 1038–39 (5th Cir. 1977) (noting “early judicial hostility to the use of
privately agreed upon contract damage remedies”). Second, they appear to rely,
as was comm on for opinions of the time, on the notion that decisions followed
naturally from axioms that were presumed to be self-evident— for example, the
axiom that once a party has violated the terms of a contract, it has abrogated all
terms in the same contract and cannot then enforce rights under it. Thus,
Tahlequah, 245 P. at 996, cited by Hutton, quotes favorably the following
language from a hoary authority know n as Ruling Case Law:
The plaintiff cannot recover liquidated damages for a breach for
which he himself is responsible or to which he has contributed, and
as a rule there can be no apportionment of liquidated damages w here
both parties are at fault. Hence, if the parties are mutually
responsible for the delays because of which the date fixed by the
-22-
contract for completion is passed, the obligation for liquidated
damages is annulled, and in the absence of some provision under
which another date can be substituted, it cannot be revived. And so
it has been held that a provision in a contract to the effect that
deviations may be made at the instance of the owner without
annulling or invalidating the contract, does not operate to renew a
right to liquidated damages for delay in completing the work after the
provision therefor has been abrogated by delay to which the owner
materially contributed.
Id. at 996. It then summarizes this principle as follows: “The right to recover
liquidated damages being once abrogated cannot be renewed or revived except by
subsequent agreement.” Id.
For some time now, however, Kansas contract law has follow ed the parties’
intentions rather than formalism. See Koepp v. Pribyl, 485 P.2d 1388, 1390 (Kan.
1971) (“The purpose of the contract, so as to carry out the intention of the parties,
is to be arrived at by considering and construing the instrument in its entirety.”).
And when there are gaps in the contract, Kansas courts will fill them with terms
that are “reasonable in the circumstances.” NEA-Coffeyville v. Unified Sch. Dist.
No. 445, 996 P.2d 821, 829 (K an. 2000) (quoting Restatement, supra, § 204). W e
believe that whether we surmise what the parties’ views would have been when
the contract was executed or whether we simply insert a reasonable term in that
contract, damages for delay should be imposed for those delays, and only those
delays, for which the contractor is responsible. Apportionment of damages based
on fault comports w ith modern notions of fairness, as reflected, for example, in
the near-universal adoption of comparative responsibility in tort actions. And
-23-
such apportionment can encourage efficient behavior. See Stop Loss Ins. Brokers,
Inc. v. Brown & Toland M ed. Group, 143 Cal. App. 4th 1036, 1052 (Cal. Ct. App.
2006). Persuasive authority supports this approach.
The Supreme Court long ago so interpreted a government contract. In
Robinson v. United States, 261 U.S. 486, 488 (1923), the Court held that damages
could be apportioned under a contract that it described as follow s:
The original contract provided that the contractor “shall be allowed
one day, additional to the time herein stated, for each and every day
of . . . delay [that may be caused by the Government]”; “that no
claim shall be made or allowed to [the contractor] for any damages
which may arise out of any delay caused by [the Government],” and
that the contractor shall pay $420 for each and every day’s delay not
caused by the U nited States.
Id. at 487–88. In an opinion by Justice Brandeis, the Court reasoned:
The fact that the government’s action caused some of the delay
presents no legal ground for denying it compensation for loss
suffered wholly through the fault of the contractor. Since the
contractor agreed to pay at a specified rate for each day’s delay not
caused by the government, it was clearly the intention that it should
pay for some days’ delay at that rate, even if it were relieved from
paying for other days.
Id.
Although the W illiston treatise, relying primarily on older cases, concludes
that delay caused by the parties is “not generally . . . apportioned,” it recognizes
an exception for construction contracts in circumstances similar to ours:
In building contracts, the architect often has the power to extend the
time of performance under certain circumstances, and a delay caused
by the owner operates merely as an extension of the time for
-24-
performance, and a new time is substituted for the old. In that event
though the owner causes delay the builder is liable in liquidated
damages, but the period of delay caused by the owner is deducted
from the total delay.
24 Richard A. Lord, W illiston on Contracts § 65:8 (4th ed. 2006) (footnote
omitted). As in the situations described by the treatise, the force-majeure clause
in Hutton’s contract with the City extends the time for completion for delays
caused by “acts or omissions of the [City] with respect to matters for which the
[City] is solely responsible,” Aplt. App. Vol. IV at 933, although Hutton was
required to request the extension within 10 days of the delay-causing event.
M oreover, our review of decisions during the past 30 years shows that a
strong majority adopt our view. See Dallas-Fort Worth Reg’l Airport Bd. v.
Combustion Equip. Assocs., Inc., 623 F.2d 1032, 1038 (5th Cir. 1980) (approving,
under Texas law, apportionment of liquidated damages for delay based on fault of
parties, although reversing because answers to special interrogatories w ere
irreconcilable); Ernst, 551 F.2d at 1038–39; Aetna Cas. & Sur. Co. v.
Butte-M eade Sanitary Water Dist., 500 F. Supp. 193, 197 (D.S.D. 1980) (applying
South Dakota law, which had not addressed this issue, and stating that “recent
case law is clearly in favor of such apportionment of fault and that simply
because Defendant contributed to the delay in the completion of the project, it
should not be barred from recovering liquidated damages.”); Hertzberg v. Nunn
Bush Shoe Co. (In re Const. Diversification, Inc.), 36 B.R. 434, 437 (Bankr. D.C.
-25-
M ich. 1983) (“[T]he non-apportionment rule simply does not apply to . . . a
situation where responsibility for discrete days of delay can be apportioned under
a per diem liquidated damages provision.”) Stop Loss Ins. Brokers, 143 Cal. App.
4th at 1052 (“Rejecting the prior all-or-nothing rule, [California] courts have
applied apportionment principles to allocate contractual liquidated damages w here
delays in construction projects have been caused both by the owner and by the
contractor.”); Calumet Constr. Corp. v. M etro. Sanitary Dist. of Greater Chicago,
533 N.E.2d 453, 457 (Ill. App. Ct. 1988) (applying what it calls the “modern rule
of apportionment”). But see San Ore-Garner v. M o. Pac. R.R. Co., 496 F. Supp.
1337, 1349 (D.C. Ark. 1980) (calling the traditional rule the “better rule”);
Higgins v. City of Fillmore, 639 P.2d 192, 193 n.2 (Utah 1981) (“Even when an
owner is not entirely responsible for the delay, but has contributed thereto, he
may be precluded from obtaining liquidated damages.”). W e believe that Kansas
would adopt the modern view and allow liquidated damages to be apportioned
when faced with damages that are in fact divisible, as they were here.
At oral argument Hutton suggested that the period of delay in this case was
not in fact divisible, for a day of delay in one part of the year might (because of
weather, for instance) be more significant than one in another part of the year.
But the very purpose of the contract’s liquidated-damages provision was to avoid
requiring proof of the significance of individual days of delay; the contract
provides for an undifferentiated sum of $500 per day, regardless of the time of
-26-
year or other characteristics of the delay. Now is not the time for Hutton to
contend that days of delay are nonfungible.
W e affirm the district court’s decision to apportion delay in awarding
liquidated damages.
C. Prejudgm ent Interest
Hutton contests the district court’s denial of prejudgment interest on its
damages award. But its argument is without merit. Under Kansas law
prejudgment interest is generally allowable on liquidated claims and “may be
allowable on unliquidated damages w here necessary to arrive at full
compensation.” M iller v. Botwin, 899 P.2d 1004, 1012 (Kan. 1995). In either
event the award “is a matter which lies within the sound discretion of the trial
court.” Id. at 1013; see also Leeper v. Schroer, Rice, Bryan & Lykins, P.A., 736
P.2d 882, 887 (Kan. 1987) (prejudgment interest on liquidated damages is a
matter of equitable discretion rather than a matter of legal right). W e therefore
review denial of an award for abuse of discretion. See H ofer v. UNUM Life Ins.
C o. of Am ., 441 F.3d 872, 879 (10th Cir. 2006).
“A claim becomes liquidated when both the amount due and the date on
which it is due are fixed and certain, or w hen the same becomes definitely
ascertainable by mathematical computation. The fact that a good faith
controversy exists as to whether the party is liable for the money does not
preclude a grant of prejudgment interest.” M iller, 899 P.2d at 1012 (citations and
-27-
internal quotation marks omitted). The court’s award of $24,659.47 to Hutton did
not represent a liquidated amount before the entry of judgment because the
amount itself, not just the liability for that amount, was subject to dispute. See
Restatement, supra, § 354 cmt. c, illus. 9 (“A contracts to build a bungalow for B
for $30,000. After completion but before B has paid the final $6,000, B occupies
the bungalow but refuses to pay the balance because the workmanship and
materials are unsatisfactory. A sues B and recovers only $4,000 on the ground
that B’s claim entitles him to compensation in the amount of $2,000. The sum of
$4,000 was not sufficiently definite to give A a right to interest on it. The
allowance of interest is within the discretion of the court. The fact that A was
himself in breach will be considered.”). H utton asserts that at a minimum, som e
of the $110,159.47 retainage w as undisputedly due to H utton (and therefore
liquidated). O ddly, though, it does not identify a particular liquidated amount.
M ore importantly, its assertion is simply incorrect. Hutton stated in its trial brief
that “C offeyville claims that the project was not completed timely and that it is
entitled to an offset against any monies it owes to Hutton for liquidated
damages.” Aplee. Supp. App. at 338. Similarly, Hutton states in its opening brief
on appeal that “after Hutton filed the present litigation, Coffeyville claimed 633
days of liquidated damages under the contract, for a total of $316,500.00.” A plt.
Br. at 11. Clearly, then, the City disputed that it owed any portion of the
-28-
retainage to Hutton, and no portion of the award of $24,659.47 was liquidated
prior to judgment.
In any event, whether or not the damages w ere liquidated, the district court
acted well within its discretion in denying prejudgment interest, particularly
because Hutton was itself partially at fault and the City’s presuit letter of
August 5, 2002, offered Hutton more than what it later obtained through its
judgment.
D. Special Interrogatory on M odification of Contract
The contract between Hutton and the City called for a commencement date
to be “determined by the Engineer after notice in writing . . . from [Hutton] that
[Hutton] has sufficient materials to warrant comm encement and continuation of
construction.” Aplt. App. Vol. IV at 933. At a preconstruction conference on
August 4, 2000, this date was set at August 9, 2000, although Hutton has
contended that the date was not set properly.
On August 14 Hutton requested “that the commencement date be adjusted
to October 23, 2000, due to the insufficient material being on hand.” Id. at 1066.
The October 10 response from the Engineer conveyed the City’s acceptance of the
request, but subject to a condition: “Coffeyville is willing to forgo liquidated
damages provided that the project is entirely completed within 45 days as defined
in the contract, with construction beginning on October 23, 2000.” Id. at 1069.
That is, the City proposed to agree to Hutton’s request if construction was
-29-
completed within 45 days from the new date; otherwise, the City reserved the
right to seek liquidated damages for delays that occurred before October 23.
The jury found that the commencement date was October 23, 2000, and that
construction was not complete until M ay 4, 2001. Because the jury further found
that Hutton was entitled to only 20 extra days due to bad weather, construction
took far longer than the 45 days allowed. The jury also found that the parties had
modified the liquidated-damages provision according to the terms set forth in the
October 10 letter. Therefore, the district court, in computing damages, included
75 days of delay from August 9 to October 23, 2002.
Hutton challenges the addition of those 75 days. It focuses on Question 1
of the Special Verdict Form, which stated:
Do you find that the parties agreed to modify certain provisions of
the original contract, specifically the construction comm encement
date and the liquidated damages clause, as set forth in [the] October
10, 2000 letter to [H utton]?
Aplt. App. Vol. I at 110. Hutton’s view appears to be that the commencement
date was definitively October 23 and delays preceding that date could not be
considered for purposes of liquidated damages even if construction took more
than 45 days after October 23. In other w ords, it is asserting that no effect should
be given to the part of the October 10 letter that imposed a condition on agreeing
to the October 23 commencement date. It argues that it did not assent to that
condition and that the condition was not supported by any consideration. Thus, it
-30-
concludes, the jury could not properly find that the parties modified their contract
to incorporate the condition.
Regarding assent, Hutton argues that as a matter of law, “the October 10,
2000 letter from Coffeyville to Hutton did not modify the terms of the liquidated
damages clause” and that Question 1 therefore misstates the law. Aplt. Br. at 31.
W e agree that the letter itself did not adjust the terms of the parties’ contract.
Because it imposed a condition on acceptance of Hutton’s proposal, it was merely
a counteroffer. See Restatement, supra, § 59. But the Special Verdict Form does
not presuppose that the letter itself modified the contract; rather, it asks the jury
to determine whether there was a modification “as set forth in” the letter. This
modification need not have occurred on October 10 or by virtue of the letter’s
mailing. All that was required was acceptance of the terms by Hutton at some
point in time.
Hutton argues that the October 10 letter accepted Hutton’s proposed
comm encement date of October 23 and then, separately, requested the
modification of other terms of the contract. But the letter simply cannot be read
this way; any purported acceptance in the October 10 letter is made “provided
that the project is entirely completed within 45 days.” Aplt. App. Vol. IV at
1069. There is no freestanding acceptance in the letter, as there would be if the
City had expressed a hope or a request instead of a proviso. Cf. Restatement,
supra, § 61 cmt. a, illus. 1 (“A offers to sell B 100 tons of steel at a certain price.
-31-
B replies, ‘I accept your offer. I hope that if you can arrange to deliver the steel
in weekly installments of 25 tons you will do so.’ There is a contract, but A is not
bound to deliver in installments.”).
The letter thus had no binding effect absent a separate acceptance by
Hutton. In Kansas, however, acceptance of a proposed modification of a contract
need not be explicit. “The intent of the parties to modify a contract can be
implied from their conduct if they do not continue to act according to the original
terms of the contract.” Galindo v. City of Coffeyville, 885 P.2d 1246, 1253 (Kan.
1994). In particular, Hutton’s silence in this context— making no response to the
City’s setting this condition in the letter— can be construed as acceptance. See
Restatement, supra, § 69(1) (“W here an offeree fails to reply to an offer, his
silence and inaction operate as an acceptance . . . [w]here because of previous
dealings or otherwise, it is reasonable that the offeree should notify the offeror if
he does not intend to accept.”). After all, the letter was responding to a request
by H utton “that the commencement date be adjusted” to a date more than two
months after the previously set date. If Hutton would have preferred to keep that
earlier commencement date (although perhaps reserving the right to litigate its
propriety) rather than to accept the City’s reasonable conditions (reasonable in
that Hutton would suffer no adverse consequence if it could perform with as much
speed as the contract originally called for), one would expect it to express its
-32-
opposition. Or at least the jury could reasonably have drawn that inference and
found that Hutton and the C ity had agreed to the terms of the O ctober 10 letter.
Hutton further argues in its reply brief that the contract could not have been
modified as set forth in the October 10 letter because the parties did not use the
same City form that the parties had used in July 2000 to modify the contract. But
we do not consider arguments raised for the first time on appeal in a reply brief.
See United States v. Hall, 473 F.3d 1295, 1301 n.1 (10th Cir. 2007). In any
event, this argument is unconvincing. Although the prior conduct of parties can
of course aid courts in interpreting their agreement, Hutton has given us no reason
to believe that the parties bound themselves to make all contract amendments
using the same form.
W e also reject Hutton’s contention that the m odification— or, to be more
precise, the condition imposed by the City— was not supported by consideration.
If nothing else, the City gave up its right to insist on the commencement date set
at the preconstruction conference. Even if it were ultimately determined that the
City had improperly set the date at that conference, forbearance from a colorable
claim is sufficient consideration. See Schiffelbein v. Sisters of Charity, 374 P.2d
42, 45 (Kan. 1962) (“Forbearance to sue can be good consideration for a promise,
regardless of the actual validity of the claim, if the one w ho forbears has a
reasonable and sincere belief in its validity.”); Evco Distrib., Inc. v. Brandau, 626
-33-
P.2d 1192, 1196 (Kan. Ct. App. 1981) (“The principle that forbearance may
constitute consideration to support a contract is established in K ansas.”).
H utton also seems to attack Question 1 as a misstatement of contract law ,
but the instruction does not in fact state any law . And as the City’s brief points
out, a separate jury instruction fully laid out the law governing the modification
of contracts, including the requirement of consideration. W e hold that there was
no error in asking Question 1 or in the jury’s answering it in the affirmative.
E. Jury Q uestions
During its deliberations the jury asked the court to clarify several matters
concerning the computation of liquidated damages. The questions were posed as
relating to Question 6 on the Special Verdict Form, which stated:
If you answ ered [that the City breached its duty of good faith and fair
dealing], you must now determine the number of days for which the
City, due to its breach of its duty of good faith and fair dealing,
should not recover liquidated damages. Please state the number of
days below .
Aplt. App. Vol. I at 111. The jury first asked:
Question 6
Regards to total number of liquidated damage days— Are we looking
at the City of Coffeyville potential liquidated damages equal to (633
× 500) $316,500
or
Is it to be the total days between Construction Commencement Date
and Completion Construction Date that we have established from the
evidence.
-34-
Id. at 77. The court responded:
Dear Jury:
Question 6 does not ask for the number of days of liquidated
damages. Rather, Question 6 asks for the specific number of days for
which the City should not recover liquidated damages, due to a
breach of its duty of good faith and fair dealing.
Id. The jury followed up with another question:
Question 6
Does 142 days compute to $71,000 (142 days × $500 liquidated
damages) in damages awarded to Hutton?
Please circle
Y es or No
Id. at 78. The court responded:
Dear Jury,
This question, like several other questions asks about matters
that are factual in nature, and it is never appropriate for the Court to
answ er such questions. Question 6 asks for a number of days, not a
monetary amount.
Id. Finally, the jury asked:
Question:
Please clarify—
How many days is the City charging Hutton for liquidated damages.
Id. at 79. The court answered:
Dear Jury,
-35-
The answ er to your question is something you, the jury, will
have to determine from the evidence.
Id.
Hutton challenges the district court’s responses and seeks a new trial.
Hutton’s argument is not clear, but it appears to be arguing either that the jury
questions themselves demonstrate the jury’s confusion and that this alone requires
a new trial or that the court’s responses were somehow improper. “A district
court’s actions in responding to questions from the jury, as well as supplemental
instructions given to the jury, are reviewed for abuse of discretion.” Allen v.
M innstar, Inc., 97 F.3d 1365, 1370 (10th Cir. 1996).
The responses that the district court chose to give did not misstate the law
or otherw ise mislead the jury. The court simply emphasized to the jury that it
was the jury’s function to answer factual questions, and that the court would not
supply advice on how to answ er these factual questions. W e cannot find any fault
in the way the court responded to the questions.
Neither do Hutton’s arguments make clear precisely how the jury was
confused in any relevant respect. To begin with, even if the jury was initially
confused about its proper role as fact finder, the district court’s answ ers likely
cleared up the confusion. “[P]laintiff's argument is entirely speculative and could
arguably be raised in any case in which a jury presents questions to a trial court.
As we have previously noted, a verdict will not be upset on the basis of
-36-
speculation about possible jury confusion.” Id. at 1373 (internal quotation marks
omitted); see Howard D. Jury, Inc. v. R & G Sloane M fg. Co., 666 F.2d 1348,
1351 (10th Cir. 1981) (“[T]he question before us is whether the confusion in the
jurors’ minds was eliminated before the verdicts were returned, not whether the
jurors were confused prior to that time.”). Hutton argues only that “the jury
questions demonstrate that the jury was confused with regard to how many days it
should allocate for liquidated damages,” Aplt. Br. at 36; but the jury’s questions
show— at most— that it may have been confused about the dollar figure owing
from Hutton to the City or the number of days with which Hutton would be
charged in light of the jury’s other answers. The jury’s potential confusion over
matters unrelated to its special verdicts is irrelevant.
III. C ON CLU SIO N
The district court’s judgment is AFFIRMED.
-37-