NRG Power Marketing, LLC v. Maine Public Utilities Commission

(Slip Opinion) OCTOBER TERM, 2009 1 Syllabus NOTE: Where it is feasible, a syllabus (headnote) will be released, as is being done in connection with this case, at the time the opinion is issued. The syllabus constitutes no part of the opinion of the Court but has been prepared by the Reporter of Decisions for the convenience of the reader. See United States v. Detroit Timber & Lumber Co., 200 U. S. 321, 337. SUPREME COURT OF THE UNITED STATES Syllabus NRG POWER MARKETING, LLC, ET AL. v. MAINE PUB- LIC UTILITIES COMMISSION ET AL. CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT No. 08–674. Argued November 3, 2009—Decided January 13, 2010 The Mobile-Sierra doctrine—see United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332, and FPC v. Sierra Pacific Power Co., 350 U. S. 348—requires the Federal Energy Regulatory Commis sion (FERC) to presume that an electricity rate set by a freely negoti ated wholesale-energy contract meets the Federal Power Act’s (FPA) “just and reasonable” prescription, 16 U. S. C. §7824d(a); the pre sumption may be overcome only if FERC concludes that the contract seriously harms the public interest. Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. ___, ___. For many years, New England’s supply of electricity capacity was barely sufficient to meet the region’s demand. FERC and New Eng land’s generators, electricity providers, and power customers made several attempts to address the problem. This case arises from the latest effort to design a solution. Concerned parties reached a com prehensive settlement agreement (Agreement) that, inter alia, estab lished rate-setting mechanisms for sales of energy capacity and pro vided that the Mobile-Sierra public interest standard would govern rate challenges. FERC approved the Agreement, finding that it pre sents a just and reasonable outcome that is consistent with the public interest. Objectors to the settlement sought review in the D. C. Cir cuit, which largely rejected their efforts to overturn FERC’s approval order, but agreed with them that when a challenge to a contract rate is brought by noncontracting third parties, Mobile-Sierra’s public in terest standard does not apply. Held: The Mobile-Sierra presumption does not depend on the identity of the complainant who seeks FERC investigation. The presumption is not limited to challenges to contract rates brought by contracting par 2 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Syllabus ties. It applies, as well, to challenges initiated by noncontracting parties. Pp. 5–11. (a) Morgan Stanley did not reach the question presented here, but its reasoning strongly suggests that the D. C. Circuit’s holding mis perceives the aim, and diminishes the force, of the Mobile-Sierra doc trine. Announced three months after the Court of Appeals’ disposi tion in this case, Morgan Stanley reaffirmed Mobile-Sierra’s instruction to FERC to “presume that the rate set out in a freely ne gotiated . . . contract meets the ‘just and reasonable’ requirement” unless “FERC concludes that the contract seriously harms the public interest.” 554 U. S., at ___. The Morgan Stanley opinion makes it unmistakably clear that the public interest standard is not, as the D. C. Circuit suggested, independent of, and sometimes at odds with, the “just and reasonable” standard. Rather, the public interest stan dard defines “what it means for a rate to satisfy the just-and reasonable standard in the contract context.” Id., at ___. And if FERC itself must presume just and reasonable a contract rate result ing from fair, arms-length negotiations, noncontracting parties may not escape that presumption. Moreover, the Mobile-Sierra doctrine does not neglect third-party interests; it directs FERC to reject a con tract rate that “seriously harms the consuming public.” 554 U. S., at ___. Finally, the D. C. Circuit’s confinement of Mobile-Sierra to rate challenges by contracting parties diminishes the doctrine’s animating purpose: promotion of “the stability of supply arrangements which all agree is essential to the health of the [energy] industry.” Mobile, 350 U. S., at 344. A presumption applicable to contracting parties only, and inoperative as to everyone else—consumers, advocacy groups, state utility commissions, elected officials acting parens patriae— could scarcely provide the stability Mobile-Sierra aimed to secure. Pp. 5–10. (b) Whether the rates at issue qualify as “contract rates” for Mo bile-Sierra purposes, and, if not, whether FERC had discretion to treat them analogously are questions raised before, but not ruled upon by, the D. C. Circuit. They remain open for that court’s consid eration on remand. Pp. 10–11. 520 F. 3d 464, reversed in part and remanded. GINSBURG, J., delivered the opinion of the Court, in which ROBERTS, C. J., and SCALIA, KENNEDY, THOMAS, BREYER, ALITO, and SOTOMAYOR, JJ., joined. STEVENS, J., filed a dissenting opinion. Cite as: 558 U. S. ____ (2010) 1 Opinion of the Court NOTICE: This opinion is subject to formal revision before publication in the preliminary print of the United States Reports. Readers are requested to notify the Reporter of Decisions, Supreme Court of the United States, Wash­ ington, D. C. 20543, of any typographical or other formal errors, in order that corrections may be made before the preliminary print goes to press. SUPREME COURT OF THE UNITED STATES _________________ No. 08–674 _________________ NRG POWER MARKETING, LLC, ET AL., PETITIONERS v. MAINE PUBLIC UTILITIES COMMISSION ET AL. ON WRIT OF CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT [January 13, 2010] JUSTICE GINSBURG delivered the opinion of the Court. The Federal Power Act (FPA or Act), 41 Stat. 1063, as amended, 16 U. S. C. §791a et seq., authorizes the Federal Energy Regulatory Commission (FERC or Commission) to superintend the sale of electricity in interstate commerce and provides that all wholesale-electricity rates must be “just and reasonable,” §824d(a). Under this Court’s Mo bile-Sierra doctrine, FERC must presume that a rate set by “a freely negotiated wholesale-energy contract” meets the statutory “just and reasonable” requirement. Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. ___, ___ (2008) (slip op., at 1). “The presumption may be overcome only if FERC con­ cludes that the contract seriously harms the public inter­ est.” Ibid. This case stems from New England’s difficulties in maintaining the reliability of its energy grid. In 2006, after several attempts by the Commission and concerned parties to address the problems, FERC approved a com­ prehensive settlement agreement (hereinafter Settlement Agreement or Agreement). Most relevant here, the 2 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Opinion of the Court Agreement established rate-setting mechanisms for sales of energy capacity, and provided that the Mobile-Sierra public interest standard would govern rate challenges. Parties who opposed the settlement petitioned for review in the United States Court of Appeals for the D. C. Circuit. Among multiple objections to FERC’s order approving the Agreement, the settlement opponents urged that the rate challenges of nonsettling parties should not be controlled by the restrictive Mobile-Sierra public interest standard. The Court of Appeals agreed, holding that “when a rate challenge is brought by a non-contracting third party, the Mobile-Sierra doctrine simply does not apply.” Maine Pub. Util. Comm’n v. FERC, 520 F. 3d 464, 478 (2008) (per curiam). We reverse the D. C. Circuit’s judgment to the extent that it rejects the application of Mobile-Sierra to noncon­ tracting parties. Our decision in Morgan Stanley, an­ nounced three months after the D. C. Circuit’s disposition, made clear that the Mobile-Sierra public interest standard is not an exception to the statutory just-and-reasonable standard; it is an application of that standard in the con­ text of rates set by contract. The “venerable Mobile-Sierra doctrine” rests on “the stabilizing force of contracts.” Morgan Stanley, 554 U. S., at ___ (slip op., at 19); see id., at 22 (describing contract rates as “a key source of stabil­ ity”). To retain vitality, the doctrine must control FERC itself, and, we hold, challenges to contract rates brought by noncontracting as well as contracting parties. I In a capacity market, in contrast to a wholesale energy market, an electricity provider purchases from a generator an option to buy a quantity of energy, rather than pur­ chasing the energy itself. To maintain the reliability of the grid, electricity providers generally purchase more capacity, i.e., rights to acquire energy, than necessary to Cite as: 558 U. S. ____ (2010) 3 Opinion of the Court meet their customers’ anticipated demand. For many years in New England, the supply of capacity was barely sufficient to meet the region’s demand. FERC and New England’s generators, electricity providers, and power customers made several attempts to address this problem. This case stems from the latest effort to design a solution. In 2003, a group of generators sought to enter into “reliability must-run” agreements with the New England Independent System Operator (ISO), which operates the region’s transmission system.1 In its orders addressing those agreements, FERC directed the ISO to develop a new market mechanism that would set prices separately for various geographical sub-regions. Devon Power LLC, 103 FERC ¶61,082, pp. 61,266, 61,271 (2003). In March 2004, the ISO proposed a market structure responsive to FERC’s directions. See Devon Power LLC, 107 FERC ¶61,240, p. 62,020 (2004). FERC set the matter for hearing before an Administrative Law Judge (ALJ), who issued a 177-page order largely accepting the ISO’s proposal. Devon Power LLC, 111 FERC ¶63,063, p. 65,205 (2005). Several parties filed exceptions to the ALJ’s order; on September 20, 2005, the full Commission heard argu­ ments on the proposed market structure, and thereafter established settlement procedures. Devon Power LLC, 113 FERC ¶61,075, p. 61,271 (2005). After four months of negotiations, on March 6, 2006, a settlement was reached. Of the 115 negotiating parties, only 8 opposed the settlement. The Settlement Agreement installed a “forward capacity market” under which annual auctions would set capacity —————— 1 An ISO is an independent company that has operational control, but not ownership, of the transmission facilities owned by member utilities. ISOs “provide open access to the regional transmission system to all electricity generators at rates established in a single, unbundled, grid­ wide tariff . . . .” Midwest ISO Transmission Owners v. FERC, 373 F. 3d 1361, 1364 (CADC 2004) (internal quotation marks omitted). 4 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Opinion of the Court prices; auctions would be conducted three years in ad­ vance of the time when the capacity would be needed. Devon Power LLC, 115 FERC ¶61,340, pp. 62,304, 62,306– 62,308 (2006). Each energy provider would be required to purchase enough capacity to meet its share of the “in­ stalled capacity requirement,” i.e., the minimum level of capacity needed to maintain reliability on the grid, as determined by the ISO. Id., at 62,307. For the three-year gap between the first auction and the time when the ca­ pacity procured in that auction would be provided,2 the Agreement prescribed a series of fixed, transition-period payments to capacity-supplying generators. Id., at 62,308–62,309. The issue before us centers on §4.C of the Agreement (hereinafter Mobile-Sierra provision). Under that provi­ sion, challenges to both transition-period payments and auction-clearing prices would be adjudicated under “the ‘public interest’ standard of review set forth in United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332 (1956)[,] and [FPC] v. Sierra Pacific Power Co., 350 U. S. 348 (1956) (the ‘Mobile-Sierra’ doctrine).” App. 95. Mo bile-Sierra applies, §4.C instructs, “whether the [price is challenged] by a Settling Party, a non-Settling Party, or [by] the FERC acting sua sponte.” Ibid. FERC approved the Settlement Agreement, “finding that as a package, it presents a just and reasonable out­ come for this proceeding consistent with the public inter­ est.” 115 FERC, at 62,304. The Mobile-Sierra provision, FERC explicitly determined, “appropriately balances the need for rate stability and the interests of the diverse entities who will be subject to the [forward capacity mar­ ket’s auction system].” Id., at 62,335. Six of the eight objectors to the settlement sought re­ view in the D. C. Circuit. For the most part, the Court of —————— 2 The transition period runs from December 1, 2006 to June 1, 2010. Cite as: 558 U. S. ____ (2010) 5 Opinion of the Court Appeals rejected the objectors’ efforts to overturn FERC’s order approving the settlement. 520 F. 3d, at 467. But the objectors prevailed on the Mobile-Sierra issue: The D. C. Circuit held that Mobile-Sierra applies only to con­ tracting parties. Id., at 478. In this Court, the parties have switched places. Defenders of the settlement, includ­ ing the Mobile-Sierra provision, are petitioners; objectors to the settlement, victorious in the Court of Appeals only on the Mobile-Sierra issue, are respondents. Because of the importance of the issue, and in light of our recent decision in Morgan Stanley, we granted certio­ rari, 556 U. S. ___ (2009), to resolve this question: “[Does] Mobile-Sierra’s public-interest standard appl[y] when a contract rate is challenged by an entity that was not a party to the contract[?]” Brief for Petitioners i. Satisfied that the answer to that question is yes, we reverse the D. C. Circuit’s judgment insofar as it rejected application of Mobile-Sierra to noncontracting parties. II The FPA gives FERC authority to regulate the “sale of electric energy at wholesale in interstate commerce.” See 16 U. S. C. §824(b)(1). The Act allows regulated utilities to set rates unilaterally by tariff; alternatively, sellers and buyers may agree on rates by contract. See §824d(c), (d). Whether set by tariff or contract, however, all rates must be “just and reasonable.” §824d(a). Rates may be exam­ ined by the Commission, upon complaint or on its own initiative, when a new or altered tariff or contract is filed or after a rate goes into effect. §§824d(e), 824e(a). Follow­ ing a hearing, the Commission may set aside any rate found “unjust, unreasonable, unduly discriminatory or preferential,” and replace it with a just and reasonable rate. §824e(a). The Mobile-Sierra doctrine originated in twin decisions announced on the same day in 1956: United Gas Pipe Line 6 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Opinion of the Court Co. v. Mobile Gas Service Corp., 350 U. S. 332, and FPC v. Sierra Pacific Power Co., 350 U. S. 348. Both concerned rates set by contract rather than by tariff. Mobile involved the Natural Gas Act, which, like the FPA, requires utili­ ties to file all new rates with the regulatory commission. 15 U. S. C. §717c(c). In Mobile, we rejected a gas utility’s argument that the file-all-new-rates requirement author­ ized the utility to abrogate a lawful contract with a pur­ chaser simply by filing a new tariff. 350 U. S., at 336–337. Filing, we explained, was a precondition to changing a rate, not an authorization to do so in violation of a lawful contract. Id., at 339–344; see Morgan Stanley, 554 U. S., at ___ (slip op., at 4). The Sierra case involved a further issue. Not only had the Commission erroneously concluded that a newly filed tariff superseded a contract rate. In addition, the Com­ mission had suggested that, in any event, the contract rate, which the utility sought to escape, was itself unjust and unreasonable. The Commission thought that was so “solely because [the contract rate] yield[ed] less than a fair return on the [utility’s] net invested capital.” 350 U. S., at 355. The Commission’s suggestion prompted this Court to home in on “the question of how the Commission may evaluate whether a contract rate is just and reasonable.” Morgan Stanley, 554 U. S., at ___ (slip op., at 4). The Sierra Court answered the question this way: “[T]he Commission’s conclusion appears on its face to be based on an erroneous standard. . . . [W]hile it may be that the Commission may not normally impose upon a public utility a rate which would produce less than a fair return, it does not follow that the public utility may not itself agree by contract to a rate af­ fording less than a fair return or that, if it does so, it is entitled to be relieved of its improvident bar­ Cite as: 558 U. S. ____ (2010) 7 Opinion of the Court gain. . . . In such circumstances the sole concern of the Commission would seem to be whether the rate is so low as to adversely affect the public interest—as where it might impair the financial ability of the public util­ ity to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory.” 350 U. S., at 354–355 (some emphasis added). In a later case, we similarly explained: “The regulatory system created by the [FPA] is premised on contractual agreements voluntarily devised by the regulated compa­ nies; it contemplates abrogation of these agreements only in circumstances of unequivocal public necessity.” Per mian Basin Area Rate Cases, 390 U. S. 747, 822 (1968).3 Two Terms ago, in Morgan Stanley, 554 U. S. ___, the Court reaffirmed and clarified the Mobile-Sierra doctrine. That case presented two questions: First, does the Mobile- Sierra presumption (that contract rates freely negotiated between sophisticated parties meet the just and reason­ able standard imposed by 16 U. S. C. §824d(a)) “apply only when FERC has had an initial opportunity to review a contract rate without the presumption?” 554 U. S., at ___ (slip op., at 1). “Second, does the presumption [generally] impose as high a bar to challenges by purchasers of whole­ sale electricity as it does to challenges by sellers?” Id., at —————— 3 Consistent with the lead role of contracts recognized in Mobile- Sierra, we held in United Gas Pipe Line Co. v. Memphis Light, Gas and Water Div., 358 U. S. 103, 110–113 (1958), that parties may contract out of the Mobile-Sierra presumption. They could do so, we ruled, by specifying in their contracts that a new rate filed with the Commission would supersede the contract rate. Courts of Appeals have approved an option midway between Mobile-Sierra and Memphis Light: A contract that does not allow the seller to supersede the contract rate by filing a new rate may nonetheless permit the Commission to set aside the contract rate if it results in an unfair rate of return, without a further showing that it adversely affects the public interest. See, e.g., Papago Tribal Util. Auth. v. FERC, 723 F. 2d 950, 953 (CADC 1983); Louisiana Power & Light Co. v. FERC, 587 F. 2d 671, 675–676 (CA5 1979). 8 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Opinion of the Court ___ (slip op., at 1–2); see id., at 19–20. Answering no to the first question and yes to the second, the Court empha­ sized the essential role of contracts as a key factor foster­ ing stability in the electricity market, to the longrun bene­ fit of consumers. Id., at ___, ___ (slip op., at 19, 22); see, e.g., Market-Based Rates ¶6, 72 Fed. Reg. 39906 (2007) (noting chilling effect on investments caused by “uncer­ tainties regarding rate stability and contract sanctity”); Nevada Power Co. v. Duke Energy Trading & Marketing, L. L. C., 99 FERC ¶61,047, pp. 61,184, 61,190 (2002) (“Competitive power markets simply cannot attract the capital needed to build adequate generating infrastructure without regulatory certainty, including certainty that the Commission will not modify market-based contracts unless there are extraordinary circumstances.”). Morgan Stanley did not reach the question presented here: Does Mobile-Sierra’s public interest standard apply to challenges to contract rates brought by noncontracting parties? But Morgan Stanley’s reasoning strongly sug­ gests that the D. C. Circuit’s negative answer misperceives the aim, and diminishes the force, of the Mobile-Sierra doctrine. In unmistakably plain language, Morgan Stanley re­ stated Mobile-Sierra’s instruction to the Commission: FERC “must presume that the rate set out in a freely negotiated wholesale-energy contract meets the ‘just and reasonable’ requirement imposed by law. The presump­ tion may be overcome only if FERC concludes that the contract seriously harms the public interest.” 554 U. S., at ___ (slip op., at 1). As our instruction to FERC in Morgan Stanley conveys, the public interest standard is not, as the D. C. Circuit presented it, a standard independent of, and sometimes at odds with, the “just and reasonable” stan­ dard, see 520 F. 3d, at 478; rather, the public interest standard defines “what it means for a rate to satisfy the just-and-reasonable standard in the contract context.” Cite as: 558 U. S. ____ (2010) 9 Opinion of the Court Morgan Stanley, 554 U. S., at ___ (slip op., at 17). And if FERC itself must presume just and reasonable a contract rate resulting from fair, arms-length negotiations, how can it be maintained that noncontracting parties nevertheless may escape that presumption? 4 Moreover, the Mobile-Sierra doctrine does not overlook third-party interests; it is framed with a view to their protection. The doctrine directs the Commission to reject a contract rate that “seriously harms the consuming pub­ lic.” Morgan Stanley, 554 U. S., at ___ (slip op., at 17); see Verizon Communications Inc. v. FCC, 535 U. S. 467, 479 (2002) (When a buyer and a seller agree upon a rate, “the principal regulatory responsibility [i]s not to relieve a contracting party of an unreasonable rate, . . . but to pro­ tect against potential discrimination by favorable contract rates between allied businesses to the detriment of other wholesale customers.” (Emphasis added.)). Finally, as earlier indicated, see supra, at 7–8, the D. C. Circuit’s confinement of Mobile-Sierra to rate challenges by contracting parties diminishes the animating purpose of the doctrine: promotion of “the stability of supply ar­ rangements which all agree is essential to the health of the [energy] industry.” Mobile, 350 U. S., at 344. That dominant concern was expressed by FERC in the order on review: “Stability is particularly important in this case, —————— 4 The D. C. Circuit emphasized a point no doubt true, but hardly dis­ positive: Contracts bind parties, not nonparties. Maine Pub. Util. Comm’n v. FERC, 520 F. 3d 464, 478 (2008) (per curiam). Mobile- Sierra holds sway, however, because well-informed wholesale-market participants of approximately equal bargaining power generally can be expected to negotiate just-and-reasonable rates, see Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. ___, ___ (2008) (slip op., at 17), and because “contract stability ultimately benefits consumers,” id., at ___ (slip op., at 22). These reasons for the presumption explain why FERC, surely not legally bound by a contract rate, must apply the presumption and, correspond­ ingly, why third parties are similarly controlled by it. 10 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N Opinion of the Court which was initiated in part because of the unstable nature of [installed capacity] revenues and the effect that has on generating units, particularly those . . . critical to main­ taining reliability.” 115 FERC, at 62,335. A presumption applicable to contracting parties only, and inoperative as to everyone else—consumers, advocacy groups, state utility commissions, elected officials acting parens pa triae—could scarcely provide the stability Mobile-Sierra aimed to secure.5 We therefore hold that the Mobile-Sierra presumption does not depend on the identity of the complainant who seeks FERC investigation. The presumption is not limited to challenges to contract rates brought by contracting parties. It applies, as well, to challenges initiated by third parties. III The objectors to the settlement appearing before us maintain that the rates at issue in this case—the auction rates and the transition payments—are prescriptions of general applicability rather than “contractually negotiated rates,” hence Mobile-Sierra is inapplicable. See Brief for Respondents 15–17, and n. 1 (internal quotation marks omitted). FERC agrees that the rates covered by the settlement “are not themselves contract rates to which the Commission was required to apply Mobile-Sierra.” Brief for FERC 15. But, FERC urges, “the Commission had discretion to do so,” id., at 28; furthermore, “[t]he court of appeals’ error in creating a third-party exception to the Mobile-Sierra presumption is a sufficient basis for revers­ ing its judgment,” id., at 22. Whether the rates at issue —————— 5 The FPA authorizes “[a]ny person, electric utility, State, municipal­ ity, or State commission” to complain. 16 U. S. C. §825e (emphasis added). FERC regulations similarly permit “[a]ny person [to] file a complaint seeking Commission action.” 18 CFR §385.206(a) (2009) (emphasis added). Cite as: 558 U. S. ____ (2010) 11 Opinion of the Court qualify as “contract rates,” and, if not, whether FERC had discretion to treat them analogously are questions raised before, but not ruled upon by, the Court of Appeals. They remain open for that court’s consideration on remand. See Tr. of Oral Arg. 16. * * * For the reasons stated, the judgment of the Court of Ap­ peals for the D. C. Circuit is reversed to the extent that it rejects the application of Mobile-Sierra to noncontracting parties, and the case is remanded for further proceedings consistent with this opinion. It is so ordered. Cite as: 558 U. S. ____ (2010) 1 STEVENS, J., dissenting SUPREME COURT OF THE UNITED STATES _________________ No. 08–674 _________________ NRG POWER MARKETING, LLC, ET AL., PETITIONERS v. MAINE PUBLIC UTILITIES COMMISSION ET AL. ON WRIT OF CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT [January 13, 2010] JUSTICE STEVENS, dissenting. The opinion that the Court announces today is the third chapter in a story about how a reasonable principle, ex tended beyond its foundation, becomes bad law. In the first chapter the Court wisely and correctly held that a seller who is a party to a long-term contract to provide energy to a wholesaler could not unilaterally repudiate its contract obligations in response to changes in market conditions by simply filing a new rate schedule with the regulatory commission. Only if the rate was so low that the seller might be unable to stay in business, thereby impairing the public interest, could the seller be excused from performing its contract. That is what the Court held in United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332 (1956), and FPC v. Sierra Pacific Power Co., 350 U. S. 348 (1956). In the second chapter the Court unwisely and incor rectly held that the same rule should apply to a buyer who had been forced by unprecedented market conditions to enter into a long-term contract to buy energy at abnor mally high prices. The Court held the Federal Energy Regulatory Commission (FERC) could not set aside such a contract as unjust and unreasonable, even though it sad dled consumers with a duty to pay prices that would be considered unjust and unreasonable under normal market 2 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N STEVENS, J., dissenting conditions, unless the purchaser could also prove that “the contract seriously harms the public interest.” Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. ___, ___ (2008) (slip op., at 1). The Court held in Morgan Stanley that Mobile-Sierra established a presumption: FERC “must presume that the rate set out in a freely negotiated wholesale-energy con tract meets the ‘just and reasonable’ requirement imposed by law.” 554 U. S., at ___ (slip op., at 1). And that pre sumption, according to the Court, is a simple application of the just-and-reasonable standard to contract rates, not a different standard of review. Id., at ___ (slip op., at 6) (rejecting the “obviously indefensible proposition that a standard different from the statutory just-and-reasonable standard applies to contract rates”). But applying the presumption nonetheless sets a higher bar for a rate chal lenge.1 FERC may abrogate the rate only if the public interest is seriously harmed. Id., at ___ (slip op., at 22) (“[U]nder the Mobile-Sierra presumption, setting aside a contract rate requires a finding of ‘unequivocal public necessity,’ ” Permian Basin Area Rate Cases, 390 U. S. 747, 822 (1968), “or ‘extraordinary circumstances,’ Arkansas Louisiana Gas Co. v. Hall, 453 U. S. 571, 582 (1981)”). As I explained in my dissent in Morgan Stanley, the imposition of this additional burden on purchasers chal lenging rates was not authorized by the governing statute. Under the Federal Power Act (FPA), all wholesale electric ity rates must be “just and reasonable.” 16 U. S. C. §824d(a). “[N]othing in the statute mandates differing application of the statutory standard to rates set by con —————— 1 Whether the Court explains the Mobile-Sierra doctrine as a pre sumption or as a different standard of review, “[t]here is no significant difference between requiring a heightened showing to overcome an otherwise conclusive presumption and imposing a heightened standard of review.” Morgan Stanley, 554 U. S., at ___ (slip op., at 3) (STEVENS, J., dissenting). Cite as: 558 U. S. ____ (2010) 3 STEVENS, J., dissenting tract.” Morgan Stanley, 554 U. S., at ___ (slip op., at 3) (STEVENS, J., dissenting) (internal quotation marks omit ted; emphasis deleted). And the Mobile-Sierra line of cases did not “mandate a ‘serious harm’ standard of re view,” much less “require any assumption that high rates and low rates impose symmetric burdens on the public interest.” Morgan Stanley, 554 U. S., at ___ (slip op., at 7) (STEVENS, J., dissenting). Instead, “the statement in Permian Basin about ‘unequivocal public necessity,’ 390 U. S., at 822, speaks to the difficulty of establishing injury to the public interest in the context of a low-rate chal lenge,” i.e., one brought by sellers of electricity. Id., at ___ (slip op., at 8). It does not establish a new standard that applies as well to a “high-rate challenge” brought by pur chasers. Ibid. But even accepting Morgan Stanley as the law, the Court unwisely goes further today. In this third chapter of the Mobile-Sierra story, the Court applies a rule—one designed initially to protect the enforceability of freely negotiated contracts against parties who seek a release from their obligations—to impose a special burden on third parties exercising their statutory right to object to unjust and unreasonable rates. This application of the rule represents a quantum leap from the modest origin set forth in the first chapter of this tale. As the Court of Appeals correctly concluded in the opinion that the Court sets aside today: “This case is clearly outside the scope of the Mobile-Sierra doctrine.” Maine Pub. Util. Comm’n v. FERC, 520 F. 3d 464, 477 (CADC 2008) (per curiam). As the D. C. Circuit noted,2 “[c]ourts have rarely men —————— 2 Because the D. C. Circuit’s opinion was written before this Court’s decision in Morgan Stanley, that court’s purported error in describing the Mobile-Sierra doctrine as an “exception” to the just-and-reasonable standard, 520 F. 3d, at 477, is understandable. As that court recog nized, and the majority does not change today, the Mobile-Sierra standard in fact “makes it harder for [respondents] to successfully 4 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N STEVENS, J., dissenting tioned the Mobile-Sierra doctrine without reiterating that it is premised on the existence of a voluntary contract between the parties.” Ibid. But, the Court asks, “[I]f FERC itself must presume just and reasonable a contract rate resulting from fair, arms-length negotiations, how can it be maintained that noncontracting parties nevertheless may escape that presumption?” Ante, at 9. This Court’s understanding of Sierra provides an answer. “Sierra was grounded in the commonsense notion that ‘[i]n wholesale markets, the party charging the rate and the party charged [are] often sophisticated businesses enjoying presumptively equal bargaining power, who could be expected to negotiate a “just and reasonable” rate as be tween the two of them.’ ” Morgan Stanley, 554 U. S., at ___ (slip op., at 17) (quoting Verizon Communications Inc. v. FCC, 535 U. S. 467, 479 (2002); emphasis added). This “commonsense notion” supports the rule requiring FERC to apply a presumption against letting a party out of its own contract, as the D. C. Circuit recognized. 520 F. 3d, at 478 (“The Mobile-Sierra doctrine applies a more defer ential standard of review to preserve the terms of the bargain as between the contracting parties”). It does not, however, support a rule requiring FERC to apply a pre sumption against abrogating any rate set by contract, even when, as in this case, a noncontracting party may be required in practice to pay a rate it did not agree to. The Court further reasons that “confinement of Mobile- Sierra to rate challenges by contracting parties diminishes the animating purpose of the doctrine,” which is ensuring the stability of contract-based supply arrangements. Ante, at 9. Maybe so, but applying Mobile-Sierra to rate chal lenges by noncontracting parties loses sight of the animat ing purpose of the FPA, which is “the protection of the public interest.” Sierra, 350 U. S., at 355. That interest is —————— challenge rates.” 520 F. 3d, at 478. Cite as: 558 U. S. ____ (2010) 5 STEVENS, J., dissenting “the interest of consumers in paying ‘ “the lowest possible reasonable rate consistent with the maintenance of ade quate service in the public interest.” ’ ” Morgan Stanley, 554 U. S., at ___ (slip op., at 7) (STEVENS, J., dissenting) (quoting Permian Basin, 390 U. S., at 793). I do not doubt that stable energy markets are important to the public interest, but “under the FPA, Congress has charged FERC, not the courts, with balancing the short-term and long-term interests of consumers” under the just-and reasonable standard of review. Morgan Stanley, 554 U. S., at ___ (slip op., at 9) (STEVENS, J., dissenting). The Court today imposes additional limits upon FERC’s ability to protect that interest. If a third-party wholesale buyer can show a rate harms the public interest (perhaps because it is too high to be just and reasonable under normal review), but cannot show it seriously harms the public, FERC may do nothing about it.3 The Court assures respondents that the “public interest standard” does not “overlook third-party interests” and is “framed with a view to their protection.” Ante, at 8, 9. Perhaps in practice the Mobile-Sierra doctrine will protect third parties’ interests, and the public interest, just as well as the so-called “ordinary” just-and-reasonable stan dard. But respondents are rightly skeptical. The Mobile- Sierra doctrine, as interpreted by the Court in Morgan Stanley, must pose a higher bar to respondents’ rate chal lenge—that is, it requires them to show greater harm to —————— 3 FERC agrees with petitioners that the public interest standard “govern[s] all challenges to the rates set by contract, regardless of the identity of the challenger.” Reply Brief for FERC 4. But “not even FERC has the authority to endorse [this] rule.” Morgan Stanley, 554 U. S., at ___ (slip op., at 9) (STEVENS, J., dissenting). “The FPA does not indulge, much less require, a ‘practically insurmountable’ presumption, see Papago Tribal Util. Auth. v. FERC, 723 F. 2d 950, 954 (CADC 1983) (opinion for the court by Scalia, J.), that all rates set by contract com port with the public interest and are therefore just and reasonable.” Id., at ___ (slip op., at 9–10). 6 NRG POWER MARKETING, LLC v. MAINE PUB. UTIL. COMM’N STEVENS, J., dissenting the public.4 Otherwise, it would hardly serve to protect contract stability better than the plain vanilla just-and reasonable standard and the Court’s decision in Morgan Stanley would have little effect. Furthermore, the Court today reiterates that the doctrine poses a high bar. See ante, at 7–8. It was sensible to require a contracting party to show something more than its own desire to get out of what proved to be a bad bargain before FERC could abrogate the parties’ bargain. It is not sensible, nor authorized by the statute, for the Court to change the de facto standard of review whenever a rate is set by private contract, based solely on the Court’s view that contract stability should be —————— 4 In my view, “whether a rate is ‘just and reasonable’ is measured against the public interest, not the private interests of regulated [parties].” Id., at ___ (slip op., at 7). But I note the Court’s assertion that the Mobile-Sierra doctrine protects “third-party interests,” ante, at 9, is a new twist on the “public interest standard” as traditionally understood. As the Court recognized in Morgan Stanley, one conse quence of applying Mobile-Sierra is that “ ‘the sole concern of the Commission’ ” is the public interest, and FERC cannot consider, for example, whether a rate guarantees a sufficient rate of return to a regulated entity. 554 U. S., at ___ (slip op., at 4) (quoting FPC v. Sierra Pacific Power Co., 350 U. S. 348, 355 (1956)); see also Morgan Stanley, 554 U. S., at ___ (slip op., at 17, n. 3). In addition to requiring that FERC find some greater degree of harm to the public than would be required under the ordinary just-and-reasonable standard, therefore, the Mobile-Sierra doctrine leaves little room for respondents—at least one of which did not negotiate the rate but must nonetheless purchase electricity at that price in the forward capacity market unless it self supplies its capacity—to assert their private interest in making a rate challenge. The Court suggests that FERC could set aside a rate under the public interest standard if the contract established favorable rates between allied businesses to the detriment of other wholesale custom ers, ante, at 9, but has not spelled out whether a challenger would still have to show that circumstance harmed the public interest. It remains unclear whether a noncontracting party that must purchase or sell electricity at a rate it did not negotiate could argue that a rate fails the “public interest standard” because the rate is detrimental to that entity’s private interest. Cite as: 558 U. S. ____ (2010) 7 STEVENS, J., dissenting preserved unless there is extraordinary harm to the public interest. For these reasons, I respectfully dissent.