FILED
FEB 03 2011
NOT FOR PUBLICATION MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
TOLL BROTHERS, INC., a Delaware No. 09-16955
corporation,
D.C. No. 3:08-cv-00987-SC
Plaintiff-Counter-Defendant-
Appellant,
MEMORANDUM*
v.
CHANG SU-O LIN; HONG LIEN LIN;
HONG YAO LIN, individuals,
Defendants-Counter-
Claimants, Appellees.
Appeal from the United States District Court*
for the Northern District of California
Samuel Conti, District Judge, Presiding
Argued and Submitted November 4, 2010
San Francisco, California
Before: GOULD, CALLAHAN, Circuit Judges, and KORMAN, District Judge.**
Toll Brothers, Inc. (“Toll”) appeals from a judgment entered in the United States
*
This disposition is not appropriate for publication and is not precedent
except as provided by 9th Cir. R. 36-3.
**
The Honorable Edward R. Korman, Senior United States District Judge,
Eastern District of New York, sitting by designation.
District Court for the Northern District of California following a bench trial in favor of
Chang Su-O Lin, Hong Lien Lin, and Hong Yao Lin (“the Lins”). The complaint, based
on diversity of citizenship, arose out of a purchase and sale agreement (“PSA”) in which
the Lins agreed to sell Toll–a national homebuilder– three separate parcels of land in
Dublin, California in three separate closings for a total sale price of $241,500,000. Toll
deposited $21,735,000 into an escrow account to be paid out in increments with each
property closing. Toll and the Lins successfully closed on two parcels of land, Sub-
Areas 1 and 2. The disputed issue here involves the Sub-Area 3 closing scheduled for
June 30, 2007.
Specifically, without consulting Toll, the Lins had negotiated and executed an
easement to PG&E across Sub-Area 3 on December 12, 2005 for the construction of
temporary overhead power lines. In addition, the Lins installed six above-ground utility
vaults on the property, which Toll challenged on the basis that not all of the vaults were
necessary and the placement of the vaults interfered with Toll’s development plans for
the property. Although the Lins had proposed language terminating the recorded
easement on December 31, 2006, PG&E would not agree to a fixed termination date.
By September 2006 the Lins had completed all of the work necessary for the removal
of the temporary power lines from Sub-Area 3and applied to PG&E for removal of the
temporary overhead power lines. Despite numerous unsuccessful emails and phone
calls from the Lins to PG&E throughout 2007 attempting to get the easement
2
extinguished, PG&E did not quitclaim the power line easement back to the Lins prior
to the scheduled closing of Sub-Area 3. With the easement still conveyed to PG&E, and
no knowledge or reasonable expectation of when it would be extinguished, Toll
terminated the PSA in December 2007, more than five months after the closing date for
Sub-Area 3 specified in the PSA.
Toll then filed suit for a return of escrow for Sub-Area 3 in the amount of
$7,735,000 alleging that the conveyance and continued existence of the power line
easement to PG&E over Sub-Area 3 and the installation of the utility vaults constituted
breaches of the PSA. In the alternative, Toll alleged that the PSA was illegal and void
because it failed to comply with the Subdivision Map Act. Pursuant to § 4.4 of the PSA,
the Lins seek to retain Toll’s $7,735,000 deposit as liquidated damages.1
Although numerous issues are raised, we need only address two of them here to
resolve the appeal.
A. The Power Line Easement
The first and most significant issue is whether the power line easement across
Sub-Area 3 that continued to exist for more than five months after the scheduled close
of Sub-Area 3 constituted a breach of the PSA sufficient to permit Toll to rescind the
contract and recover its deposit.
1
Section 4.4 of the PSA provides that if the sale of property is not “consummated
as a result of the buyer’s default under the agreement and if seller is not also in default,”
the deposit “shall be retained by seller as liquidated damages.”
3
The district judge found that the Lins’ grant of an easement to PG&E for the
installation of temporary power lines did not constitute a breach of the PSA because it
did not interfere with Toll’s planning for Sub-Area 3. In arriving at this conclusion, the
district judge relied on the following findings of fact: 1) Toll knew the power lines were
intended to be a temporary installation; 2) Toll had ceased making plans to develop
Sub-Area 3 at the time of the scheduled closing in June 2007; and, 3) Toll’s planning
for the development of Sub-Area 3, if restarted, would have taken at least a year so the
easement, extinguished in June 2008, did not limit Toll’s ability to develop the land.
Despite finding that the Lins “had not complied with all the requirements in the PSA”
in granting the easement, the district judge held that the Lins’ violation of the PSA “was
not significant enough to justify Toll’s termination of the contract.” In sum, although
the Lins may have violated the contract, their conduct did not amount to a material
breach sufficient to justify Toll’s rescission. We disagree.
Under California law, the buyers of real property are entitled to take title clear of
encumbrances or defects. See Eason v. Montgomery, 27 P. 280, 282 (Cal. 1891) (in
contracts “for the sale of land there is an implied condition that the title of the vendor
is good, and that he will transfer to the vendee... a title unencumbered and without
defect”); Crim v. Umbsen, 103 P. 178, 180 (Cal. 1909) (it is a buyer’s “right... to receive
a perfect title of record... within the time specified in the agreement”). A marketable
title “means a title which a reasonable purchaser, well informed as to the facts and their
4
legal bearings, willing and anxious to perform his contract, would, in the exercise of that
prudence which business men ordinarily bring to bear on such transactions, be willing
and ought to accept.” Hocking v. Title Ins. & Trust Co., 234 P.2d 625, 649-50 (Cal.
1951).
A seller’s failure to deliver unencumbered, marketable or agreed-upon title when
a contract matures constitutes a breach and allows rescission. See Post v. Palpar, Inc.,
7 Cal. Rptr. 823, 826 (Cal. Ct. App. 1960) (holding that the “failure to tender marketable
title at the time the contract matures is a material breach”); Fristad v. Thompson, 276
P.2d 116, 118 (Cal. Ct. App. 1954) (when seller deeds a perpetual easement to the city
for the construction of a sewer across property under contract to a homebuilder,
rescission by the homebuilder is valid because he was “entitled to a conveyance of the
full title and to possession of all of the property”); Thomas v. Spitzer, 260 P. 833, 833-34
(Cal. Ct. App. 1927) (where a seller’s failure to obtain a guarantee of title as stipulated
in the agreement permitted buyer’s rescission); Switzler v. Robert A. Klein & Co., 271
P. 367, 369-70 (Cal. Ct. App. 1928) (when seller grants an easement to the city to build
a sewer line without the knowledge or consent of buyers who had entered into an
agreement to purchase the land, consideration failed and the plaintiffs were entitled to
rescind the contract).
Rescission by the buyer when seller cannot deliver marketable title after a
reasonable period of time is justified even when seller claims that a remedy to the
5
encumbrance or defect is available or forthcoming, because a buyer “is entitled to a title
that is fairly deducible of record, free from reasonable doubt and litigation.” Whelan v.
Rosseter, 82 P. 1082, 1083 (Cal. Ct. App. 1905); Crim v. Umbsen, 103 P. 178, 180 (Cal.
1909); see also, Fristad v. Thompson, 276 P.2d 116, 118 (Cal. Ct. App. 1954) (a buyer
is “not obliged to accept a mere paper title, to bring an action for possession against
another party, and to rely upon their possible success in such an action”). A marketable
title “must not only be free of actual defects but also of reasonable doubt and probable
litigation.” Lansburgh v. Market St. Ry. Co., 220 P.2d 423, 426 (Cal. Ct. App. 1950).
Particularly apposite here is Leiter v. Handelsman, 270 P.2d 563, 564-65 (Cal.
Ct. App. 1954), where the seller was unable to deliver clear title on the closing date
because the land contained guy wires and an easement in favor of the power company.
Although the power company agreed to remove the guy wires and quitclaim the land
back to the seller, these actions were delayed, leading the buyers to cancel escrow and
demand a return of their deposit. Id. at 564. Despite the fact that the power company
removed the wires and executed a quitclaim deed the day after the buyer’s rescission,
only three weeks after the scheduled closing date, id., the rescission was upheld because
the sellers were unable to deliver marketable title “[w]ithin a reasonable time after the”
scheduled closing. Id. at 568. Similarly, in Ward v. Downey, 213 P.2d 523, 526 (Cal.
Ct. App. 1950), it was held that the possibility of an estate tax in an unspecified amount
6
on property to be sold constituted a defect in title that made it unmarketable, thereby
allowing buyers to rescind the contract even though the exact amount of such tax was
determined within 12 days of the scheduled closing and could have been cured by the
sellers if they paid the taxes.2 Moreover, as the dissent points out, under California law,
motive “is irrelevant to determining if there was a breach or inevitable breach on closing.”
Dissent at 4. Nevertheless, relying on the Restatement (Second) of Contracts, the dissent
suggests that motive is relevant “in assessing whether that breach was material.” Dissent at
4. Research has not uncovered a California case relying on the Restatement (Second)
of Contracts § 241 (1981) (or a comparably worded section in the Restatement (First)
of Contracts § 275 (1932)) in the context of a contract for the sale of real property.
Moreover, California law holds that a buyer’s motive in rescinding a contract for the
sale of land is not relevant to an assessment of his legal rights or fulfillment of legal
obligations under a contract, including whether a material breach occurred. Specifically,
as the Supreme Court of California has held:
We cannot consider the motives which prompted respondent
to rescind the contract of sale. It was his right under that
2
While these are, for the most part, intermediate appellate court decisions, under
Erie Railroad Co. v. Tompkins, 304 U.S. 64, 78 (1938), “[w]here an intermediate
appellate state court rests its considered judgment upon the rule of law which it
announces, that is a datum for ascertaining state law which is not to be disregarded by
a federal court unless it is convinced by other persuasive data that the highest court of
the state would decide otherwise.” West v. American Tel. & Tel. Co., 311 U.S. 223,
236-37 (1940); see also, Hangarter v. Provident Life and Acc. Ins. Co., 373 F.3d 998,
1012-13 (9th Cir. 2004).
7
instrument to receive a perfect title of record at the time or
within the time specified in the agreement. This the
plaintiffs could not give him. He was entitled to rest upon
the provisions of the contract, whether or not his real purpose
was to avoid taking and paying for a tract of land that had
depreciated in value.
Crim, 103 P. 178, 180 (Cal. 1909); see also De Bairos v. Barlin, 190 P. 188, 191 (Cal.
Ct. App. 1920) (“The courts have held that the motives of the vendee in rescinding may
not be inquired into when he has a legal reason for rescinding and relies thereon”).
Contrary to the dissent, we do not suggest that “California law requires us
invariably to view any failure to be in a position to tender clear title on the closing date
as per se a material breach.” Dissent at 1. Our decision that the power line easement
constituted a breach of the PSA is not based solely on the inability of the Lins to deliver
unencumbered title on the scheduled closing date. Indeed, Toll did not rescind because
the Lins had not cured the defect in title by the closing date specified in the PSA.
Instead, Toll waited over five months beyond the scheduled closing before rescinding
the contract. Moreover, despite the fact that the Purchase Sale Agreement gave the Lins
the option to extend closing in order to cure a breach of contract, the Lins made it clear
prior to the scheduled closing on June 30, 2007, that they would not extend closing.
Later, in negotiations after the scheduled closing, the Lins offered to extend the close
only if Toll provided additional security and agreed to accept the current location of the
utility vaults which was also in dispute between the parties.
8
Significantly, the dispute created by the power line easement was of the Lins own
making because they chose to violate the Purchase Sale Agreement by conveying an
easement to PG&E without Toll’s knowledge or consent and without requiring a
termination date on the conveyed easement. Moreover, the breach created by the power
line easement was, as the dissent acknowledges, “of uncertain and unspecified
duration.” Dissent at 2. Thus, despite seeking the removal of the power lines following
the completion of an underground trench in September 2006 and numerous
communications with PG&E throughout 2007, the Lins were unsuccessful in
extinguishing the easement and could not provide a date-certain as to when the easement
would be extinguished. While the dissent argues, with the benefit of hindsight, that the
easement had “no practical impact,” Dissent at 5, it ignores the fact that, when Toll
rescinded the contract, it did not know when or if the easement would be extinguished,
or if doing so would require legal action.
Nor do we agree with the dissent that the “Lins suffer a major forfeiture over
what seems a hypertechnical breach.” Dissent at 5. We pass over the fact that the major
forfeiture here may be the $7,735,000 that Toll will forfeit to the Lins as liquidated
damages without regard to any actual damage suffered by the Lins. In essence, if the
Lins prevail, they will get to keep their land plus $7,735,000. This notwithstanding the
fact that they rejected the option to extend the closing of Sub-Area 3, insisting instead
upon closing as scheduled despite their inability to convey title “free from reasonable
9
doubt and litigation,” Whelan v. Rosseter, 82 P. at 1083.3 Under California law, this
was more than a “hypertechnical breach.” Dissent at 5; see Ward, 213 P.2d at 526;
Leiter, 270 P.2d at 564-65. Moreover, although the dissent suggests that at issue here
is “a large development contract that placed certain obligations on each party, and that
called for cooperation,” Dissent at 6, our review of the record suggests that it was the
Lins rather than Toll whose conduct was consistent with this vague mandate. Toll
waited more than five months after the specified closing date before rescinding the
contract and, unlike the Lins, was willing to extend the closing date even further.
B. The School Site
The PSA obligated Toll, as the buyer of Sub-Area 2, to reconvey a parcel of Sub-
Area 2 to the Lins after designating this land as a “School Site.” Reconveyance of the
school site was made a special closing condition for the third closing: “Buyer shall have
reconveyed to Seller or Seller’s assignee the elementary school parcel in Sub-Area 2.”
The Lins argue that reconveyance of the school site “was a fundamental governmental
3
Toll does not challenge the validity of § 4.4, the clause in the PSA that provides
for payment of liquidated damages to the Lins in the amount equal to the $7, 735,000
held in escrow in the event of Toll’s default, provided that the Lins are not in default.
While such clauses in the sale of real property are valid if the down payment is a
reasonable amount, when “the evidence establishes that it would not ‘be impracticable
or extremely difficult to fix the actual damage’... such a provision may not be enforced
as one for liquidated damages.” See Freedman v. Rector, Wardens & Vestrymen of St.
Mathias Parish, 230 P.2d 629, 633 (Cal. 1951) (internal citations omitted) (Traynor, J.).
Because Toll does not raise the issue of the enforceability of the liquidated damages
clause, however, we did not reach it here.
10
and regulatory prerequisite for the entire development,” the failure of which permitted
the Lins “to extend the close of escrow past the original scheduled ‘close’ date.”
The district judge held that “Toll’s failure to reconvey the school site was not a
failure to perform a condition precedent to the Lins’ duty to sell Sub-Area 3,” because
the school site had been assigned to another party prior to the closing of Sub-Area 3 and
therefore was not Toll’s to convey. Accordingly, Toll did not breach the PSA by failing
to reconvey the school site. Nevertheless, he held that Toll’s failure to comply with this
provision gave the Lins the right to extend closing beyond the scheduled date of June
30, 2007.
We agree with the district judge that Toll did not breach the PSA by failing to
reconvey the school site – a holding that the Lins do not challenge on this appeal.
Notwithstanding his finding that there was no breach, the district judge held that Toll’s
failure to reconvey the school site gave the Lins the right to indefinitely extend the
closing date. Consequently, their failure to close, as late as five months after the
closing date specified in the PSA, did not constitute a breach entitling Toll to rescind the
agreement. While the logic of this argument escapes us, even if the Lins had the right
to extend closing, this right was effectively waived when they insisted, with full
knowledge that the school site had yet to be reconveyed, that the closing of Sub-Area
3 proceed as scheduled.
The judgment of the District Court is
11
REVERSED.
12
FILED
Toll Brothers, Inc. v. Su-O Lin et al., No. 09-16955 FEB 03 2011
MOLLY C. DWYER, CLERK
GOULD, J., dissenting: U.S. COURT OF APPEALS
I respectfully dissent. The district court held a trial that occupied nine days.
The district court made detailed factual findings that illuminate the grounds for its
decision that the Lins had not materially breached the purchase and sale agreement.
Those factual findings are not challenged on appeal and thus are conceded as true.
The majority rests its opinion primarily on the premise, I think questionable, that
California law requires us invariably to view any failure to be in a position to
tender clear title on the closing date as per se a material breach.1 Hence, the
majority reasons, the granting of a temporary easement to Pacific Gas & Electric
Company (PG&E) for overhead power lines constituted a material breach of the
purchase and sale agreement. The majority relies on California law for the
principle that there is an implied condition in every contract for sale of real
property that the seller will convey title unencumbered and without defect, and that
the failure to tender marketable title at the time a contract matures is a material
breach granting the purchaser the right to rescind. See, e.g., Crim v. Umbsen, 103
1
The majority disclaims reliance on this premise and mentions other
circumstances, such as the delay from scheduled closing to declaration of breach,
to support its conclusion. However, I believe the majority comes close to this
premise because the other circumstances cited do not significantly impact the
analysis.
1
P. 178, 180 (Cal. 1909).
In a case such as this, we are bound to apply state law, which requires us to
make our best estimate of how the California Supreme Court would rule on the
issue if tendered to it. See Vestar Dev. II, LLC v. Gen. Dynamics Corp., 249 F.3d
958, 960 (9th Cir. 2001). Here, in light of the consistent statements in the
California cases on the importance of tendering clear title, I concur in the
majority’s conclusion that at least the temporary power line easement, and perhaps
also the building of the six utility vaults without consent or consultation was a
breach. Nonetheless, I believe that in the unusual circumstances of this case, the
California Supreme Court would view the power line and utility vault easements as
at most partial breach. Largely for reasons supported by the district court’s
extensive and unchallenged factual findings, I would hold that only a partial breach
occurred, not one permitting Toll Brothers to rescind the contract.
Here are some of the salient points that impact my analysis. First, the power
easement was temporary, and, although it was of uncertain and unspecified
duration and had to be removed by PG&E, it is also true that the local governing
authority, the city, would not allow above ground power lines to remain. Given the
temporary nature of these lines, I must view any breach by their introduction on the
land as a de minimis problem that surely would have been worked out before Toll
2
Brothers had to do any development work or construction on the project.
Second, although California law may compel us to conclude there was a
breach by inability to tender clear title, I do not accept the idea that all of the
circumstances detailed by the district court in its findings after trial are wholly
irrelevant to whether the breach was a partial breach or a material breach. There
are California cases, e.g. Fristad v. Thompson, 276 P.2d 116, 118 (Cal. Ct. App.
1954), suggesting that a failure to deliver clear title warrants rescission, but I see
nothing from the California Supreme Court stating that that must invariably be the
conclusion. Instead, I take the position that circumstances such as Toll Brothers
ceasing work on development efforts regarding Sub-Area 3 before the planned
closing date, its failure to cooperate in avoiding problems preventing closing, and
its motivation to avoid proceeding during an economic downturn can properly be
considered in assessing whether the breach was partial or material. I predict that
the California Supreme Court would not view this as a material breach. I am not
prepared to rest, so heavily in substance, see supra note 1, on the notion that the
California Supreme Court would make the transfer of clear title a per se
prerequisite to avoid a material breach.
Third, much the same analysis applies to the utility vault issue. Again, title
was encumbered by the vaults and attendant easements, but I’m disinclined to view
3
that as a material breach. There was clear testimony that the vaults could be
moved at a cost in the range of $300,000-500,000, and so I don’t see why, even if
damages are uncertain, a district court could not make a finding on partial breach
damages and deduct that from the obligations of Toll Brothers. In the total scheme
of the contract, the placement of the utility vaults did not constitute material
breach, and the evidence showed that a partial breach was compensable.
Fourth, while some California authority suggests that motive is irrelevant,
see, e.g., Crim, 103 P. at 180, and I would agree it is irrelevant to determining if
there was a breach or inevitable breach on closing, I think motive can permissibly
be considered in assessing whether that breach was material. Under the
Restatement (Second) of Contracts, the key factors are (1) the extent to which the
injured party will be deprived of the benefit reasonably expected; (2) the extent to
which the injured party can be adequately compensated for deprivation of benefit;
(3) the extent to which the party failing to perform or to offer to perform will suffer
forfeiture; (4) the likelihood that the party failing to perform or to offer to perform
will cure his failure, taking account of all the circumstances including any
reasonable assurances; and (5) the extent to which the behavior of the breaching
party comports with standards of good faith and fair dealing. Restatement
(Second) of Contracts § 241 (1981). Here, those factors in my assessment tend to
4
favor the Lins rather than Toll Brothers. And I see nothing in California law
indicating that this influential Restatement principle of contract law would not be
followed by the California Supreme Court. That the breach by the Lins in
delivering clear title does not seem motivated by any bad faith or errant intentions
to me counsels for viewing the breach as not material in context.
Another factor that might be argued to favor Toll Brothers is whether the
encumbrance deprives it of what it expected to buy; however, given the temporary
nature of the easement, and given that Toll Brothers had suspended development,
there is no practical impact of deprivation. Toll Brothers reasonably could have
expected the temporary easement to have been removed before it was time for it to
start work on construction or antecedent planning. If the temporary easement
caused some delay, in my view it is no insurmountable obstacle for experts to give
testimony and for the district court to make a finding on the damages from the
delay. Conversely, as the majority sees this case, the Lins suffer a major forfeiture
over what seems a hypertechnical breach. Also, it was likely that the Lins could
cure the breach because of the temporary nature of the easement.
The crux of material breach analysis is this: Toll Brothers was not deprived
of any significant part of its bargain as a result of the Lins’ breach, in light of Toll
Brothers’ own plans, a temporary delay on clear title caused it no harm. At the
5
same time, the Lins did not act in bad faith. A determination of partial breach at
most, as made by the district court, is correct.
Finally, there are pragmatic grounds favoring the district court’s approach.
This was a large development contract that placed certain obligations on each
party, and that called for cooperation. I fear that the majority’s approach will only
lead to gamesmanship and less than cooperative behavior between landowner and
developer, between a master developer and a developer of component parts, and
that aggressive jockeying for position without regard to cooperation will ultimately
impose higher prices on consumers who buy homes in the development.
For the above reasons, I would characterize the failings of the Lins as
breaches but not as material breaches. Hence I respectfully dissent.
6