United States Court of Appeals
For the First Circuit
Nos. 06-1658, 06-2054
TOWN OF NORWOOD, MASSACHUSETTS,
Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent.
__________
NEW ENGLAND POWER COMPANY,
Intervenor.
ON PETITIONS FOR REVIEW OF ORDERS OF THE
FEDERAL ENERGY REGULATORY COMMISSION
Before
Boudin, Chief Judge,
Cyr, Senior Circuit Judge,
and Lipez, Circuit Judge.
Robert A. Jablon with whom Elaine C. Lippmann, Spiegel &
McDiarmid, Charles F. Wheatley, Jr., Wheatley & Ranquist, P.A., J.
Owen Todd, Juliet A. Davison, Heidi A. Nadel and Todd & Weld LLP
were on consolidated brief for petitioner.
Michael E. Kaufmann with whom John S. Moot, General Counsel,
and Robert H. Solomon, Solicitor, Federal Energy Regulatory
Commission, were on consolidated brief for respondent.
Kenneth G. Jaffe with whom Alston & Bird LLP, and John F.
Sherman III, Deputy General Counsel, National Grid USA Services
Company, Inc., were on brief for intervenor.
February 2, 2007
BOUDIN, Chief Judge. The Town of Norwood, Massachusetts
("Norwood"), which operates a municipal electric system serving
local businesses and residents, seeks review of an order of the
Federal Energy Regulatory Commission ("FERC"). The order sustained
a contract termination charge contained in a tariff previously
filed by New England Power Company ("NEPCO"). The background
events have been the subject of prior litigation in this court,
principally in Town of Norwood v. FERC ("Norwood I"), 202 F.3d 392
(1st Cir.), cert. denied, 531 U.S. 818 (2000).
For many years, NEPCO was a major power wholesaler in New
England. It operated generating plants and a transmission network,
and sold power wholesale to affiliated distribution companies (such
as Massachusetts Electric Company, which served Massachusetts, and
Narragansett Electric Company, which served Rhode Island) as well
as to non-affiliated distributors like Norwood. Service to Norwood
was provided under a long-term requirements contract of a kind then
common in the utilities industry.
The contract, which began in 1983 and thereafter was
extended by Norwood until October 2008, required NEPCO to supply,
and Norwood to purchase, Norwood's power requirements from NEPCO at
rates provided by NEPCO's Tariff No. 1. The contract could be
terminated by Norwood without penalty but only upon seven years'
prior notice. The present litigation arises out of NEPCO's action
-2-
in providing, and Norwood's decision to exercise, a new option
permitting customers to terminate their contracts early.
Beginning in late 1996, in response to legislative and
regulatory initiatives to promote competition and consumer choice
in the electric power industry, NEPCO made a series of regulatory
filings. Among these were settlements offered by NEPCO to NEPCO's
distributor customers--both affiliates and non-affiliates
(including Norwood)--permitting them to terminate their NEPCO
requirements contracts earlier than otherwise permitted, upon
payment of a contract termination charge.
The aim was to allow distributors flexibility to choose
new suppliers while permitting NEPCO to recover its "stranded
costs"--that is, investments made by NEPCO to meet the projected
long-term requirements of its distributor customers.1 The proposed
settlement terms also provided that NEPCO would offer its
affiliates, but not Norwood, low (but gradually escalating)
"wholesale standard offer" rates for power without the need for a
contract; the affiliates were required to offer corresponding
retail standard offer rates to their retail customers, but Norwood,
as a municipal utility, was not. Mass. Gen. Laws ch. 164, § 47A.
1
See Norwood I, 202 F.3d at 399. See also Order No. 888,
Promoting Wholesale Competition Through Open Access Non-
Discriminatory Transmission Services by Public Utilities; Recovery
of Stranded Costs by Public Utilities and Transmitting Utilities,
61 Fed. Reg. 21,540, 21,628 (1996) (rule codified as revised at 18
C.F.R. pts. 35 & 385).
-3-
Additionally, as part of its restructuring, NEPCO sought
approval from FERC to sell virtually all of its non-nuclear
generating facilities. The buyer, USGen New England, Inc., agreed
to assume responsibility for providing the "wholesale standard
offer" service to NEPCO's affiliates who terminated, and agreed not
to raise rates for NEPCO's remaining distributor customers,
including Norwood. New Eng. Power Co., 82 F.E.R.C. ¶ 61,179, at
61,658-60 (1998) ("New Eng. Power VII"), reh'g denied, 83 F.E.R.C.
¶ 61,275 (1998) ("New Eng. Power VIII").
FERC approved the settlement offers and divestiture over
Norwood's objection.2 NEPCO's three affiliated customers and three
of its unaffiliated municipal customers opted to accept NEPCO's
settlement offer, to terminate early, and to pay the contract
termination charge. Other non-affiliates opted to continue to
purchase their power requirements from NEPCO at Tariff No. 1 rates
through the contractual seven-year notice period for termination.
Norwood was unwilling to take either course of action.
It did not want to continue buying power at Tariff No. 1 rates when
its distributor "competitors" had been offered lower non-contract
2
See New Eng. Power Co., 78 F.E.R.C. ¶ 61,080 (1997) ("New
Eng. Power I"); New Eng. Power Co., 80 F.E.R.C. ¶ 63,003 (1997)
("New Eng. Power II"); New Eng. Power Co., 81 F.E.R.C. ¶ 61,281
(1997) ("New Eng. Power III"), reh'g denied, 83 F.E.R.C. ¶ 61,265
(1998) ("New Eng. Power IV"); New Eng. Power VII, 82 F.E.R.C. at
61,656. See also New Eng. Power, 83 F.E.R.C. ¶ 61,085 (1998) ("New
Eng. Power V"); New Eng. Power Co., 81 F.E.R.C. ¶ 61,334 (1997)
("New Eng. Power VI").
-4-
rates; it viewed such an arrangement as discriminatory. Nor did it
want to pay a contract termination charge for NEPCO's stranded
costs; because it purchased its transmission services from Boston
Edison, not NEPCO, it fell outside the stranded cost obligations
imposed by FERC under Order No. 888.3
Instead, Norwood notified NEPCO on March 4, 1998, that on
April 1 it would unilaterally terminate its contract with NEPCO--
without giving the required seven years' notice--and switch to a
different power supplier. NEPCO then filed a tariff amendment to
its Tariff No. 1 permitting any of its remaining distributor
customers, including Norwood, to terminate their requirements
contracts on thirty days' notice upon the payment of a contract
termination charge ("CTC") whose formula was specified in the
tariff amendment. Norwood I, 202 F.3d at 397.
This CTC was calculated using a formula that would enable
NEPCO to recover the revenues that it would have collected had a
terminating customer continued to pay the tariff rate then in
effect through the end of the contract term. The CTC equaled the
number of years remaining on the contract (L) multiplied by the
difference between the expected annual revenue from the terminating
3
Order No. 888 obligated power companies to transmit ("wheel")
power for customers which had purchased both power and transmission
services from a single company, but who now wished to purchase
power from another provider; and it obligated such customers to
compensate for any resulting stranded costs. Because Norwood had
bought power but not transmission services from NEPCO, it fell
outside the terms of Order No. 888. Norwood I, 202 F.3d at 398-99.
-5-
customer based on the rates in effect at the time of termination
(R)4 and the estimated market value of the released capacity (M);
that is, CTC = L x (R - M). The CTC was capped so as not to exceed
the terminating customer's contribution to NEPCO's fixed power
supply costs; the tariff defined that contribution as L multiplied
by the difference between R and NEPCO's annual average fuel costs
with respect to the customer.
This CTC was in several respects less favorable than the
contract termination charge applied to settling customers: it did
not provide the terminating customer a credit for the recovery of
costs associated with NEPCO's business, for example, through the
profitable divestiture of generating plants; and it did not update
("true-up") the formula values to reflect actual, rather than
projected, market values for released capacity. New Eng. Power
Co., 83 F.E.R.C. ¶ 61,174, at 61,723 nn.5, 13 (1998) ("New Eng.
Power IX"), reh'g denied, 84 F.E.R.C. ¶ 61,175 (1998) ("New Eng.
Power X"); New Eng. Power V, 83 F.E.R.C. at 61,419 n.5.
4
More precisely, R was to equal Total Revenue minus
Transmission Revenue. Total Revenue was to "equal the annual
average of revenues received by [NEPCO] from [the terminating
customer] over three years under the presently effective rates
. . . In the event that the rates paid by the Customer . . . [had]
changed during the three-year period, Total Revenue shall be
determined using the Customer's revenue for the 12 months"
preceding termination. Transmission Revenue referred to the annual
average revenue credited to the customer for transmission services
performed by a third party. The focus of this appeal is on the
Total Revenue component of the R value.
-6-
In proceedings before FERC, Norwood objected to the
tariff amendment on a number of grounds, including claims that it
violated the "stranded cost recovery" provisions of FERC Order No.
888, and that the disparities between the CTC offered to Norwood
and the CTC offered to settling customers constituted an "undue
preference" in violation of the Federal Power Act. 16 U.S.C. §
824d(b) (1994). Norwood also sought an evidentiary hearing on the
reasonableness of the CTC amount (which it estimated at $78
million). Norwood I, 202 F.3d at 401.
FERC rejected Norwood's claims, found the tariff
amendment to be "reasonable," New Eng. Power IX, 83 F.E.R.C. at
61,723, and on rehearing refused to provide an evidentiary hearing
because "no party [had] raised any issue of material fact." New
Eng. Power X, 84 F.E.R.C. at 61,920. FERC noted that Norwood could
file a section 206 complaint5 arguing that the underlying contract
was no longer reasonable and that Norwood should be able to break
it without paying the amounts owed under it. New Eng. Power IX, 83
F.E.R.C. at 61,724.
5
Section 206 of the Federal Power Act, 16 U.S.C. § 824e,
provides a procedure for filing a complaint with the Commission
that a "rate [or] charge . . . charged . . . by any public utility
. . . is unjust, unreasonable, unduly discriminatory or
preferential." If after a hearing the Commission agrees, it "shall
determine the just and reasonable rate [or] charge . . . to be
thereafter observed and in force, and shall fix the same by order."
-7-
Norwood I affirmed FERC's decision, holding inter alia
that Order No. 888 did not by its terms apply to Norwood, 202 F.3d
at 399, and that the disparity between Norwood's CTC and the
contract termination charge of settling customers did not
constitute an "undue preference." Id. at 402. At several points
Norwood's present appeal appears to attempt to relitigate these two
issues, but in these respects it is foreclosed by our prior
adjudication. Springfield Television Corp. v. FCC, 609 F.2d 1014,
1019 (1st Cir. 1979).
We also upheld the CTC formula as designed "to cover
certain projected losses to New England Power caused by not
supplying electricity after preparing to do so, calculated based on
rates already approved by FERC" and said that Norwood had failed to
show any factual dispute requiring an evidentiary hearing. Norwood
I, 202 F.3d at 401. However, we left open the possibility that
Norwood could file a section 206 complaint "challenging the
substance of the contract termination charge." Id.6
Norwood declined to pay the termination charge and, faced
with state court proceedings to recover amounts due under the
contract, Norwood filed a section 206 complaint with FERC in 2002,
alleging (among other things) that NEPCO erroneously calculated the
6
In a companion case, Norwood alleged a breach of contract and
antitrust violation by NEPCO. We affirmed the district court's
dismissal of these claims, except for one antitrust claim that we
remanded. Town of Norwood v. New Eng. Power Co. ("Norwood II"),
202 F.3d 408 (1st Cir.), cert. denied, 531 U.S. 818 (2000).
-8-
CTC and CTC cap by relying on incorrect R and M values. In
particular, Norwood claimed that the R value should have been
reduced to reflect NEPCO's profitable divestiture of its non-
nuclear generating plants, that the M value should have been
"trued-up" to reflect actual, post-termination market values, and
that these omissions were unreasonable under section 206.
The Commission set Norwood's claims for a hearing, saying
that it had "accepted NEPCO's CTC formula, but ha[d] not accepted
the individual components of the CTC calculation." Town of Norwood
v. Nat'l Grid USA, 104 F.E.R.C. ¶ 61,030, at 61,074 (2003) ("Nat'l
Grid I"). Before the ALJ, Norwood also argued belatedly that the
interest rate of 18 percent applied by NEPCO to overdue CTC
payments was contrary to the tariff amendment and, since the rate
was in excess of NEPCO's cost of money, "unjust [and]
unreasonable." 16 U.S.C. § 824e.
The ALJ accepted Norwood's argument that it should get a
reduction in the R value figure to reflect the non-nuclear plant
divestitures7 but rejected its other claims. On review, the
Commission reversed the ALJ as to the credit for plant
divestitures, ruling (1) that the language of the CTC formula did
7
The ALJ held that the CTC formula could be read to suggest
that the preceding twelve months' revenue was simply a "starting
point" in fixing the R value (see note 4, above), and that a
downward adjustment--in the amount of a 28 percent of R--should be
made to "reflect divestiture sales that were known and measurable"
at the time the CTC was calculated. Town of Norwood v. Nat'l Grid
USA, 107 F.E.R.C. ¶ 63,041, at 65,191 (2004) ("Nat'l Grid II").
-9-
not provide for an adjustment for divestiture of assets, and (2)
that the disparity between the CTC formula applied to Norwood and
the contract termination charge offered to settling customers was
not an undue preference because the parties were not similarly
situated.8 The Commission did not directly address Norwood's
argument that the formula was unreasonable in failing to provide a
credit for plant divestitures.
On the interest rate issue, the Commission in its initial
decision rejected the ALJ's ruling in NEPCO's favor, instead siding
with Norwood. Nat'l Grid III, 112 F.E.R.C. at 61,637-38. On
rehearing, it reversed itself and sided with NEPCO.9 FERC also
reaffirmed its holding in favor of NEPCO on the R and M values.
Nat'l Grid IV, 114 F.E.R.C. at 61,633-34. The Commission
thereafter denied Norwood's request for further rehearing on the
interest rate issue. Nat'l Grid V, 115 F.E.R.C. at 62,552. This
appeal followed.
We begin by considering Norwood's arguments concerning
the R and M values. To the extent that Norwood purports to
interpret the language of the CTC tariff amendment as requiring
8
Town of Norwood v. Nat'l Grid USA, 112 F.E.R.C. ¶ 61,099, at
61,629 (2005) ("Nat'l Grid III"), modified on reh'g, 114 F.E.R.C.
¶ 61,187 (2006) ("Nat'l Grid IV"), further reh'g denied, 115
F.E.R.C. ¶ 61,396 (2006) ("Nat'l Grid V").
9
The Commission said that it had misread the tariff in its
initial decision, and that the tariff incorporated an 18 percent
rate on overdue payments. Nat'l Grid IV, 114 F.E.R.C. at 61,636.
-10-
credit for divestiture of assets and true-ups, its arguments are
properly before us but fail on the merits. The CTC provides for
certain kinds of credit adjustments to R, including for
transmission services provided by third parties, but nowhere
mentions credit for divestiture of assets. The CTC was clearly
intended as a formula--not, as the staff urged, merely as "a
starting point." Nat'l Grid II, 107 F.E.R.C. at 65,191.
Norwood says that such a credit was implicitly intended
because the CTC was modeled on the contract termination charge-
formula approved in Order No. 888 and offered to settling
customers, which provided credit for asset divestiture. But when
FERC approved the CTC tariff amendment, it expressly noted that
"[t]he proposed formula . . . differs from that applicable to other
wholesale power customers." New Eng. Power IX, 83 F.E.R.C. at
61,723 nn.5, 13.
Nor does the CTC anywhere indicate that the M values will
be trued-up; quite to the contrary, the letter accompanying the
tariff states that, although NEPCO planned to periodically update
the estimates of market value provided in the tariff, "[a]ny
updated estimates . . . would not affect the contract termination
charges payable by a customer that exercised the early termination
-11-
charge prior to the filing of the update."10 In short, the CTC
tariff language is clear and adverse to Norwood.
However, the main thrust of Norwood's position on appeal
is that the CTC formula, as FERC reads it, is unlawful under the
statute. Norwood argues that, because the formula fails to account
for the divestiture of assets or to incorporate trued-up market
values for power, it is not cost-based--that is, the CTC would give
NEPCO more than it needs to recover any losses incurred by not
supplying power to Norwood after preparing to do so; and that the
CTC is therefore "unjust [and] unreasonable." 16 U.S.C. § 824e.
As we have noted, the Commission did not address these
unreasonableness claims on the merits. Its position is that
Norwood cannot now raise them because the reasonableness of the CTC
formula--as opposed to its application--is res judicata. Although
the Commission would likely prevail on the merits, this would
likely require a remand and further proceedings. We agree that
they need not be reached because Norwood's attacks on the
reasonableness of the formula are foreclosed.
10
Norwood also appears to argue that FERC erred in accepting
NEPCO's market estimates, which, Norwood asserts, were too low.
But we defer to the Commission and ALJ's reasoned explanation as to
why NEPCO's market estimates were just and reasonable: the market
prices in NEPCO's forecast were close to--and indeed slightly
higher than--the prices in Norwood's contract with its new power
supplier, the prices Norwood was offered by another power supplier,
and the prices in Norwood's offer to continue buying power from
NEPCO. Nat'l Grid III, 112 F.E.R.C. at 61,633; Nat'l Grid II, 107
F.E.R.C. at 65,187-91.
-12-
Over seven years ago, the Commission pronounced the CTC
formula to be "reasonable" despite the fact that it failed to
provide for any adjustments for asset divestiture or true-ups. New
Eng. Power IX, 83 F.E.R.C. at 61,723 & nn.5, 13. Norwood sought
review of the FERC decision in Norwood I; but on appeal Norwood
developed only its discrimination claim and a different
unreasonableness argument but not the unreasonableness arguments
concerning R and M that it now makes.
To permit Norwood now to advance new (and previously
available) theories in opposition to an already-litigated tariff
amendment would frustrate the values of repose and efficiency that
res judicata doctrine is meant to protect. Univ. of Tenn. v.
Elliott, 478 U.S. 788, 798 (1986). Res judicata does not merely
prevent re-litigation of issues actually decided but also the
presentation of new grounds that could and should have been raised
when the same transaction was the subject of earlier, different
attacks. Restatement (Second) of Judgments § 24 (1982).
Generally speaking, such res judicata doctrine applies to
agencies when they are acting in an adjudicative capacity to
resolve a controversy between two parties. Aunyx Corp. v. Canon
U.S.A., Inc., 978 F.2d 3, 7 (1st Cir. 1992), cert. denied, 507 U.S.
973 (1993). Here and in the prior proceeding in which Norwood
sought rejection of the CTC tariff, the parties are the same and,
so far as Norwood contests the validity of the CTC formula, the
-13-
subject matter is the same. The first proceeding resolved the
reasonableness issue in what was effectively a final judgment;
attacks not properly developed there cannot now be resurrected.11
Norwood says that when we sustained FERC in Norwood I, we
expressly left open to Norwood a section 206 challenge to "the
substance of the contract termination charge," adding that "[i]f
these charges were miscomputed or unsupported, Norwood might well
have a legitimate objection." 202 F.3d at 401. When setting for
hearing the claim currently on appeal, FERC agreed that it had "not
[yet] approved the individual components used in NEPCO's
calculation" of the CTC. Nat'l Grid I, 104 F.E.R.C. at 61,074.
But what was left open by these statements was the proper
computation of the R and M values according to the formula--not new
attacks on the formula itself. Norwood, quoting the FERC staff,
says that the prior reservation could not have meant only to
"giv[e] Norwood a chance to challenge NEPCO's arithmetic." But
whether the figures proffered by NEPCO complied with the formula
mattered a good deal and Norwood itself did urge that NEPCO had
employed unreasonable estimates of the market value of the released
11
For these reasons, we also reject Norwood's arguments
concerning the CTC cap. Norwood claims that it cannot be required
to "contribut[e] to . . . fixed power supply costs" for facilities
that NEPCO has since profitably divested. But the CTC cap, like
the CTC generally, is a formula incorporating values determined at
the time of termination: it is equal to R minus NEPCO's average
fuel costs with respect to Norwood. Norwood does not contest on
appeal the calculation of NEPCO's average fuel costs; it does
contest R, but this challenge is dealt with above.
-14-
load and had miscalculated its fixed power supply costs in
determining the CTC cap.
Norwood says that rate orders are not subject to the
rules of res judicata: a rate that was once reasonable may, in
light of changed circumstances, become unreasonable. Tesoro Alaska
Petroleum Co. v. FERC, 234 F.3d 1286, 1290 (D.C. Cir. 2000). But
the CTC is not a rate; it is "a formula-driven charge . . .
calculated based on rates already approved by FERC," Norwood I, 202
F.3d at 401, payment of which permitted Norwood to opt out of a
contract before it had run its course. The charge became a fixed
and final contractual obligation at the time of termination.
Norwood counters that the CTC, if not itself a rate,
incorporated rates that should be open to challenge as unreasonably
high. But there is nothing in the statute or case law cited by
Norwood that prevents the construction of termination charge based
on rates in effect as of a certain date. Creating a fixed and
knowable obligation had advantages and disadvantages for Norwood in
choosing whether to terminate; but the terms of the CTC were clear
when it made its decision.
In effect, NEPCO bore the risk of higher costs and lower
market prices than the CTC incorporated, and Norwood bore the risk
of lower costs and higher market prices. Norwood was free to
argue, in its original CTC challenge, that the tariff rates to be
incorporated by the CTC were unreasonably high in light of what was
-15-
known then about NEPCO's costs; but Norwood chose not to do so.
Norwood was also free to terminate and contest the CTC terms as
unlawful--which it did, albeit unsuccessfully. What it could not
do was to defer some of the available attacks on the CTC formula
and now raise them in court for the first time eight years later.
Indeed, if we were to permit this kind of hide and seek
litigation tactic, nothing would prevent Norwood from filing
tomorrow a new section 206 attack to present new arguments as to
why the original CTC formula was unlawful. Norwood has managed to
defer making the full installment payments for years. It is now
faced with large past-due obligations; but the obligations are ones
easily foreseen, have been enlarged by delays in payment and are
the product of Norwood's own choices.
Norwood would not likely have prevailed even if the
merits were open. The reasonableness of NEPCO's approach in
excluding true-ups and future plant divestitures is a regulatory
issue within the province of FERC and reviewed by a court only for
arbitrariness. Cent. Maine Power Co. v. FERC, 252 F.3d 34, 40 n.3
(1st Cir. 2001). There is nothing obviously unreasonable about
framing a charge for contract termination that approximates, as of
the time of termination, projected revenues promised by the buyer
less projected avoided loss for the seller.
This brings us to the important issue of the interest
rate. In December 1998, after FERC's 1998 order approving the CTC,
-16-
NEPCO brought a breach of contract action against Norwood in
Massachusetts state court, seeking to collect then-overdue CTC
payments and late payment charges. In March 2001, the
Massachusetts trial court granted NEPCO's summary judgment motion
and awarded it $27,149,054.08, equal to the CTC and late payment
charges due through January 31, 2001.12
In October 2003, the Appeals Court affirmed, noting
specifically that "[w]e have . . . considered Norwood's arguments
with respect to . . . the inclusion of an improper interest rate in
the calculation and conclude that they lack merit." New Eng.
Power, 797 N.E.2d 26, at *2. But it thereafter remanded,
directing the trial court to conform to the FERC order that is the
subject of this appeal, "or to any further modifications of that
order by FERC." New Eng. Power, 847 N.E.2d 366, at *2. So the
matter turns on FERC's ultimate determination.
We turn, therefore, to Norwood's claims regarding the
interest rate for late payment of the CTC installments, which are
two: one is that FERC misconstrued the tariff and that it is
entitled under the tariff to pay a lower interest rate than the 18
percent ordered by FERC; the other is that the 18 percent rate is
12
New Eng. Power Co. v. Town of Norwood, No. 982650A, 2001 WL
543172 (Mass. Super. Ct. Mar. 14, 2001), aff'd, 797 N.E.2d 26, at
*2 (Mass. App. Ct. 2003) (unpublished), review denied, 440 Mass.
1108 (2003), cert. denied, 541 U.S. 1073 (2004), amended, 847
N.E.2d 366 (Mass. App. Ct. 2006) (unpublished).
-17-
unlawful or at least inconsistent with prior Commission precedent.
We treat the two issues in that order.
NEPCO has in its successive unpaid bills to Norwood
applied an 18 percent interest rate to Norwood's overdue CTC
payments, citing Section J of Tariff No. 1's schedule of general
terms and conditions:
When all or part of any bill shall remain unpaid for
more than thirty (30) days after the rendering thereof
by the Company, interest at the rate of 1½% per month
shall accrue to the Company from and after the
rendering of said bill . . . .
Norwood first argues that the Section J rate is
inapplicable to late CTC payments. Instead, it claims that section
N applies; Section N was added to the tariff as part of the
amendment permitting early termination of contracts under the
formula we have been discussing. It states:
The Contract Termination Charge shall be payable in
equal monthly installments of principal and interest
. . . The Customer's payments shall include carrying
charges on the unpaid amount of the Contract
Termination Charge at the interest rate determined
pursuant to section 35.19a of the Commission's
regulations (18 C.F.R. 35.19a) effective on the Early
Termination Date and compounded monthly.
Although the termination charge was to be calculated at
the time of termination, section N permitted its payment in
installments over the remaining life of the contract and imposed,
as "the carrying charge" (that is, interest) on the deferred
-18-
payments, an interest rate specified in FERC regulations.13 18
C.F.R. § 35.19a. The cited regulations provided that, for refunds
by carriers to customers where new rates had gone into effect but
were later disallowed, the Federal Reserve prime interest rate
applied.
The prime rate varies over time, but it has in recent
years been considerably less than 18 percent. Norwood claimed in
the Commission proceeding that the prime rate (varying over time),
rather than the 18 percent rate, should be applied to its unpaid
CTC bills. The Commission, after initially agreeing, ultimately
held that the prime rate regulation did not apply and that the 18
percent rate in section J did. See note 9, above.
We think the question is close. The phrase "unpaid
amount" in Section N could be read to include both unbilled CTC
amounts and amounts billed but as yet unpaid (e.g., overdue
payments). But the Commission is entitled to deference in
interpreting tariffs filed with it, Koch Gateway Pipeline Co. v.
FERC, 136 F.3d 810, 814 (D.C. Cir. 1998); the CTC is part of the
tariff; and FERC's construction is reasonable, even though not
inevitable, as we now explain.
13
NEPCO further explains that the monthly installments are
calculated by (a) calculating the present discounted value of the
total CTC amount using the section 35.19a rate and then (b)
converting that lump sum into monthly installment payments that
incorporate a carrying charge equal to the section 35.19a rate.
-19-
Section N can easily be read to apply the prime rate only
in calculating the installment amount due each month from the buyer
who terminated, remaining silent as to the interest rate charged to
overdue monthly installment payments. The fact that the carrying
cost language is juxtaposed with the option to pay in installments
supports this reading. And, if Section J is read as a catchall
provision directed to all late payments, there would be no reason
to address that subject in section N.
By contrast, Section J--which imposes an 18 percent
interest rate on late payments--applies to "any bill"; and
Norwood's monthly installment obligation is the subject of a
"bill." Norwood argues that Section J applies only to bills for
electricity sales, pointing to the fact that Section J defines a
"month" as "the period between two meter readings . . . ." But the
fact that the provision applies to metered sales does not exclude
its application to other bills as well.
Norwood suggests that it is inconsistent to use two
different interest rates, but interest rates reflect policy choices
and the overdue payment context is not the same as the installment
payment context. In particular, the prime rate can be viewed as a
surrogate for the carrier's cost of money (although only very
approximately); an 18 percent rate on overdue bills is, in recent
years, considerably more than the carrier's cost of money and
-20-
justifiable primarily to offset collection costs and encourage
prompt payment.
This takes us directly to Norwood's alternative argument,
namely, that if the tariff does impose an 18 percent rate on
overdue CTC payments, it is unreasonable because such a rate is in
excess of NEPCO's cost of money. Taken in the abstract, this would
be unpersuasive: deterring delayed payments is a legitimate
purpose, quite apart from collection costs, and nothing in the
statute prevents the Commission from treating a penalty as
reasonable. If the Commission had said this and had no
inconsistent precedent, that would be the end of the matter.
But Norwood's case is somewhat stronger because in
Connecticut Light & Power Co., 59 F.P.C. 811 (1977), FERC itself
rejected a proposed 18 percent annual charge on late payments as
"not supported by cost data." Id. at 821. The decision said that
a late payment penalty might be warranted in cases of chronic
delinquency, but in general "we do not believe as a matter of
policy that this Commission should assume the functions of a bill
collection enforcement agency except in otherwise hopeless
situations." Id. See also Pub. Serv. Co. of N.M. v. FERC, 832
F.2d 1201 (10th Cir. 1987).
In its order, the Commission distinguished Connecticut
Light & Power on the ground that it involved a proposed penalty
interest rate, so that the power company bore the burden of showing
-21-
it to be reasonable; here, by contrast, the 18 percent rate had
been part of the tariff since the mid-1970s, so Norwood bore the
burden of showing it to be unreasonable. And, says the Commission,
Norwood never offered cost evidence or other facts to show that the
provision was unreasonable. Nat'l Grid V, 115 F.E.R.C. at 62,551-
52.
We do not find this a persuasive explanation. NEPCO does
not seriously suggest that 18 percent represents its cost of money.
So the real question is whether the Commission has altered its
Connecticut Light & Power policy--which it could do with an
explanation, Atchison, Topeka & Sante Fe R.R. v. Witchita Bd. of
Trade, 412 U.S. 800, 808 (1973)--or thinks that there is something
about Norwood's situation that justifies such a penalty even though
prior precedent would not allow it for an ordinary overdue bill,
absent special circumstances.
Frankly, the Commission--with some reason--appears merely
to have run out of patience with Norwood's attempts to re-litigate
issues that it earlier lost or forfeit. In fact, even the interest
rate issue was raised belatedly; but the state court judgment no
longer poses a res judicata objection and the Commission itself
chose to address the objection on the merits. Having chosen to
decide the issue, the Commission must face it squarely and
adequately resolve it.
-22-
On remand the Commission is not limited to a single
choice. Conceivably it could sustain the 18 percent figure against
attack and modify its Connecticut Light and Power policy (or
adequately distinguish it). Or it might find the 18 percent figure
unreasonable and find the prime rate or some other rate above the
prime rate to be appropriate. We do agree that this remains a
section 206 proceeding in which Norwood is attacking a longstanding
tariff provision and bears the ultimate burden of proof.
We address one other loose end as to interest. Norwood
has also argued that even if the 18 percent rate is applicable to
CTC late payments, the rate should not be applied to payments due
prior to FERC's order of February 22, 2006, since before that point
the CTC amount had not been determined. It is true that the CTC
amount had been in dispute and in that sense had not yet been
finally determined by the Commission.
But section J makes it quite clear that, when a customer
disputes an amount billed by a carrier, the carrier is entitled to
prescribed interest that accrues "from . . . the rendering of said
bill" on "the amount finally determined to be due and payable."
Norwood has challenged the amount of interest prescribed; but
whatever the figure FERC finds justified, the tariff provides that
Norwood owes that amount from the time the bill was rendered.
We affirm the Commission's order insofar as it determines
the amount of principal due; as to the interest, we also affirm the
-23-
order insofar as it requires interest payments based on at least
the prime rate--the figure Norwood itself seeks--and remand only as
to whether more is properly due. Our stay order of August 21,
2006, will terminate when the mandate issues. Each party will bear
its own costs in this court.
Affirmed in part and remanded in part.
-24-