FOR PUBLICATION
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
STATE OF OREGON, by and through
its Department of Environmental
Quality, Department of Land
Conservation and Development,
and Department of Energy, No. 09-70269
Petitioner, FERC Nos.
v. CP06-365-002
CP06-366-002
FEDERAL ENERGY REGULATORY
CP06-376-002
COMMISSION,
CP06-377-002
Respondent,
NORTHERNSTAR ENERGY LLC;
BRADWOOD LANDING LLC,
Intervenors.
3035
3036 STATE OF OREGON v. FERC
COLUMBIA RIVERKEEPER; SIERRA
CLUB; LANDOWNERS AND
CITIZENS FOR A SAFE COMMUNITY;
WAHKIAKUM FRIENDS OF THE RIVER;
WILLAPA HILLS AUDUBON SOCIETY;
GAYLE KISER,
No. 09-70442
Petitioners,
FERC Nos.
NEZ PERCE TRIBE,
Intervenor, CP06-365-002
CP06-366-002
v. CP06-376-002
FEDERAL ENERGY REGULATORY CP06-377-002
COMMISSION,
Respondent,
NORTHERNSTAR ENERGY LLC;
BRADWOOD LANDING LLC,
Intervenors.
THE STATE OF WASHINGTON, No. 09-70477
DEPARTMENT OF ECOLOGY, FERC Nos.
Petitioner, CP06-365-000
v. CP06-366-000
CP06-376-000
FEDERAL ENERGY REGULATORY
COMMISSION, CP06-377-000
Respondent, CP06-365-002
CP06-366-002
NORTHERNSTAR ENERGY LLC; CP06-376-002
BRADWOOD LANDING LLC, CP06-377-002
Intervenors.
OPINION
On Petition for Review of an Order of the
Federal Energy Regulatory Commission
STATE OF OREGON v. FERC 3037
Argued and Submitted
February 10, 2011—Seattle, Washington
Filed March 2, 2011
Before: Betty B. Fletcher, Richard A. Paez, and
Sandra S. Ikuta, Circuit Judges.
Per Curiam Opinion
3038 STATE OF OREGON v. FERC
COUNSEL
Stephanie M. Parent (argued) and Eric C. Lagesen, Oregon
Department of Justice, Portland, Oregon, for petitioner State
of Oregon.
Joan M. Marchioro, Office of the Washington Attorney Gen-
eral, Olympia, Washington, for petitioner State of Washing-
ton.
Tom Buchele, Pacific Environmental Advocacy Center, Port-
land, Oregon, for petitioner Columbia Riverkeeper et al.
STATE OF OREGON v. FERC 3039
Michael Lopez, Nez Perce Tribe Office of Legal Counsel,
Lapwai, Idaho, and Erin Madden, Cascadia Law PC, Portland,
Oregon, for intervenor Nez Perce Tribe.
Kristen M. Fletcher, Washington, DC, for amicus curiae
Coastal States Organization.
Jackson D. Logan, III, Louisiana Department of Justice,
Baton Rouge, Louisiana, for amici curiae State of Louisiana
et al.
Robert M. Kennedy, Jr. (argued), Federal Energy Regulatory
Commission, Washington, DC, for respondent Federal Energy
Regulatory Commission.
OPINION
PER CURIAM:
The states of Oregon and Washington, Columbia
Riverkeeper et al., and the Nez Perce Tribe (collectively, peti-
tioners) seek review of a September 18, 2008 order of the
Federal Energy Regulatory Commission (FERC). For the rea-
sons stated below, we dismiss the petition for review as moot
and vacate the agency’s September 18, 2008 order.
I
FERC’s September 18, 2008 order incorporated two differ-
ent authorizations, each with conditions. First, pursuant to
Section 3 of the Natural Gas Act (NGA), 15 U.S.C. § 717b(a),
FERC authorized Bradwood Landing LLC (Bradwood) to
site, construct, and operate a liquefied natural gas (LNG)
import terminal in Clatsop County, Oregon. Second, pursuant
to Section 7 of the NGA, id. § 717f(c)(1)(A), FERC issued a
Certificate of Public Convenience and Necessity (CPCN)
3040 STATE OF OREGON v. FERC
authorizing NorthernStar Energy LLC (NorthernStar) to con-
struct and operate a natural gas pipeline that would connect
the new Bradwood LNG terminal to the Pacific Northwest’s
existing natural gas pipeline network.1 The pipeline would
traverse Clatsop and Columbia Counties, Oregon, and Cow-
litz County, Washington. The FERC order also gave North-
ernStar blanket certificates to perform certain routine
construction activities and operations, and to provide trans-
portation services on an open access basis. After FERC twice
denied rehearing, the petitioners seek judicial review in this
court under the Administrative Procedure Act. See 5 U.S.C.
§§ 702, 704.
The parties have informed us that the following events
occurred after the petition for review was filed. First, on May
4, 2010, Bradwood and NorthernStar filed petitions in bank-
ruptcy for Chapter 7 liquidation. See In re NorthernStar Natu-
ral Gas, Inc., No. 10-33856 (Bankr. S.D. Tex.); In re
Bradwood Landing LLC, No. 10-33867 (Bankr. S.D. Tex.).
Second, in a letter dated August 18, 2010, Washington denied
without prejudice the proponents’ request for certification
under the Clean Water Act, (CWA) 33 U.S.C. § 1341(a)(1),2
1
We refer to the terminal and pipeline collectively as “the project,” and
to Bradwood and NorthernStar collectively as the “project proponents.”
2
The relevant portion of the CWA states:
Any applicant for a Federal license or permit to conduct any
activity including, but not limited to, the construction or opera-
tion of facilities, which may result in any discharge into the navi-
gable waters, shall provide the licensing or permitting agency a
certification from the State in which the discharge originates or
will originate . . . that any such discharge will comply with the
applicable provisions of sections 1311, 1312, 1313, 1316, and
1317 of this title. . . . No license or permit shall be granted until
the certification required by this section has been obtained or has
been waived as provided in the preceding sentence. No license or
permit shall be granted if certification has been denied by the
State . . . .
33 U.S.C. § 1341(a)(1).
STATE OF OREGON v. FERC 3041
on account of the proponents’ failure to submit information
requested by the state. Third, in a letter dated September 14,
2010, Oregon objected to the project proponents’ federal con-
sistency determination under the Coastal Zone Management
Act (CZMA), 16 U.S.C. § 1456(c)(3)(A).3 Oregon made this
objection because the project proponents had failed to provide
required information, a component of the project was incon-
sistent with the state’s enforceable land use policies, and the
project proponents had failed to obtain necessary state and
local authorizations. Finally, on November 5, 2010, BL Credit
Holdings, LLC purchased all permits and intellectual property
owned by Bradwood at a foreclosure auction.4
II
[1] A case is moot when it has “lost its character as a pres-
ent, live controversy of the kind that must exist if we are to
avoid advisory opinions on abstract propositions of law.” Hall
v. Beals, 396 U.S. 45, 48 (1969) (per curiam). We “are with-
out power to decide questions that cannot affect the rights of
litigants in the case before [us].’ ” DeFunis v. Odegaard, 416
U.S. 312, 316 (1974) (per curiam) (quoting North Carolina v.
Rice, 404 U.S. 244, 246 (1971)). This is such a case.
[2] While FERC may authorize a permittee to transfer a
Section 3 permit to a new project proponent, 18 C.F.R.
§ 153.9(a), the CPCN “is not transferable in any manner,” id.
§ 157.20(e). Once NorthernStar is liquidated in the bank-
ruptcy proceeding, it will no longer exist, and thus will not be
able to renew its efforts to obtain Washington’s certification
3
The statute provides, in pertinent part: “No license or permit shall be
granted by the Federal agency until the state or its designated agency has
concurred with the applicant’s certification [that the permit complies with
the state’s coastal management program] or until, by the state’s failure to
act, the concurrence is conclusively presumed . . . .” 16 U.S.C.
§ 1456(c)(3)(A).
4
The parties’ submissions make no mention of NorthernStar’s assets.
3042 STATE OF OREGON v. FERC
under the CWA or Oregon’s concurrence in the proponents’
federal consistency determination under the CZMA, or pro-
ceed with the pipeline project in any other manner. Nor can
it transfer the CPCN to a third party. While Bradwood’s Sec-
tion 3 permit is theoretically transferable, the petitioners con-
cede that the terminal and the pipeline essentially constitute
a single project that will go forward together, or not at all,
even though the terminal and the pipeline are formally subject
to two different permits. Given that the project proponents
have filed Chapter 7 petitions, and failed to demonstrate com-
pliance with Washington state water quality standards or con-
sistency with Oregon’s land use policies and project
authorization requirements, the future of the project as cur-
rently permitted is in grave doubt.
[3] Under these circumstances, the possibility that the proj-
ect authorized by FERC’s September 18, 2008 order could be
revived to threaten the interests of the petitioners is “too
remote and too speculative a consideration to save this case
from mootness.” Ctr. for Biological Diversity v. Lohn, 511
F.3d 960, 964 (9th Cir. 2007) (citing Headwaters, Inc. v.
Bureau of Land Mgmt., 893 F.2d 1012, 1015 (9th Cir. 1989)).
Consequently, we hold that the petitioners’ challenge to the
FERC order is moot.
III
In cases where intervening events moot a petition for
review of an agency order, the proper course is to vacate the
underlying order. A.L. Mechling Barge Lines, Inc. v. United
States, 368 U.S. 324, 330-31 (1961); see 15 U.S.C. § 717r(b).
Accordingly, we dismiss the petition as moot and vacate
FERC’s September 18, 2008 order.
PETITION DISMISSED; ORDER VACATED.