United States Court of Appeals for the Federal Circuit
06-1080
LEAR SIEGLER SERVICES, INC.,
Appellant,
v.
Donald H. Rumsfeld, SECRETARY OF DEFENSE,
Appellee.
Daniel B. Abrhams, Epstein Becker & Green, P.C, of Washington, DC, argued for
appellant. With him on the brief was Shlomo D. Katz.
Marla T. Conneely, Attorney, Commercial Litigation Branch, Civil Division, United
States Department of Justice, of Washington, DC, argued for appellee. With her on the
brief were Peter D. Keisler, Assistant Attorney General; David M. Cohen, Director; and
James M. Kinsella, Deputy Director. Of counsel on the brief was John T. Lauro,
Department of the Air Force, Air Force Legal Services Agency, of Arlington, Virginia.
Terry R. Yellig, Sherman, Dunn, Cohen, Leifer & Yellig, P.C., of Washington, DC,
for amicus curiae International Association of Machinists and Aerospace Workers, AFL-
CIO.
Mark D. Colley, Holland & Knight LLP, of Washington, DC, for amicus curiae
Professional Services Council. With him on the brief were David P. Metzger, Kara L.
Daniels, and Eric L. Yeo.
Appealed from: United States Armed Services Board of Contract Appeals
United States Court of Appeals for the Federal Circuit
06-1080
LEAR SIEGLER SERVICES, INC.,
Appellant,
v.
Donald H. Rumsfeld, SECRETARY OF DEFENSE,
Appellee.
________________________
DECIDED: July 28, 2006
________________________
Before, NEWMAN, GAJARSA, and LINN, Circuit Judges.
GAJARSA, Circuit Judge.
Lear Siegler Services, Inc. (“LSI” or “the contractor”) appeals from the decision of
the Armed Services Board of Contract Appeals (“Board”), granting summary judgment
to the government and denying summary judgment to LSI. Lear Siegler Servs., Inc.,
2005 ASBCA LEXIS 31, 2005-1 B.C.A. (CCH) P32,937, ASBCA No. 54449, aff’d on
reconsideration, 2005 ASBCA LEXIS 90, 2005-2 B.C.A. (CCH) P33,110. LSI had
claimed that the Price Adjustment Clause (part of the regulatory scheme of the Service
Contract Act of 1965) required the government to compensate LSI for increases in the
cost of providing its employees with a defined-benefit health plan, as required by the
terms of a collective bargaining agreement (“CBA”). See Service Contract Act of 1965,
ch. 286, Pub. L. No. 89-286, 79 Stat. 1034 (codified as amended at 41 U.S.C. § 351-
358); 48 C.F.R. § 52.222-43 (“Price Adjustment Clause”). LSI timely appealed.
The Board had jurisdiction pursuant to the Contract Disputes Act, 41 U.S.C.
§ 607(d)(2), and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10) and 41 U.S.C.
§ 607(g)(1)(A). For the reasons discussed below, we hold that the Board erred in
granting summary judgment in favor of the government, and it abused its discretion in
denying summary judgment to LSI. Accordingly, we reverse.
I. BACKGROUND
The Air Force awarded a firm, fixed price contract to LSI, under which LSI was to
provide aircraft maintenance services at Sheppard Air Force Base, Texas. The base
year of the contract ran from October 2001 to October 2002, with multiple renewal
options thereafter. LSI’s predecessor contractor was Lockheed Martin.
LSI’s contract incorporated the terms of the Service Contract Act (“SCA”), which
serves generally to protect the wages and fringe benefits of service workers. The
contract included both a SCA wage/benefit determination, which incorporated the
wages and fringe benefits set forth in the CBA between the Air Force and Lockheed’s
predecessor, and a Price Adjustment Clause, which required the government to pay LSI
for “increase[s] . . . in applicable . . . fringe benefits . . . made to comply with . . . [the]
wage determination . . . .” 48 C.F.R. § 52.222-43.
LSI’s CBA specifically required it to provide its employees with a defined-benefit
health plan. As distinct from a defined-contribution plan, a defined-benefit plan
obligates an employer to spend whatever is necessary to continue to provide its
employees with an agreed-upon level of benefit. A defined-benefit plan thereby ensures
06-1080 2
that employees will continue to receive the same level of benefit (here health coverage),
even as costs rise. Although the future costs of providing benefits under a defined-
benefit plan are not known with certainty at the time of contracting, such costs may
reasonably be projected on the basis of actuarial determinations.
In February, 2003, LSI submitted a request for a price adjustment under the SCA
Price Adjustment Clause for Option Year 2003, seeking reimbursement for the
increased costs of providing its employees with the defined-benefit health plan. The Air
Force denied the request, and LSI appealed to the Board. The Board distinguished
between increases in an employer’s costs of providing benefits, which it deemed
insufficient to trigger the Price Adjustment Clause, and increases in the benefits
themselves. See 48 C.F.R. § 52.222-43(d) (requiring “increase[s] . . . in applicable . . .
fringe benefits . . . ”).
Observing that there had been no “change in the CBA . . . [or the] scope of
benefits to be provided,” it concluded that the CBA-based wage determination did not
require LSI to incur the increased cost of maintaining the defined level of health benefit,
and that the Price Adjustment Clause was therefore inapplicable. Accordingly, the
Board granted summary judgment in favor of the Air Force and denied LSI’s request for
the same. The Board also rejected LSI’s course-of-dealing argument, holding that a
course of dealing cannot alter the meaning of an unambiguous contract term. LSI
timely appealed to this court, and we have jurisdiction pursuant to 28 U.S.C.
§ 1295(a)(10) and 41 U.S.C. § 607(g)(1)(A).
06-1080 3
II. DISCUSSION
The principal issue on appeal is whether the Board erred in its construction of the
Price Adjustment Clause. For the reasons discussed below, we conclude that it did
commit legal error in its determination, and we reverse the judgment of the Board
without needing to reach the merits of LSI’s other arguments.
A. Standard of Review
This case requires us to review the Board’s construction of the Price Adjustment
Clause. Our standard of review is governed by the Contracts Disputes Act, which
provides that “the decision of the agency board on any question of law shall not be final
or conclusive . . . .” 41 U.S.C. § 609(b). Statutory and regulatory constructions are
questions of law, which we review de novo. The interpretation of a government contract
is also question of law, which we review de novo on appeal. Forman v. United States,
329 F.3d 837, 841 (Fed. Cir. 2003). Nonetheless, we give the Board’s legal conclusions
“careful consideration due to the board’s considerable experience in construing
government contracts.” Wickham Contracting Co. v. Fischer, 12 F.3d 1574, 1577 (Fed.
Cir. 1994). See also Titan Corp. v. West, 129 F.3d 1479, 1481 (Fed. Cir. 1997) (“The
Board’s interpretation of a contract is not final, and is subject to de novo review on
appeal, although due respect is often warranted by the Board’s experience in
interpreting the Federal Acquisition Regulations (FAR).”); Erickson Air Crane Co. v.
United States, 731 F.2d 810, 814 (Fed. Cir. 1984) (“[L]egal interpretations by tribunals
having expertise are helpful to us, even if not compelling.”).
Summary judgment is properly granted only when there is no genuine issue of
material fact. Fed. R. Civ. P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-
06-1080 4
48 (1986). While we review de novo a district court’s grant of summary judgment, we
review its denial of summary judgment for abuse of discretion. Pickholtz v. Rainbow
Techs., 284 F.3d 1365, 1371 (Fed. Cir. 2002).
B. Service Contract Act
The SCA requires most government service contracts to contain clauses that
protect workers’ wages and fringe benefits. See 41 U.S.C. § 351(a). More specifically,
the SCA directs the Secretary of Labor (“Secretary”) to issue special minimum wage
orders, called “wage determinations,” for each class of service worker employed in a
particular locality, and it forbids contractors (that is, employers) from paying less than
the Secretary’s wage determinations. See 41 U.S.C. § 351(a)(1). A similar SCA
provision applies to fringe benefits. See 41 U.S.C. § 351(a)(2).
In this manner, the SCA prevents contractors from underbidding each other (and
hence being awarded government contracts) by cutting wages or fringe benefits to its
service workers:
Since labor costs are the predominant factor in most service contracts, the
odds on making a successful low bid for a contract are heavily stacked in
favor of the contractor paying the lowest wages. Contractors who wish to
maintain an enlightened wage policy may find it almost impossible to
compete for Government service contracts with those who pay wages to
their employees at or below the subsistence level. When a Government
contract is awarded to a service contractor with low wage standards, the
Government is in effect subsidizing subminimum wages.
Fort Hood Barbers Ass’n v. Herman, 137 F.3d 302, 309 (5th Cir. 1998) (citing H.R. Rep.
No. 89-948, at 2-3 (1965); S. Rep. No. 89-798, at 3-4 (1965), reprinted in 1965
U.S.C.C.A.N. 3737, 3739).
Although the SCA, as originally enacted, worked well to prevent the depression
of wages/benefits (by using wage determinations to set a wage/benefit “floor”), it did not
06-1080 5
provide a mechanism to prevent the erosion of wage/benefit gains made through
collective bargaining, wherein labor groups had succeeded in negotiating
wages/benefits that were higher than the Secretary’s general wage determination. As
the Fifth Circuit aptly noted:
[T]he nature of government contracting, calling for frequent rebidding,
combined with the SCA's sole emphasis and reliance on the prevailing
wage rate scheme, effectively diminished the bargaining power of
unionized workforces. A contractor without a CBA covering its employees,
or with a CBA setting comparatively low wage and benefit rates, was able
to easily outbid an incumbent contractor bound by a CBA with higher
wages and rates that would survive the commencement date of the new
contract.
Id.
Consequently, the SCA was amended to insert the so-called “successor
contractor rule,” which prohibits a successor contractor from paying its employees less
than its predecessor had paid its employees pursuant to the predecessor’s CBA:
No contractor or subcontractor under a contract, which succeeds a
contract subject to this Act and under which substantially the same
services are furnished, shall pay any service employee under such
contract less than the wages and fringe benefits, including accrued wages
and fringe benefits, and any prospective increases in wages and fringe
benefits provided for in a collective-bargaining agreement as a result of
arm’s-length negotiations, to which such service employees would have
been entitled if they were employed under the predecessor contract . . . .
41 U.S.C. § 353(c); see also Gracey v. Int’l Bhd. of Elec. Workers, 868 F.2d 671, 675
(4th Cir. 1989) (“[T]he purpose of that section was to remedy the practice of
underbidding for government contracts by slashing wages.”); see also 29 C.F.R.
§ 4.163(k) (“No provision of this section shall be construed as permitting a successor
contractor to pay its employees less than the wages and fringe benefits to which such
06-1080 6
employees would have been entitled under the predecessor contractor’s collective
bargaining agreement.”).
The successor contractor rule is a direct statutory obligation that is self-
executing. See Guardian Moving & Storage Co. v. Hayden, 421 F.3d 1268, 1270 (Fed.
Cir. 2005) (“[The successor-contractor rule] is a direct statutory obligation and
requirement placed on the successor contractor . . . and is not contingent or dependent
upon the issuance or incorporation in the contract of a wage determination based on the
predecessor contractor’s collective bargaining agreement.” (citing 29 C.F.R.
§ 4.163(b))).
Here, LSI is subject to the successor contractor rule because it succeeded
Lockheed on the contract and was thus a successor in its base year of the contract. In
addition, LSI was also a “successor contractor” during its first option year (the second
year it was providing services), because LSI succeeded itself. See 29 C.F.R. § 4.163(e)
(stating that a contractor can also become a successor to itself, such as when it, like
LSI, performs an additional term pursuant to an option exercised by the government).
C. Price Adjustment Clause
LSI’s contract with the government incorporated by reference the provisions of 48
C.F.R. § 52.222-43, including the so-called “Price Adjustment Clause.”
(a) This clause applies to both contracts subject to area prevailing wage
determinations and contracts subject to collective bargaining agreements.
***
(d) The contract price or contract unit price labor rates will be adjusted to
reflect the Contractor’s actual increase or decrease in applicable wages
and fringe benefits to the extent that the increase is made to comply with
or the decrease is voluntarily made by the Contractor as a result of:
06-1080 7
(1) The Department of Labor wage determination applicable on the
anniversary date of the multiple year contract, or at the beginning of
the renewal option period.
48 C.F.R. § 52.222-43 (emphases added).
Regulations make clear that the term “wage determination” includes a CBA-
defined benefit level. See 29 C.F.R. § 4.50 (explaining that there are two types of wage
and fringe benefit determinations, namely those that are based on prevailing wage data
generally and those based on the level of benefits required pursuant to a CBA that a
successor contractor is required to maintain); see also 48 C.F.R. § 52.222-43(a) (“This
clause applies to both contracts subject to area prevailing wage determinations and
contracts subject to collective bargaining agreements.”). In addition, the parties
stipulated that the CBA of LSI’s predecessor listed fringe benefits that included the
defined-benefit health insurance at issue in this case.
D. Analysis
Here we must determine whether a “wage determination” (i.e., the CBA) required
an “actual increase . . . in . . . fringe benefits . . . .” 48 C.F.R. § 52.222-43. We
conclude that it did, thereby triggering the government’s obligations under the Price
Adjustment Clause. For several reasons, we find no merit in the argument that the
Price Adjustment Clause is triggered only by enlarged benefits rather than enlarged
costs of providing those benefits.
First, the language of the clause itself is instructive. See 48 C.F.R. § 52.222-
43(d) (“The contract price or contract unit price labor rates will be adjusted to reflect the
Contractor’s actual increase or decrease in applicable wages and fringe benefits . . . .”)
(emphasis added). The Clause does not address increases in the nature of the
06-1080 8
contract’s requirements, but rather the effect on the Contractor, which logically can only
refer to changes in cost.
Second, this construction is consistent with other provisions of the regulatory
scheme, which provide for the “equivalency” of fringe benefits to be measured not in
terms of value to the employee, but cost to the employer. See 29 C.F.R. § 4.177(a)(3)
(“When a contractor discharges his fringe benefit obligation by furnishing, in lieu of
those benefits specified in the applicable fringe benefit determination, other ‘bona fide’
fringe benefits, cash payments, or a combination thereof, the substituted fringe benefits
and/or cash payments must be ‘equivalent’ to the benefits specified in the
determination. As used in this subpart, the terms equivalent fringe benefit and cash
equivalent mean equal in terms of monetary cost to the contractor.”) (emphasis added).
Third, this court’s precedent in United States v. Service Ventures, Inc., leads to
this conclusion. See 899 F.2d 1 (Fed. Cir. 1990). In that case, the applicable wage
determination required that employees be given specified amounts of vacation time,
depending on their seniority. Id. at 2 (requiring Service Ventures to pay “2 weeks paid
vacation after 1 year of service with a contractor or successor; 3 weeks after 5 years”).
During the first option year, a greater number of employees were entitled to vacation
benefits under the language of the wage determination. Accordingly, Service Ventures
had to pay more in order to comply with the mandate of the wage determination, and it
therefore sought to receive a price adjustment. Id.
As in this case, the actual language of the wage determination had not changed.
Service Venture’s obligations had remained nominally the “same” in that it was still
required to provide a specified level of benefits to each employee in a specified class.
06-1080 9
However, its costs of compliance had changed because of changes in the numbers of
employees in each vacation benefit “class.” Far from adopting a narrow view of what
constituted a “change” to a wage determination, in Service Ventures we held that the
“benefits were due entirely to the [wage determination] applicable at the beginning of
the renewal option period and were required to be paid in accordance with the [Price
Adjustment] clause.” Id. at 3.
This case is analogous. In Service Ventures, the employer’s costs of compliance
changed in a manner not known in advance with certainty, by virtue of changes in the
composition of the workforce. Nonetheless, the nominally unchanged wage
determination required Service Ventures to pay out whatever total sum of benefits was
necessary for it to meet its obligations thereunder. Likewise, in this case, a wage
determination (here, from a CBA) required LSI to pay whatever was necessary for it to
meet its obligations to its employees, in light of changes in the costs of providing them
with an agreed-upon level of health care benefit.
Just as we held such changes in cost to trigger the Price Adjustment Clause in
Service Ventures, we hold them to do so here. In short, the Price Adjustment Clause is
triggered by changes in an employer’s cost of compliance with the terms of a wage
determination. The fact that there has been no nominal change in the mandated
benefit—i.e., that there has been no change in the level of benefit provided by the
defined-benefit plan—is simply irrelevant.
Finally, we address the government’s argument that the Price Adjustment Clause
does not apply because LSI can somehow satisfy its fringe-benefit obligations by
making equivalent payments directly to its employees. See, e.g., 41 U.S.C. § 351(a)(2)
06-1080 10
(stating that “[t]he obligation [to provide fringe benefits] . . . may be discharged by
furnishing any equivalent combinations of fringe benefits or by making equivalent or
differential payments in cash under rules and regulations established by the Secretary”).
We see no merit in this argument. If LSI pays its employees the “equivalent” of the
fringe benefit, then applicable regulations would require it to pay them an amount equal
to its own costs of providing the benefit. See 29 C.F.R. § 4.177(a)(3) (“[E]quivalent
means equal in terms of monetary cost to the contractor.”). The extent of LSI’s CBA-
based obligations would remain unchanged.
***
For the reasons stated above, we hold that the Board erred in granting summary
judgment in favor of the government, and it abused its discretion in denying summary
judgment to LSI. We agree with the Board, however, that this case involves no genuine
issue of material fact, and it is therefore suitable for summary judgment. Accordingly,
we reverse both holdings below and grant summary judgment in favor of LSI.
REVERSED
Costs to Appellant.
06-1080 11