United States Court of Appeals for the Federal Circuit
05-5052
JACOBS ENGINEERING GROUP, INC.,
Plaintiff-Appellant,
v.
UNITED STATES,
Defendant-Appellee.
Robert J. Symon, Spriggs & Hollingsworth, of Washington, DC, argued for
plaintiff-appellant.
James W. Poirier, Trial Attorney, Commercial Litigation Branch, Civil Division,
United States Department of Justice, of Washington, DC, argued for defendant-
appellee. With him on the brief were Peter D. Keisler, Assistant Attorney General and
David M. Cohen, Director.
Appealed from: United States Court of Federal Claims
Judge George W. Miller
United States Court of Appeals for the Federal Circuit
05-5052
JACOBS ENGINEERING GROUP, INC.,
Plaintiff-Appellant,
v.
UNITED STATES,
Defendant-Appellee.
______________________________
DECIDED: January 19, 2006
______________________________
Before MAYER, Circuit Judge, FRIEDMAN, Senior Circuit Judge, and BRYSON, Circuit
Judge.
FRIEDMAN, Senior Circuit Judge.
A development and construction contract required the government to reimburse
the contractor for 80 percent of its cost of performing the contract. The contract’s
termination-for-the-convenience-of-the-government clause (“termination clause”)
required the government upon such termination to pay the contractor “[a]ll costs
reimbursable” under the contract. See 48 C.F.R. § 52.249-6(g); Jacobs Eng’g Group,
Inc. v. United States, 63 Fed. Cl. 451, 455 (2005) (trial court decision). The question is
whether, when the government so terminated the contract, it was required to reimburse
the contractor for all of the costs the contractor incurred up to that point or only for 80
percent of them. Reversing the United States Court of Federal Claims, we hold that the
contractor may recover all of its cost, rather than 80 percent.
I
The government entered into a contract with Jacobs Engineering Group, Inc.
(“Jacobs”)’ predecessor (whose contract Jacobs took over when it acquired the
predecessor) to develop, design, fabricate, construct, and install a gasification
improvement facility. No fee was payable to the contractor, but the contract contained
the following cost sharing provision covering the “total estimated cost for the work” of
$28,750,375:
Cost Sharing. The Contractor and the Government agree to
share the cost of the effort for Phase I and Phase II as
follows:
Government Contractor Total
(80%) (20%) (100%)
Phase I $19,850,784 $4,962,696 $24,813,480
Phase II 3,149,515 787,379 3,936,894
Total $23,000,299 $5,750,075* $28,750,374
*Includes foregone fee in the amount of $1,181,594 for
Phase I and $169,531 for Phase II.
The contract further provided that if the contracting officer approved a cost
overrun, the contractor’s share would be 20 percent.
The contract also contained a standard termination for convenience clause,
Federal Acquisition Regulation (“FAR”) § 52.249-6 (May 1986), which authorized the
government to “terminate performance of work [if] [t]he Contracting Officer determines
that a termination is in the Government’s interest.” If that occurred, the government was
required to pay the contractor “[a]ll costs reimbursable under this contract, not
previously paid, for the performance of this contract before the effective date of the
termination, and part of those costs that may continue for a reasonable time with the
05-5052 2
approval of or as directed by the Contracting Officer.” FAR § 52.249-6(g)(1) (May
1986).
The contract also authorized the contractor to discontinue the project after Phase
I was completed unless it received what it deemed “adequate cost sharing and . . . an
advanced patent waiver.” If the contractor did so, it would “be liable for 20% of the
costs incurred during the performance period.”
During performance, the government terminated the contract for its convenience
(because it did not have funds to complete performance). Jacobs submitted a
termination settlement proposal which sought reimbursement of 100 percent of its costs,
which the government rejected. The contracting officer then rejected Jacobs’ claim for
recovery of all of its costs, limiting recovery to 80 percent. Jacobs challenged that
decision in the United States Court of Federal Claims.
On cross-motion for summary judgment, the court granted the government’s
motion and entered a judgment on its behalf. 63 Fed. Cl. at 459. The court stated:
The termination clause does not invalidate the cost-sharing
provision of the Contract. Rather, it clearly seeks to fashion
a remedy for the contractor in conjunction with the cost-
sharing provisions. Thus, only those costs that would be
reimbursed under the Contract will be paid to the contractor
in the event of a termination for convenience. Here 80
percent of Jacobs’s costs were reimbursable under the cost-
sharing provision and therefore, under the termination for
convenience clause, Jacobs is entitled to only 80 percent of
its costs not previously paid.
Id. At 457 (emphasis in original) (citations omitted).
II
The termination clause required the government, upon terminating the contract,
to pay the contractor “[a]ll costs reimbursable under this contract.” The government
05-5052 3
contends, as the Court of Federal Claims held, that since the contract required it to
reimburse the contractor for only 80 percent of the costs, its payment under the
termination clause is limited to 80 percent of the costs. We conclude, however, that the
term “all costs reimbursable” defines the type or kind of costs for which the contract
provides reimbursement and not the amount of such costs.
The contract specifies a substantial number of costs that are reimbursable and
some that are not. Reimbursable costs include “fabricated or unfabricated, parts, work
in process, completed work, supplies, and other materials procured or acquired for the
work terminated, . . . completed or partially completed plans, drawings, information, and
other property that . . . would be required to be furnished to the Government, . . . and
the jigs, dies, fixtures, and other special tools and tooling acquired or manufactured for
this contract.” FAR § 52.249-6(c)(6) (May 1986). They also include costs allowable
under FAR § 31.2 (see FAR § 52.249-6(h) (May 2004)), such as labor relations costs
(FAR § 31.205-21), plant protection costs (FAR § 31.205-29), and help-wanted
advertising costs for jobs specific to the project (FAR § 31.205-34(a)(1)). On the other
hand, entertainment costs (FAR § 31.205-14), fines and penalties (FAR § 31.205-15),
and general help-wanted advertisement costs (FAR § 31.205-34(b)) are not
reimbursable. The termination clause’s reference to “all costs reimbursable” under the
contract appears designed to incorporate the contract’s division between reimbursable
and non-reimbursable costs.
Throughout the contract, when the parties intended the 80 percent – 20 percent
division of costs to cover particular situations, they explicitly so provided. The table
shown above specified the amount of the costs for each phase of the contract that each
05-5052 4
party would bear. If the contractor terminated performance after Phase I was
completed, it would “be liable for 20% of the costs incurred during the performance
period.” If there was an approved cost overrun, the contractor was required to absorb
20 percent of it.
In these circumstances, it seems most unlikely that if the parties had intended the
termination clause to limit the contractor to 80 percent of the termination costs, they
would not have said so instead of providing that the government would pay “[a]ll costs
reimbursable” under the contract. We cannot read the latter phrase covering “all”
reimbursable costs to mean 80 percent of such costs. In any event, to the extent there
is an ambiguity on the point, it must be resolved in favor of Jacobs, the non-drafter of
the contract.
Our conclusion also accords with the basic financial situation underlying the
contract. FAR § 16.303(b) states that “[a] cost-sharing contract may be used when the
contractor agrees to absorb a portion of the costs, in the expectation of substantial
compensating benefits.” If the contract had been completely performed at an estimated
cost of more than $28 million, the government’s reimbursement of only 80 percent of
that amount presumably would have resulted in a substantial loss to the contractor.
Jacobs tells us in its brief that the reason the contractor entered into such a seemingly
unattractive venture was the anticipation that as a result of its performance, it would
obtain valuable patent rights, to which the contract referred.
As a result of the government’s termination of the contract, Jacobs was denied
the opportunity to obtain such patent rights. In these circumstances, it seems unfair to
Jacobs to deny it full reimbursement for the costs of its performance up to the
05-5052 5
government’s contract termination, which thwarted its possibility of obtaining the patent
rights. “A contractor is not supposed to suffer as the result of a termination for
convenience of the Government, nor to underwrite the Government’s decision to
terminate. If he has actually incurred costs . . . , it is proper that he be reimbursed
those costs when the Government terminates for convenience and thereby custs [sic]
off his ability to amortize those costs completely.” In re Kasler Elec. Co., DOTCAB
1425, 84-2 BCA ¶ 17374 (May 21, 1984).
CONCLUSION
The judgment of the Court of Federal Claims is reversed and the case is
remanded to that court to award damages.
REVERSED AND REMANDED.
05-5052 6