Pennwalt Corp. v. Public Service Commission 1

136 Mich. App. 530 (1984) 357 N.W.2d 712

PENNWALT CORPORATION
v.
PUBLIC SERVICE COMMISSION # 1

Docket Nos. 69405, 70167.

Michigan Court of Appeals.

Decided August 7, 1984.

Dickinson, Wright, Moon, Van Dusen & Freeman (by Peter S. Sheldon), for plaintiff.

Frank J. Kelley, Attorney General, Louis J. Caruso, Solicitor General, and Don L. Keskey and Leo H. Friedman, Assistants Attorney General, for the Public Service Commission.

Christopher C. Nern, A. Robert Pierce, Jr., and Fischer, Franklin, Ford, Simon & Hogg (by George Hogg, Jr., and Philip E. Chafee), for The Detroit Edison Company.

Before: CYNAR, P.J., and J.H. GILLIS and R.C. ANDERSON,[*] JJ.

PER CURIAM.

In docket No. 69405, plaintiff has filed an appeal as of right from the January 14, 1983, order of Ingham County Circuit Court Judge Robert Holmes Bell which dismissed the cause for lack of progress. In docket No. 70167, plaintiff has filed an appeal as of right from the March 3, 1983, order of Judge Bell which denied plaintiff's motion for reinstatement. On April 7, 1983, this Court on its own motion consolidated the two appeals.

At issue in this case is the proper interpretation of GCR 1963, 501.3 which reads:

"Call of No Progress Cases. Not less than once in *532 each calendar quarter, at such time and place as the court may by order designate, the judge in open court shall supervise the call of all the actions on the civil calendar pending and undisposed of in which no steps or proceedings appear to have been taken within 1 year. If none of the parties or their attorneys appear at the time and place set for the general call and answer when their action is called, the court may direct the clerk to enter an order dismissing the action for want of prosecution. If at the call it is shown that the failure to take steps or proceedings is not due to the plaintiff's fault or lack of reasonable diligence on his part, the action will not be dismissed. The court may then order the action set down for final disposition at a specified date, or place it on the calendar for trial or hearing in due course, or make such other orders as may facilitate its prompt and just disposition. Local rules may provide for notice by publication in place of the general call of the calendar in open court." (Emphasis added.)

The complaint in this case was filed on August 20, 1981, and the matter was assigned to Judge James T. Kallman. An answer was filed on September 3, 1981, by The Detroit Edison Company, and an answer was filed on September 21, 1981, by the Michigan Public Service Commission. A year later, in August, 1982, a motion to consolidate this case with four others was filed by the Michigan Public Service Commission. That motion was resisted by plaintiff and on October 21, 1982, Judge Kallman denied the motion to consolidate as to this case, although he did grant consolidation as to the four remaining cases.

On January 11, 1983, following oral argument, this case was dismissed by Judge Bell for lack of progress. The next day, January 12, 1983, plaintiff filed a motion for reinstatement. Answers to that motion were filed by the defendants later in January, 1983. On March 3, 1983, Judge Bell, after oral argument, denied the motion for reinstatement.

*533 It is undisputed that there was no activity in this file between September, 1981, and the dismissal for lack of progress, well over a year later, on January 11, 1983, except for the motion to consolidate filed by the Michigan Public Service Commission in September, 1982, and denied as requested by plaintiff on October 21, 1982.

The trial court ruled at the conclusion of the hearing on the motion for reinstatement that the motion to consolidate was not a step or proceeding directed toward resolution of this case "as a matter of law".

On appeal, plaintiff argues that this action was not properly placed on the no-progress docket under subrule 501.3, because the motion to consolidate, filed by defendant commission, was step or proceeding within the meaning of subrule 501.3, and further, plaintiff's diligent pursuit in developing evidence directly applicable to this case in a related matter, even though not appearing on the docket in this case, constituted "steps or proceedings" sufficient to make this matter ineligible for the no-progress call. In support of that argument, plaintiff asserts that the issue presented in this case, except for the test year, is identical to one of the issues which was before the Michigan Public Service Commission in U-6949, and that the proceedings in U-6949 were ongoing and included the taking of testimony of various expert witnesses and the filing of briefs, with this activity taking place throughout the calendar year 1982 and including testimony of expert witnesses and rebuttal witnesses in December of 1982.

The defendants argue that the motion to consolidate this case with four other appeals was merely for administrative purposes, since the four other statutory appeals from the commission's interim *534 and final rate orders in U-6488 had been assigned to three separate circuit court judges. Thus, it was in the interest of judicial economy to consolidate such cases; but, the motion to consolidate was not dispositive of the issues presented, and plaintiff's contention that the commission's motion to consolidate was a "step or proceeding" directed towards resolution of this action is fallacious. The defendants contend that the purpose of GCR 1963, 501.3 is to remove from the pending court cases those in which no affirmative progress, steps, or proceedings have been shown or taken within the year, and that it is not mere "activity" or a line entry or a mere formal order which constitutes the required progress or "steps or proceedings" directed toward resolution of a case. Regarding plaintiff's claim that its discovery in U-6949 should count as steps or proceedings in this case, the defendants state that at no time did plaintiff ever communicate this position to the court or to the defendants prior to the dismissal of this case.

In a recent case, Northern Michigan Exploration Co v Public Service Comm, 131 Mich. App. 571, 578; 345 NW2d 618 (1983), this Court held that the filing of interrogatories not material to plaintiff's trial preparation failed to constitute "affirmative action" so as to require reversal of the order dismissing plaintiff's cause of action for lack of progress.

Similarly, this Court now holds that the circuit court correctly construed subrule 501.3 when it held that a step or proceeding within the meaning of that subrule must be directed toward resolution of the case, and that as a matter of law a motion to consolidate filed by another party was not such a step or proceeding directed toward resolution.

Further, this Court holds that the circuit court *535 correctly rejected plaintiff's argument that its discovery activity in another case should constitute steps or proceedings in this case so as to avoid dismissal for no progress, where plaintiff failed to assert that position prior to dismissal. In Kelley v Frank D McKay Realty Co, 34 Mich. App. 370, 377; 191 NW2d 123 (1971), lv den 385 Mich. 788 (1971), this Court said "plaintiff should not at this late date be permitted to assert that his activity in case no. CA 4522 kept this action alive".

Affirmed.