Citizens Alert Regarding the Environment v. Leavitt

355 F. Supp. 2d 366 (2005)

CITIZENS ALERT REGARDING THE ENVIRONMENT, et al. Plaintiffs,
v.
Mike LEAVITT, et al. Defendants.

No. CIV.A.04-1667 ESH.

United States District Court, District of Columbia.

January 21, 2005.

*367 Andrea C. Ferster, Washington, DC, for Plaintiffs.

Guillermo A. Montero, Dept. of Justice, for Defendants.

MEMORANDUM OPINION

HUVELLE, District Judge.

Presently before the Court is defendants' motion to dismiss plaintiffs' (collectively "CARE") complaint for lack of subject matter jurisdiction on the grounds that plaintiffs lack standing and their suit is moot. Because the defendant Agency has already disbursed all grant funds, and therefore no remedy is available to plaintiffs, defendants' motion is granted.

BACKGROUND

In this suit, plaintiffs seek injunctive and declaratory relief against defendants, who are the EPA Administrator, its regional Administrator (collectively "the Agency"), and the Chairman of the Jefferson Township Sewer Authority ("the Sewer Authority") in Lackawanna County, Pennsylvania. Plaintiffs identify purported flaws under the National Environmental Policy Act ("NEPA") in the Agency's Environmental Assessment and its Finding of No Significant Impact ("FONSI") concerning the sewer project recently built in Jefferson Township near the Moosic Mountain Barrens ("the project"). The chief problem they isolate is the Agency's purported "failure to consider the secondary and cumulative impacts that will be spurred by construction of a sewer pipeline, particularly in the undeveloped Moosic Mountain barrens." (Pis.' Opp'n at 7.) They contend *368 such errors, if corrected, would necessitate inclusion of ameliorative conditions in a $1.7 million federal grant that supported the project. (Compl. ¶¶ 36-57; Pis.' Opp'n at 18.)

This sewer project has generated substantial litigation in this Court, as well as others. In 1995 the Honorable Gladys Kessler enjoined federal defendants from moving ahead with development plans related to it until they complied with NEPA. See CARE I, 1995 U.S. Dist. LEXIS 18619, at *16-36 (D.D.C. Dec. 8, 1995). Subsequently in 2003, plaintiffs' motions for a preliminary injunction and summary judgment to stop the project and its funding were denied, because, inter alia, no major federal action had yet occurred—the Agency's EA review, which is a prerequisite to issuing a federal grant, see 42 U.S.C. 4332(2)(C), was ongoing—and therefore there was nothing for this Court to enjoin pursuant to NEPA. See CARE II v. U.S. EPA 259 F. Supp. 2d 9, 20-22 (D.D.C.2003). The Circuit Court affirmed this Court's reasoning, holding that "[u]ntil EPA completes its [NEPA] review and reaches a decision, there has been no final agency action within the meaning of 5 U.S.C. § 704 (2004) and the matter is not ripe for judicial review." CARE III, 102 Fed.Appx. 167, 168 (D.C.Cir.2004).

Following the Circuit's decision, the Agency completed its EA of the sewer project and signed the final FONSI on August 6, 2004, a copy of which the Agency sent to plaintiffs, as well as others who had commented on the project. On August 25, the Agency executed a grant award offer to the Sewer Authority, which the latter accepted on September 7. The Agency, based on an intervening inspection showing that the project was between ninety-five and ninety-eight percent complete, disbursed ninety percent of the $1.7 million grant on September 27. Following notification that the project was entirely complete (absent a few minor punchlist items), the Agency authorized disbursal of the remaining ten percent on November 9. (See Defs.' Mot. at 7 and sources cited therein.) At this juncture, the federal grant has been paid in full and the locally-administered sewer project is complete and operational. (See Defs.' Mot. Ex. 9.)

ANALYSIS

Defendants submit that this Court lacks subject matter jurisdiction over this suit for two reasons. First, they contend that the suit is moot because the project has been completed and the grant funds have been disbursed. Second, they argue that plaintiffs lack standing both because there is no causation between the federal grant and plaintiffs' purported injuries and because plaintiffs' injuries are not remediable through this suit.

Plaintiffs, however, object that the Court may not rule on defendants' Fed.R.Civ.P. 12(b)(1) motion because it relies on disputed issues of fact. (Pis.' Opp'n at 3-5.) A complaint should not be dismissed "unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief." Conley v. Gibson, 355 U.S. 41, 45-16, 78 S. Ct. 99, 2 L. Ed. 2d 80 (1957). Although all reasonable inferences and all factual doubts must be resolved in favor of plaintiffs, Ramirez de Arellano v. Weinberger, 745 F.2d 1500, 1506 (D.C.Cir.1984) (en banc), plaintiffs have not presented any disputed issues of fact relevant to the jurisdictional questions before the Court. The most they argue is that it is disputed whether the Agency "retains the ability, if directed by the Court, to redress the injury to plaintiffs notwithstanding disbursal of the grant and project completion." (Pis.' Opp'n at 5.) They object that, without discovery and production of the administrative *369 record, the Court cannot resolve this purported issue of fact. (Id.)

Plaintiffs' argument fails, for the issue they raise is a question of law. Production of the administrative record and discovery would not shed light on the question of whether the Agency, as a matter of law, may retroactively add conditions to or even rescind its grant to the Sewer Authority. Such authority either exists by virtue of statute, the existing terms of the grant, or some other legal source, or it is nonexistent. Neither production of a record detailing the agency's analysis of the project's environmental effects on the Moosic Mountains and other Scranton environs or any other type of discovery would clarify this legal question.

As defendants rightly note, this Court has an "an affirmative obligation to ensure that it is acting within the scope of its jurisdictional authority." Grand Lodge of Fraternal Order of Police v. Ashcroft, 185 F. Supp. 2d 9, 13 (D.D.C.2001). (Defs.' Reply at 4.) In determining whether it has jurisdiction, the Court may, as it sees fit, look beyond the allegations of the complaint to extra-pleading material. See Hohri v. United States, 782 F.2d 227, 241 (D.C.Cir.1986), vacated on other grounds, 482 U.S. 64, 107 S. Ct. 2246, 96 L. Ed. 2d 51 (1987); see also Scolaro v. D.C. Board of Elections and Ethics, 104 F. Supp. 2d 18, 22 (D.D.C.2000) (citing Herbert v. Nat'l Academy of Sciences, 974 F.2d 192, 197 (D.C.Cir.1992)); Haase v. Sessions, 835 F.2d 902, 906 (D.C.Cir.1987). The Court therefore will exercise its discretion to examine the statutes governing the Agency and the terms of the grant itself in order to resolve the threshold jurisdictional questions raised by the defendants.

I. Mootness

For this Court to rule on plaintiffs' complaint, the suit must present a live case or controversy. "Even where litigation poses a live controversy when filed, the [mootness] doctrine requires a federal court to refrain from deciding it if `events have so transpired that the decision will neither presently affect the parties' rights nor have a more-than-speculative chance of affecting them in the future." Clarke v. United States, 915 F.2d 699, 701 (D.C.Cir.1990) (quoting Transwestern Pipeline Co. v. FERC, 897 F.2d 570, 575 (D.C.Cir.1990)). Where intervening events preclude the Court from granting plaintiffs any effective relief, even if they were to prevail on their underlying claim, the Court must dismiss a suit as moot for want of subject matter jurisdiction. Church of Scientology v. United States, 506 U.S. 9, 11, 113 S. Ct. 447, 121 L. Ed. 2d 313 (1992). See, e.g., Murphy v. Hunt, 455 U.S. 478, 481-82, 102 S. Ct. 1181, 71 L. Ed. 2d 353 (1982); Burlington N. R.R. Co. v. Surface Transp. Bd., 75 F.3d 685, 688 (D.C.Cir. 1996).

Plaintiffs' point is well taken that "any effective relief encompasses acts that may not necessarily undo a fait accompli, but that may serve to mitigate it. See Neighbors of Cuddy Mountain v. Alexander, 303 F.3d 1059, 1065 (9th Cir. 2002). (Pis.' Opp'n at 6.) However, unlike the cases relied on by plaintiffs, this case is not amenable to pragmatic relief such as allowing more salmon to spawn in a subsequent year, Northwest Envtl. Def. Ctr. v. Gordon, 849 F.2d 1241, 1244-45 (9th Cir. 1988), creating replacement nesting areas for birds, Cantrell v. City of Long Beach, 241 F.3d 674, 678-79 (9th Cir.2001), or undertaking a "direct species population intervention." Alexander, 303 F.3d at 1066. Unlike endangered species or major projects on federal lands, this local Pennsylvania sewer project is not automatically subject to NEPA. See CARE II, 259 F.Supp.2d at 15-16. The only manner in *370 which the Agency or this Court could have dictated the relief plaintiffs now seek under NEPA would have been for the Sewer Authority to decide to accept a grant subject to such conditions. See id. at 16; see also CARE III, 102 Fed.Appx. at 169. Thus, unlike the controversies confronting the Ninth Circuit in the above cases, the instant matter does not give a regulatory authority a later opportunity to correct a supposed previous error, for example, by issuing fishery regulations for a subsequent season that account for an earlier inadequacy. See Gordon, 849 F.2d at 1245.

Rather, this controversy is governed by principles of contract law, and the Sewer Authority was offered and accepted the grant on the basis of certain conditions, which this Court may not retroactively revisit. As a general matter,

legislation enacted pursuant to the spending power is much in the nature of a contract: in return for federal funds, the States agree to comply with federally imposed conditions. The legitimacy of Congress' power to legislate under the spending power thus rests on whether the State voluntarily and knowingly accepts the terms of the "contract." There can, of course, be no knowing acceptance if a State is unaware of the conditions or is unable to ascertain what is expected of it. Accordingly, if Congress intends to impose a condition on the grant of federal moneys, it must do so unambiguously. By insisting that Congress speak with a clear voice, we enable the States to exercise their choice knowingly, cognizant of the consequences of their participation.

Pennhurst State Sch. & Hosp. v. Haiderman, 451 U.S. 1, 17, 101 S. Ct. 1531, 67 L. Ed. 2d 694 (1981) (internal citations and footnote omitted); accord Virginia Dep't of Educ. v. Riley, 23 F.3d 80, 85 (4th Cir.1994) ("[A]gencies of the federal government cannot be permitted freely to change funding conditions right in the middle of a multi-year grant period. Allowing such mid-grant shifts would enable the federal government to overlook its obligation of fair dealing with the states in the administration of funding programs. This obligation has been clearly stated with respect to Congress, see Pennhurst, 451 U.S. at 17, 101 S. Ct. 1531, and it is equally applicable to the agencies charged with administering federal grant programs.").

The same principles govern the Agency's contract with the Sewer Authority. Unless the Sewer Authority explicitly agreed to be bound by NEPA or to comply with conditions the Agency recommended as a result of its Environmental Assessment, the Authority had no such compliance duty. See CARE III, 102 Fed.Appx. at 169 (holding that "[n]onfederal participants in federal actions need not themselves comply with NEPA") (citing Macht v. Skinner, 916 F.2d 13, 18 (D.C.Cir.1990)). The grant agreement does not include any catchall clause allowing the Agency to add conditions to the agreement retroactively. It simply provides that "[t]his agreement is subject to applicable U.S. Environmental Protection Agency statutory provisions and assistance regulations." (Defs.' Mot. Ex. 5.) Thus, unless those statutes and regulations provide the Agency with the powers the plaintiffs seek to compel it to invoke, plaintiffs' suit is moot, because the grant payments and the conditions under which the Authority accepted them are a done deal that may not be revisited.

Plaintiffs direct the Court's attention to the Agency's powers, pursuant to 40 C.F.R. § 35.965, to terminate or annul grants, debar the grantee from future federal assistance, and the like. (See Pis.' Opp'n at 9.) But those powers are explicitly limited to circumstances where the "grantee has failed to comply with any *371 provision of this subpart." 40 C.F.R. § 35.965 (emphasis added). Plaintiffs' complaint does not even allege that the Sewer Authority has breached particular duties under Subpart E, which governs grants for construction of treatment works under the Clean Water Act. Rather, as plaintiffs admit, they take issue with the Agency's compliance with NEPA, not the Sewer Authority's. (See Pis.' Opp'n at 7 ("[T]he primary thrust of Plaintiffs' NEPA challenge and the reason why the Plaintiffs are injured by the EPA's noncompliance with NEPA is the EPA's failure to consider the secondary and cumulative impacts that will be spurred by construction of a sewer pipeline.") (emphasis added).) Thus, the Agency's enforcement powers under section 35.965 do not enable it to retroactively change the terms of the grant in order to afford the relief that plaintiffs seek.

Plaintiffs also point to 40 C.F.R. § 6.512, which provides for Agency monitoring of "mitigation measures and other grant conditions identified in the [FONSI]," and for enforcement actions where "the grantee fails to comply with grant conditions" (emphasis added). Because the FONSI at issue contains no grant conditions and sets forth no mitigation measures (see Defs.' Mot. Ex. 2), this regulation likewise provides no basis for amending the grant to provide the relief sought here. Again, there is no allegation that the Sewer Authority as grantee has failed to meet the conditions of the grant as envisioned by 40 C.F.R. § 6.512; rather, plaintiffs' "primary thrust" is against the Agency instead. Where the alleged wrongdoing is the Agency's failure to meet its obligations under NEPA, the principles of Pennhurst do not permit the other, innocent contracting party to have the grant retroactively rewritten to its detriment on account of the government's purported mistakes in entering into the contract without meeting the Agency's obligations. See Pennhurst, 451 U.S. at 17, 101 S. Ct. 1531.

The result here might have been different if the grant offer had been withdrawn and reissued subject to plaintiffs' proposed conditions prior to its acceptance. But plaintiffs failed to seek a restraining order or a preliminary injunction to arrest the grant-making process before the Sewer Authority accepted the government's grant offer. As stated, the Authority has long since accepted the Offer, and the grant has been paid in full. Indeed, if plaintiffs are correct that the Agency did not comply with NEPA, they could have moved in early November for emergency relief to argue that the Agency must be precluded from finalizing payment of the second grant installment, which was processed on November 9, 2004. (Defs.' Mot. Ex. 7.) The fact that in CARE II the Court was unable to enjoin the Sewer Authority's construction of the project did not make it futile to move in the instant proceeding to enjoin the Agency from disbursing a grant allegedly granted in violation of NEPA. Compare CARE II, 259 F.Supp.2d at 22. (See Pis.' Opp'n at 12-13; Defs.' Reply at 9-10.) In short, plaintiffs could have been afforded a remedy, and mootness would thereby have been avoided, had they diligently sought a restraining order prior to the Agency's finalizing grant payments to the Authority. But they did not, and Pennhurst and its progeny preclude this Court from inflicting unenvisioned grant conditions on the Authority at this late date. Thus, plaintiffs are not entitled to the remedy they seek, and their suit is moot.

Plaintiffs argue that their suit falls within the mootness exception for actions that are capable of repetition but evade review. See Weinstein v. Bradford, 423 U.S. 147, 148-49, 96 S. Ct. 347, 46 L. Ed. 2d 350 (1975). (Pis.' Opp'n at 11-12.) This *372 exception applies where "(1) the challenged action was in its duration too short to be fully litigated prior to its cessation or expiration, and (2) there was a reasonable expectation that the same complaining party would be subjected to the same action again." Id. at 149, 96 S. Ct. 347. Even assuming arguendo that plaintiffs might again challenge the Agency's NEPA compliance, plaintiffs have failed to show that the instant payment process is likely to occur in the future on as short a timetable as was present in this case. The fact that in this rare instance, a local government body received a grant for a project that was all but complete even absent federal funding, and which grant therefore could be paid in full within three months, does not establish that this short timeframe is likely to recur in litigation in which plaintiffs are involved. Rather, in any future litigation the timetable of the normal grant-awarding process is likely to be operative, and thus, litigation may be brought prior to the final disbursement of the federal grant monies. (See Defs.' Mot. at 10.) In the future, plaintiffs are likely to have more than adequate time to fully litigate a suit against defendants challenging their NEPA compliance, and therefore, this suit does not merit the application of the Weinstein exception. Accord Northwest Res. Info. Ctr., Inc. v. Nat'l Marine Fisheries Serv., 56 F.3d 1060, 1070 (9th Cir.1995) (holding that a mooted challenge to a permit valid for less than one year did not "evade review" because a subsequent permit was of more than adequate duration to allow for full litigation of the issues).

In sum, this Court is unable to grant plaintiffs any effective relief, and as a result, their suit is therefore moot because the Court lack jurisdiction.

II. Plaintiffs' Standing

As an alternative basis for its dismissal of plaintiffs' suit, the Court holds that plaintiffs lack standing, and therefore, the Court has no subject matter jurisdiction to hear this case.

To establish that this Court has jurisdiction to hear plaintiffs' claims, plaintiffs must show that they have standing to raise them. See Florida Audubon Soc'y v. Bentsen, 94 F.3d 658, 663, 666 (D.C.Cir. 1996) (en banc). Standing exists where (1) a plaintiff has suffered a concrete and particularized injury or threat of injury, (2) that injury can fairly be traced to the challenged action of the defendant ("causation"), and (3) the relief sought will likely alleviate plaintiffs alleged injury ("redressability").[1]See id. at 663-64. Defendants contend that plaintiffs have failed to show both (2) or (3). (See Defs.' Mot. at 8-9.)

The same reasoning underlying the Court's mootness decision compels the suit's dismissal for lack of standing. For the reasons stated, plaintiffs' alleged injuries will not be redressed through the relief sought, because such relief cannot be granted pursuant to the now-final terms and conditions of the grant and because the Sewer Authority has not done anything wrong that would warrant enforcement actions against it. Plaintiffs therefore fail the redressability prong of the standing analysis.

*373 Furthermore, plaintiffs cannot show that their injury is fairly traceable to the Agency's purportedly inadequate NEPA review. As this Court previously held, and as this Circuit affirmed, completion of the sewer project was proceeding apace regardless of the outcome of the Agency's Environmental Assessment. See CARE II, 259 F.Supp.2d at 21-22; CARE III, 102 Fed. Appx. at 169 ("While the Township arguably jeopardizes its federal funding by proceeding with construction before EPA has reached a decision on the grant request, because this course of action limits the Township's ability to make alterations to the project that might be necessary to secure EPA's approval, nothing in NEPA prevents the Township from taking that risk."). Thus, plaintiffs would have sustained their alleged injuries—e.g., anticipated increased development in the Moosic Mountain Barrens—notwithstanding the Agency's purported noncompliance with NEPA, and thus, their claim of injury is simply too attenuated to be fairly traceable to any action by defendants. See Florida Audubon Soc'y, 94 F.3d at 670 (rejecting a similarly "protracted chain of causation") ("The greater number of uncertain links in a causal chain, the less likely it is that the entire chain will hold true."). In sum, in addition to failing to show redressability, plaintiffs also cannot show causation, and they therefore lack standing to bring this suit. For this reason as well, the Court lacks subject matter jurisdiction.

CONCLUSION

While only one of the above-discussed issues would be sufficient to deprive this Court of subject matter jurisdiction, in fact there are three independent reasons why the Court may not hear this case. The suit is moot, plaintiffs cannot demonstrate causation between their injuries and the challenged action sufficient to establish standing, and plaintiffs cannot show that their injuries are redressable so as to afford them standing. It therefore cannot proceed, and defendants' motion is granted and this case is dismissed with prejudice. An appropriate Order accompanies this Memorandum Opinion.

ORDER

For the reasons stated in the accompanying Memorandum Opinion, it is hereby

ORDERED that Federal Defendants' motion to dismiss [# 7] is GRANTED; and it is

FURTHER ORDERED that this case is dismissed with prejudice.

This is a final appealable order.

NOTES

[1] Citing the Ninth Circuit, see Cantrell, 241 F.3d at 682, plaintiffs contend that as litigants accorded procedural rights, the standing showing they must make is "relaxed." (Pis.' Opp'n at 16.) However, this Circuit has unequivocally held that such plaintiffs have "never [been] freed" from the "irreducible" standing requirements of showing causation and redressability. See Florida Audubon Soc'y, 94 F.3d at 664. Accordingly, the Court proceeds with its standing analysis.