UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
____________________________________
)
IN THE MATTER OF THE )
FORT TOTTEN METRORAIL CASES )
Arising Out of the Events of June 22, 2009 )
)
) Miscellaneous Case No. 10-314 (RBW)
LEAD CASE: Jenkins v. Washington )
Metropolitan Area Transit Authority, et al. )
)
THIS DOCUMENT RELATES TO: )
ALL CASES )
____________________________________)
AMENDED MEMORANDUM OPINION 1
This action was instituted on behalf of individuals who were killed or injured in a
collision between two Washington Metropolitan Area Transit Authority (“WMATA”) trains that
occurred on June 22, 2009, near WMATA’s Fort Totten Metrorail station. Currently before the
Court are the following seven contested dispositive motions: (1) WMATA’s motion to dismiss
Alstom Signaling, Inc.’s (“Alstom”) statute of repose affirmative defense, ECF No. 353; 2 (2)
Ansaldo STS USA, Inc.’s (“Ansaldo”) motion for judgment on Counts 7, 11, and 15 of the
Second Amended Master Complaint, ECF No. 367; (3) WMATA’s motion to dismiss the
equitable indemnification cross-claims against it, ECF No. 424; (4) Alstom, Ansaldo, and
ARINC Incorporated’s (“ARINC”) (collectively “corporate defendants”) joint motion for
summary judgment on all claims, ECF No. 425; (5) Ansaldo’s motion for summary judgment,
1
This Amended Memorandum Opinion amends and supersedes the August 16, 2012 Memorandum Opinion.
2
In this Memorandum Opinion, the Court will cite to the parties’ filings by referencing the document number
generated by the Court’s electronic case filing system (“ECF No.”), followed by the page number assigned to the
document by the filing party.
1
ECF No. 426; (6) Alstom’s motion for summary judgment, ECF No. 427; and (7) ARINC’s
motion for summary judgment, ECF No. 428. Upon careful consideration of the parties’
submissions, the Court concludes for the following reasons that (1) WMATA’s motion to
dismiss Alstom’s statute of repose defense must be granted in part and denied in part; (2)
Ansaldo’s motion for judgment on Counts 7, 11, and 15 of the Second Amended Master
Complaint must be granted; (3) WMATA’s motion to dismiss the equitable indemnification
cross-claims against it must be granted; (4) the corporate defendants’ motion for summary
judgment must be denied; (5) Ansaldo’s motion for summary judgment must be denied; (6)
Alstom’s motion for summary judgment must be denied; and (7) ARINC’s motion for summary
judgment must be granted in part and denied in part.
I. Standards of Review
A. Motion to Dismiss under Rule 12(b)(1)
When a defendant moves for dismissal under Federal Rule of Civil Procedure 12(b)(1),
“the plaintiff[] bear[s] the burden of proving by a preponderance of the evidence that the Court
has subject matter jurisdiction.” Biton v. Palestinian Interim Self-Gov’t Auth., 310 F. Supp. 2d
172, 176 (D.D.C. 2004); see Lujan v. Defenders of Wildlife, 504 U.S. 555, 561 (1992). A court
considering a Rule 12(b)(1) motion must “assume the truth of all material factual allegations in
the complaint and ‘construe the complaint liberally, granting [a] plaintiff the benefit of all
inferences that can be derived from the facts alleged.’” Am. Nat’l Ins. Co. v. FDIC, 642 F.3d
1137, 1139 (D.C. Cir. 2011) (quoting Thomas v. Principi, 394 F.3d 970, 972 (D.C. Cir. 2005)).
However, “the district court may consider materials outside the pleadings in deciding whether to
grant a motion to dismiss for lack of jurisdiction.” Jerome Stevens Pharm., Inc. v. FDA, 402
2
F.3d 1249, 1253 (D.C. Cir. 2005) (citing Herbert v. Nat’l Acad. of Sciences, 974 F.2d 192, 197
(D.C. Cir. 1992)).
B. Motion for Judgment on the Pleadings under Rule 12(c)
Federal Rule of Civil Procedure 12(c) permits “a party [to] move for judgment on the
pleadings” so long as the motion is made “[a]fter the pleadings are closed—but early enough not
to delay trial.” “The standard for a motion for judgment under Rule 12(c) is essentially the same
standard as a motion to dismiss under Rule 12(b)(6).” Rollins v. Wackenhut Servs., 802 F. Supp.
2d 111, 116 (D.D.C. 2011) (citing, among others, Schuchart v. La Taberna Del Alabardero, Inc.,
365 F.3d 33, 35 (D.C. Cir. 2004)). Accordingly, when considering a Rule 12(c) motion, “the
court must accept the nonmovant’s allegations as true and should view the facts in the light most
favorable to the nonmovant.” Bowman v. District of Columbia, 562 F. Supp. 2d 30, 32 (D.D.C.
2008). “The court should grant a motion for judgment on the pleadings if the movant ‘is entitled
to judgment as a matter of law.’” Id. (quoting Burns Int’l Sec. Servs. v. Int’l Union, 47 F.3d 14,
16 (2d Cir. 1995)).
C. Motion for Summary Judgment under Rule 56
A motion for summary judgment will be granted “if the movant shows that there is no
genuine dispute as to any material fact and the movant is entitled to judgment as a matter of
law.” Fed. R. Civ. P. 56(a). The moving party bears the initial burden of showing the absence of
a disputed material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The party opposing
a motion for summary judgment “may not rest upon the mere allegations or denials of his
pleading, but . . . must set forth specific facts showing that there is a genuine issue for trial.”
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A material fact is one that “might
affect the outcome of the suit under the governing law.” Id. “The evidence is to be viewed in
3
the light most favorable to the nonmoving party and the court must draw all reasonable
inferences in favor of the nonmoving party.” Talavera v. Shah, 638 F.3d 303, 308 (D.C. Cir.
2011) (citing Anderson, 477 U.S. at 255). “Although summary judgment is not the occasion for
the court to weigh credibility or evidence, summary judgment is appropriate ‘if the nonmoving
party fails to make a showing sufficient to establish the existence of an element essential to that
party’s case, and on which that party will bear the burden of proof at trial.’” Id. (citations
omitted). “[T]here is no issue for trial unless there is sufficient evidence favoring the nonmoving
party for a [reasonable] jury to return a verdict for that party.” Anderson, 477 U.S. at 249. “The
mere existence of a scintilla of evidence in support of the [non-moving party’s] position will be
insufficient; there must be evidence on which the jury could reasonably find for the [non-moving
party].” Id. at 252 (emphasis added).
II. WMATA’s motion to dismiss Alstom’s statute of repose affirmative defense 3
A. Introduction
Alstom asserts, as an affirmative defense, that WMATA’s cross-claims for contribution
and contractual indemnity are time-barred under the District of Columbia’s (“District”) statute of
repose. WMATA moves to dismiss this affirmative defense, arguing that its cross-claims fall
under two exceptions to the District’s statute of repose: (1) the exception for claims asserted by
the District of Columbia government, and (2) the exception for claims based on a contract.
3
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) the
Memorandum in Support of WMATA’s Motion to Dismiss Alstom’s Statute of Repose Affirmative Defense [ECF
No. 353-1]; (2) Alstom Signaling Inc’s Opposition to WMATA’s Motion to Dismiss Alstom’s Statute of Repose
Affirmative Defense [ECF No. 382]; and (3) the Reply Memorandum in Support of WMATA’s Motion to Dismiss
Alstom’s Statute of Repose Affirmative Defense [ECF No. 396].
4
The Court concludes that WMATA’s cross-claim for contractual indemnity falls under
the statute of repose’s exception for claims based on a contract, but that its cross-claim for
contribution does not. The Court also concludes that neither cross-claim falls under the statute of
repose’s exception for claims brought by the District. Accordingly, WMATA’s motion is
granted in part and denied in part.
B. Background
WMATA filed a cross-claim against Alstom containing two counts: Count I is for
contribution, and Count II is for contractual indemnity. See ECF No. 140 ¶¶ 84-90. The
contribution claim asserts that if WMATA is found liable to the plaintiffs, WMATA is entitled to
contribution from Alstom with respect to damages proximately caused by Alstom’s negligently
and defectively designed automatic train control system. Id. ¶¶ 85-86. The contractual
indemnity claim asserts that if WMATA is found liable to the plaintiffs, it is entitled to
indemnification from Alstom pursuant to several provisions of a contract between the parties. Id.
¶ 88. In its Answer to WMATA’s cross-claim, Alstom asserts that WMATA’s cross-claims for
contribution and indemnification are time-barred under the District’s statute of repose. ECF No.
178 ¶ 10.
The District’s statute of repose bars “any action” for “personal injury” or “wrongful death
. . . resulting from the defective or unsafe condition of an improvement to real property” if the
injury or death occurs more than ten years after the “improvement was substantially completed.”
D.C. Code § 12-310(a)(1)(A) (2001). 4 The statute also bars any action “for contribution or
indemnity which is brought as a result of such injury or death” if the injury or death occurs more
4
The parties do not dispute that WMATA’s cross-claim against Alstom arises from an allegedly “defective or
unsafe condition of an improvement to real property.” Id.
5
than ten years after the “improvement was substantially completed.” Id. § 12-310(a)(1)(B).
However, the statute’s ten-year limitations period does not apply to, among other lawsuits, “any
action based on a contract, express or implied,” id. § 12-310(b)(1), or “any action brought by the
District of Columbia government,” id. § 12-310(b)(4).
WMATA now moves for judgment on the pleadings under Rule 12(c), contending that
Alstom’s statute of repose defense fails as a matter of law because WMATA’s cross-claim falls
under both of the foregoing exceptions to the statute of repose. First, WMATA argues that the
statute’s exception for “any action brought by the District of Columbia government,” id. § 12-
310(b)(4), applies because WMATA is an agency of the District under the terms of the interstate
compact that created it, and thus should be treated as “the District of Columbia government” for
the purposes of the statute of repose, ECF No. 353-1 at 5. It further contends that even if § 12-
310(b)(4) is construed to apply only when the District is suing to vindicate public rights, the
exception still applies here because WMATA’s cross-claim against Alstom seeks to protect the
public from negligent design defects in Alstom’s train control system, and to replenish
WMATA’s treasury to enable it to perform a public function (i.e., rail transportation). See id. at
11-15. Second, WMATA maintains that the statute of repose’s exception for “any action based
on a contract, express or implied,” D.C. Code § 12-310(b)(1), also applies because its cross-
claim against Alstom is primarily based on the contract between the parties, ECF No. 353-1 at
16-18.
The majority of Alstom’s opposition brief focuses on the merits of WMATA’s cross-
claim (i.e., WMATA’s entitlement to contribution and indemnity from Alstom). These
arguments, however, are irrelevant to the issues presented in WMATA’s motion, and will be
considered by the Court only in the context of Alstom’s motion for summary judgment (which is
6
discussed infra in this Memorandum Opinion). Alstom makes only one argument responsive to
WMATA’s motion: it contends that the statute of repose’s exception for “any action brought by
the District of Columbia government,” id. § 12-310(b)(4), does not apply here because (1)
WMATA is not “the District of Columbia government,” and (2) even if it were, this statutory
exception applies only when the District’s lawsuit vindicates a public right, and WMATA’s
cross-claim to recover the costs of its own negligence vindicates no such right. See ECF No. 382
at 7-12.
C. Analysis
Notwithstanding the order in which WMATA presents it arguments, the Court finds that
its strongest position is based on the statute of repose’s exception for contract claims. The Court
thus considers the applicability of that exception first, and then turns to the exception for claims
asserted by the District.
1. Does the statute of repose’s exception for “any action based on a contract,” §
12-310(b)(1), apply to WMATA’s cross-claim against Alstom?
As noted, WMATA’s cross-claim asserts two counts: Count I for contribution, and Count
II for contractual indemnity. See ECF No. 140 ¶¶ 84-90. Despite WMATA’s misleading
argument that its cross-claim against Alstom is “primarily” based on a contract, its contribution
cross-claim plainly sounds in tort, not contract. See id. ¶ 85 (seeking contribution from Alstom
insofar as its negligence proximately caused WMATA’s liability, and not referencing any
contract). And “[c]ontribution is one of several theories used to apportion damages among
tortfeasors to an injured party.” D.C. v. Wash. Hosp. Cent., 722 A.2d 332, 336 (D.C. 1998)
(emphasis added). Thus, WMATA’s contribution cross-claim is not exempt from the statute of
repose under § 12-310(b)(1).
7
WMATA’s contractual indemnity cross-claim is another story. This claim asserts that
Alstom is contractually bound to indemnify WMATA for any damages it pays to the plaintiffs.
See ECF No. 140 ¶¶ 88-90. Because this claim is “based on a contract” between Alstom and
WMATA, it is exempt from the statute of repose under § 12-310(b)(1).
2. Does the statute of repose’s exception for “any action brought by the District
of Columbia government,” § 12-310(b)(4), apply to WMATA’s cross-claim
against Alstom?
Determining the applicability of this exception entails three, interrelated questions: First,
should WMATA be considered “the District of Columbia government” within the meaning of §
12-310(b)(4)? Second, if WMATA is the District government for purposes of § 12-310(b)(4),
does this provision exempt from the statute of repose any action filed by WMATA, or only those
actions brought to enforce public rights? And third, if § 12-310(b)(4) only exempts those actions
brought to enforce public rights, does WMATA’s cross-claim against Alstom seek to enforce
such a right? 5
i. Is WMATA “the District of Columbia government” within the
meaning of § 12-310(b)(4)?
“WMATA was created by an interstate compact entered into by the District of Columbia
and the states of Maryland and Virginia.” Watters v. WMATA, 295 F.3d 36, 39 (D.C. Cir.
2002). The interstate compact establishes that WMATA is “an instrumentality and agency of
each of the signatory parties,” which includes the District. D.C. Code § 9-1107.01, art. III, § 4
(2001); see also id., art. II, § 2 (“The purpose of this Title is to create a regional instrumentality,
as a common agency of each signatory party.”). Nevertheless, “[s]ince WMATA’s conception in
5
It bears noting that the applicability of this statute of repose exception is critical only to WMATA’s contribution
claim (Count II) since, as explained above, WMATA’s contractual indemnity claim (Count I) plainly falls into the
statute of repose’s exception for contract claims.
8
1981, the unique nature of the compact has spawned a great deal of litigation regarding the
proper scope of WMATA’s jurisdiction and liability,” with many cases turning upon “whether
WMATA can be considered an agency of the District of Columbia.” Griggs v. WMATA, 66 F.
Supp. 2d 23, 27 (D.D.C. 1999) (surveying caselaw where WMATA is treated as a District
agency for some purposes, but not others). The determination of whether WMATA is part of the
District government, in other words, varies depending on the particular circumstances of each
case. See id.
The issue here is whether WMATA should be considered “the District of Columbia
government” within the meaning of the statute of repose’s exception for “any action brought by
the District of Columbia government.” D.C. Code § 12-310(b)(4). The Court concludes that it
should for the following reasons.
D.C. Code § 12-310(b)(4) was enacted as part of the District of Columbia Statute of
Limitations Amendment Act of 1986. D.C. Water & Sewer Auth. (“WASA”) v. Delon Hampton
Assocs., 851 A.2d 410, 414 (D.C. 2004). The D.C. Court of Appeals has recognized that this
legislation codified the common law doctrine of nullum tempus (“no time runs against the
sovereign”). See id. (“[A]n underlying aim of the [D.C.] Council” in enacting the law “was to
ensure that the District received, at the least, the benefit of the common law principle of ‘nullum
tempus.’”). Under the doctrine of nullum tempus, “sovereigns enjoy a common-law immunity
from the operation of statutes of limitations and repose . . . when [they] sue[] to vindicate public
rights.” D.C. v. Owens-Corning Fiberglas Corp., 572 A.2d 394, 401, 406 (D.C. 1989). Of
particular relevance here, nullum tempus immunity is generally considered a type of sovereign
immunity. See Solid Rock Church, Disciples of Christ v. Friendship Pub. Charter Sch., Inc., 925
A.2d 554, 559-60 (D.C. 2007) (“[T]he District . . . enjoys limited sovereign immunity from the
9
operation of statutes of limitation under the common law doctrine of nullum tempus.” (emphasis
added)); Owens-Corning, 572 A.2d at 405 (noting that “[s]ince Congress is sovereign in the
District, it enjoys the usual sovereign immunities, including the benefit of nullum tempus”
(emphasis added)); accord Shootman v. Dep’t of Trans., 926 P.2d 1200, 1206 (Colo. 1996)
(“[N]ullum tempus is simply an aspect of sovereign immunity.”); New Jersey Educ. Facilities
Auth. v. Gruzen, 592 A.2d 559, 561 (N.J. 1991) (same); Wash. Suburban Sanitary Comm’n v.
Pride Homes, 435 A.2d 796, 801 (Md. 1981) (same). This point is significant because, in
signing the interstate compact, Maryland, Virginia, and the District “conferred each of their
respective sovereign immunities” on WMATA. Watters, 295 F.3d at 39. The Fourth Circuit has
consequently interpreted the interstate compact’s conferral of sovereign immunity on WMATA
to include immunity from Virginia’s statute of limitations. See Delon Hampton v. WMATA,
943 F.2d 355, 359 (4th Cir. 1991) (stating that, “[a]s a general proposition, an agency of the state
shares the same privileges as that of the state, including sovereign immunity,” and holding that
WMATA, “as an agency and instrumentality of the Commonwealth of Virginia,” was “exempt
from application of the statute of limitations” pursuant to Virginia statute which codified nullum
tempus). Employing similar reasoning here, this Court concludes that WMATA derives nullum
tempus immunity from the District because it is an agency of the District that shares its sovereign
immunity, and that WMATA consequently qualifies as the “District of Columbia government”
within the meaning of § 12-310(b)(4). 6
6
Even if WMATA does not fall within the exception to the statute of repose codified at § 12-310(b)(4), it would still
be entitled, as an agency of the District, to common law nullum tempus immunity, so long as it brought its lawsuit to
vindicate a public right. See Owens-Corning, 572 A.2d at 401.
10
Resisting this conclusion, Alstom relies upon the D.C. Court of Appeals’ decision in
WASA, 851 A.2d at 414. There, the court held that the “functions and activities of WASA [the
D.C. Water and Sewer Authority], a separate corporate body distinct from the District of
Columbia, are proprietary in nature and thus beyond the protection of nullum tempus” and, in
turn, outside the exception to the statute of limitations for “actions brought by the District of
Columbia government” codified at D.C. Code § 12-301 (2001). Id. at 416. To be sure, WASA
and WMATA have some similarities—they can both sue and be sued in their own names, and
they can enter into contracts with the District. Compare D.C. Code §§ 43-1672, 43-1673 (2001)
(WASA enabling legislation), with D.C. Code § 9-1107.1, Tit. III, Art. II, § 2; id., Art. V, §§
12(a), 12(f) (2001) (WMATA Compact). However, whereas WASA’s enabling legislation
makes clear that it is “an independent authority of the District government” and a “corporate
body . . . that has a separate legal existence within the District government,” D.C. Code § 34-
2202.02(a) (2001) (emphasis added), the interstate compact declares that WMATA is “an
instrumentality and agency of each of the signatory parties,” including the District. D.C. Code §
9-1107.01, art. III, § 4 (2001). And WMATA derives sovereign immunity from the District, see
Watters, 295 F.3d at 39, which includes nullum tempus immunity. WASA apparently does not.
Because of these key distinctions between WASA and WMATA, Alstom’s reliance on WASA is
misplaced.
ii. Does § 12-310(b)(4) exempt from the statute of repose any action filed
by the District/WMATA, or only those actions brought to enforce
public rights?
Even though WMATA may be treated as the District government for purposes of § 12-
310(b)(4), that does not end the Court’s inquiry. According to Alstom, § 12-310(b)(4) merely
codifies the doctrine of nullum tempus, and thus only exempts lawsuits from the statute of repose
11
when the District is seeking to enforce a public right. ECF No. 382 at 8-9. WMATA, on the
other hand, emphasizes that the plain language of § 12-310(b)(4) applies to “any action brought
by the District of Columbia government,” regardless of whether the suit is brought to enforce a
public right. ECF No. 396 at 11-12. In support of this position, WMATA highlights a passage
from WASA where the court of appeals stated that § 12-310 was designed “to ensure that the
District received, at the least, the benefit of the common law principle of ‘nullum tempus.’” 851
A.2d at 414 (emphasis added). The court’s inclusion of the phrase “at the least,” WMATA
contends, suggests that § 12-310 extends beyond nullum tempus immunity. ECF No. 396 at 11.
The Court disagrees.
While WMATA’s position may find support in stray phrases from WASA, the actual
reasoning of that decision indicates that § 12-310(b)(4) only codifies nullum tempus and extends
no further. 7 Indeed, the WASA court did not simply analyze whether WASA was an agency of
the District and therefore within the scope of § 12-301’s exemption to the statute of limitations.
It instead surveyed legislative history which showed that “a purpose of the draft bill was to
‘make clear that the limitations provisions of § 12-301 and § 12-310 of the D.C. Code do not
apply to the District government when it sues to enforce public rights.’” Id. at 414 (citation
omitted). Accordingly, “in deciding what juridical entities the [D.C.] Council intended to
encompass within the phrase ‘District of Columbia government,’” the court deemed it “useful to
determine whether th[e] action brought by WASA was brought to enforce a public right.” Id.
7
Although WASA concerned D.C. Code § 12-301, which exempts “actions brought by the District of Columbia
government” from the statute of limitations, the court’s analysis is equally applicable to the statute of repose
exception for actions brought by the District codified at § 12-310(b)(4), insofar as § 12-301 and § 12-310(b)(4) use
identical language and were both enacted as part of the District of Columbia Statute of Limitations Amendment Act
of 1986. See id. at 414.
12
(emphasis added). After discussing District of Columbia case law concerning the application of
nullum tempus immunity, the court found that the “functions and activities of WASA, a separate
corporate body distinct from the District of Columbia are proprietary in nature and thus beyond
the protection of nullum tempus,” which, in turn, led the court to “hold that the phrase ‘District
of Columbia government’ in § 12-301 does not encompass the separate juridical entity of which
WASA consists.” Id. at 416. This analysis indicates that the D.C. Court of Appeals construes §§
12-301 and 12-310 as merely coextensive with, but no broader than, the principle of nullum
tempus. Subsequent decisions confirm this view. See, e.g., Solid Rock Church, 925 A.2d at
559-60 (“The law is settled that the District of Columbia, as a municipality, enjoys limited
sovereign immunity from the operation of statutes of limitation under the common law doctrine
of nullum tempus, and under D.C. Code § 12-301 (2001), while in the performance of public
functions.” (emphasis added)); D.C. Housing Auth. v. D.C. Office of Human Rights, 881 A.2d
600, 609 (D.C. 2005) (noting that § 12-301 was amended “in 1986 to ensure that the statute of
limitations does not prevent the District government from bringing suit to enforce public rights”
(emphasis added)). 8
8
It also makes good sense to exempt the District from the statutes of limitations and repose only when it sues to
enforce public rights. As the D.C. Court of Appeals explained in its discussion of the evolution of the nullum
tempus doctrine:
Like immunity from suit, the sovereign exemption from the running of time originated as a royal
privilege, and perhaps survived the Revolution more by force of habit or precedent than by reason.
. . . Ultimately, it seems, the lone explanation of historical prerogative was unsatisfactory, perhaps
because, in arbitrary fashion, it seemed to give the government a right that was withheld from the
people. . . . Therefore the Supreme Court explained in Guaranty Trust [Co. v. United States, 304
U.S. 126, 132 (1938)], that the rule expresses a legitimate public policy of preserving “public
rights, revenues, and property from injury or loss, by the negligence of public officers. And
although this is sometimes called a prerogative right, it is in fact nothing more than a reservation,
or exception, introduced for the public benefit, and equally applicable to all governments.” Thus,
the policy of protecting the lawgiver was reunited with more democratic principles, for it was
recognized that the people, as sovereign, are entitled to immunity from government functionaries’
lax prosecution of public rights. The inherent limitation of this doctrine, of course, is that the
(continued . . . )
13
iii. Does WMATA’s cross-claim against Alstom seek to enforce a public
right?
Having found that WMATA qualifies as the District government for purposes of § 12-
310(b)(4), and that § 12-310(b)(4) only applies to claims brought to enforce a public right, the
question now becomes whether WMATA’s cross-claim against Alstom seeks to enforce a public
right. The Court concludes that it does not.
The D.C. Court of Appeals discussed the “public function requirement” of nullum tempus
immunity at length in Owens-Corning:
The government enjoys immunity from the running of time only when it sues to
vindicate public rights. Thus, our task will not be complete until we have
determined whether, with respect to the particular issue on appeal, the District is
suing to vindicate a public or a proprietary right. This question is by no means an
easy one. The line between rights that accrue to the public’s benefit and those
that are ultimately proprietary to the government is a fine one, especially since
any financial loss to the government is ultimately a loss to the public fisc.
***
In [D.C. v. Weiss, 263 A.2d 638 (D.C. 1970)], where we held that the District’s
suit to recover fees [from a patient treated for tuberculosis at] a public hospital
was not barred by the statute of limitations, we said:
The District of Columbia is seeking to replenish its treasury of
money expended by a public instrumentality in the exercise of a
public function. Recovery of the funds, which will benefit the
public as a whole when applied to the continued operation of
Glenn Dale Hospital, should not be made contingent on the
diligence of public servants.
263 A.2d at 640. This passage emphasizes the expenditure of the disputed monies
by a public instrumentality, its application to a public function, and the policy
( . . . continued)
rights protected must be of a public nature, and not merely the private or proprietary interests of
particular institutions.
Owens-Corning, 572 A.2d at 401 (internal citations and footnotes omitted).
14
against allowing the laxity of public servants to erect a bar to suit. We stress,
however, that while all monies the District sues upon affect the public fisc, it does
not follow that every time the District sues for money it performs a public
function. While the line is hard to draw, it can fairly be stated that something
more is required than a naked financial interest; thus in Weiss we spoke of
replenishing the treasury of funds earmarked for the performance of a particular
public function. Where the District acquires a right of action directly related to its
duty to perform a service to the public, or to vindicate an overwhelmingly public
interest or right, a suit to recover money damages to enable the District to perform
that service is public rather than proprietary. Of course, there may be other
considerations, unique to each case, which must guide future courts in
determining whether the public function test is met.
572 A.2d at 406-407. Applying these principles, the court in Owens-Corning held that the
District’s lawsuit seeking to recover costs for the removal of asbestos from roughly 2,400 public
buildings was brought “to vindicate a public right” because the public “[u]nquestionably” had “a
profound interest in the elimination of a danger so extreme and widespread.” Id. at 396, 407.
Drawing on Owens-Corning, WMATA maintains that its cross-claim against Alstom
“seeks to protect the public at large from the negligent design defects in Alstom’s automatic train
control system.” ECF No. 353-1 at 13. WMATA also contends that this case is analogous to
Weiss because its cross-claim “seeks to replenish the public treasures of money expended, and
potential liabilities incurred, in the exercise of a public function, i.e., providing rail transportation
in the Washington, D.C. metropolitan area.” Id. at 15. Alstom responds by arguing that, in
contrast to the District’s lawsuits in Owens-Corning and Weiss, WMATA’s cross-claim “does
not seek to recover any costs incurred by the District of Columbia in eliminating a public hazard
such as asbestos or tuberculosis. Rather, WMATA seeks to recover the costs which WMATA
caused [the p]laintiffs to incur as a result of its own negligence—assuming it is found liable to
[the p]laintiffs at trial—through equitable contribution as a joint tortfeasor and contractual
indemnity of tort liability.” ECF No. 382 at 10 (emphasis in original). Noting that WMATA’s
15
recovery for contribution and indemnity necessarily depends on WMATA being found liable in
the first instance, Alstom argues that “WMATA’s suit to recover the costs of its own wrongdoing
is plainly not a public function.” Id. at 11 (emphasis in original).
The Court finds that WMATA’s cross-claim against Alstom does not enforce a public
right. 9 First, WMATA’s cross-claim bears no similarity to the claims asserted by the District in
Owens-Corning and Weiss. In both of those cases, the District took actions to secure the public
health first (i.e., removing asbestos in Owens-Corning and paying for a hospital patient’s
tuberculosis treatment in Weiss), and then filed suit to recover the costs of those actions from the
responsible parties. WMATA took no similar actions here. This is not a case, for instance,
where WMATA first expended resources on fixing Alstom’s allegedly faulty automatic train
control system, and then brought suit to recover the costs of those remedial efforts. Rather,
WMATA took no action in the first instance, the train collision occurred, and it now seeks
reimbursement from Alstom in the event that WMATA is itself found liable at trial. In other
words, rather than seeking reimbursement from a wrongdoer for proactive actions taken to
prevent public harm, WMATA seeks reimbursement for Alstom’s alleged share of the fault if
WMATA itself is deemed a wrongdoer. It is difficult to discern how the public’s rights are
vindicated by such a claim. Second, the Court views as tenuous WMATA’s argument that its
cross-claim is necessary to protect the public from the alleged defects in Alstom’s automatic
train control system. WMATA could (and should) independently evaluate the adequacy of
Alstom’s equipment, and if it is defective, take any necessary remedial steps. Its cross-claim
9
The Court notes that an exhaustive search of the case law revealed no decision, either state or federal, discussing
the applicability of nullum tempus to a state government’s claims for indemnification or contribution against a
private contractor.
16
against Alstom is not necessary to achieve that end. At most, WMATA’s cross-claim will
mitigate its own tort liability in this case, and thus will further a proprietary rather than a public
interest. While it is true that “any financial loss to the government is ultimately a loss to the
public fisc,” WMATA’s cross-claim vindicates the type of “naked financial interest” that is not
protected by nullum tempus. Owens-Corning, 572 A.2d at 406-407. Thus, because WMATA’s
cross-claim against Alstom does not enforce a public right, it does not fit the statute of repose’s
exception for claims brought by the District of Columbia government.
In sum, WMATA’s cross-claim for contractual indemnity (Count I) falls under the statute
of repose’s exception for claims based on a contract, but its cross-claim for contribution (Count
II) does not. And neither count of WMATA’s cross-claim fits the statute of repose’s exception
for claims brought by the District. Accordingly, WMATA’s motion to dismiss Alstom’s statute
of repose affirmative defense is granted in part and denied in part.
III. Ansaldo’s motion for judgment on Counts 7, 11, and 15 of the plaintiffs’ Second
Amended Master Complaint10
This motion warrants only brief discussion. In their briefings, the parties agree to the
dismissal of Count 14 (Negligent Train Traffic Control) of the plaintiffs’ Second Amended
Master Complaint because it is duplicative of Count 7. See ECF No. 390 at 1; ECF No. 394 at 1.
The Court will therefore dismiss Count 14 of the Second Amended Master Complaint.
Ansaldo also moves for judgment on Count 11 (Breach of the Implied Warranty of
Merchantability), and Count 15 (Breach of Warranty & Implied Warranty of Fitness for a
10
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) Ansaldo STS
USA Inc.’s Motion for Judgment on Counts 7, 11, and 15 of the Second Amended Master Complaint [ECF No.
367]; (2) the Plaintiffs’ Joint Opposition to Defendant Ansaldo’s Motion for Judgment on Counts 7, 11, and 15 of
the Second Amended Master Complaint [ECF No. 390] ; and (3) Ansaldo STS USA Inc.’s Reply in Support of its
Motion for Judgment on Counts 11, 14, and 15 [ECF No. 394].
17
Particular Purpose) of the Second Amended Master Complaint. The Court previously dismissed
these counts as to Alstom, holding that “where a plaintiff alleges claims for both strict products
liability and breach of implied warranties based on allegedly defective products against a party
not in privity with the plaintiff, the implied warranty claims must be dismissed because the
actions are the same.” In re Fort Totten Metrorail Cases, 793 F. Supp. 2d 133, 152 (D.D.C.
2011). In their opposition to Ansaldo’s motion, the plaintiffs merely reincorporate the arguments
that the Court previously rejected. See ECF No. 390 at 2. Accordingly, consistent with its prior
ruling, the Court will dismiss Counts 11 and 15 of the Second Amended Master Complaint as to
Ansaldo.
IV. WMATA’s motion to dismiss the equitable indemnification cross-claims against it 11
A. Introduction
In this motion, WMATA asserts that the corporate defendants’ cross-claims against it for
equitable indemnification must be dismissed because the interstate compact does not waive
WMATA’s sovereign immunity for equitable indemnification claims. The Court agrees with
WMATA and concludes that its motion must therefore be granted.
B. Background
The three corporate defendants, ARINC, Ansaldo, and Alstom, have all asserted cross-
claims for equitable indemnification against WMATA. 12 WMATA now moves to dismiss these
11
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) the
Memorandum in Support of Motion to Dismiss the Equitable Indemnification Cross-Claims Brought Against
WMATA [ECF No. 424-1]; (2) the Joint Opposition by Defendants and Cross-Plaintiffs Alstom, Ansaldo and
ARINC to WMATA’s Motion to Dismiss the Equitable Indemnification Cross-Claims Brought Against WMATA
[ECF No. 478]; and (3) the Reply Memorandum in Support of Motion to Dismiss Equitable Indemnification Cross-
Claims Brought Against WMATA [ECF No. 548].
18
cross-claims for lack of subject matter jurisdiction under Rule 12(b)(1), arguing that the
interstate compact’s waiver of sovereign immunity is limited to liability for contractual breaches
or tortious conduct occurring as a result of the performance of its non-governmental functions.
WMATA asserts that because equitable indemnity is a distinct legal claim for which immunity
was not waived, the corporate defendants’ equitable indemnification claims are barred by
sovereign immunity and must be dismissed for lack of subject matter jurisdiction. 13 The cross-
plaintiffs, however, maintain that equitable indemnity sounds in tort under District law and the
cross-claims concern tortious conduct stemming from WMATA’s proprietary functions.
WMATA replies that the cross-plaintiffs’ argument that their indemnity claims sound in tort
blurs the lines between the parties and their respective positions in this litigation.
C. Analysis
1. What is the nature of the cross-claims asserted against WMATA?
In addressing whether the corporate defendants’ cross-claims against WMATA are barred
by sovereign immunity, it is first necessary to explore the nature of an equitable indemnification
( . . . continued)
12
Count II of Defendant ARINC, INC.’s Cross-Claim Against Defendant WMATA asserts: “Should plaintiffs
recover damages against ARINC, the equities would require a shifting of responsibility from ARINC, whose product
and actions did not contribute to or cause the injuries alleged, to WMATA, whose actions and omissions were
directly responsible for the injuries alleged. It is just and fair that, as between WMATA and ARINC, WMATA
should bear the total responsibility of any losses recovered by Plaintiffs here.” ECF No. 139 ¶ 60.
Count II of the Crossclaim by Defendant Ansaldo Against Co-Defedants ARINC, Alstom, and WMATA asserts:
“Ansaldo is entitled to equitable indemnification against WMATA for all costs, fees, and damages.” ECF No. 141 ¶
28.
Count II of Defendant Alstom Signaling Inc.’s Cross-Claims Against Co-Defendants WMATA, Ansaldo and
ARINC asserts: “[I]n the event [that] Alstom is held liable to Plaintiffs under any or all of the alleged claims in the
Master Complaint, Alstom is entitled to equitable or common law indemnification from any and all cross-claim
defendants for such damages and costs awarded Plaintiffs under any or all of their claims, as available under
applicable law.” ECF No. 143 ¶ 26.
13
“Sovereign immunity is a jurisdictional issue that may be raised at any time during the course of the litigation.”
Watters, 295 F.3d at 39 n.2.
19
claim. “Although the right to indemnify may arise by contract, ‘[the District of Columbia Court
of Appeals has] recognized that the obligation to indemnify may be implied in fact (on an
implied contract theory) or implied in law in order to achieve an equitable result.’” District of
Columbia v. Wash. Hosp. Ctr., 722 A.2d 332, 340 (D.C. 1998) (quoting R. & G. Orthopedic
Appliances v. Curtin, 596 A.2d 530, 544 (D.C. 1991)). In such situations, “[a]n obligation to
indemnify exists where the equities of the case and the relationship of the parties support shifting
responsibility from one party to another.” Howard Univ. v. Good Food Servs., 608 A.2d 116,
122 (D.C. 1992); Quandrangle Dev. Corp. v. Otis Elevator Co., 748 A.2d 432, 434, n.2 (D.C.
2000) (noting the parties’ concession that their contract “did not contain any express
indemnification provision,” and concluding that “[t]herefore, their claim is one of implied
indemnification, based on equitable principles”). Stated differently, “[i]n the absence of an
express contractual duty to indemnify, a right to indemnify exists where a duty to indemnify may
be implied out of a relationship between the parties to prevent a result which is unjust.” Howard,
608 A.2d at 123; see also Johnson v. Mercedes-Benz, USA, LLC, 182 F. Supp. 2d 58, 65
(D.D.C. 2002) (“When based on equitable principles, indemnity may be granted to an indemnitee
if there is a ‘significant difference in the kind and quality’ between the indemnitee’s and the
indemnitor’s wrongdoing.” (quoting Quandrangle Dev. Corp., 748 A.2d at 435)).
WMATA maintains that the “[c]ross-claimaints’ causes of action for indemnification
against WMATA are expressly based on equity, and do not rely on a contract.” ECF No. 424-1
at 5. The corporate defendants disagree, claiming that “equitable indemnity sounds in tort under
controlling D.C. law.” ECF No. 478 at 1. The corporate defendants are incorrect. Equitable
indemnification is premised on “the equities of the case and the relationship of the parties.”
Howard Univ., 608 A.2d at 122. While the corporate defendants may be correct that determining
20
the equities in a given case will often require an examination of the “kind and quality,”
Quandrangle Dev. Corp., 748 A.2d at 435, of the tortious conduct at issue, this does not mean
that equitable indemnification sounds in tort. Rather, this examination of the tortious conduct
provides the basis from which to assess the equities. Thus, although “the [c]ross-plaintiffs’
equitable indemnification cross-claims concern WMATA’s [allegedly] tortious misconduct,”
ECF No. 478 at 10 (emphasis added), they are not tort claims. The cross-plaintiffs’ equitable
indemnification claims are based on equitable principles—not tort or contract law.
2. Has WMATA waived its sovereign immunity as to equitable indemnification
claims?
WMATA asserts that “[t]he cross-claimants cannot show the existence or applicability of
any waiver of sovereign immunity that would make WMATA amenable to suit for implied
indemnification.” ECF No. 424-1 at 7. The Court agrees.
“In signing the WMATA Compact, Maryland, Virginia, and the District of Columbia
conferred upon WMATA their respective sovereign immunities.” Beebe v. WMATA, 129 F.3d
1283, 1287 (D.C. Cir. 1997). “Although [section 12(a) of] the WMATA Compact provides that
WMATA may ‘[s]ue and be sued,’ [the Circuit has] held that provision to extend only as far as
the more specific (and partial) waiver of sovereign immunity contained in section 80 of the
Compact.” Watters, 295 F.3d at 40. In relevant part, Section 80 of the interstate compact
provides:
The Authority shall be liable for its contracts and for its torts and those of its
Directors, officers, employees and agent[s] committed in the conduct of any
proprietary function, in accordance with the law of the applicable signatory
(including rules on conflict of laws), but shall not be liable for any torts occurring
in the performance of a governmental function.
D.C. Code § 9-1107.01(80) (emphasis added).
21
“Waivers [of sovereign immunity] must be construed strictly in favor of the sovereign
and not enlarged beyond what the language requires.” Kingston Constructors, Inc. v. WMATA,
860 F. Supp. 886, 888-89 (D.D.C. 1994) (citing Library of Congress v. Shaw, 478 U.S. 310, 317,
318 (1986)). “‘There can be no consent by implication or by use of ambiguous language . . . .
The consent necessary to waive [sovereign] immunity must be express, and it must be strictly
construed.”’ Id. (quoting Shaw, 478 U.S. at 318); see also Watters, 295 F.3d at 40 (“We may
find a waiver of sovereign immunity ‘only where stated by the most express language or by such
overwhelming implications from the text as will leave no room for any other reasonable
construction.’” (quoting Morris v. WMATA, 781 F.2d 218, 221 (D.C. Cir 1986))).
Although there appear to be no cases dealing specifically with whether the WMATA
compact waives sovereign immunity for equitable indemnification claims, courts have concluded
that the compact does not waive sovereign immunity for other equitable remedies. For example,
in Martin v. WMATA, 273 F. Supp. 2d 114 (D.D.C. 2003), another judge of this Court held that
WMATA was immune from the plaintiff’s promissory estoppel claim. See id. at 119 (“Section
80’s waiver only denotes WMATA’s liability for its contracts and torts occurring in the
performance of a non-governmental function; it does not mention promissory estoppel, which is
a distinct legal theory.”). And in Watters, the Circuit determined that an attorney’s lien was not a
contract with, or tort of, WMATA. 295 F.3d at 40. The court explained that “such a lien is an
equitable device,” and is “merely a claim to equitable interference by the court to have [a]
judgment or settlement held as security.” Id. at 41 (internal quotation marks and citation
omitted). Most recently, the United States District Court for the District of Maryland held that
because “WMATA has not explicitly waived its immunity as to quasi-contract claims [such as
equitable estoppel], [it was] entitled to assert its sovereign immunity defense as to [the
22
p]laintiff’s Statute of Frauds claim.” Greenbelt Ventures, LLC v. WMATA, No. 10-cv-157,
2011 WL 2175209, at *6 (D. Md. June 2, 2011).
In light of the need to strictly construe the WMATA compact’s waiver, which only
expressly waives WMATA’s sovereign immunity for contracts and proprietary-function torts,
and considering the foregoing case law finding WMATA immune from other forms of equitable
claims, the Court concludes that WMATA has not waived its sovereign immunity as to equitable
indemnification claims. Accordingly, WMATA’s motion to dismiss is granted, and the
corporate defendants’ claims for equitable indemnification are dismissed for lack of subject
matter of jurisdiction.
V. The corporate defendants’ joint motion for summary judgment on all claims 14
A. Introduction
The corporate defendants jointly move for summary judgment on the ground that
WMATA’s alleged negligence constitutes a superseding cause that severed the causal connection
between the corporate defendants’ purported negligence and the June 22, 2009 train collision.
Because this case does not present the type of “exceptional circumstances” necessary to remove
issues of causation from the jury, the Court will deny the corporate defendants’ motion.
14
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) Defendants
Alstom, Ansaldo and ARINC’s Memorandum of Points and Authorities in Support of their Joint Motion for
Summary Judgment on All of the Plaintiffs’ Claims [ECF No. 425-1]; (2) Defendant WMATA’s Memorandum in
Opposition to the Co-Defendants’ Joint Motion for Summary Judgment [ECF No. 483]; (3) the Plaintiffs’
Opposition to Defendants Alstom, Ansaldo and ARINC’s Joint Motion for Summary Judgment [ECF No. 487]; and
(4) Defendants Alstom, Ansaldo, and ARINC’s Reply in Support of their Joint Motion for Summary Judgment on
All of Plaintiffs’ Claims [ECF No. 549].
23
B. Background 15
1. Overview of WMATA’s Metrorail System
A brief overview of two components—track circuits and the Advanced Information
Management software—that play a part in WMATA’s operation of the Metrorail system is
necessary to resolve the corporate defendants’ motion. First, to operate the Metrorail system,
“WMATA uses an [Automatic Train Control] system that consists of a series of track circuits (or
‘blocks’), each with an electronic transmitter [module], receiver [module], vital relay, and
impedance bonds.” ECF No. 425-1 at 2. Each circuit has two impedance bonds. ECF No. 483
at 3. As the corporate defendants explain (and WMATA does not dispute):
The system works by the transmitter sending an audio frequency signal through a
cable to the impedance bond at one end of the block. When no train is present, the
signal runs along the rails to the impedance bond at the other end of the block
where it travels through a cable to the receiver, thereby completing the electrical
circuit. If the circuit is completed, the relay is energized and the block reports as
unoccupied. If a train is present, however, the train’s metal wheels and axles
“short” or “shunt” the signal before it reaches the impedance bond at the receiver
end of the block, causing an interruption of the circuit that de-energizes the relay.
De-energizing of the relay indicates that a train occupies the particular block and
allows the appropriate information to be conveyed to oncoming trains in the
WMATA Metrorail system.
ECF No. 425-1 at 2-3. A “bobbing” circuit is one in which the relay signal “fluctuates between
an energized (indicating [a] vacant [circuit]) to a de-energized state (indicating [an] occupied
[circuit]) regardless of whether a train is actually present in the track circuit.” Id. at 4. A
phenomenon known as “parasitic oscillation” occurs when the transmitter module bypasses the
impedance bonds and sends a signal directly to the receiver module. In other words, parasitic
15
The following facts are undisputed unless otherwise noted.
24
oscillation is when the modules ignore the other components of the circuit and therefore convey
information that is not based on the whole circuit.
Second, WMATA’s Operations Central Control uses a software program called
Advanced Information Management, which was developed by ARINC. ECF No. 483 at 15. The
software generates alarms associated with bobbing circuits, false occupancies (i.e., always
reporting blocks), and false vacancies (i.e., never reporting blocks). Id.; see also ECF No. 425-1
at 9 (“A ‘track circuit failed vacant’ alarm means that the track circuit is reporting a vacancy
when, in fact, the track circuit may actually be occupied.”). The software designates a false
vacancy as “minor,” which means the alarm is self-acknowledging and self-deleting (i.e., that
they do not require operator attention or intervention). ECF No. 483 at 15.
2. Activity at Circuit B2-304 from June 17, 2009, until June 22, 2009
The WMATA track circuit located at the site of the collision that resulted in this litigation
is Circuit B2-304. At the time of the collision on June 22, 2009, Circuit B2-304 consisted of
Alstom transmitter/receiver modules and Ansaldo impedance bonds. Id. at 3.
On June 17, 2009, WMATA replaced an Alstom impedance bond at Circuit B2-304 with
an Ansaldo impedance bond. ECF No. 425-1 at 4. WMATA protocol calls for a “shunt
verification test” after the installation of an impedance bond. Id. The test is conducted by laying
a shunt strap between the rails. ECF No. 483 at 4. If the relay detects the presence of the shunt
strap and interprets it as a train, the circuit is considered to have passed the shunt verification
test. Id. The leader of the WMATA work crew that installed the impedance bond at Circuit B2-
304 on June 17, 2009, has testified that she did not observe bobbing when the shunt verification
test was being conducted, but stated that she observed that the circuit was bobbing after she
completed the shunt verification test. Id. at 10.
25
After the WMATA work crew left the site, WMATA’s Maintenance Operations Center
opened a work order for the bobbing at Circuit B2-304. ECF No. 425-1 at 7. Despite the work
order, and visits by different work crews to Circuit B2-304 on June 18, 19, and 22, 2009, Circuit
B2-304 was still bobbing when the collision occurred on June 22, 2009. Id. at 7-8. And, no one
at WMATA had instituted an “absolute block”—closing down specific locations of track into
which no train would be permitted to enter—while Circuit B2-304 was bobbing.
3. The Advanced Information Management System Alarms
Between June 17 and 22, 2009, the Advanced Information Management system generated
“hundreds and hundreds” of “track circuit failed vacant” alarms on the Red Line in the area
between the Takoma and the Fort Totten Metrorail stations. ECF No. 425-1 at 9. In the hour
before the June 22, 2009 collision, the Advanced Information Management system generated
seventeen separate “track circuit failed vacant” alarms. Id. Indeed, two minutes before the
collision, while the train that was struck was stopped between the Takoma and Fort Totten
stations, the system generated a “track circuit failed vacant” alarm for that area of the track. Id.
at 9-10. WMATA did not have a protocol at its Operations Central Control for responding to a
failed vacant alarm, and neither controller on duty at the time of the collision instituted an
absolute block in response to the failed vacant alarm. Id. at 10.
C. The Parties’ Arguments
In moving for summary judgment, the corporate defendants maintain that “[t]he key
undisputed fact is that WMATA placed a known, malfunctioning track circuit in service,
contrary to its own policies.” ECF No.425-1 at 11. The corporate defendants further assert that
“[e]ven if the Court found Alstom, Ansaldo, or ARINC’s equipment to be defective, or that there
was a lack of safety testing, WMATA’s reckless actions were the superseding cause of the
26
accident, thereby relieving Alstom, Ansaldo, and ARINC of all liability as a matter of law.” Id.
at 12. WMATA and the plaintiffs disagree. Specifically, WMATA argues that it viewed
bobbing track circuits as a maintenance, rather than a safety, issue, ECF No. 483 at 2, and that its
work crews were consequently unaware of the actual hazard at Circuit B2-304. Accordingly,
WMATA asserts that there are questions of fact “about whether WMATA responded in a manner
that was reasonable and foreseeable under the circumstances.” Id. The plaintiffs assert that from
each of the corporate defendants’ “particular positions,” “it was foreseeable that WMATA might
fail to remediate [the corporate defendants’] negligence.” ECF No. 487 at 7-8. As a result, the
plaintiffs maintain, WMATA’s negligence does not absolve the corporate defendants of liability.
Id.
D. Analysis
1. Can the Court conclude that, as a matter of law, WMATA’s negligence was a
superseding or intervening cause that precludes the corporate defendants’
liability?
“Proximate cause has been defined as that cause which, in natural and continual
sequence, unbroken by any efficient intervening cause, produces the injury, and without which
the result would not have occurred.” Convit v. Wilson, 980 A.2d 1104, 1125 (D.C. 2009).
“Superseding cause is a subset of the inquiry into proximate cause,” id. at 1125-26, and
essentially it is “a concept that the action of a subsequent tortfeasor may be a superseding cause
which breaks the chain of causation and relieves the first tortfeasor of liability to the injured
party,” id. at 1126. “The question of proximate causation . . . is at base one of foreseeability.”
Rieser v. District of Columbia, 563 F.2d 462, 479 (D.C. Cir. 1977). “If a negligent, intentional
or even criminal intervening act or end result was reasonably foreseeable to the original actor, his
liability will not ordinarily be superseded by that intervening act.” Id.
27
As even the corporate defendants acknowledge, proximate causation is ordinarily a
question of fact for the jury. See ECF No.425-1 at 22. Indeed, the cases are legion holding that
it is only the “exceptional case” in which questions of proximate cause “pass from the realm of
fact to one of law.” Majeska v. District of Columbia, 812 A.2d 948, 950 (D.C. 2002) (emphasis
added); accord Rieser, 563 F.2d at 480 (“Proximate causation, including the question of
superseding cause, . . . is ordinarily a question of fact for the jury.”); Smith v. Hope Village, Inc.,
481 F. Supp. 2d 172, 185 (D.D.C. 2007) (Walton, J) (citing cases).
This case is not so exceptional as to warrant removing the determination of causation
from the jury. Compare, for example, the facts of this case to that in In re Korean Air Lines
Disaster, No. 83-cv-0345, 1985 WL 9447 (D.D.C. Aug. 2, 1985), which the corporate defendants
cite in support of their motion. In Korean Air, a jet owned and operated by Korean Air Lines
inadvertently veered into the airspace of the Soviet Union and was intentionally shot down by
Soviet missile attack. Id. at *1. The parties had conceded defects in the plane’s navigational
systems, and the sole question before the court was the foreseeability of the Soviet Union’s
actions. Id. The Court ruled that the defendants, manufacturers of the plane’s navigational
systems, could not “be held liable for the unexpected act of aggression by the Soviet Union.” Id.
at *7.
Here, in contrast to the Soviet Union’s deliberate launching of missiles in In re Korean
Air, WMATA’s alleged superseding acts were merely negligent, not intentional. Such negligent
acts are not so unforeseeable that the corporate defendants can be absolved of liability as a matter
of law. On the contrary, a reasonable jury could conclude that the corporate defendants should
have foreseen that WMATA would fail to take action on a work order for five days, despite
WMATA’s own policies to respond to a work order, carry out the task it involves, and close the
28
order within one business day of completion of the work. See ECF No. 425-1 at 7. A reasonable
jury could also conclude that the corporate defendants—specifically, ARINC—should have
foreseen that WMATA would ignore the “track circuit failed vacant alarms” in the days, hours,
and minutes preceding the collision. Accordingly, because this is not a case where the proximate
cause determination should “pass from the realm of fact to one of law,” Majeska, 812 A.2d at
950, the corporate defendants’ motion for summary judgment on all claims and cross-claims
against them is denied.
VI. Ansaldo’s Motion for Summary Judgment 16
A. Introduction
Ansaldo moves for summary judgment as to all claims on the following grounds: (1) it is
entitled to derivative sovereign immunity because all of the claims against it stem from
WMATA’s “immune decision” to sequence the installation of Ansaldo’s impedance bonds and
modules; (2) there is no evidence that Ansaldo’s impedance bonds and Alstom’s modules were
incompatible; (3) the failure to warn claims against Ansaldo fail because (a) there is no duty to
warn about another manufacturer’s (i.e., Alstom) products, and (b) WMATA is a “sophisticated
user” to which Ansaldo owed no duty to warn; and (4) the derivative counts of wrongful death
and survival must be dismissed if the underlying counts are dismissed.
16
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) Ansaldo STS
USA, Inc.’s Memorandum of Points and Authorities in Support of its Motion for Summary Judgment [ECF No. 426-
1]; (2) Defendant WMATA’s Memorandum in Opposition to Defendant Ansaldo STS USA, Inc.’s Motion for
Summary Judgment [ECF No. 480]; (3) Defendant Alstom Signaling Inc.’s Opposition to Ansaldo STS USA, Inc.’s
Motion for Summary Judgment [ECF No. 481]; (4) the Plaintiffs’ Opposition to Defendant Ansaldo STS USA,
Inc.’s Motion for Summary Judgment [ECF No. 482]; and (5) Ansaldo STS USA, Inc.’s Reply to the Opposition
Briefs Submitted by Plaintiffs, Washington Metropolitan Transit Authority, and Alstom Signaling, Inc. to Ansaldo’s
Motion for Summary Judgment [ECF No. 550].
29
The Court concludes that (1) Ansaldo’s attempt to invoke derivative sovereign immunity
fails as a matter of law because the claims against it do not relate to any “immune” decisions
made by WMATA; instead, the claims assert that Ansaldo breached its contractual obligations to
WMATA and that Ansaldo performed under the contract negligently; (2) Ansaldo’s argument
that there is no evidence of incompatibility is essentially a causation issue that must be decided
by a jury; (3) Ansaldo did have a legal duty to warn WMATA; and (4) the derivative counts
should not be dismissed because the underlying counts remain. Accordingly, the Court denies
Ansaldo’s motion in its entirety.
B. Background
As explained above, WMATA employs an “automatic train control system” to ensure
safe train detection, separation, and speed restrictions. ECF No. 480 at 3. This system is
comprised of “track circuits,” which are railroad segments of varying lengths. Id. Two
impedance bonds are located on each track circuit. Id. The impedance bonds communicate via
transmitters and receivers called “modules,” which are located at the nearest station in an
unmanned train control room. Id.
Communication between the impedance bonds and the modules is accomplished by
transmitter and receiver modules that exchange audio-frequency signals. Id. A train’s presence
on the track is sensed when its wheels and axles cause a short between the rails. Id. This is
known as a “shunt.” Id. A “shunt” causes a vital relay, which is connected to the modules, to
de-energize or “drop.” Id. Otherwise, the relay remains energized, or “picked,” when a track
circuit is actually vacant. Id.
Alstom designed WMATA’s original automatic train control system in the 1970s,
including its impedance bonds and modules. Id. at 3-4. Beginning in 2002, WMATA contracted
30
with Ansaldo to replace the Alstom impedance bonds and modules with Ansaldo products. Id. at
4. Two separate contracts were executed by the parties. ECF No. 426-1 at 15. Under the first
contract, Ansaldo was originally required to replace the impedance bonds and modules
simultaneously. Id. However, due to safety concerns about non-WMATA personnel working on
the tracks, WMATA altered the replacement process as follows: first, only WMATA employees
would replace the impedance bonds; second, WMATA employees would conduct a safety test of
the track circuit; and third, Ansaldo employees would replace the modules and conduct another
safety test of the track circuit. Id. at 15; ECF No. 480 at 5. This change in the replacement
project resulted in a temporarily “mixed track circuit” consisting of the old Alstom modules and
the new Ansaldo impedance bonds. ECF No. 480 at 5.
The second contract, which covered track circuit replacements at 22 locations throughout
WMATA’s system, reflected this “temporary mixed track circuit configuration.” Id.
Specifically, the contract provided that “WMATA personnel will perform all wayside installation
[of the Ansaldo] impedance bonds,” and that Ansaldo “will replace [the Alstom] . . . modules
[with Ansaldo modules] after the associated wayside equipment has been installed.” ECF No.
480-9 (Contract No. F05143) § 1.01.C (emphasis added). Recognizing that, as a result of this
revised replacement process, “[n]ew impedance bonds will temporarily be in service with
existing [Alstom] . . . modules,” the contract directed that the Ansaldo “impedance bonds being
provided on this Contract must be compatible with the existing [Alstom] . . . modules.” Id.
(emphasis added). The contract also required Ansaldo to provide a “Hazard Mode and Effect
Analysis, which, as a minimum, identifies one example of each hazard that may be produced by
each possible failure in [Ansaldo’s] equipment and software.” Id. § 1.06. Finally, the contract
provided that “[t]he system shall be proven by [Ansaldo] to be fail safe and operational upon
31
completion of the installation.” Id. § 1.01.A. In the context of a public transit railroad, the term
“fail safe” means that “if a vital component fails, the system will automatically revert to a less
permissive state which restricts the movement of trains.” ECF No. 480-1 at 2.
According to WMATA, despite Ansaldo’s “contractual requirement to provide
compatible equipment,” Ansaldo “took no actions whatsoever to evaluate the safety of using its
[impedance] bonds with Alstom’s modules.” ECF No. 480 at 7-8. WMATA further claims that
prior to the June 22, 2009 Fort Totten train collision, Ansaldo became aware of specific
compatibility problems with the Ansaldo impedance bonds and Alstom modules, but did nothing
to address them. See id. at 8-9.
The track circuit at issue in this case, Circuit B2-304, contained a mixed configuration of
Ansaldo impedance bonds and Alstom modules when the accident occurred. Id. at 9. In seeking
to explain the cause of the June 22, 2009 train collision, WMATA contends that a latent defect in
the automatic train control system known as “parasitic oscillation” caused a signal to be
transmitted which falsely indicated that Circuit B2-304 was vacant. Id. at 2-3. This, in turn, led
Train No. 112 to crash into Train No. 214. Id. WMATA argues that power increases required
by the installation of the new Ansaldo impedance bonds “created the conditions necessary for the
parasitic oscillation to pass through the rack structure, couple to the receiver, and mimic the track
vacant signal.” Id. at 13.
C. Analysis
1. Is Ansaldo entitled to derivative sovereign immunity under Yearsley v. W.A.
Ross Construction Co., 309 U.S. 18 (1940)?
Ansaldo asserts that all of the claims and cross-claims against it “stem from WMATA’s
decision to sequence the timing of bond and module installation,” which led to track circuits
32
temporarily consisting of Ansaldo impedance bonds and Alstom modules, and that this decision
of WMATA is protected by sovereign immunity. ECF No. 426-1 at 14. Ansaldo further
contends that because it “followed WMATA’s safety and scheduling directions, as required by
its contract with WMATA,” it is entitled to “derivative sovereign immunity” under Yearsley v.
W.A. Ross Construction Co., 309 U.S. 18 (1940), and its progeny. Id. at 14-15.
In Yearsley, the Supreme Court considered whether a contractor that built dikes in the
Missouri River pursuant to a contract with the federal government could be held liable for
damage caused by the construction of the dikes. See 309 U.S. at 19-20. The contract was part of
a federal project “authorized by an Act of Congress.” Id. at 19. The Court concluded that the
contractor could not be held liable, reasoning that when the “authority to carry out [a] project [is]
validly conferred, that is, [when] what [is] done was within the constitutional power of Congress,
there is no liability on the part of the contractor for executing [Congress’s] will.” Id. at 20-21.
The Court observed, however, that “[w]here an agent or officer of the Government purporting to
act on its behalf has been held to be liable for his conduct causing injury to another, the ground
of liability has been found to be either that he exceeded his authority or that it was not validly
conferred.” Id. at 21.
Federal courts have construed Yearsley as creating the so-called “doctrine of derivative
sovereign immunity.” McMahon v. Presidential Airways, Inc., 502 F.3d 1331, 1343 (11th Cir.
2007). To claim such immunity, a private contractor generally must show that (1) it “was
working pursuant to the authorization and direction of the federal government,” and (2) “the acts
of which the plaintiff complained fell within the scope of those government directives.” In re
World Trade Center Disaster Site Litig., 521 F.3d 169, 196 (2d. Cir. 2008) (citing Yearsley, 309
U.S. at 20-21).
33
Several initial hurdles impede Ansaldo’s efforts to invoke the Yearsley doctrine in this
case. First, no court in this Circuit has applied the doctrine. Second, the Circuits that have
applied it are not in consensus regarding the doctrine’s requirements. 17 Third, because it is a
federal common law doctrine, Yearsley has been almost exclusively applied in cases involving
federal government contractors (as was the case in Yearsley itself), and the question of whether
WMATA can be deemed a federal agency is unresolved. See Elcon Enterp. v. WMATA, 977
F.2d 1472, 1480 (D.C. Cir. 1992) (declining to resolve the issue). One could plausibly argue,
then, that the Yearsley doctrine does not apply to WMATA’s contractors because they do not
contract directly with the federal government. Nevertheless, even assuming that all of these
preliminary issues are resolved in Ansaldo’s favor, the Court finds that it is not entitled to
derivative sovereign immunity under Yearsley for the following reasons.
The Yearsley doctrine is subject to two important limitations. First, “a key premise of
Yearsley, and one that has been reiterated by [various federal courts] is that the contractor was
following the sovereign’s directives.” Chesney v. Tenn. Valley Auth., 782 F. Supp. 2d 570, 582
(E.D. Tenn. 2011) (citing, among others, Yearsley, 309 U.S. at 20-21). “While Yearsley
established that a private corporation performing governmental functions pursuant to
17
For example, the Circuits disagree as to whether the contractor must show a common law agency relationship with
the government to avail itself of derivative sovereign immunity. Compare McMahon, 502 F.3d at 1343 (“[T]he
entity claiming the immunity must at a bare minimum have been a common law agent of the government at the time
of the conduct underlying the lawsuit.”), and In re Hanford Nuclear Reservation Litig., 534 F.3d 986, 1001 (9th Cir.
2008) (“The [Yearsley] Court limited the applicability of the defense to principal-agent relationships where the
agent had no discretion in the design process and completely followed government specifications.”), with Ackerson
v. Bean Dredging LLC, 589 F.3d 196, 205-206 (5th Cir. 2009) (“The Supreme Court’s decision in Yearsley does not
require a public-works contractor defendant to establish a traditional agency relationship with the government.”),
and Butters v. Vance Intern., Inc., 225 F.3d 462, 466 (4th Cir. 2000) (citing Yearsley for the principle that
“contractors and common law agents acting within the scope of their employment for the United States have
derivative sovereign immunity” (emphasis added)).
34
contractually delegated authority will not be liable in tort to third parties, it also acknowledged
that an agent or officer of the Government purporting to act on its behalf, but in actuality
exceeding his authority, shall be liable for his conduct causing injury to another.” In re KBR,
Inc., 736 F. Supp. 2d 954, 967 (D. Md. 2010) (citing Yearsley, 309 U.S. at 21); accord Myers v.
United States, 323 F.2d 580, 583 (9th Cir. 1963) (“To the extent that the work performed by [the
federal contractor defendant] was done under its contract with the Bureau of Public Lands, and in
conformity with the terms of said contract, no liability can be imposed upon it for any damages
claimed to have been suffered by the appellants.” (citing Yearsley, 309 U.S. at 18) (emphasis
added)). Second, derivative sovereign immunity is not available to contractors who act
negligently in performing their obligations under the contract. See Ackerson, 589 F.3d at 207
(indicating that a contractor that commits a “separate act of negligence” is not entitled to
derivative sovereign immunity under Yearsley); City of Worcester v. HCA Mgmt. Co., 753 F.
Supp. 31, 38 (D. Mass. 1990) (Yearsley does not apply “when a private corporation who
performs governmental duties pursuant to contractual authority from the government is sued for
negligence in the performance of these duties.”).
In assessing whether Ansaldo is entitled to derivative sovereign immunity under the
foregoing principles, it is first necessary to identify the conduct of Ansaldo that is being
challenged by the plaintiffs and cross-plaintiffs (WMATA and Alstom). The parties, not
surprisingly, disagree as to what that conduct is. According to Ansaldo, all of the claims and
cross-claims against it arise from WMATA’s “safety and scheduling decision to sequence the
installation of bonds and modules,” a decision which Ansaldo claims is protected by sovereign
immunity. ECF No. 550 at 1. The plaintiffs and cross-plaintiffs, on the other hand, argue that
the claims against Ansaldo are predicated not on WMATA’s decision to sequence the installation
35
of the impedance bonds and modules, but rather on Ansaldo’s breach of its contractual
obligations and its negligence in performing those obligations. See ECF No. 480 at 18; ECF No.
481 at 11; ECF No. 482 at 33-35. The Court agrees with the plaintiffs and cross-plaintiffs.
Ansaldo’s derivative sovereign immunity argument mischaracterizes the nature of the
claims and cross-claims being asserted against it. As previously noted, the operative contract
between Ansaldo and WMATA required Ansaldo to ensure that its impedance bonds were
“compatible” with the existing Alstom modules, in recognition of the fact that the “[n]ew
impedance bonds will temporarily be in service with existing [Alstom] . . . modules.” ECF No.
480-9 (Contract No. F05143) § 1.01.C. The contract also required Ansaldo to perform a Hazard
Modes and Effects Analysis and safety testing on the track circuit to ensure that it was “fail
safe.” See id. §§ 1.06, 1.01.A. The plaintiffs assert that Ansaldo negligently failed to perform
safety and compatibility testing in violation of its contractual obligations and applicable
standards of care, and that Ansaldo failed to warn WMATA about various issues related to the
mixing of the Ansaldo and Alstom products. See ECF No. 482 at 1-2. Similarly, WMATA’s
cross-claim asserts that Ansaldo breached its contractual obligations to WMATA and acted
negligently by failing to ensure the compatibility of the Ansaldo and Alstom products, and by
failing to perform the requisite safety testing. See ECF No. 480 at 18. Thus, the very premise of
these claims is that Ansaldo acted against the “will of the sovereign” by breaching its contractual
duties to WMATA and by performing negligently under the contract. 18 Derivative sovereign
18
To be clear, although WMATA and the plaintiffs allege that Ansaldo breached its contractual obligations, they do
not appear to assert breach of contract claims against Ansaldo. Instead, they rely upon Ansaldo’s purported breach
of contract in support of their negligence claims. See, e.g., ECF No. 140 ¶ 93 (“If WMATA is found liable to the
[p]laintiffs, WMATA submits that Ansaldo’s . . . negligent . . . performance of the duties it assumed under Contract
No. F05143/EAC . . . [was a] direct contributing and proximate cause[] of such liability.”).
36
immunity under Yearsley does not shield such claims. See Yearsley, 309 U.S. at 20-21;
Ackerson, 589 F.3d at 207; Myers, 323 F.2d at 583; City of Worcester, 753 F. Supp. at 38.
Indeed, the fact that WMATA, the purportedly sovereign entity, is seeking to impose liability
upon Ansaldo undermines its attempt to invoke derivative immunity.
Ansaldo nonetheless maintains that all of its alleged liability in this case flows from
WMATA’s “immune decision” to sequence the replacement of the impedance bonds and
modules, noting that “[]Ansaldo would not be in this case if WMATA had not made the
protected decision to use []Ansaldo bonds for a short period of time with the defective []Alstom
modules.” ECF No. 550 at 2-3. This argument confuses the issues. True, it was WMATA’s
decision to temporarily use Ansaldo impedance bonds and Alstom modules on the same track
circuit. But after WMATA made that decision, the plaintiffs and WMATA contend that Ansaldo
contractually guaranteed that those two products would be “compatible” and that it would
conduct certain tests to ensure their safe operation. The claims against Ansaldo alleging that it
acted negligently in performing its contractual obligations thus do not challenge WMATA’s
purportedly “immune decision,” but instead concern Ansaldo’s voluntary conduct after that
decision was made. Consequently, Ansaldo is not entitled to derivative sovereign immunity
under Yearsley as to these claims.
2. Can Ansaldo be held liable for the alleged incompatibility between its
impedance bonds and Alstom’s track circuit modules?
i. Is there evidence from which a reasonable jury could infer that the
alleged incompatibility played a role in causing the collision?
Ansaldo argues that summary judgment should be granted in its favor because “[n]on-
defective [Alstom] track circuit modules are compatible with [Ansaldo] impedance bonds” and
because “lack of ‘compatibility’ did not cause the crash.” ECF No. 426-1 at 23. Ansaldo
37
continues: “Nothing . . . is compatible with a dangerous, oscillating track circuit module and no
impedance bond can ever mitigate the dangers associated with track circuit modules that break
into parasitic oscillations.” Id. Ansaldo thus strenuously maintains that “compatibility issues
were not the cause of the accident.” Id. There is sufficient evidence, however, from which a
reasonable jury could conclude that, even if the parasitic oscillation was the sole cause of the
June 22, 2009 collision, Ansaldo’s bonds contributed to the oscillation.
For example, as noted above, WMATA argues that power increases required by the
installation of the new Ansaldo impedance bonds “created the conditions necessary for the
parasitic oscillation to pass through the rack structure, couple to the receiver, and mimic the track
vacant signal.” ECF No. 480 at 13; see also id. at 36 (“The need to increase power levels when
Ansaldo bonds were installed is a significant factor in explaining how the incompatibility of the
Ansaldo equipment contributed to the loss of train detection at [Circuit] B2-304.”). Indeed, one
of Alstom’s expert witnesses, Dr. Duncan Glover, has provided testimony on the “many
electrical differences between” the Alstom bonds that were replaced with the Ansaldo bonds, and
has explained that one of these differences—bondline impedance—is “important because the
lower impedance of the Ansaldo bond draws more current from the module, which in turn makes
the transistors within the module more likely to oscillate.” ECF No. 481 at 4; see also ECF No.
481-1 ¶ 247 (“Q. Will a lower impedance make a transistor work harder? A. For the same power
level setting? Q. Yes. A. If the power level . . . setting were the same and the impedance
looking into the bond were lower, it would require more current to achieve the same voltage
level. . . . [H]igher currents could make those parasitics have a higher magnitude.”). There is
thus a dispute of fact as to whether Ansaldo’s impedance bonds played a role in the parasitic
oscillation that Andsaldo vigorously claims was the sole cause of the collision. While Ansaldo
38
may attempt to frame the issue in terms of questioning whether there is sufficient evidence of
compatibility, see ECF No. 426-1 at 22, 24, Ansaldo’s compatibility arguments are nothing more
than claims that their bonds played no part in causing the collision. And, as has been set forth
earlier in this Memorandum Opinion, it is only the “exceptional case” in which questions of
proximate cause “pass from the realm of fact to one of law.” Majeska, 812 A.2d at 950
(emphasis added).
ii. Is there evidence from which a reasonable jury could conclude that
Ansaldo’s conduct breached a duty of care?
Ansaldo maintains that even if there is evidence of incompatibility, the claims relating to
that incompatibility must fail because Ansaldo’s expert is the only expert in the case to have
cited “any industry recognized definition relating to the compatibility of track circuit
equipment.” ECF No. 426-1 at 26. That expert, of course, testified that Ansaldo breached no
duty of care regarding compatibility. See, e.g., ECF No. 426-2 ¶¶ 156-57 (describing the
testimony of Professor Mark Horenstein).
“The plaintiff in a negligence action bears the burden of proof on three issues: ‘the
applicable standard of care, a deviation from that standard by the defendant, and a causal
relationship between that deviation and the plaintiff’s injury.’” Toy v. District of Columbia, 549
A.2d 1, 6 (D.C. 1988) (quoting Meek v. Shepard, 484 A.2d 579, 581 (D.C. 1984)). “Thus, at the
outset, to establish a prima facie negligence case, the plaintiff must prove that the defendant
deviated from the applicable standard of care.” Toy, 549 A.2d at 6. From these legal
requirements, Ansaldo asserts that “the definition of ‘compatible,’ and the appropriate standard
for compatibility testing, are matters that must be established by expert testimony.” ECF No.
426-1 at 28. This, however, puts too fine a point on the standard of care burden of proof. For
39
example, in Caldwell v. Bechtel, 631 F.2d 989 (D.C. Cir. 1980), the court explained that “the
analysis of both [the appellee] and the district court is overly reliant upon contract theory to the
point of losing focus of the nature of the claim made here, which asserts negligence, rather than
breach of contract.” Id. at 996-97. In Bechtel, the plaintiff was a worker who had contracted a
lung condition while working in the construction of a Metrorail tunnel. WMATA had contracted
with Bechtel, a consultant, to ensure safe working conditions during the course of construction.
The Circuit assessed “whether the contractual authority vested in Bechtel with respect to job site
safety regulations created a special relationship between Bechtel and [the plaintiff/appellant]
under with Bechtel owed a duty to take reasonable steps to protect him from foreseeable risk.”
Id. at 993. Bechtel asserted it owed the duty only to WMATA, not to the actual workers, an
argument rejected by the Circuit:
The duties that Bechtel undertook in its contract with WMATA are relevant to
this case, not because they illustrate Bechtel’s point that a contractual duty was
owed only to WMATA, but because by assuming a contractual duty to WMATA,
Bechtel placed itself in the position of assuming a duty to appellant in tort. The
particular circumstances of this case, including the Bechtel-WMATA contract,
Becthel’s superior skills and position, and Bechtel’s resultant ability to foresee the
harm that might reasonably be expected to befall appellant, created a duty to take
reasonable steps to prevent harm to appellant.
Id. at 997; see also Long v. District of Columbia, 820 F.2d 409, 418 (D.C. Cir. 1988) (“Like
Bechtel, PEPCO entered into a contract to perform services within its field of expertise; PEPCO
thereby acquired a duty to foreseeable plaintiffs (in this case, members of the travelling public)
to perform these services with reasonable care.”)
As in Bechtel, the Ansaldo-WMATA contract supplies only the basis of the duty of care
and does not determine the standard of care required by that duty. In other words, while the
compatibility of the circuit parts is relevant, the more pressing inquiry is how Ansaldo undertook
40
and fulfilled its contractual duties, including, but not limited to, its assessment of compatibility.
Although expert testimony may be required in a breach of contract action to ascertain the
meaning of compatibility between track circuit parts, the expert testimony here concerns the
standard of care resulting from the tort duty owed by Ansaldo to WMATA. And WMATA,
Ansaldo, and the plaintiffs have all provided expert testimony as to the safety analyses that
should have been employed by Ansaldo. See ECF No. 480 at 29; ECF No. 482 at 38.
Accordingly, the Court rejects Ansaldo’s argument that evidence regarding the applicable
standard of care is lacking.
3. Does the failure to warn claim against Ansaldo fail as a matter of law?
i. Did Ansaldo have a duty to warn?
“The threshold question in a failure-to-warn case is ‘whether a duty to warn exists.’”
McNeal v. Hi-Lo Powered Scaffolding, Inc., 836 F.2d 637, 641 (D.C. Cir. 1988) (quoting Hull v.
Eaton Corp., 825 F.2d 448, 454 (D.C. Cir. 1987)). “In the District of Columbia that
determination turns on whether the manufacturer knew or should have known of a danger
sufficiently serious to require a warning.” McNeal, 836 F.2d at 641 (internal quotation marks
and citation omitted). “A plaintiff need not show that there was a manufacturing defect in order
to recover: a product can be perfectly made and still require directions or warnings on proper use
in order to be safe.” Id. (internal quotation marks and citation omitted). “[P]revious decisions
[of the District of Columbia Court of Appeals] indicate that fact-intensive issues concerning the
existence of a duty to warn and whether the warning was sufficiently specific to discharge the
duty are generally reserved for the jury and may be resolved as a matter of law only when the
evidence would not permit differences of opinion by reasonable jurors.” East Penn. Mfg. v.
Pineda, 578 A.2d 1113, 1115 (D.C. 1990).
41
Ansaldo argues that it did not have a duty to warn because it was merely the seller of a
component part. See ECF No. 426-1 at 39. Ansaldo asserts that “[i]t had no duty to warn
WMATA of dangers arising from the use of a product from another manufacturer that had been
in use in the WMATA system for 35 years [i.e., the Alstom modules].” Id. Here, again,
Ansaldo’s argument is premised on its assertion that the sole cause of the collision was the
parasitic oscillation between the Alstom modules. This misses the point. It is undisputed here
that Ansaldo was aware that its impedance bonds would be paired with Alstom modules. And
there is a factual dispute as to the type of safety analyses undertaken by Ansaldo in ensuring the
compatibility of its bonds with Alstom’s modules and, similarly, disputes as to Ansaldo’s
knowledge regarding the possible hazards attendant to the mixed configuration track circuits.
See ECF No. 480 at 41. Accordingly, in light of the factual disputes as to Ansaldo’s actions and
knowledge regarding mixed track circuits, the question of Ansaldo’s duty to warn is proper for
decision by a jury. See East Penn. Mfg., 578 A.2d at 1115.
ii. Can the Court conclude as a matter of law that WMATA was a
“sophisticated user” that should have known about the defect, thus
absolving Ansaldo of any duty to warn?
In the alternative, Ansaldo argues that even if it did have a duty to warn, its duty was
negated by the fact that WMATA was a sophisticated user. ECF No. 426-1 at 39, 41-44. “[T]he
‘experienced user’ exception to the duty to warn is properly viewed as a form of the ‘knowledge
of danger’ rule.” East Penn Mfg., 578 A.2d at 1120. And “[b]ecause it focuses on actual or
constructive knowledge—what the user knew or reasonably should have known—the
applicability of the ‘experienced user’ exception to the duty to warn is a question of fact for the
jury when the extent of the [user’s] knowledge is in dispute.” Id.
42
Here, as the plaintiffs point out, the WMATA-Ansaldo contract, in which Ansaldo was
expressly informed that the bonds would be used in mixed configuration circuits and tasked with
ensuring compatibility, suggests that WMATA was relying on Ansaldo’s expertise—not that
Ansaldo could rely on WMATA’s expertise. See ECF No. 482 at 42. Indeed, “WMATA
disputes Ansaldo’s arguments that [its knowledge was] superior to [Ansaldo,] the designer and
manufacturer of track circuit signaling components.” ECF No. 480 at 41; see also ECF No. 480-
1 ¶ 116 (collecting deposition testimony from various WMATA engineers and technicians as to
their knowledge of parasitic oscillation and the attendant safety concerns). Accordingly, in light
of the factual disputes regarding the knowledge and expertise of the user, the Court cannot
decide as a matter of law that WMATA was a sophisticated user, thus obviating Ansaldo’s duty
to warn.
4. The derivative claims of wrongful death and survival
Because the underlying counts are not being dismissed, Ansaldo is not entitled to
summary judgment on the derivative claims of wrongful death and survival based upon the non-
existence of the required substantive claims.
43
VII. Alstom’s Motion for Summary Judgment 19
A. Introduction
In this motion for summary judgment, Alstom notes that the Court’s June 22, 2011
Memorandum Opinion dismissed all claims against Alstom in its capacity as a designer of the
track equipment as time-barred under the District’s statute of repose. Relying on this ruling,
Alstom asserts that all of the claims and cross-claims against it are, at root, design defect claims
and must fail. Alternatively, Alstom argues that, even if the failure to warn claims are not barred
on the basis of being design defect claims, it had no duty to warn. Next, Alstom asserts that
because there is no basis for finding it liable for the June 22, 2009 collision, it is entitled to
summary judgment on the plaintiffs’ derivative wrongful death and survival statute claims, the
co-defendants’ contribution cross-claims, and WMATA’s contractual indemnification cross-
claim.
The Court concludes that because its June 22, 2011 Memorandum Opinion explicitly
found that Alstom could be found liable in its role as a manufacturer and seller—as opposed to
designer—the statute of repose does not bar the plaintiffs’ remaining claims. The Court further
finds that there are disputed issues of fact as to (1) when Alstom became aware of the parasitic
oscillation in its modules, and (2) whether a letter sent by Alstom can be construed as a warning.
And because the claims asserting primary liability against Alstom remain, there is no basis for
19
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) Defendant
Alstom Signaling, Inc.’s Memorandum of Points and Authorities in Support of its Motion for Summary Judgment
[ECF No. 427-1]; (2) Ansaldo STS USA, Inc.’s Opposition to Alstom Signaling, Inc.’s Motion for Summary
Judgment [ECF No. 479]; (3) the Plaintiffs’ Opposition to Defendant Alstom Signaling Inc.’s Motion for Summary
Judgment [ECF No. 484]; (4) WMATA’s Memorandum in Opposition to Alstom Signaling, Inc.’s Motion for
Summary Judgment [ECF No. 485]; and (5) Alstom’s Reply in Support of its Motion for Summary Judgment [ECF
No. 551].
44
dismissing the derivative claims against it. Accordingly, Alstom’s motion for summary
judgment is denied in its entirety.
B. Background
In addition to information set forth above about the general history of WMATA (e.g., the
Metrorail system’s construction in the 1970s), and the structure and components of the
Automatic Train Control system, two other pieces of undisputed background are important to the
resolution of this motion. First, in a September 7, 2004 letter sent marking the recent celebration
by Alstom of its 100th year of business, Alstom represented that “over the past two years, there
has been an increasing trend of extraordinary events involving Alstom electromechanical
products that we feel is critical now to discuss with our customers.” ECF No. 484 at 8. Second,
in 2005, “in a tunnel near [WMATA’s] Rosslyn [Metrorail] station, three WMATA trains nearly
[collided] because there was a loss of shunt that led to trains being given maximum speed
commands.” Id. at 12. Then, about a week later, WMATA identified a track circuit near its
Silver Spring station that was similarly failing to detect trains. Id. WMATA requested the
assistance of Alstom engineers in investigating these incidences, and Alstom twice sent the same
engineer to assist WMATA in conducting its investigation. Id. at 12-13.
C. Analysis
1. Does the Court’s June 22, 2011 Memorandum Opinion foreclose the
plaintiffs’ claims against Alstom?
In its June 22, 2011 Memorandum Opinion, the Court concluded that “Alstom’s
arguments that the plaintiffs’ negligence and strict products liability claims (Counts 7, 9, 10, and
14 of the Master Complaint and Counts 1, 2, 3, and 8 of the McMillan Estate Complaint) [had to]
be dismissed as barred by the statute of repose fail, except to the extent that these claims extend
45
to Alstom in its capacity as a designer.” In re Fort Totten Metrorail Cases, 793 F. Supp. 2d 133,
156 (D.D.C. 2011); see also id. at 142 n.10 (“A product may have a defective design without
being defectively manufactured, and vice versa. Therefore, dismissing the design defect claims
against Alstom would limit its liability to manufacturing defects only.”). Thus, the Court has
already ruled that the claims against Alstom in its capacity as the manufacturer and seller of the
modules are not barred by the statute of repose.
2. The Plaintiffs’ Manufacturing Defect Claims
“In a manufacturing defect case, plaintiff may seek to prove either a ‘specific defect’—
that is, that a specific, identifiable part of the [product] was defective and was the cause of the
accident—or a ‘general defect’—which, more accurately, is an unspecified defect, which the
plaintiffs ask the finder of fact to infer from the accident itself.” Pappas v. Ford Motor Co., 7 F.
Supp. 2d 22, 26 (D.D.C. 1998). “To prove a specific defect . . . , plaintiffs generally introduce
expert testimony based on an examination of the accident.” Id. “To prove an unspecified defect,
plaintiffs generally introduce circumstantial evidence, and expert opinion based thereon, that
some defect attributable to the manufacturer must have been the cause of the accident.” Id.
Although it is unclear whether the plaintiffs maintain that the parasitic oscillation
constitutes a specific defect or a general defect, there is sufficient evidence of parasitic
oscillation within the Alstom modules at B2-304 from which a jury could either (1) conclude that
the modules were defective and were a cause of the accident, or (2) infer, based on the evidence
presented with regard to the structure of a track circuit and the nature of the collision, that the
modules were defective. See ECF No. 485-1 ¶¶ 38W, 39W (explaining parasitic oscillation, why
it is dangerous, and opining what Alstom should have done to remedy the problem of oscillating
46
modules). Alstom is therefore not entitled to summary judgment on the manufacturing defect
claims.
3. The Plaintiffs’ Failure to Warn Claims
There are several instances from which a reasonable jury could conclude that Alstom had
a duty to warn that it breached. 20 First, in the 1970s, Alstom entered into a contractual
relationship with WMATA and thereby acquired the duty to use reasonable care in performing
its contractual obligations. See Bechtel, 631 F.2d at 1001. Next, a reasonable jury could
conclude that Alstom’s September 2004 letter evinced knowledge of the dangers of mixed track
circuits. Finally, because “even if there is no duty to warn at the time of sale, facts may
thereafter come to the attention of the manufacturer which make it imperative that a warning
then be given,” Owens-Illinois, Inc. v. Zenobia, 325 Md. 420, 446 (Md. 1992); see also Ferguson
v. F.R. Winkler GMBH & Co., 79 F.3d 1221, 1226 (D.C. Cir. 1996) (noting that “the Maryland
courts . . . have often served as an aid in interpreting the products-liability law of the District of
Columbia”), it is arguable that Alstom’s participation in the 2005 investigation of the Rosslyn
and Silver Spring incidents either gave or should have given Alstom knowledge that parasitic
oscillation in its modules was causing issues in train detection. And, as noted above, “previous
decisions [of the District of Columbia Court of Appeals] indicate that fact-intensive issues
concerning the existence of a duty to warn and whether the warning was sufficiently specific to
discharge the duty are generally reserved for the jury and may be resolved as a matter of law
only when the evidence would not permit differences of opinion by reasonable jurors.” East
Penn. Mfg., 578 A.2d at 1115. Thus, because there is evidence from which a reasonable jury
20
The Court discussed the applicable legal standards for failure-to-warn claims supra at page 41 of this
Memorandum Opinion.
47
could conclude that Alstom was aware of problems with its modules, Alstom is not entitled to
summary judgment on the failure to warn claims. Moreover, the question of whether Alstom’s
September 2004 letter constituted a warning, much less a sufficient warning, is a question for a
jury.
4. The Plaintiffs’ Derivative Survival and Wrongful Death Claims
Because the underlying negligence and strict liability claims are not being dismissed,
Alstom is not entitled to summary judgment on the plaintiffs’ derivative survival and wrongful
death claims based on the erroneous assumption that the underlying claims would not exist.
5. The Co-defendants’ Cross-Claims against Alstom
i. The Co-defendants’ Contribution Claims against Alstom
In light of the foregoing conclusion that a reasonable jury could find Alstom liable to the
plaintiffs, Alstom is not entitled to summary judgment on the co-defendants’ contribution claims.
ii. WMATA’s Contractual Indemnity Claim against Alstom
Alstom asserts that it is entitled to summary judgment on WMATA’s contractual
indemnity cross-claim for two reasons: (1) that there is no basis for finding Alstom negligent,
and (2) that the WMATA-Alstom contract limits WMATA’s indemnity rights “to the period of
time before acceptance of the work, which has long since passed.” ECF No. 427-1 at 22. Both
of these arguments must be rejected.
First, in light of the foregoing conclusion that a reasonable jury could find Alstom liable
to the plaintiffs, Alstom is not entitled to summary judgment on WMATA’s claim for contractual
indemnity. And because the plaintiffs are not precluded as a matter of law from establishing
Alstom’s liability, there is no need to evaluate WMATA’s argument that it is not barred from
establishing Alstom’s liability to the plaintiffs even if the plaintiffs cannot do so. See ECF No.
48
485 at 24 (asserting that two exceptions to the statute of repose permit WMATA to establish
Alstom’s liability to the plaintiffs even if plaintiffs are precluded from doing so).
Second, it is not clear from the contract that the parties intended to limit WMATA’s
contractual rights to indemnity to the time prior to acceptance of the work performed under the
contract. In fact, it is clear that they did not so intend. Article 47 of the WMATA-Alstom
contract provides:
(a) The Contractor shall save and keep harmless and indemnify the Authority
against any and all liability claims . . . for injury, including personal injury to or
death of any person or persons, and for loss or damage to any property; occurring
in connection with or in any way incident to or arising out of the occupancy, use,
service, operations, or performance of work in connection with this contract,
resulting in whole or in part from the negligent acts, errors or omissions of the
Contractor.
...
(b) The Contractor shall procure and maintain, at his own cost and expense,
during the entire period of the performance under this contract, the following
types of insurance: . . . .
(c) Before the contract will be executed by the Authority, the Contractor shall
forward to the Authority for approval a certificate, or certificates, of the insurance
required, under the foregoing provisions, including special endorsements. . . . In
addition to any provisions hereinbefore required, a provision of such insurance
policies shall be that . . . they will be automatically renewed upon expiration and
continued in full force and effect until final acceptance by the Authority of all the
work covered by the Contract, unless the Authority is given thirty (30) days
written notice, before any change or a cancellation is made effective.
....
(g) Any contract of insurance or indemnification naming the Authority . . . shall
be endorsed to provide that the insurer will not contend in the event of any
occurrence, accident or claim that the Authority or the United States of America .
. . are not liable in tort by virtue of the fact of being governmental
instrumentalities or public or quasi-public bodies.
ECF No. 427-2 ¶ 65 (emphasis added); see also ECF No. 485-3 at 37. Subsections (a) and (c)
pertain to different topics and each has its own limiting provision that cannot, and should not, be
49
imputed to the other. Specifically, the indemnification section—subsection (a)—very clearly
entitles WMATA to indemnification arising out of the “occupancy, use, service, operations, or
performance of work in connection with [the] contract.” Subsection (c), however, just as clearly
limits the maintenance of insurance until acceptance of the work performed under the contract.
And the text of subsection (c) makes clear that its requirements apply only to “such insurance
policies.” Indeed, the word indemnification does not appear in subsection (c). Accordingly, as it
is undisputed that that the Alstom impedance bonds were in use on June 22, 2009, should Alstom
be found negligent, WMATA is entitled to contractual indemnification for that negligence.
Alstom’s claim that it is entitled to summary judgment on WMATA’s contractual
indemnification cross-claim is therefore rejected.
VIII. ARINC’s Motion for Summary Judgment 21
A. Introduction
ARINC moves for summary judgment in its favor as to all claims on the following
grounds: (1) it is entitled to the government contractor defense under Boyle v. United
Technologies Corp., 487 U.S. 500 (1988); (2) there is no evidence of a causal nexus between any
alleged defect in ARINC’s alarm system and the train collision; (3) the plaintiffs cannot meet
their burden of establishing a design defect because they have offered no evidence of an
alternative design; (4) the breach of express warranty fails as a matter of law because the
21
The Court considered the following filings and their supporting exhibits in resolving this motion: (1) Defendant
ARINC Incorporated’s Memorandum of Points and Authorities in Support of Motion for Summary Judgment [ECF
No. 428-51]; (2) Defendant Alstom Signaling, Inc.’s Memorandum of Points and Authorities in Opposition to
ARINC’s Motion for Summary Judgment [ECF No. 486]; (3) Defendant WMATA’s Memorandum in Opposition to
Defendant ARINC, Inc.’s Motion for Summary Judgment [ECF No. 488]; (4) the Plaintiff’s Opposition to
Defendant ARINC Inc.’s Motion for Summary Judgment [ECF No. 489]; and (5) Defendant ARINC Incorporated’s
Reply to Oppositions to Motion for Summary Judgment Submitted by Plaintiffs, WMATA, and Alstom [ECF No.
552].
50
plaintiffs did not provide notice of the alleged breach to ARINC; (5) WMATA’s contractual
indemnity claim fails because the contract’s indemnity provision does not establish a “clear
intention” that ARINC would indemnity WMATA for WMATA’s own negligence; and (6)
because ARINC is not a joint tortfeasor, it is entitled to summary judgment on all contribution
claims against it.
The Court concludes that (1) ARINC does not qualify for the government contractor
defense under Boyle because it has not shown that this case raises “uniquely federal interests”;
(2) there is sufficient evidence of causation to create a jury question; (3) there is evidence of an
alternative design sufficient to sustain the plaintiffs’ design defect claim; (4) the plaintiffs’
express warranty claim does not fail for lack of notice; (5) the indemnity provision in the
contract between WMATA and ARINC does not require ARINC to indemnify WMATA for
WMATA’s own negligence; and (6) because there is evidence that ARINC is a joint tortfeasor,
the contribution claims against it cannot be dismissed. Accordingly, ARINC’s motion is granted
in part and denied in part.
B. Background
As explained above, WMATA relies on an Automatic Train Control system to control
train movement and direct train operators. Since the mid-1990s, the Automatic Train Control
system used a software package called the Rail Operations Control Software. ECF No. 486 at 3.
Then, in 2003, WMATA contracted with ARINC, “a provider of communications and
engineering solutions to at least 15 to 20 major metrorail systems in the United States,” to update
the system with ARINC’s Advanced Information Management software. Id. The WMATA-
ARINC contract made clear that the new software should exceed the functionality of the old
51
software and emphasized that the new software should maintain the highest levels of safety and
reliability. Id. at 4.
The Advanced Information Management software collects data from over 50,000 data
points—including train circuits—and was designed to alert WMATA to the existence of
dangerous conditions. Id. at 3-4. The software issues two types of alarms for failed track
circuits: (1) a “track circuit failed vacant” alarm, which indicates that a train is in the circuit but
the circuit is not reporting a train present, and is also known as a non-reporting block; and (2) a
“track circuit failed occupied,” alarm, which means that the circuit is indicating the presence of a
train despite the fact that the circuit is empty. Id. at 4.
The following facts regarding ARINC’s Advanced Information Management software are
undisputed. First, the software designated the non-reporting block alarm as a “minor alarm.” Id.
at 4. This means that the alarm is deleted by the system if not acknowledged by a user within 60
seconds. Id. For all of its other mass transit customers, however, ARINC had classified non-
reporting block alarms as major alarms. Id. at 8. Second, although ARINC designed the
software for WMATA to issue a non-reporting block alarm 35 seconds after the event occurred
(meaning that if the circuit malfunctioned for 34 seconds and then self-corrected, no alarm would
ever be issued), it designed software for other transit systems that contains a much shorter delay
before issuing a non-reporting block alarm—only 5 to 10 seconds. Id. at 5. Third, ARINC’s
Advanced Information Management software would remove trains from its system while the
trains were in service, without explanation and without issuing alarms for the Operations Central
Control operators. Id. WMATA noticed this problem before the new software was fully
implemented and informed ARINC that it considered disappearing trains a major safety issue.
52
Id. Finally, ARINC’s Advanced Information Management software was in operation when the
train collision occurred on June 22, 2009. Id. at 2.
C. Analysis
1. Is ARINC entitled to the government contractor defense established in Boyle
v. United Technologies Corp., 487 U.S. 500 (1988)?
ARINC contends that all of the claims against it should be dismissed because it is entitled
to the government contractor defense recognized in Boyle v. United Technologies Corp., 487
U.S. 500 (1988). ECF No. 428-51 at 9. In Boyle, a “Marine helicopter copilot, was killed when
the . . . helicopter in which he was flying crashed off the coast of Virginia Beach, Virginia,
during a training exercise.” 487 U.S. at 502. “Although Boyle survived the impact of the crash,
he was unable to escape from the helicopter and drowned.” Id. His estate filed suit under
Virginia tort law against the helicopter manufacturer, alleging that the helicopter’s emergency
escape hatch was defectively designed. Id. at 503. The helicopter manufacturer argued that the
door was provided in accordance with Department of Defense specifications and that,
consequently, the plaintiff’s state tort claims were federally preempted. See id. at 509. The
Supreme Court agreed. Id.
The Supreme Court began its analysis by explaining that “a few areas, involving
‘uniquely federal interests,’ are so committed by the Constitution and laws of the United States
to federal control that state law is pre-empted and replaced, where necessary, by . . . ‘federal
common law.’” Id. at 504 (emphasis added). It noted that the dispute in Boyle bordered upon
two areas that the Court had previously identified as involving “uniquely federal interests” to
which federal common law applied: (1) “the obligations to and rights of the United States under
its contracts,” and (2) “the civil liability of federal officials for actions taken in the course of their
53
duty.” Id. at 504-05 (citations omitted). The Court found that “the reasons for considering these
closely related areas to be of ‘uniquely federal’ interest apply as well to the civil liabilities
arising out of the performance of federal procurement contracts.” Id. at 505-06.
The Court thus deemed “the procurement of equipment by the United States . . . an area
of uniquely federal interest.” Id. at 507. However, this “merely establishe[d] a necessary, not a
sufficient, condition for the displacement of state law.” Id. “Displacement will occur only
where . . . a ‘significant conflict’ exists between an identifiable ‘federal policy or interest and the
[operation] of state law, or the application of state law would ‘frustrate specific objectives’ of
federal legislation.” Id. (citations omitted). The Boyle Court found such a “significant conflict”
between state law and federal interests under the facts of that case. See id. at 509. In
determining the parameters of this conflict, the Court looked to the discretionary function
exception of the Federal Tort Claims Act, which exempts the United States from liability for
claims “‘based upon the exercise or performance or the failure to exercise or perform a
discretionary function or duty on the part of a federal agency or employee of the Government,
whether or not the discretion involved be abused.’” Id. at 511 (quoting 28 U.S.C. § 2680(a)).
Because “the selection of the appropriate design for military equipment to be used by our Armed
Forces is assuredly a discretionary function within the meaning of this provision,” and because
“permitting ‘second-guessing’ of these judgments through state tort suits against contractors
would produce the same effect sought to be avoided by the FTCA exemption” insofar as
contractors would pass through the financial burden of adverse judgments to the United States,
the Court concluded that “that state law which holds Government contractors liable for design
defects in military equipment does in some circumstances present a ‘significant conflict’ with
54
federal policy and must be displaced.” Id. at 511-12 (citation omitted). The Court then
established the following three-part test to determine the “scope of displacement” of state law:
Liability for design defects in military equipment cannot be imposed, pursuant to
state law, when (1) the United States approved reasonably precise specifications;
(2) the equipment conformed to those specifications; and (3) the supplier warned
the United States about the dangers in the use of the equipment that were known
to the supplier but not to the United States.
Id. at 512.
ARINC jumps directly to this three-part test in its opening brief, arguing that it is entitled
to the government contractor defense because it designed its Advanced Information Management
system in conformance with specifications approved by WMATA and that WMATA was aware
of any dangers associated with the system. See ECF No. 428-51 at 10-22. But ARINC
overlooks the two prerequisites to invoking the Boyle defense: “first, the case must involve ‘an
area of uniquely federal interest’; and second, there must exist ‘a significant conflict . . . between
an identifiable federal policy or interest and the [operation] of state law.’” Kormendi/Gardner
Partners v. Surplus Acquisition Venture, LLC, 606 F. Supp. 2d 114, 117 (D.D.C. 2009) (quoting
Boyle, 487 U.S. at 507); accord Glassco v. Miller Equip. Co., 966 F.2d 641, 642 (11th Cir. 1992)
(stating that government contractors seeking to invoke the Boyle defense must first satisfy both
the “uniquely federal interest” and “significant conflict” prongs, and explaining that the “three-
part inquiry elaborates the ‘significant conflict’ prong of the test”). Moreover, “[t]he party
seeking to displace state law bears the burden of demonstrating that both conditions exist.”
Kormendi/Gardner Partners, 606 F. Supp. 2d at 117. The Court concludes for the following
reasons that ARINC has failed to carry its burden of showing that this case raises uniquely
federal interests.
55
Courts have found uniquely federal interests in a variety of cases involving federal
government contractors. See, e.g., Boyle, 487 U.S. at 507 (liability arising from federal
procurement contracts); Saleh v. Titan Corp., 580 F.3d 1, 5, 9 (D.C. Cir. 2009) (liability arising
from military contractors’ participation in combatant activities over which the military retains
command authority); In re World Trade Ctr. Disaster Site Litig., 521 F.3d 169, 197 (2d Cir.
2008) (coordination of “federal disaster assistance and streamlining the management of large-
scale disaster recovery projects”); Hudgens v. Bell Helicopters v. Textron, 328 F.3d 1329, 1334
(11th Cir. 2003) (maintenance of U.S. military aircraft according to procedures specified by the
federal government). The common thread of all these cases is that “the interests of the United
States [would] be directly affected” by the imposition of state tort liability on the contractor.
Boyle, 487 U.S. at 507.
The biggest obstacle for ARINC in claiming the government contractor defense under
Boyle is that it contracted with WMATA, not the federal government. Recognizing this
distinction, ARINC asserts that uniquely federal interests are nonetheless at stake here because
(1) the interstate compact creating WMATA has been deemed an Act of Congress; (2) Congress
has taken an active role in creating and funding WMATA; (3) the federal government is
dependent upon WMATA to transport federal employees in the Washington, D.C. metropolitan
area; 22 and (4) courts have applied federal common law to immunity issues involving WMATA.
See ECF No. 552 at 6-9.
22
Ironically, the federal government’s purported interest in transportation for its employees is actually advanced
(rather than undermined) by state tort suits against WMATA’s contractors which seek to expose harmful defects in
WMATA’s transit system. ARINC seemingly overlooks this reality.
56
The Court finds ARINC’s arguments unpersuasive. True, the federal government may
have some general interest and involvement in WMATA’s operations and its success, and courts
have applied federal common law to certain immunity issues involving WMATA. But these
truisms are beside the point. The relevant inquiry under Boyle is whether “the interests of the
United States [would] be directly affected” by imposing tort liability on ARINC for designing its
Advanced Information Management system in conformance with specifications approved by
WMATA. Boyle, 487 U.S. at 507 (emphasis added). In Boyle, for instance, the Court found it
“plain that the Federal Government’s interest in the procurement of equipment is implicated by
suits such as the present one” because “[t]he imposition of liability on Government contractors
will directly affect the terms of Government contracts: either the contractor will decline to
manufacture the design specified by the Government, or it will raise its price. Either way, the
interests of the United States will be directly affected.” Id. at 506-07. Here, ARINC has not
shown that imposing liability upon it will have any effect on the United States’s interests, much
less a direct one. It simply lists all the connections that WMATA has to the federal government.
That is not enough to establish preemption of state tort claims under Boyle.
This case is more like Miree v. DeKalb County, 433 U.S. 25 (1977), than Boyle. Miree
concerned “whether certain private parties could sue as third-party beneficiaries to an agreement
between a municipality and the Federal Aviation Administration.” Boyle, 487 U.S. at 506 (citing
Miree, 433 U.S. at 30). The Supreme Court held that federal common law did not govern the
case based on its conclusion that “the resolution of petitioners’ breach-of-contract claim against
respondent [would] have no direct effect upon the United States or its Treasury.” Miree, 433
U.S. at 29; see id. at 32-33 (“‘[A]ny federal interest in the outcome of the [dispute] . . . is far too
speculative, far too remote a possibility to justify the application of federal law.’” (citation
57
omitted)). As in Miree, the claims against ARINC will have no direct effect on the United States
or its Treasury, nor does the United States have any other discernible interest in this case. The
Court therefore rejects ARINC’s attempt to invoke the Boyle government contractor defense,
and will preclude ARINC from pursuing this affirmative defense at trial.
2. Can the Court conclude, as a matter of law, that the Advanced Information
Management System was not a proximate cause of the collision?
As noted above, “[p]roximate cause has been defined as that cause which, in natural and
continual sequence, unbroken by any efficient intervening cause, produces the injury, and
without which the result would not have occurred.” Convit, 980 A.2d at 1125. It is only the
“exceptional case” in which questions of proximate cause “pass from the realm of fact to one of
law.” Majeska, 812 A.2d at 950 (emphasis added).
ARINC argues that the plaintiffs’ “causation argument with regard to ARINC is that if
the [Advanced Information Management] system were free of the defects they identified, one of
the [Operations Central Control] supervisors would have communicated with the operator of
Train 112 to warn her of the non-reporting block at Fort Totten and the accident would have
been avoided.” ECF No. 428-51 at 23-24. ARINC maintains that the plaintiffs’ claim must fail
because WMATA had no procedure requiring the Operations Central Control supervisors to
route trains around a non-reporting block and thus a better alarm would not have prevented the
accident. Id. WMATA responds, however, that it “had an absolute block procedure for routing
trains around locations that were experiencing actual loss of train detection.” ECF No. 488 at 26.
Accordingly, there is a factual dispute as to how WMATA would have responded had the
Advanced Information Management software accurately notified the Operations Central Control
personnel of the problem at Circuit B2-304. See ECF No. 488-2 ¶¶ 117-19. Moreover, there is
58
sufficient other evidence from which a reasonable jury could conclude that ARINC’s software
was a proximate cause of the accident: its tendency to delete trains, the delay on issuing a non-
reporting block alarm, its designation of a non-reporting block alarm as minor, and the sheer
number of alarms generated by the system. See, e.g., id. ¶¶ 94, 118-19
3. Absence of Evidence of a Safer Alternative Design in Support of Design
Defect Claim
ARINC next asserts that it is entitled to summary judgment on the plaintiffs’ design
defect claim because the plaintiffs “have failed to identify an expert to testify as to the existence
of an alternative design” to its Advanced Information Management system. ECF No. 428-51 at
32. The Court does not agree.
Whether or not the claim of defective design is premised on negligence or strict liability,
a plaintiff must show the risks, costs, and benefits of the product in question, as well as an
alternative design. See Hull v. Eaton Corp., 825 F.2d 448, 453-54 (D.C. Cir. 1987). With
respect to the safer alternative design of the allegedly defective product, “[a]ll that is required is
that it be commercially feasible at the time of manufacture.” Artis v. Corona Corp. of Japan, 703
A.2d 1214, 1217 (D.C. 1997).
Here, the plaintiffs and co-defendants maintain that not only was an alternative design
commercially feasible, but that ARINC was itself manufacturing alternatively designed software
systems for operators of other mass transit systems. See, e.g., ECF No. 486 at 8 (asserting that
ARINC should have designed the Advanced Information Management software to designate
non-reporting block alarms as major, and opining that this “is a commercially feasible design, as
is best evidenced by the fact that every other transit system ARINC works with makes” such
alarms major alarms). Accordingly, as there are disputed issues of material fact with regard to
59
the feasibility of an alternative design, ARINC is not entitled to summary judgment on the design
defect claims asserted against it.
4. The Plaintiffs’ Express Warranty Claim
“In order to succeed on a breach of warranty claim, a plaintiff must prove notice as well
as that the defendant breached an express promise made about the product sold.” Witherspoon v.
Philip Morris, Inc., 964 F. Supp. 455, 464 (D.D.C. 1997). “[T]he purpose of the notice
requirement is to open the doors to negotiation”; accordingly, a plaintiff need not “threaten
litigation in order to provide notice.” Id. (citing Rock Creek Ginger Ale Co., Inc. v. Thermice
Corp., 352 F. Supp. 522, 528 (D.D.C. 1971). “Constructive notice, if established, will satisfy the
requirement.” Id. Finally, “when a seller willfully fails to disclose a defect, failure to notify
cannot be raised as a defense.” Id. at 465 (internal quotation marks and citation omitted).
ARINC contends that the plaintiffs’ breach of express warranty claim fails because “no
claim for breach of an express warranty may be made absent notice to ARINC of the alleged
breach,” and because “neither WMATA nor Plaintiffs provided ARINC with the required notice
at any time prior to the accident.” ECF No. 428-51 at 33. WMATA responds by arguing: (1)
that ARINC cannot prove as a matter of law that the warranty language cited in ARINC’s motion
is controlling, ECF No. 488 at 35; (2) that ARINC cannot establish that the warranty language it
cites is enforceable as a matter of law, id. at 36; (3) that ARINC was provided with constructive
notice of problems with the Advanced Information Management system, id. at 39; and (4) that
ARINC was not entitled to notice, id. at 40. Because ARINC’s motion focuses only on the
argument that no notice was provided and does not appear to assert that no warranty was made,
the Court will address only the latter two of WMATA’s arguments.
60
Here, WMATA argues that, drawing all reasonable inferences in its favor, there is a
question of fact as to whether ARINC received constructive notice. Alternatively, WMATA
maintains that ARINC was not entitled to notice because it willfully failed to disclose defects in
its Advanced Information Management system. Either one of these arguments suffices to
preclude the Court from granting summary judgment to ARINC on the breach of express
warranty claims. First, WMATA raised the issue of the disappearing train with ARINC and
made clear that it considered this to be a major safety issue. See ECF No. 486 at 5-6. Second,
WMATA maintains that ARINC failed to disclose several aspects of the Advanced Information
Management software that deviated from the software used by other operators of mass transit
systems. See id. at 5, 8-9. Accordingly, whether ARINC received constructive notice and
whether ARINC willfully failed to disclose defects and was therefore not entitled to notice are
questions that must be answered by a jury.
5. WMATA’s Contractual Indemnity Claim Against ARINC
Although “[o]ne of the most common, and simple bases of indemnity is a contract that
provides for it,” East Penn Mfg., 578 A.2d at 1126, “[a]n indemnity provision . . . ‘should not be
construed to permit an indemnitee to recover for his . . . own negligence unless the court is
firmly convinced that such an interpretation reflects the intention of the parties,’” W.M.
Schlosser Co., Inc. v. Maryland Drywall Co., Inc., 673 A.2d 647, 653 (D.C. 1996) (quoting
United States v. Seckinger, 397 U.S. 203, 211 (1970)) (emphasis added). Indeed, “[i]f a party
‘expects to shift responsibility for its negligence . . . the mutual intention of the parties to this
effect should appear with clarity from the face of the contract.’” Schlosser, 673 A.2d at 653
(quoting Seckinger, 397 U.S. at 211) (emphasis added).
61
In Count 6 of its cross-claim, WMATA seeks contractual indemnification from ARINC
in the event that WMATA is found liable to the plaintiffs. See ECF No. 428-51 at 36 (citing
ECF No. 140 at 20). ARINC explains that “on its face, WMATA’s claim includes
indemnification for [WMATA’s] own negligent acts,” and maintains that it has “no obligation to
indemnify WMATA for [WMATA’s] own negligence in the absence of clear contractual
language to the contrary, which does not exist here.” Id. The Court agrees.
The pertinent section of the ARINC-WMATA contract reads:
The Contractor will save and keep harmless and indemnify WMATA against any
and all liability claims, and the cost of whatsoever kind and nature arising or
alleged to have arisen for injury, including personal injury to or death of person or
persons, and for loss or damage occurring in connection with this Contract and or
any acts in connection with activities to be performed under this Contract
resulting in whole or in part from the acts, errors or omissions of the contractor, or
any employee, agent or representative of the Contractor.
Id. (emphasis added).
WMATA argues that “a plain reading of the provision [following the words ‘and or’] is
that the language pertaining to ARINC’s own acts, errors, or omissions is part of an ‘in addition
to’ or ‘alternative’ clause,” and contends that the words “and or” are “intended to broaden the
indemnity, not limit it as ARINC argues.” ECF No. 488 at 41-42. The Court, however, has
struggled to make heads or tails of this section of the contract, much less conclude that any sort
of “plain reading” may be made of it. On this poorly drafted contractual language, the Court is
far from “firmly convinced,” Schlosser, 673 A.2d at 653, that ARINC intended to permit
WMATA to receive indemnification from ARINC for losses resulting from WMATA’s own
negligence. By way of brief example, the reading urged by WMATA makes no sense as it
renders the “and or” clause entirely superfluous. Indeed, negligent acts on the part of the
contractor are seemingly encompassed by the phrase “any and all liability claims . . . occurring in
62
connection with this Contract.” The Court is therefore unclear how the “and or” clause broadens
the indemnity requirement as WMATA urges. See ECF No. 488 at 41. Next, the Court has
trouble interpreting the differing meanings—if, in fact, any were intended—by the language
“occurring in connection with this Contract’’ and “to be performed under this Contract.” And as
these two differing temporal phrases are central to the two clauses, it would appear the parties
meant to establish limitations on the resulting indemnity obligation. Accordingly, ARINC is
entitled to summary judgment on WMATA’s cross-claim for contractual indemnification to the
extent that WMATA seeks indemnification from ARINC for WMATA’s own negligence, should
a jury determine that WMATA was negligent.
6. The Co-defendants’ Contribution Claims Against ARINC
Because the Court is not granting summary judgment to ARINC on the plaintiffs’ claims
against it, there is no basis to grant ARINC summary judgment on the co-defendants’
contribution cross-claims, as a reasonable jury could deem ARINC a joint tortfeasor responsible
for the June 22, 2009 collision.
IX. Conclusion
For the foregoing reasons, (1) WMATA’s motion to dismiss Alstom’s statute of repose
defense is granted in part and denied in part; (2) Ansaldo’s motion for judgment on Counts 7, 11,
and 15 of the Second Amended Master Complaint is granted; (3) WMATA’s motion to dismiss
the equitable indemnification cross-claims against it is granted; (4) the corporate defendants’
motion for summary judgment is denied; (5) Ansaldo’s motion for summary judgment is denied;
63
(6) Alstom’s motion for summary judgment is denied; and (7) ARINC’s motion for summary
judgment is granted in part and denied in part. 23
REGGIE B. WALTON
United States District Judge
23
The Court previously issued an Order consistent with this Amended Memorandum Opinion on August 16, 2012.
64