UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
______________________________
)
SIERRA CLUB, )
)
Plaintiff, )
)
v. )
)
UNITED STATES DEPARTMENT OF )
AGRICULTURE, RURAL UTILITIES )
SERVICE, et al., ) Civ. Action No. 07-1860(EGS)
)
Defendants, )
)
and )
)
SUNFLOWER ELECTRIC POWER )
CORPORATION, )
)
Defendant-Intervenor. )
)
_____________________________)
MEMORANDUM OPINION
Plaintiff Sierra Club brought this action alleging that the
Department of Agriculture’s Rural Utilities Service (“RUS”) and
certain officials in the Department of Agriculture
(collectively, “the federal defendants”) violated the National
Environmental Policy Act of 1969 (“NEPA”) by failing to produce
an environmental impact statement in connection with its
involvement in the expansion of Sunflower Electric Power
Corporation’s (“Sunflower”) coal-fired generating plant in
Holcomb, Kansas. Sunflower intervened as a defendant.
On March 29, 2011, the Court granted plaintiff’s motion for
summary judgment, concluding that the federal defendants had
violated NEPA. NEPA requires federal agencies to include an
environmental impact statement (“EIS”) “in every recommendation
or report on proposals for legislation and other major Federal
actions significantly affecting the quality of the human
environment[.]” 42 U.S.C. § 4332(C). “If any significant
environmental impacts might result from the proposed agency
action then an EIS must be prepared before the [agency] action
is taken.” Sierra Club v. Van Antwerp, 661 F.3d 1147, 1153
(D.C. Cir. 2011) (internal quotations omitted). The Court found
that the financial assistance given to Sunflower by RUS in the
form of debt forgiveness and consent to a lien subordination, as
well as RUS’s approvals relating to the expansion of the power
plant, amounted to a “major federal action” within the meaning
of NEPA such that an EIS was required. Mem. Op. at 26, Mar. 29,
2011.
The Court ordered the parties to submit supplemental
briefing on the appropriate remedy. That issue is now before
the Court. Upon consideration of the supplemental briefs, the
responses and replies thereto, the applicable law, the entire
record, and for the reasons set forth below, the Court will
grant declaratory and limited injunctive relief and remand to
the agency for any necessary further proceedings.
2
I. BACKGROUND
The factual background of this case is set forth in detail
in the Court’s March 29, 2011 Memorandum Opinion. Briefly
stated, the Rural Electrification Administration (the
predecessor agency to RUS) approved a loan and loan guarantees
to Sunflower’s predecessor in 1980 after an EIS was completed.1
The loan and loan guarantees, totaling approximately $543
million, were provided for the construction of a coal-fired
generating station (“Holcomb Unit 1”) to be located near
Holcomb, Kansas. Administrative Record (“AR”) 03866. However,
soon after the construction of Holcomb Unit 1, the company
became unable to meet its debt repayment obligations to RUS and
other creditors. AR 04546. Accordingly, in 1987, the parties
entered into new agreements. Under the terms of these new
agreements, Sunflower’s predecessor issued three new classes of
1
The Rural Electrification Act of 1936 gave the Secretary of
Agriculture authority, which has been delegated to RUS, to “make
loans in the several States and Territories of the United States
for rural electrification and for the purpose of furnishing and
improving electric and telephone service in rural areas, . . .
and for the purpose of assisting electric borrowers to implement
demand side management, energy efficiency and conservation
programs, and on-grid and off-grid renewable energy systems.”
Id. § 902(a). The Rural Electrification Act further authorizes
RUS to make loans for rural electrification to corporations
organized “for the purpose of financing the construction and
operation of generating plants, electric transmission and
distribution lines or systems for the furnishing and improving
of electric service to persons in rural areas[.]” 7 U.S.C.
§ 904(a).
3
promissory notes, AR 00149.2 Furthermore, in order to secure the
notes, Sunflower granted a lien to RUS and its other secured
creditors on substantially all of its assets. AR 00276.
After the 1987 restructuring, the company was again unable
to make payments on all of the promissory notes. Of particular
concern, because the interest was capitalized on one class of
notes, the principal owed to RUS on these notes had increased
from the $98.3 million owed in 1987 to $413.9 million in 2002.
Because the company was at risk of defaulting, Sunflower and its
creditors elected to negotiate another restructuring. AR 00004-
11. The 2002 corporate and debt restructuring (the “2002
Restructuring”) divided the assets owned by Sunflower’s
predecessor between two new corporations, Sunflower Electric
Power Corporation (the party to this action, “Sunflower”) and
the Holcomb Common Facilities (“HCF”). Significantly, Sunflower
purchased the predecessor company’s assets by issuing an
entirely new set of notes to the holders of the old promissory
notes. AR 00173-175. Although HCF did not issue new promissory
notes, in exchange for the assets it received, RUS and the other
creditors received a security interest in HCF and an assignment
2
The three classes of notes were referred to as the A Notes,
B Notes, and C Notes. RUS’s share of the principal balance on
the A Notes was $294.5 million; on the B Notes it was $98.3
million; on the C Notes it was $61.4 million. Fed. Defs.’
Statement of Facts Supp. Cross-Mot. Summ. J. (“Fed. Defs.’
Statement of Facts”) ¶¶ 5-7.
4
of annual rent payments from the use of certain related
facilities. AR 00190. The 2002 Restructuring also affected the
lien held by RUS. The agency agreed that it will, in the
future, release portions of its lien, if and when a second
generating plant (“Holcomb Unit 2”) is developed. In exchange,
Sunflower agreed to grant to RUS a security interest in the rent
paid for the use of the relevant facilities.
In connection with the 2002 Restructuring, Sunflower also
agreed to obtain approval from RUS before undertaking a variety
of activities or entering certain types of contracts. Of
particular significance to the issue presently before the Court,
Sunflower agreed: (i) that it would not “enter into any
agreement or other arrangements . . . for the development of
Holcomb Unit 2 without the prior written approval of RUS,” and
“[a]ny RUS approval will be on such terms and conditions as RUS,
in its sole discretion, may require at such time” (AR 04391);
and (ii) that it would not “enter into any agreement or
arrangement . . . for Holcomb Site Development . . . or for
other use of the Holcomb Unit 1 site, the fair market value of
which would exceed $1 million annually[,] without the prior
written approval of RUS,” and “[a]ny RUS approval will be on
5
such terms and conditions as RUS, in its sole discretion, may
require at such time” (AR 04391).3
Since the 2002 Restructuring, Sunflower has sought approval
from RUS on a number of occasions in accordance with the
conditions outlined above. Most relevant to this action, on
several occasions Sunflower sought approvals relating to the
development of new generating plants at the Holcomb site. In
October of 2005, RUS granted conditional approval of Sunflower’s
execution of a Memorandum of Agreement with Tri-State Generation
and Transmission Association, Inc. (“Tri-State”) regarding the
proposed development of two new generating units at the Holcomb
site. AR 04574. Subsequently, in September of 2006, RUS
granted conditional approval for Sunflower to enter into a
3
In addition, and even more comprehensively, Sunflower also
agreed (i) that it will not “[c]onstruct, make, lease, purchase
or otherwise acquire any extensions or additions to its system
or enter into any contract therefore” without the prior written
approval of RUS (AR 04389); (ii) that it will not “[p]urchase,
lease or otherwise acquire any parcel or parcels of land or
enter into any contract therefore” without the prior written
approval of RUS (AR 04389); (iii) that it will not enter into
any contracts or arrangements regarding power purchase or sale
arrangements, power supply and delivery arrangements, power
marketing contracts, system management and maintenance
contracts, or any contracts relating to financial products such
as options, futures or hedges without the prior written approval
of RUS (AR 04389-04390); (iv) that it would not “charge, assign,
pledge, mortgage or otherwise encumber any of its property”
without prior written approval from RUS (AR 04459); and (v)
Sunflower agreed to limitations on mergers, sale of its business
or assets, leases and transfers of its capital assets in the
absence of prior approval from RUS (AR 04467-04468).
6
Purchase Option and Development Agreement with Tri-State, as
well as various other related agreements, again for the proposed
development of two new generating units at the Holcomb site. AR
04610-4611. In addition to the development of Holcomb Unit 2,
the agreements provided for the potential construction of a
“Holcomb Unit 3” and a “Holcomb Unit 4.”
In addition, on July 26, 2007, RUS also provided Sunflower
with a separate letter, referred to by the parties as the
“Additional Consideration Letter.” AR 08218-8216. The terms of
the Additional Consideration Letter modified the earlier
arrangement from 2002 whereby RUS and the other creditors had
received a security interest in HCF and an assignment of annual
rent payments for the use of certain facilities. Under the new
terms, for each additional power plant being considered for the
Holcomb site, RUS received an entirely new set of promissory
notes.4 These notes are interest bearing, but payment is due
only if and when the respective generating unit is placed into
commercial operation. Furthermore, each of these 2007
promissory notes, totaling $91 million, will be cancelled on
4
With respect to Holcomb Unit 2, Sunflower issued promissory
notes (the “2007 Holcomb 2 Notes”) in the amount of $52 million;
with respect to the 2007 Holcomb 3 Notes, the amount was $23
million; and with respect to the 2007 Holcomb 4 Notes, the
amount was $16 million. AR 08228, 08239, 08244.
7
December 31, 2021 if the respective generating unit has not been
placed into commercial operation.
The principal question before the Court in its March 29,
2011 Memorandum Opinion was whether NEPA applied to the actions
taken by RUS in connection with the Holcomb Expansion Project.5
Because NEPA requires that an EIS be prepared in connection with
any “recommendation or report on proposals for legislation and
other major Federal actions significantly affecting the quality
of the human environment,” 42 U.S.C. § 4332(C), the Court had to
determine whether a “major federal action” had taken place.
For the reasons detailed in the Court’s Memorandum Opinion,
the Court concluded that RUS’s involvement in the Holcomb
Expansion Project constituted a major federal action, both in
connection with the 2002 Restructuring and in connection with
the approvals granted in 2007. In short, the Court held that,
because RUS gave necessary approvals for the Holcomb Expansion
Project and because RUS provided financial assistance to the
project, the Holcomb Expansion Project was subject to “Federal
control and responsibility,” 40 C.F.R. § 1508.18, and therefore
RUS’s involvement amounted to a major federal action within the
5
The parties have referred to the plans involving the
development of additional generating units at the Holcomb site
as the “Holcomb Expansion Project,” and the Court will do the
same.
8
meaning of NEPA. Accordingly, by failing to prepare an EIS, the
agency violated NEPA.
II. ANALYSIS
The sole remaining issue before the Court is the
appropriate remedy. At the outset, the Court notes that the
plaintiff and the federal defendants are largely in agreement
regarding the appropriate remedy. Specifically, both maintain
that declaratory relief and prospective injunctive relief would
be sufficient to remedy the NEPA violation. Their agreement is
premised on the assumption that the approvals awarded by RUS in
2007 are no longer valid because Sunflower has significantly
altered the configuration of the proposed expansion of the
Holcomb site.
According to plaintiff and the federal defendants, at the
time of the 2007 approvals, the plans for the Holcomb Expansion
Project called for three coal-fired electric generating units,
each with a generating capacity of approximately 600-750
megawatts. Since then, however, Sunflower has revised the
configuration and now has plans to construct only a single
generating unit with a capacity of 875 megawatts. Accordingly,
plaintiff and the federal defendants argue that – in light of
the contractual arrangements between Sunflower and RUS that
obligate Sunflower to seek approval from RUS for plans and
agreements relating to the Holcomb expansion – Sunflower is
9
obligated to seek new approvals in light of these drastic
changes. The federal defendants, for example, assert that
“[d]ue to the material changes in the development of the Holcomb
Expansion Project . . . RUS has concluded that its approvals and
implementing documents require Sunflower to seek new approvals
from RUS for the drastic changes to the Holcomb Expansion
Project from the proposal RUS previously reviewed and approved
in 2007.” Fed. Defs.’ Supp. Br. at 8. Similarly, Sierra Club
asserts that “RUS has an affirmative role going forward because
RUS will have to grant additional consents and approvals before
the Expansion can lawfully proceed.” Pl.’s Supp. Br. at 6.
Accordingly, rather than asking the Court to vacate the 2002
restructuring or the 2007 approvals given by RUS in connection
with the Holcomb Expansion Project, the plaintiff and the
federal defendants ask that the Court simply order RUS to
prepare an EIS on the Holcomb Expansion Project.6
Sunflower, on the other hand, asserts that the 2007
approvals that it obtained from RUS are still valid, and it need
6
Plaintiff argues in the alternative that, if the Court
concludes that the 2007 approvals are still valid and Sunflower
need not return to RUS for additional approvals before
proceeding with the Holcomb Expansion Project, the Court should
vacate the 2007 approvals. Specifically, Sierra Club proposes
that the Court vacate two consents issued by RUS in 2007, namely
the July 26, 2007 “Additional Consideration Letter” mentioned
above, AR 08218-8216, and the letter approving Sunflower’s
execution of the effective date and purchase date documents with
Tri-State, AR 7444. Pl.’s Supp. Reply Br. at 25-26.
10
not seek additional approvals before proceeding with the
construction of an additional power plant. In particular,
Sunflower argues that the relevant agreements “clearly provide
for the possibility that anywhere from zero to three new
[generating] units could be constructed at Holcomb, and that new
generating units could be smaller or larger than 700 MW.”
Sunflower’s Supp. Br. at 7. According to Sunflower, “nothing
has occurred to invalidate the 2007 RUS Approvals.” Sunflower’s
Supp. Br. at 9. Sunflower takes the position that “[t]he only
appropriate relief in this case is to enter a declaratory
judgment setting forth how RUS violated NEPA and to remand to
RUS to determine what further action, if any, is appropriate[.]”
Sunflower’s Supp. Br. at 3.
A. Appropriate Injunctive Relief Against RUS
The Court has authority to grant an injunction to remedy a
NEPA violation. However, “a plaintiff seeking a permanent
injunction must satisfy a four-factor test before a court may
grant such relief.” Monsanto Co. v. Geertson Seed Farms, 130 S.
Ct. 2743, 2756 (2010)(quoting eBay Inc. v. MercExchange, L.L.C.,
547 U.S. 388, 391 (2006)). In particular, “[a] plaintiff must
demonstrate: (1) that it has suffered an irreparable injury; (2)
that remedies available at law, such as monetary damages, are
inadequate to compensate for that injury; (3) that, considering
the balance of hardships between the plaintiff and defendant, a
11
remedy in equity is warranted; and (4) that the public interest
would not be disserved by a permanent injunction.” Id.
In the instant case, the plaintiff and the federal
defendants essentially agree upon two proposals for injunctive
relief against RUS. First, the parties ask that the Court order
RUS to immediately conduct a review of the Holcomb Expansion
Project, including the preparation of an EIS. Specifically, the
plaintiff asks that the Court order RUS “to commence forthwith
preparation of a legally valid environmental impact statement
. . . evaluating the impacts of, and alternatives to, further
approval or support for the Holcomb Expansion Project.” Pl.’s
Proposed Order. Similarly, the federal defendants propose that
the Court enter an order first directing Sunflower “to seek
approval from RUS for the newly proposed 895 MW Holcomb
Expansion Project” and then order RUS “to conduct its review of
the changes to the configuration of the Holcomb Expansion
Project as a ‘major federal action’ within the meaning of 40
C.F.R. § 1508.18 and, for purposes of NEPA and RUS’s
implementing regulations, to conduct its review of the revised
Holcomb Expansion Project as a generation project receiving
federal financial assistance from RUS[.]” Fed. Defs.’ Proposed
Order.
Second, the parties request that the Court enter a
prospective injunction that would direct RUS to perform an EIS
12
before proceeding with any future actions in connection with the
Holcomb Expansion Project. The language proposed by plaintiff
would enjoin RUS “from taking any action, including any approval
of or consent to Sunflower’s actions pursuant to the governing
loan contracts, in support of the Holcomb Expansion Project”
until after an EIS is completed. Pl.’s Proposed Order. The
federal defendants propose similar language, suggesting that the
Court order RUS “not to issue any approvals or consents for
agreements or arrangements directly related to the Holcomb
Expansion Project” until RUS conducted its review of the
project. Fed. Defs.’ Proposed Order.
i. Proposed Order Directing the Agency to
Immediately Perform an EIS for the Holcomb
Expansion Project
With respect to the first of the parties’ proposals, namely
one that would essentially order an immediate EIS, the Court
finds that such an injunction is not appropriate for the
following reasons. First, the Court is not aware of any
proposals for any type of major federal action related to the
Holcomb Expansion Project presently being considered by RUS.
The Court, in its March 29, 2011 Memorandum Opinion concluded
that “RUS’s involvement in the Holcomb Expansion Project
constituted a major federal action, both in connection with the
2002 Restructuring and in connection with the approvals granted
in 2007[.]” Mem. Op. at 26-27, Mar. 29, 2011. However, the
13
record does not reflect that the agency is presently considering
a similar major federal action. Plaintiff and the federal
defendants both propose that the Court enter an injunction that
would require the agency to perform an EIS for the “newly
proposed 895 MW Holcomb Expansion Project.” However, although
NEPA would require an EIS if RUS were considering an approval,
financial assistance for the project, or some other major
federal action, the Court has not been made aware of any such
action. 42 U.S.C. § 4332.
Plaintiff and the federal defendants request that the Court
remedy this problem by simply entering an order requiring
Sunflower to seek additional approval from RUS. Then RUS would
have a “major federal action” for which an EIS would be
necessary. The plaintiff proposes that the Court “declare[]
that previous consents and approvals that specifically reference
one or more 600 to 700 MW coal-fired generation facilities do
not constitute approval for the current configuration of the
Holcomb Expansion Project, and that Sunflower will need
additional approval from RUS before taking any additional action
with respect to the Project.” Pl.’s Proposed Order. The
federal defendants similarly propose that the Court order
Sunflower “to seek approval from RUS for the newly proposed 895
MW Holcomb Expansion Project.” Fed. Defs.’ Proposed Order.
However, although the federal defendants have made it clear that
14
they consider the 2007 approvals to be insufficient in light of
subsequent changes to the scope of the proposed Project, and
have taken the position that Sunflower will need to seek
additional approvals before proceeding with the Holcomb
Expansion Project, the continuing validity of the 2007 approvals
is simply not before the Court in this action.
The federal defendants’ primary argument in this respect is
that Sunflower signed a settlement agreement in May 2009 with
the State of Kansas that drastically altered the plans for the
Holcomb Expansion Project. (For example, as noted above,
instead of three 700 MW generating units, the settlement calls
for the construction of a single 895 MW generating unit.) The
federal defendants assert that Sunflower failed to consult with
or seek approval from RUS before signing the settlement
agreement with the State of Kansas and argue that Sunflower
should now be ordered to seek such approval. The plaintiff
similarly reasons that the existing agreements between RUS and
Sunflower will require Sunflower to seek approvals from RUS in
the future, and the failure by Sunflower to obtain RUS approval
before entering into the settlement with the State of Kansas
constituted a breach of their existing contractual obligations.
The plaintiff and the federal defendants would have the
Court, at this late stage in the proceedings, delve into the
question of whether Sunflower is presently in breach of its
15
contractual obligations toward RUS, based largely on Sunflower’s
actions in 2009, a full two years after this action was
commenced. While RUS has clearly taken the position that
Sunflower is, or will be, in breach of its contractual
obligation to seek approvals from RUS for certain actions, that
question is not properly before this Court. Accordingly, an
injunction directing Sunflower to immediately seek approval from
RUS is inappropriate at this juncture.
ii. Proposed Order Directing RUS to Perform an EIS
for Any Future Actions Related to the Holcomb
Expansion Project
This brings the Court to the next proposal, again supported
by both the plaintiff and the federal defendants, for an
injunction that would essentially direct RUS to refrain from
granting any approvals, financial support or take any other
major federal action in connection with the Holcomb Expansion
Project without performing an EIS. While this proposal does not
suffer from the same flaws as the one previously discussed, the
Court must still consider whether plaintiff has satisfied the
four-factor test. The four factors, as noted above, are “(1)
that [plaintiff] has suffered an irreparable injury; (2) that
remedies available at law, such as monetary damages, are
inadequate to compensate for that injury; (3) that, considering
the balance of hardships between the plaintiff and defendant, a
remedy in equity is warranted; and (4) that the public interest
16
would not be disserved by a permanent injunction.” Monsanto,
130 S. Ct. at 2756 (internal quotations omitted).
The Court concludes that plaintiff has met its burden.
First, plaintiff has sufficiently demonstrated irreparable harm.
Plaintiff argues that “the Holcomb Expansion will emit
substantial quantities of air pollutants that endanger human
health and the environment” and thereby cause irreparable harm.
Pl.’s Supp. Reply Br. at 14. In support of its position,
plaintiff relies upon the affidavits submitted in support of its
motion for a preliminary injunction, particularly that of Dr.
Jonathan Levy, an Associate Professor of Environmental Health
and Risk Assessment at the Harvard School of Public Health.
Dr. Levy begins broadly with the assertion that “[c]oal-
fired power plants emit a number of pollutants of potential
concern for public health, including fine and coarse particulate
matter, sulfur dioxide, nitrogen oxides, volatile organic
compounds, mercury, and other hazardous air toxics.” Levy Decl.
¶ 4. He then discusses certain pollutants in detail. For
example, Dr. Levy considers particulate matter pollution,
defined as “a broad class of chemically and physically diverse
substances that exist as discrete particles (liquid droplets or
solids) over a range of sizes.” Levy Decl. ¶ 5. Particulate
matter pollution can be classified by particle size, and Dr.
Levy explains that “PM2.5” (particulates less than 2.5
17
micrometers in aerodynamic diameter) “pose[] a greater risk of
severe health problems (including premature death), given their
ability to penetrate deeper into the lungs. . . . [and] can
remain suspended for longer periods of time in the atmosphere
and can travel much greater distances.” Levy Decl. ¶ 7.
Relying upon various assumptions, Dr. Levy calculates the
expected quantities of PM2.5 from the Holcomb site and comes to
the conclusion that “construction and operation of the proposed
unit at the Holcomb site in Kansas would contribute to
particulate matter concentrations in the vicinity of the plant
and in downwind areas, increasing the health risks . . . to
individuals in those areas.” Levy Decl. ¶ 15. According to Dr.
Levy, “[e]xposure to airborne PM is associated with a number of
serious health problems, such as premature death, cardiovascular
and respiratory hospitalizations, and other forms of respiratory
and cardiovascular morbidity. These health problems are
particularly likely to occur in sensitive populations, including
the elderly, children, and individuals with diabetes or
cardiopulmonary disease.” Levy Decl. ¶ 6.
Similarly, Dr. Levy states that coal-burning power plants
are the “largest human-cause source of mercury emissions to the
air in the United States,” and that “[i]t is my opinion that
construction and operation of the proposed unit at the Holcomb
site in Kansas would increase concentrations of mercury in the
18
air, which may then be deposited locally or carried great
distances. Once this mercury enters the water, it will pose
health risks to persons exposed to it[.]” Levy Decl. ¶¶ 29-30.
Plaintiff also relies upon the declaration of Dr. Johannes
Feddema, a climate researcher, for an analysis of the increased
carbon dioxide emissions associated with new coal-fired power
plants. Feddema Decl. ¶¶ 4-27.
Sunflower’s main argument in opposition appears to be that
emissions from the planned 894 MW generating unit “will be
significantly below those of the average U.S. coal facility[.]”
Sunflower’s Supp. Br. at 20. In support of this assertion,
Sunflower has submitted an affidavit of Scott Bloomberg, a
consultant with expertise in “the electric sector, including new
investment options (generation choice), environmental risk and
compliance, climate policy, transmission, renewable portfolio
standards and fuel markets.” Bloomberg Aff. ¶ 2. Sunflower
also asserts that the Holcomb Expansion Project “has already
undergone, and continues to undergo, extensive environmental
review of its impact on the air, water, land, endangered
species, and human health in order to obtain the various permits
and approvals required to operate,” and that the Kansas
Department of Health and Environment has already evaluated the
potential hazardous air pollutant output for the plant.
Sunflower’s Supp. Br. at 20.
19
Even assuming Sunflower’s assertions to be true, neither
adequately counters the declaration of Dr. Levy, which contains
specific, detailed estimates of various pollutants that would be
emitted by the Holcomb site and the resulting harms. Whether or
not some other coal facility emits greater quantities of
particulate matter or mercury, for example, has no bearing on
whether or not there will be irreparable harm here. Although
Sunflower does dispute plaintiff’s assertion that one coal
facility will create a sufficient quantity of carbon dioxide
emissions to have a measurable impact on the climate, Sunflower
fails to offer any persuasive evidence that would counter
plaintiff’s detailed submissions on other pollutants.7 Upon
consideration of these submissions, as well as the other
affidavits and arguments put forward by the parties, the Court
concludes that the plaintiff has demonstrated irreparable
injury.
7
Sunflower has also submitted the affidavit of L. Earl
Watkins, Sunflower’s President and Chief Executive Officer.
Sunflower cites specifically to Mr. Watkins’ assertions that he
“disagree[s] with Plaintiff’s assertion that somehow the
construction of [the single 895 MW coal-fired unit] will
endanger the health of Kansans[.]” Watkins Aff. ¶ 9. Mr.
Watkins asserts that the Kansas Department of Health and
Environment “found that [the single 895 MW coal-fired unit] will
conform to the obligations under the [Clean Air Act] related to
impacts on National Ambient Air Quality Standards (“NAAQS”) for
sulfur dioxide (“SO2”), nitrogen oxides (“NOX”), particulate
matter less than 10 microns (“PM10”), particulate matter less
than 2.5 microns (“PM2.5”) and carbon monoxide (“CO”).” Watkins
Aff. ¶9.
20
With respect to the second factor, neither Sunflower nor
defendant disputes “that remedies available at law, such as
monetary damages, are inadequate to compensate for th[e]
injury,” Monsanto, 130 S. Ct. at 2756, and the Court concurs
that such a remedy is not available. As the Supreme Court has
explained, “[e]nvironmental injury, by its nature, can seldom be
adequately remedied by money damages[.]” Amoco Prod. Co. v.
Village of Gambell, 480 U.S. 531, 545 (1987).
This brings the Court to the third and fourth factors,
which consider the balance of hardships and the public interest.
Here, in light of the limited injunction being considered,
namely a prospective injunction that would require RUS to
perform an EIS before granting approvals or giving financial
assistance to Sunflower in connection with the Holcomb Expansion
Project, the balance of equities tips in plaintiff’s favor.
Regarding the balancing of the harms to the parties, the
federal defendants themselves have proposed a limited injunction
of this type and do not suggest any harm that would befall them
if it were granted. Moreover, although Sunflower details harms
that it might suffer if injunctive relief is awarded, its
recitation of harms appears to stem from the inaccurate
assumption that the injunction would permanently bar it from
proceeding with the Holcomb Expansion Project. See, e.g.,
Sunflower Supp. Br. at 22 (“Enjoining RUS approvals would shut
21
down Sunflower’s ability to function by preventing it from
complying with its obligations to meet reliability needs in
western Kansas and maintain and operate over 2,215 miles of
transmission lines, 76 substations, and 1,199 MW of existing
generation.” (citing Watkins Aff. ¶¶ 46, 54-56)). Similarly,
Sunflower asserts that injunctive relief would “erode
Sunflower’s liquidity and cash position” and potentially prevent
Sunflower from meeting its obligations to third parties.
However, Sunflower has failed to identify how mere delays caused
by RUS undertaking an EIS, rather than a complete bar, would
cause these or any other harms. Plaintiff, on the other, hand
has identified substantial and irreparable harm that would occur
if no injunctive relief is awarded.
Finally, Sunflower argues that the public interest is best
served by rejecting injunctive relief, citing to the interests
of RUS in carrying out its duties and the interests of energy
consumers, particularly rural consumers. Sunflower’s Supp. Br.
at 23-24. However, once again Sunflower’s arguments do not
address how a delay in the construction of the Holcomb Expansion
Project that may be necessary to allow the agency to conduct an
EIS will prejudice these interests. On the other hand, the
public has an interest in ensuring that federal agency actions
taken in connection with the building of coal-fired power plants
comply with the requirements of NEPA.
22
Accordingly, the Court concludes that limited injunctive
relief is warranted. Specifically, an order directing RUS not
to issue any approvals or consents for agreements or
arrangements directly related to the Holcomb Expansion Project,
or to take any other major federal actions in connection with
the Holcomb Expansion Project, until an EIS is complete, is
appropriate.8
B. Appropriate Injunctive Relief Against Sunflower
In addition to an injunction against RUS, plaintiff
requests an injunction against Sunflower. Plaintiff has
proposed a broadly worded injunction that would bar Sunflower
8
Both the plaintiff and the federal defendants have proposed
an injunction for this purpose, and there are only minor
differences between the parties’ proposed language. Plaintiff’s
request is a broader one, asking the Court to enjoin “any
actions” in support of the Project, rather than just “consents
and approvals.” Furthermore, RUS has added the word “directly”
to their proposal. Plaintiff argues that “the word ‘directly’
does not appear in the governing loan documents . . . nor is it
otherwise defined,” and that it is “appropriate for the Court’s
injunction to track the language that RUS and Sunflower
negotiated in the loan documentation[.]” Pl.’s Supp. Reply Br.
at 4. The federal defendants, on the other hand, assert that
their version is the appropriate one because plaintiff’s version
“is ambiguous and could be read as proposing the broadest
possible injunction, which may have the effect of preventing RUS
from administering the complex contractual terms governing
Sunflower’s outstanding debt owed to the Agency.” Fed. Defs.’
Br. at 12-13. In addition, the federal defendants argue that
plaintiff’s proposed injunction “is not sufficiently tailored so
as to address the procedural violations the Court found and yet
not unduly burden RUS in the administration of its duties and
its mission[.]” Fed. Defs.’ Br. at 13. The Court concludes
that the federal defendants have the better argument here.
23
from: “a) commencing construction of the expansion of the
Holcomb 1 coal-fired generation facility; and b) entering into
any agreement or other arrangements for the development of the
Holcomb Expansion Project.” Pl.’s Proposed Order.
Plaintiff argues that an injunction against Sunflower is
necessary for two reasons. First, plaintiff asserts that if
Sunflower were to initiate any construction activity, it would
“significantly undermine” the NEPA process and would violate 40
C.F.R. § 1506.1.9 Second, plaintiff asserts that “[i]f the Court
were to only enjoin RUS from taking action . . . Sierra Club is
concerned that Sunflower would forego requesting required RUS
approvals and move ahead with the Project while the EIS is being
prepared.” Pl.’s Supp. Br. at 15. According to plaintiff, “an
injunction against Sunflower is necessary to preserve a
meaningful opportunity for RUS’s consideration of impacts and
alternatives in a full EIS.” Pl.’s Supp. Br. at 15.
In support of its position, plaintiff relies on Foundation
on Economic Trends v. Heckler, 756 F.2d 143, 155 (D.C. Cir.
9
Section 1506.1 provides: “(a) Until an agency issues a
record of decision . . . no action concerning the proposal shall
be taken which would: (1) Have an adverse environmental impact;
or (2) Limit the choice of reasonable alternatives. . . . If any
agency is considering an application from a non-Federal entity,
and is aware that the applicant is about to take an action
within the agency’s jurisdiction that would meet either of the
criteria in paragraph (a) of this section, then the agency shall
promptly notify the applicant that the agency will take
appropriate action to insure that the objectives and procedures
of NEPA are achieved.” 40 C.F.R. § 1506.1
24
1985), in which the D.C. Circuit held that “it is well
established that judicial power to enforce NEPA extends to
private parties where non-federal action cannot lawfully begin
or continue without the prior approval of a federal agency.
Were such non-federal entities to act without the necessary
federal approval, they obviously would be acting unlawfully and
subject to injunction.” Id. (internal citations and quotation
marks omitted).
The problem with plaintiff’s position is that, particularly
given the breadth of plaintiff’s proposed injunction against
Sunflower, plaintiff has not shown that all of the non-federal
action it seeks to enjoin “cannot lawfully begin or continue
without the prior approval of a federal agency.” Id. (emphasis
added). In Foundation on Economic Trends, the court affirmed a
preliminary injunction enjoining the National Institutes of
Health (“NIH”), a federal agency, from approving an experiment
that would release genetically engineered organisms into the
open environment until an appropriate environmental assessment
was complete. Id. In so doing, the Circuit explained that,
because federal regulations required that any entity seeking to
deliberately release such organisms obtain approval from the NIH
before doing so, “the [non-federal party] cannot lawfully go
forward with its experiment, and it can thus be enjoined by the
court.” Id.
25
Here, however, unlike the plaintiff in Economic Trends,
plaintiff has failed to demonstrate that all of the “non-federal
action” envisioned by such a broad injunction “cannot lawfully
begin or continue without the prior approval of a federal
agency.” Found. on Econ. Trends, 756 F.2d at 155. This
proposed injunction is flawed for the same reasons that the
proposed injunction ordering RUS to immediately begin an EIS is
flawed. In order for such an injunction to be appropriate, the
Court would need to determine that the previous consents and
approvals granted by RUS do not constitute approval for the
current configuration of the Holcomb Expansion Project, and that
Sunflower could not lawfully take any additional action with
respect to the Holcomb Expansion Project until such approvals
are sought. As explained above, however, the continuing
validity of the 2007 approvals is simply not before the Court in
this action. Accordingly, plaintiff’s request for an injunction
against Sunflower, the non-federal party in this action, is
denied.
C. Whether Vacatur is Appropriate
The final question before the Court is whether the agency
action, specifically the 2002 restructuring and the 2007
approvals, must be vacated. The Administrative Procedure Act
(“APA”) provides that the reviewing court “shall . . . hold
unlawful and set aside agency action . . . found to be . . .
26
arbitrary, capricious, an abuse of discretion, otherwise not in
accordance with law[.]” 5 U.S.C. § 706. While vacatur may be
the default remedy for a NEPA violation, the Court is not
without discretion. “The decision whether to remand or vacate
‘depends on [1] the seriousness of the order’s deficiencies (and
thus the extent of doubt whether the agency chose correctly) and
[2] the disruptive consequences of an interim change that may
itself be changed.’” Milk Train, Inc. v. Veneman, 310 F.3d 747,
755-756 (D.C. Cir. 2002) (quoting Allied-Signal, Inc. v. U.S.
Nuclear Regulatory Comm’n, 988 F.2d 146, 150-51 (D.C. Cir.
1993)).
In Sugar Cane Growers Cooperative of Florida v. Veneman,
289 F.3d 89 (D.C. Cir. 2002), for example, this Circuit held
that the Department of Agriculture failed to comply with certain
provisions of the APA when it implemented a “payment-in-kind”
program for sugar, essentially offering sugar beet farmers an
incentive to destroy a certain amount of their crops. Rather
than vacate the agency action, however, the court ordered a
remand to the agency, explaining that:
Normally when an agency so clearly violates the APA we
would vacate its action . . . and simply remand for
the agency to start again. Unfortunately, because we
denied preliminary relief in this case, the 2001
program was launched and crops were plowed under. The
egg has been scrambled and there is no apparent way to
restore the status quo ante. . . . Appellants insist
that we have no discretion in the matter; if the
Department violated the APA – which it did – its
27
actions must be vacated. But that is simply not the
law.
Id. at 97-98 (internal citations and quotation marks omitted).
Similarly, in Milk Train, Inc. v. Veneman, milk producers
challenged a subsidy program implemented by the Department of
Agriculture. Although the court found flaws in the subsidy
program, the court concluded that “there is at least ‘a serious
possibility’ that the Secretary on remand could explain [the
subsidy program] in a manner that is consistent with the statute
or choose an allocation method to correct the problem, a factor
that favors remanding rather than vacating.” 310 F.3d at 756.
In the instant case, the Court is persuaded that injunctive
relief requiring RUS to perform an EIS before any future
approvals or consents are given or any other major federal
action taken related to the Holcomb Expansion Project, coupled
with the federal defendants’ own emphatic conclusion that
Sunflower must seek additional approvals from RUS before the
Holcomb Expansion Project can proceed, create more than “a
serious possibility” that RUS will be able to correct the
problem caused by the earlier failure to comply with NEPA.10
10
As mentioned above, the federal defendants and plaintiff
are in agreement that the 2007 approvals “are no longer
effective in light of significant changes to the configuration
of this [Holcomb Expansion] Project.” Fed. Defs.’ Supp. Br. at
6; Pl.’s Supp. Br. at 1. The federal defendants have stated in
no uncertain terms that, “due to the significant changes
Sunflower made to the configuration of the Holcomb Expansion
28
That is to say, an EIS will be completed before the construction
of the Holcomb Expansion Project can proceed. See, e.g.,
Advocates for Highway & Auto Safety v. Fed. Motor Carrier Safety
Admin., 429 F.3d 1136, 1151 (D.C. Cir. 2005) (concluding vacatur
was not appropriate in part because the plaintiff conceded that
leaving the rule in place would “do no affirmative harm”).
Next, the Court must consider the “the disruptive
consequences of an interim change that may itself be changed[.]”
Milk Train, Inc., 310 F.3d at 756. Even plaintiff states that
“[o]n the complicated facts of this case . . . the ‘default
remedy’ of vacatur of the 2002 and 2007 decisions is
unnecessary” Pl.’s Supp. Br. at 5.11 Sunflower also provided a
detailed description of the disruptive impact that vacating the
2007 approvals would have. In particular, Sunflower asserts
that after the 2007 approvals were granted by RUS “a series of
transactions was promptly consummated in reliance on the 2007
RUS Approvals.” Sunflower Supp. Br. at 33-34. Sunflower
Project subsequent to the Agency’s approvals in 2007, the
Holcomb Expansion Project requires new RUS approvals.” Fed.
Defs.’ Supp. Br. at 1. Specifically they explain that “[d]ue to
material changes in the development of the Holcomb Expansion
Project . . . RUS has concluded that its approvals and
implementing documents require Sunflower to seek new approvals
from RUS for the drastic changes to the Holcomb Expansion
Project from the proposal RUS previously reviewed and approved
in 2007.” Fed. Defs.’ Supp. Br. at 8 (emphasis added).
11
Plaintiff only asks for vacatur in the alternative to the
other relief it requests.
29
identifies Tri-State as “an express third-party beneficiary of
the 2007 RUS Approvals” and also asserts that “RUS and
Sunflower’s other secured creditors entered into agreements with
Tri-State.” As noted above, Sunflower also issued promissory
notes, to RUS and other creditors, in conjunction with the 2007
approvals. Furthermore, Sunflower points out that bills of sale
were executed among Sunflower, HCF and the predecessor company,
also in conjunction with the 2007 approvals. None of these
other parties are before this Court. Sunflower also describes
various ways in which it, as well as other parties, would suffer
substantial financial loss if the Court were to vacate the 2007
approvals. The federal defendants agree that “vacatur would
involve unwinding complex financial instruments and would affect
third parties not party to this lawsuit.” Fed. Defs.’ Supp. Br.
at 6.
The Court need not reach the question of whether, standing
alone, the disruption described by Sunflower is enough to
counsel against vacatur. However, in combination with RUS’s
stated position that Sunflower will need to seek additional
approvals from RUS (subject to an EIS), the Court concludes that
vacating the 2007 approvals is not warranted in the instant
case.
30
III. CONCLUSION
For the foregoing reasons, the Court hereby DECLARES that
RUS violated NEPA by failing to prepare an EIS prior to
providing approvals and financial support for the Holcomb
Expansion Project. It is FURTHER ORDERED that RUS shall not
issue any approvals or consents for agreements or arrangements
directly related to the Holcomb Expansion Project, or take any
other major federal actions in connection with the Holcomb
Expansion Project, until an EIS is complete. It is FURTHER
ORDERED that this matter is REMANDED to RUS to determine what
further action, if any, is necessary or appropriate in light of
the Court’s opinion. An appropriate Order accompanies this
Memorandum Opinion.
SIGNED: Emmet G. Sullivan
United States District Court Judge
January 30, 2012
31