IN THE SUPREME COURT OF MISSISSIPPI
NO. 2013-CC-00165-SCT
MISSISSIPPI COMMISSION ON
ENVIRONMENTAL QUALITY, MISSISSIPPI
DEPARTMENT OF ENVIRONMENTAL QUALITY
AND MISSISSIPPI ENVIRONMENTAL QUALITY
PERMIT BOARD
v.
BELL UTILITIES OF MISSISSIPPI, LLC
DATE OF JUDGMENT: 01/08/2013
TRIAL JUDGE: HON. DEBORAH J. GAMBRELL
ATTORNEYS FOR APPELLANTS: LISA THOMPSON OUZTS
ROY FURRH
ATTORNEY FOR APPELLEE: KATHRYN H. HESTER
NATURE OF THE CASE: CIVIL - STATE BOARDS AND AGENCIES
DISPOSITION: AFFIRMED IN PART; VACATED IN PART
AND RENDERED - 04/10/2014
MOTION FOR REHEARING FILED:
MANDATE ISSUED:
BEFORE RANDOLPH, P.J., PIERCE AND KING, JJ.
KING, JUSTICE, FOR THE COURT:
¶1. Lawrence Elliott owned and operated the Black Creek Water and Wastewater systems
in Forrest County from the 1990s until 2005. The systems are a few miles upstream of an
area of Black Creek that is designated as a National Wild and Scenic River. Under Elliott’s
ownership and operation, the systems suffered numerous violations of environmental
regulations, including multiple illegal sewage discharges. Bell Utilities purchased the
systems from Elliott in 2005 and vastly improved the situation, expending its own money in
an attempt to bring the system into compliance. In this vein, Bell entered into an Agreed
Order with the Mississippi Department of Environmental Quality in which compliance issues
were addressed, and in which Bell agreed to put up a $20,000 financial assurance that would
be returned to Bell after two years of adequate compliance. In 2010, Bell sought to sell the
Black Creek systems to Utility One, LLC, and to transfer the attendant permits to it. MDEQ
refused to transfer Bell’s wastewater permit to Utility One unless Utility One put up a
$20,000 financial assurance. Bell appealed the denial of the permit transfer to the chancery
court. The chancery court reversed the Permit Board, finding that its actions were arbitrary
and capricious because it has not promulgated regulations on how to conduct a regulatory
hearing and on when and whether to demand financial assurances prior to permit transfer.
It ordered MDEQ and the Permit Board to promulgate such regulations. MDEQ appeals to
this Court. Because this Court finds that the Permit Board’s demand of $20,000 from Utility
One to transfer the permit was beyond its power, this Court reverses and renders the Permit
Board’s denial of the permit transfer, thus affirming the portion of the chancery court
judgment that reverses the Permit Board. However, because the agencies are not required
under the APA to promulgate rules and regulations for formal Permit Board hearings, we
vacate the portion of the trial court’s judgment that requires them to do so.
FACTS AND PROCEDURAL HISTORY
¶2. Several state agencies are involved in this case. The Mississippi Commission on
Environmental Quality (“Commission”) is the agency tasked with carrying out the state’s
policies preventing, controlling, and abating pollution of the State’s air and waters by
2
enforcing pollution control laws and regulations and any permits issued by the Permit Board.
The Mississippi Environmental Quality Permit Board (“Permit Board”) has the power to take
action on permits administered through MDEQ. The Mississippi Department of
Environmental Quality (“MDEQ”) is tasked with providing technical assistance and support
to the Commission and Permit Board, and its duties include conserving, managing,
developing, and protecting the State’s natural resources. The duties of the Mississippi
Department of Health (“MSDH”) include regulating drinking water systems. The
Mississippi Public Service Commission (“PSC”) regulates water and sewer utilities,
specifically rates, service, and whether the facilities are required for the convenience and
necessity of the public.
¶3. The “Black Creek System” consists of a water treatment system and a wastewater
system, and is located in Forrest County 1 on the Black Creek. Black Creek is a state scenic
stream, and a portion downstream from the Black Creek System is designated as a National
Wild and Scenic Stream. 16 U.S.C. § 1274(a)(59); Miss. Code Ann. § 51-4-23.4 (Rev.
2003). Lawrence Elliott constructed the Black Creek System to service developments in the
area.
¶4. During his ownership, Elliott committed many compliance violations. MDEQ also
received an “inordinate” number of citizen complaints for the Black Creek System under
Elliott’s ownership. All in all, Elliott’s numerous violations and pervasive non-compliance
1
Confusingly, many key documents in the record indicate that the system is in Lamar
County, while others indicate that it is in Forrest County. At oral argument, the parties
conceded that the system is in Forrest County and that documents to the contrary are
mistaken.
3
resulted in poor to nonexistent service to residents and numerous illegal sewage discharges.
Because Elliott refused to make needed repairs, MDEQ was forced to expend over $63,000
from the Pollution Emergency Fund to keep the system operable and to protect the citizens
and the environment.
¶5. Because of the dire situation at Black Creek caused by Elliott, the PSC began looking
for someone to purchase the Black Creek System. The PSC approached Bell and asked Bell
to consider purchasing the system. Bell ultimately agreed and purchased the Black Creek
System.
¶6. In late 2004, the Commission, MSDH, and Bell entered into an Agreed Order
regarding the Black Creek System in anticipation of Bell’s impending purchase of the Black
Creek System from Elliott. The Agreed Order noted that the system was “not in compliance
with applicable permits, certificates, and federal and state laws and regulations” and that
“Bell has committed to operate the . . . System and cause . . . [it] to achieve compliance with
all federal and state laws and regulations, and permits.” The purpose of the Agreed Order
was to bring the Black Creek System into compliance, by giving Bell time and help to bring
the extremely troubled system into compliance. It also outlined some of Bell’s specific
obligations to the end of achieving compliance.
¶7. The Agreed Order provided that any sale or conveyance of the Black Creek System
would not relieve Bell of its obligations under the order:
[n]o change in ownership, corporate, and/or partnership status relating to the
[Black Creek] System that is covered by this Agreed Order will in any way
alter the responsibilities of Bell under this Agreed Order. In the event of any
conveyance of easement, or other interest in the [Black Creek System], . . . all
4
of Bell’s obligations under the Agreed Order shall remain in full force and
effect and shall continue to be met.
However, the agreement did provide that if a private party acquired the Black Creek System,
“and the acquisition is approved by the appropriate regulatory authority(s)”, then Bell’s
responsibilities under the Agreed Order would be relieved upon the transfer of all necessary
permits to the new owner. (Emphasis added). Later in the same paragraph, the Agreed Order
provided merely that “Bell shall notify the Agencies in the event of any such conveyance.”
(Emphasis added). The Agreed Order further provided that “[a]ny deed, title, or other
instrument of conveyance executed by Bell that transfers title to any part of the [Black Creek
System] shall contain a notice that the [Black Creek System] is the subject of this Agreed
Order.” The financial assurance provision of the Agreed Order stated that “Bell shall
provide financial assurance of $20,000 . . . The financial assurance shall be secured within
thirty days from obtaining all necessary permits from the Permit Board. Bell shall continue
to provide this financial assurance for a period of two years at which time the requirement
shall cease if Bell demonstrates an adequate compliance for the duration of the two-year
period.” The Agreed Order noted that if Bell and MDEQ do not agree on the adequacy of
the compliance record, the matter should be taken before the Commission for a
determination. The adequacy of the compliance was to be determined by the forfeiture
provisions of Mississippi Code Section 49-17-44(2).2
2
Section 49-17-44(2) provides that
The commission may enter an order requiring forfeiture of the bond or other
financial security, if the commission determines that:
(a) The continued operation or lack of operation and maintenance of the
facility . . . represents an imminent threat to the public health, welfare and the
5
¶8. Bell ultimately took control of the Black Creek System on January 7, 2005. MDEQ
inspected the system fairly regularly. While early inspections in 2005 indicate some
significant problems, ostensibly due to the state of disrepair the system was in when Bell
acquired it, inspections by 2006 indicated that the system was much improved regarding
compliance. Moreover, one 2005 inspection noted that erosion seemed to be a continuing
issue for the site, and that an entirely new system could be constructed at a different location
for what it would cost to permanently fix the erosion issue. It indicated that erosion should
continue to be fixed if and when it occurred.
¶9. In 2008, Bell Utilities entered into negotiations with Ni-America to sell them the
Black Creek System. Bell worked with MDEQ regarding the prospective sale. On July 1,
2008, Bell wrote to MDEQ requesting that MDEQ find that Bell had satisfied the
requirements and obligations of the Agreed Order. On July 8, 2008, MDEQ inspected the
Black Creek System “[t]o determine the facility’s compliance with [the] Agreed Order.” The
inspection report concluded that “[o]verall the site was in satisfactory operating condition
and appears to have met the conditions set forth in the Agreed Order regarding the collection
system.” On August 7, 2008, Bell transmitted the $20,000 financial assurance to MDEQ to
satisfy the Agreed Order, noting that “we anticipate closing [with Ni-America] in the next
environment because the permittee is unable or unwilling to adequately
operate and maintain the facility or the facility has been actually or effectively
abandoned by the permittee;
(b) Reasonable and practical efforts under the circumstances have been made
to obtain corrective actions from the permittee; and
(c) It does not appear that corrective actions can or will be taken within an
appropriate time as determined by the commission.
6
day at which time we will discuss the release of these funds in regards to Ni-America
assuming the responsibilities for Black Creek Utility.” The financial assurance was
submitted over three years after the submission date contemplated by the Agreed Order.
¶10. On August 11, 2008, Trey Smith, a Senior Attorney with MDEQ, sent Bell a letter
regarding the Agreed Order. The letter stated that it was “MDEQ’s written notice that Bell
Utilities of Mississippi, LLC . . . has appeared to satisfy and complete the outstanding
requirements and obligations of Agreed Order 4928-04 within the authority of the
Mississippi Commission on Environmental Quality . . . .” The letter further noted that an
inspection of the Black Creek System was performed on July 8, 2008 “at which time the
facility was found to be in compliance with the conditions of Agreed Order No. 4928-04.”
It stated that “[t]he requirements of the Order appear to have been completed and no further
action by Bell regarding Agreed Order No 4928-04 will be required by the Commission or
MDEQ.” (Emphasis added). The letter also confirmed that MDEQ was in receipt of Bell’s
$20,000 financial assurance. It then informed Bell that “[i]n the event that Bell sells, assigns
and/or otherwise transfers title and/or control of Black Creek Retreat, the financial assurance
of $20,000 provided . . ., upon the Commission receiving satisfactory replacement financial
assurance from the acquiring party, shall be returned to Bell . . . or if alternative financial
assurance was provided all rights and interests in such financial assurance shall be
immediately terminated.” It concluded that the letter did not limit the rights of MDEQ “for
future violations of environmental laws, rules, regulations and permit conditions.” The sale
of the Black Creek System to Ni-America fell through shortly thereafter.
7
¶11. MDEQ inspected the Black Creek System again on August 4, 2009. MDEQ noted a
few violations, notably that access to the lagoon was not restricted, significant erosion had
occurred at the bottom of the levee, and four-wheeler trails were on the levee and such
activity should be prevented.
¶12. In 2010, Bell and Steve Womack 3 , the operator of the Black Creek Systems since
2008, began discussing selling the Black Creek System to Womack’s newly created
company, Utility One. On September 24, 2010, Bell and Womack requested that MDEQ
transfer the permit from Bell to Womack. The cover letter stated that “[t]he form indicates
a closing date of November 1, 2010, but due to the need for . . . [PSC] approval, the final
closing may occur at a later date. . . . Please review this information and call if there are any
problems with the transfer or if you need additional information.” 4 On December 6, 2010,
counsel for Bell exchanged emails with Harry Wilson of MDEQ regarding the transfer, and
Wilson stated that MDEQ was looking into the issue and would get back to Bell shortly.
¶13. On December 7, 2010, the PSC approved the sale of the Black Creek System to Utility
One, including transferring Bell’s Certificate of Public Convenience and Necessity to Utility
One. The PSC found that Utility One was “ready, fit, willing and financially able and
intends in good faith to furnish reasonably adequate sewer service to all persons within Bell’s
certificated area that is being transferred.”
3
Womack was a Level IV Operator, who operated several wastewater systems in
Mississippi.
4
Bell apparently followed similar protocol with the MSDH, which requested that Bell
and Utility One enter into a new Agreed Order covering the water system. Bell and Utility
One did enter such an order on December 6, 2010.
8
¶14. On December 13, 2010, Bell again wrote to MDEQ requesting that it facilitate the
permit transfer. It noted that the transfer to Utility One was scheduled to close on December
14, 2010.5 MDEQ and Bell continued to go back and forth about the transfer and the
$20,000 during January, February, and March of 2011. MDEQ informed Bell that it would
require financial assurance from Utility One before recommending or approving the permit
transfer. Roy Furrh, MDEQ General Counsel, admitted that Bell dealt with the conveyance
to Utility One in the “normal regulatory way,” but indicated that, because of the Agreed
Order, that was not sufficient.
¶15. On January 28, 2011, MDEQ inspected the Black Creek System. The inspection
concluded that the lagoon should have a level measuring device installed, vegetation
overgrowth around the lagoon should be cut, the effluent pipe from the filter-box should be
repaired, and all manholes and pump stations should have covers in place. The inspection
also noted that the levee had “no apparent problems, nor any sign of recent overflows into
the surrounding area.”
¶16. On August 11, 2011, Bell filed a petition for a writ of mandamus in Hinds County
Chancery Court, requesting that the court require that MDEQ return Bell’s $20,000 financial
assurance and transfer Bell’s NPDES permit to Utility One. MDEQ represented in chancery
court that it would transfer the permit if Utility One provided the $20,000 in financial
assurance. On September 26, 2011, the Hinds County Chancery Court ordered MDEQ “to
submit the matter to the Permit Board for a transfer request at the October 11, 2011, Permit
Board meeting with comments by Bell Utilities and other interested parties as allowed under
5
The transfer did ultimately occur.
9
current Permit Board statutes.” It further ordered that, if the Permit Board denied the
transfer, Bell must be given an evidentiary hearing before the Permit Board on or before
December 13, 2011.” It stated that if the Permit Board denied the transfer, Bell may return
to the chancery court to appeal the decision.
¶17. At its October 11, 2011, meeting, the Permit Board denied Bell’s request to transfer
the permit to Utility One. It noted that “MDEQ staff informed Bell and Utility One that
MDEQ would not recommend the issuance of the permit transfer and release of the $20,000
in financial assurance provided by Bell until substitute or alternate financial assurance was
provided.” Bell therefore requested an evidentiary hearing. On October 18, 2011, Furrh sent
Bell and Womack a letter attaching the Permit Board hearing procedures and outlining a
schedule. Furrh’s letter stated that the law “is not clear regarding the authority of a party
other than the hearing petitioner to participate in an evidentiary hearing without the express
authority of the Permit Board. . . . If Utility One, LLC would also like to participate in the
hearing, I suggest that it file a Motion to Intervene with the Permit Board. . . . Requiring
parties to file Motions to Intervene in similar circumstances is standard procedure with the
Permit Board.” Permit Board procedure required that all direct and rebuttal testimony must
be pre-filed, and that parties may call “adverse” witnesses without submitting pre-filed
testimony. Bell filed an objection to the Permit Board’s procedures on November 17, 2011,
arguing that the Permit Board has failed to formally promulgate rules and regulations
governing a formal hearing and challenging the requirement that direct and rebuttal
testimony must be pre-filed. The Permit Board Hearing Officer overruled Bell’s objections
in a December 8, 2011, order. She found the Permit Board statute regarding the
10
promulgation of regulations permissive in nature and concluded that the Permit Board’s long-
standing procedures, which apply equally to all parties and aid in administrative efficiency,
were not arbitrary and capricious.
¶18. On November 16, 2011, MDEQ again inspected the Black Creek System, with the
stated purpose of rebutting Bell’s pre-filed testimony for the evidentiary hearing. The
inspection found the following alleged violations: 1) several manhole concrete lid ring collars
were cracked or unsealed; 2) one electrical power outlet at one lift station was unprotected;
3) the level-measuring device in the lagoon did not clearly indicate the depth of the lagoon;
4) the lagoon had some vegetation growth around it; 5) the lagoon levee had “significant
erosion near the toe of the levee and spanning its entire length” and there was an “absence
of established vegetative stabilizing cover on this particular levee”; and 6) while the entrance
to the lagoon access road was fenced, the lagoon perimeter was not secured.
¶19. The Permit Board held an evidentiary hearing on the matter of Bell’s permit transfer
request on December 13, 2011. At the hearing’s outset, Womack asked to participate in the
hearing by offering testimony and evidence and cross-examining witnesses. MDEQ
objected, and the Hearing Officer sustained the objection, thus denying Womack the ability
to participate in the hearing as an interested party.6
¶20. In the opening argument for MDEQ, Furrh stated that “MDEQ recommends the
proposed transfer of the state operating permit from Bell to Utility One, LLC be denied
unless or until Bell and Utility One agree to provide $20,000 in financial assurance to protect
6
Womack did testify as a witness, called by Bell.
11
this extraordinary system.” MDEQ called Harry Wilson 7 and Michael Freiman 8 to testify,
as they had performed the November 16, 2011 inspection at the Black Creek System. Both
testified that Bell had compliance problems and that Utility One should put up financial
assurance in order for the permit to be transferred. When asked how MDEQ calculated the
amount of $20,000 as applied to Utility One, Wilson testified that “I don’t have a calculation.
I think it was a number that was fair. It’s a number that seemed reasonable from what we’d
seen out there in the past couple of years. But there’s not a calculation, so to speak.” The
hearing and attendant evidence primarily centered around issues of compliance, the $20,000,
and the Agreed Order. MDEQ emphasized the erosion issues found in the November 2011
inspection. Furrh closed MDEQ’s case recommending that “the permit be denied until
financial assurance is provided.”
¶21. The hearing concluded with one of the board members unequivocally stating that he
would vote to approve the transfer if Utility One agreed to provide $20,000 in financial
assurance, and would vote to deny the transfer if Utility One did not agree to give the
$20,000 financial assurance. The Permit Board then voted three to two to deny the transfer
of the permit. On March 13, 2012, the Permit Board adopted its Findings of Fact and
Conclusions of Law (FOFCOL) regarding its denial of the permit transfer. The Permit Board
found that the erosion issues were “significant and constitute an imminent danger to Black
Creek.” It further found that the erosion issues had not been adequately nor permanently
7
Wilson was the chief of the environmental permits division of MDEQ.
8
From 2007 to November 2011, Freiman was the chief of the municipal and private
facilities branch within the permit division of MDEQ. Beginning in November 2011, he
held the position of chief of the surface water division at MDEQ.
12
addressed. The Permit Board noted that “transfer from a permittee with financial assurance
to a never-before-permitted entity which will not agree to provide financial assurance should
be denied.” It concluded that “it is entirely reasonable for the Permit Board to deny transfer
of the permit unless and until Bell or Utility One brings the Black Creek System into
compliance and provides $20,000 in financial assurance, as required by the Agreed Order,
to protect this extraordinary and precious resource.” The Permit Board concluded that the
financial assurance is a “continuing obligation that binds the Black Creek system until the
Commission finds that all obligations under its Agreed Order have been met.” It also
determined that “the ongoing compliance issues, including the levee erosion, and
noncompliance with the Agreed Order, constitute a relevant basis to deny the transfer.”
¶22. Bell appealed the Permit Board’s decision to deny the transfer to the Hinds County
Chancery Court. MDEQ then moved to transfer venue to the Forrest County Chancery
Court. The court granted MDEQ’s motion, and the appeal proceeded in the Forrest County
Chancery Court. The arguments were fully briefed at the chancery court level, with the
chancery court sitting as the appellate court. The chancery court found that the Permit
Board’s operation without formal rules and regulations allowed it to yield “unbridled
authority” and thus the operation was arbitrary and capricious. It then reversed and
remanded the denial of the permit transfer and ordered the Permit Board to promulgate rules
and regulations regarding financial assurances. Bell then moved to amend the court’s order,
and its motion was granted. The court amended its order to reverse and remand the denial
of the permit transfer and ordered MDEQ and/or the Permit Board to promulgate rules and
regulations under the Mississippi Administrative Procedures Act (“APA”) for the Permit
13
Board’s formal hearings. It further stated that “[i]f the Permit Board wishes to require
financial assurance for wastewater systems such as the Black Creek Wastewater Treatment
Facility, then the Commission on Environmental Quality must first promulgate the rules and
regulations required by Miss. Code Ann. § 49-17-44.”
¶23. Aggrieved, MDEQ appeals to this Court, arguing that: 1) the APA does not require
the Permit Board to promulgate hearing procedure regulations for its formal hearings; 2) the
lack of promulgated hearing procedures does not violate due process; 3) the financial
assurance for the Black Creek System was governed by the Agreed Order, in that the
“financial assurance is a continuing obligation that binds the Black Creek System until the
Commission finds all obligations under the Agreed Order have been met;” and 4) the
chancery court used the wrong standard of review and failed to give proper deference to the
Permit Board.
ANALYSIS
Standard of Review
¶24. At the chancery court, Permit Board matters “shall be affirmed” “[i]f no prejudicial
error is found.” Miss. Code Ann. § 49-17-29(5)(b) (Rev. 2012). “If prejudicial error is
found the decision of the board shall be reversed and the chancery court shall remand the
matter to the Permit Board for appropriate action as may be indicated or necessary under the
circumstances.” Id. Appeals are to be considered only on the record as made before the
Permit Board. Id.; Sierra Club v. Miss. Envtl. Quality Permit Bd., 943 So. 2d 673, 677
(Miss. 2006). This Court reviews the matter under the same standard as does the chancellor
in his or her review. Sierra Club, 943 So. 2d at 677. Matters of law are to be reviewed de
14
novo, giving great deference to an administrative agency’s construction of its own rules and
regulations and the statutes under which it operates. Id. at 678 (quoting McDerment v. Miss.
Real Estate Comm’n, 748 So. 2d 114, 118 (Miss. 1999)). “Therefore, an agency’s decision
will not be disturbed on appeal absent a finding that it (1) was not supported by substantial
evidence, (2) was arbitrary or capricious, (3) was beyond the power of the administrative
agency to make, or (4) violated some statutory or constitutional right of the complaining
party.” Sierra Club, 943 So. 2d at 678 (quoting McDerment, 748 So. 2d at 118). Substantial
evidence is something more than a scintilla of evidence, yet less than a preponderance of the
evidence. Sierra Club, 943 So. 2d at 678. Further, “[a]n action is arbitrary or capricious if
the agency entirely failed to consider an important aspect of the problem, or offered an
explanation for its decision that runs counter to the evidence before the agency or is so
implausible that it could not be ascribed to a difference in view or the product of agency
expertise.” Id. (internal quotations omitted). “A rebuttable presumption exists in favor of
agency decisions, and this Court may not substitute its own judgment for that of the
agency.” 9 Id.
9
Bell argues that this Court should review the agency’s decision de novo because
MDEQ, Bell’s adversary in the formal hearing, authored the Permit Board’s FOFCOL.
However, this Court recently rejected the argument that factual findings should be reviewed
under any sort of “heightened scrutiny,” even if they are adopted verbatim from a party’s
proposed findings of fact. Bluewater Logistics, LLC v. Williford, 55 So. 3d 148, 156-57
(Miss. 2011). However, “should a party suspect and suggest that the judge’s factual findings
are somehow tainted or untrustworthy, we hold that the party – upon proper proof – may seek
a new trial.” Id. at 157. Likewise, if the Permit Board’s factual findings appear tainted or
untrustworthy, this Court may find that the Permit Board’s findings are not supported by
substantial evidence and/or are arbitrary and capricious, upon proper proof.
15
Financial Assurance 10
¶25. MDEQ argues on appeal that “[t]he Permit Board denied transfer because of
unresolved compliance issues.” While the Permit Board certainly considered compliance
issues, as it had every right to do,11 the record makes abundantly clear that the Permit Board’s
decision was not based solely, or even primarily, on compliance issues. MDEQ and the
Permit Board made it abundantly and unequivocally clear that, notwithstanding the
compliance and other issues, the permit would have been transferred had Utility One
provided $20,000 in financial assurance.12 MDEQ also argues that the $20,000 and the
compliance issues are intertwined because the Agreed Order and its financial assurance
provision apply to the Black Creek System, and thus apply to Utility One. Bell argues that
the $20,000 financial assurance in the Agreed Order applies only to Bell and that the Permit
Board has no authority to demand $20,000 from Womack in exchange for agreeing to
transfer the permit.
10
The parties concede that whether MDEQ should return Bell’s $20,000 is not at issue
in this appeal.
11
The Permit Board may make permitting decisions “based upon any information as
it deems relevant.” Miss. Code Ann. § 49-17-29(3)(c). Further, “[i]n considering an
application for a permit issuance or transfer, the Permit Board may consider the applicant’s
compliance history, financial capability, financial responsibility, or any other aspect of the
applicant’s history it deems necessary or appropriate.” 11 Miss. Admin. Code Pt. 6,
1.1.3(H)(1).
12
The record contains more than twenty statements by MDEQ and the Permit Board
that, notwithstanding compliance or any other issues, the permit would be transferred if
Utility One gave them $20,000 in financial assurance. Moreover, at oral argument, MDEQ
admitted that it communicated to Bell that it would agree to the transfer if only Utility One
would provide $20,000 in financial assurance.
16
¶26. The Permit Board may require financial assurance from applicants. Miss. Code Ann.
§ 49-17-44(1) (Rev. 2012). However, “[t]he commission shall establish by regulation the
acceptable forms of financial security and the amount of financial security required for the
various types and sizes of facilities.” Id. (emphasis added). The Commission has not
established financial assurance regulations for wastewater treatment systems, thus, as a
general matter the Permit Board cannot require financial assurance from an applicant such
as Utility One. MDEQ concedes this point. Therefore, whether the Permit Board has the
authority to demand $20,000 from Utility One as a condition of the transfer depends upon
whether the financial assurance provision of the Agreed Order applies to Utility One because
the Agreed Order applies to the System, not to the particular parties.
¶27. The Agreed Order is essentially a contract in nature. Contract interpretation involves
three steps. McFarland v. McFarland, 105 So. 3d 1111, 1119 (Miss. 2013). First, a court
must determine whether the contract is ambiguous by analyzing the express wording. Id.
If it is not, the plain meaning is enforced as written. Id. Second, if the contract is
ambiguous, the Court applies the meaning more favorable to the nondrafting party. Id.
Third, if the contract’s meaning remains ambiguous, the Court may consider extrinsic
evidence. Id.
¶28. The Agreed Order states that it is between Mississippi Commission on Environmental
Quality, the Mississippi State Department of Health, Bell, and Elliott. Neither Utility One
nor Womack are signatories. The Agreed Order further goes to great pains to declare that
no change in ownership of the system will relieve Bell of its duties under the Order. This
provision indicates that the Agreed Order applies to and follows Bell, and does not follow
17
the Black Creek System. On the other hand, the Agreed Order states that “[a]ny deed, title,
or other instrument of conveyance executed by Bell that transfers title to any part of the STP
or DWP shall contain a notice that the STP and/or DWP is the subject of this Agreed
Order.” 13 However, this provision appears simply to the purpose of placing purchasers on
notice, not to obligate a nonsignatory to the contract. In the same paragraph, the order
provides that if any acquisition of the system is approved by MDEQ, only then shall Bell be
relieved of responsibility under the order.14 This language also supports the notion that the
responsibilities under the order are Bell’s, but do not follow the system.
¶29. The Agreed Order’s express purpose is “to cause the STP and DWP to achieve
compliance with all federal and state laws and regulations.” (Emphasis added). The Agreed
Order goes on to provide a detailed list of action items that Bell must complete and the time
periods in which Bell must complete them. This language indicates that, once Bell has
achieved compliance as contemplated by the order, the order is no longer in effect.
¶30. The financial assurance provision of the Agreed Order states that “Bell shall provide
financial assurance of $20,000 . . . The financial assurance shall be secured within thirty days
13
The next line of the order states that “Bell shall notify the Agencies in the event of
any such conveyance.” (Emphasis added). MDEQ seems to interpret this line to mean that
Bell required MDEQ’s permission to convey title, thus partially justifying the transfer denial.
Bell clearly notified MDEQ about the conveyance. This sentence plainly does not require
prior permission before Bell is allowed to transfer title, but merely requires that MDEQ be
notified.
14
MDEQ also attempts to use this portion of the Agreed Order to justify denying the
permit transfer, seemingly arguing that Bell is required to obtain MDEQ permission for a
sale in order to have the permit transferred. This assertion belies the plain language of the
order. The only thing affected by whether Bell obtains agency approval for the sale is
whether Bell remains liable under the Order or not. It has no bearing on permit transfer,
simply on Bell’s contractual liability.
18
from obtaining all necessary permits from the Permit Board. Bell shall continue to provide
this financial assurance for a period of two years at which time the requirement shall cease
if Bell demonstrates an adequate compliance for the duration of the two-year period.” The
Agreed Order goes on to provide that if Bell and MDEQ do not agree on the adequacy of the
compliance record, the matter will be taken before the Commission for determination.15 This
indicates that the financial assurance provision is specific to Bell. The Agreed Order clearly
obligates its signatories, but does not follow the system.
¶31. The Agreed Order plainly does not apply to Utility One, a nonsignatory. Therefore,
denying the permit transfer because of the lack of financial assurance from Utility One is
beyond the power of the Permit Board, because the Commission has not promulgated
financial assurance regulations for wastewater systems. The record makes clear that the
$20,000 was the reason for denying the transfer – MDEQ and the Permit Board made
multiple statements that they would transfer the permit for $20,000 notwithstanding any of
the other issues.
¶32. We therefore affirm the portion of the chancery court’s judgment that reversed the
Permit Board, and we reverse and render the Permit Board’s decision to deny the permit
transfer, and effectuate the transfer to Utility One. The Permit Board and MDEQ clearly
15
While Bell clearly requested its $20,000 be returned, and Bell and MDEQ clearly
disagree about the adequacy of the compliance record, it does not appear that the “matter”
of the return of the $20,000 and “adequate compliance” has been “taken” before the
Commission for a final determination. Thus, it seems that the issue of whether the Agreed
Order has been completed is as yet undetermined.
19
found that Utility One was an acceptable permittee 16 and clearly would have transferred the
permit to it had it put up the $20,000. Since the $20,000 was beyond the Permit Board’s
authority to demand, and since it was the lone impediment to transferring the permit, we find
reversing and rendering the Permit Board to be the appropriate resolution.
Whether the Permit Board is required to adopt regulations to govern its formal hearings
under the Administrative Procedures Act.
¶33. The APA requires that all agencies “[a]dopt rules of practice setting forth the nature
and requirements of all formal and informal proceedings available to the public.” Miss. Code
Ann. § 25-43-2.104(b) (Rev. 2010). However, the law notes that “[s]pecific statutory
provisions which govern agency proceedings and which are in conflict with any of the
provisions of this chapter shall continue to be applied to all proceedings of any such agency
to the extent of such conflict only” and that “to the extent that the provisions of any other law
conflict or are inconsistent with the provisions of this chapter, the provisions of such other
law shall govern and control.” Miss. Code Ann. § 25-43-1.103(3)&(4) (Rev. 2010)
(emphasis added). The Permit Board statute provides that “[t]he Permit Board may adopt
rules of practice and procedure governing its proceedings that are consistent with the
commission’s regulations.” Miss. Code Ann. § 49-17-29(3)(d) (Rev. 2012) (emphasis
added).
¶34. MDEQ argues first that the APA rule-making requirement applies to the “right of the
public to review and comment upon proposed rules and regulations, or amendment or repeal
16
We presume that if Utility One was an inappropriate permittee, the Permit Board
and MDEQ certainly would not transfer the permit to it, even with a $20,000 financial
assurance.
20
of the same, before the agency takes rule-making action.” Second, it argues that, regardless
of whether the APA applies to rules for adjudicatory hearings, the conflict of law provisions
mandate that the specific Permit Board statute, which is permissive, trumps the APA. Bell
argues that the plain language of the APA mandates that the Permit Board adopt rules and
regulations for its “formal hearing,” because such a “formal hearing” “is just such a formal
proceeding for which this minimum procedural code was required.”
¶35. We need not determine whether the Permit Board hearing is the type of proceeding
to which the APA rule-making provision applies, because the conflict provision of the APA
applies. Even if the APA applies to evidentiary proceedings, the specific statute of the
Permit Board, which is in conflict and inconsistent with the APA, trumps the APA because
that statute is clearly permissive, not mandatory. Thus, the Permit Board is not required by
the APA to promulgate rules and regulations for its evidentiary hearings. To the extent the
chancery court judgment ordered the Permit Board and MDEQ to promulgate rules and
regulations for its formal hearings, it was in error, as the agencies are not required to do so
under the APA.
Whether the lack of promulgated hearing rules violated due process.
¶36. Because this issue is capable of repetition, we write to note our concerns regarding
it. Bell argues that the Permit Board’s lack of rules and regulations are arbitrary and
capricious because the lack thereof results in “ad hoc” procedures which do not allow for a
fair and impartial hearing. “Administrative agencies must afford minimal due process
consisting of notice and an opportunity to be heard.” D.J. Koenig & Assocs., Inc. v. Miss.
State Tax Comm’n, 838 So. 2d 246, 254 (Miss. 2003). “Due process is flexible and calls for
21
such procedural protections as the particular situation demands.” Mathews v. Eldridge, 424
U.S. 319, 334 (1976). To determine whether administrative proceedings provide proper due
process, a court may examine 1) the private interest that will be affected, 2) the risk of
erroneous deprivation of the interest through the procedures used and the probable value of
additional or substitute procedural safeguard’s, and 3) the government’s interest, including
the burden that additional or substitute procedural requirement would entail. Id. at 335. A
full evidentiary hearing is not necessary to comply with procedural due process. Id. at 334-
35.
¶37. The statute governing Permit Board hearings provides that “[a]t a hearing, any
interested party may present witnesses and submit evidence and cross-examine witnesses.”
Miss. Code Ann. § 49-17-29(4)(b) (Rev. 2012) (emphasis added). An “interested party” is
defined as “any person claiming an interest relating to the property or project which is the
subject of the permit action, and who is so situated that the person may be affected by the
disposition of that action.” Id. Womack certainly fits this definition. Roy Furrh stated in
his letter to Bell that the law “is not clear regarding the authority of a party other than the
hearing petitioner to participate in an evidentiary hearing without the express authority of the
Permit Board. . . . If Utility One, LLC would also like to participate in the hearing, I suggest
that it file a Motion to Intervene with the Permit Board. . . . Requiring parties to file Motions
to Intervene in similar circumstances is standard procedure with the Permit Board.”
However, the statute is clear that any interested party, not just the hearing petitioner, may
participate in a formal hearing and does not need the express authority of the Permit Board
to do so. MDEQ’s apparent lack of adherence to this statute is concerning. MDEQ is put
22
on notice that, without formal rules and regulations, every proceeding before it may be
subject to a claim of violation of some statutory or constitutional right of the complaining
party.
CONCLUSION
¶38. The judgment of the chancery court is affirmed in part, vacated in part, and rendered.
Consequently, we reverse and render the Permit Board’s decision to deny the permit transfer,
thus effectuating the transfer of the permit to Utility One. To the extent the chancery court
reversed the denial of the permit transfer and held that the Permit Board could not require
financial assurance for wastewater systems in the absence of promulgated rules and
regulations pursuant to Mississippi Code Section 49-17-44, we affirm. We vacate the portion
of the chancery court judgment requiring the Permit Board to promulgate rules and
regulations under the APA.
¶39. AFFIRMED IN PART; VACATED IN PART AND RENDERED.
WALLER, C.J., RANDOLPH, P.J., LAMAR, KITCHENS, CHANDLER AND
PIERCE, JJ., CONCUR. DICKINSON, P.J., CONCURS IN PART AND IN RESULT
WITH SEPARATE WRITTEN OPINION JOINED BY COLEMAN, J.
DICKINSON, PRESIDING JUSTICE, CONCURRING IN PART AND IN
RESULT:
¶40. The majority recognizes that Bell suffered no due process violation, so any discussion
or warning that MDEQ “may be subject” to a possible “claim of violation of some statutory
or constitutional right” in some future case, is an advisory opinion. And because “it is not
23
within the province of this Court to render advisory opinions,” 17 I concur with the majority
in part and result.
COLEMAN, J., JOINS THIS OPINION.
17
Hughes v. Hosemann, 68 So. 3d 1260, 1263 (Miss. 2011) (citing Sheldon v.
Ladner, 205 Miss. 264, 38 So. 2d 718, 719-20 (1949)).
24