Meccon, Inc. v. University of Akron

[Cite as Meccon, Inc. v. Univ. of Akron, 126 Ohio St.3d 231, 2010-Ohio-3297.]




   MECCON, INC. ET AL., APPELLEES, v. UNIVERSITY OF AKRON, APPELLANT.
[Cite as Meccon, Inc. v. Univ. of Akron, 126 Ohio St.3d 231, 2010-Ohio-3297.]
Public-works contracts — Competitive bidding — Damages to unsuccessful
        bidder for public authority’s violation of law in awarding contract — Bid-
        preparation costs.
   (No. 2009-0950 — Submitted January 26, 2010 — Decided July 21, 2010.)
     APPEAL from the Court of Appeals for Franklin County, No. 08AP-727,
                        182 Ohio App.3d 85, 2009-Ohio-1700.
                                 __________________
                               SYLLABUS OF THE COURT
When a rejected bidder establishes that a public authority violated state
        competitive-bidding laws in awarding a public-improvement contract, that
        bidder may recover reasonable bid-preparation costs as damages if that
        bidder promptly sought, but was denied, injunctive relief and it is later
        determined that the bidder was wrongfully rejected and injunctive relief is
        no longer available.
                                 __________________
        CUPP, J.
        {¶ 1} The question before us is whether bid-preparation costs may be
recovered as damages by a bidder who establishes that its bid on a public-
improvement project was wrongfully rejected because the public authority
awarding that contract failed to comply with state competitive-bidding laws. We
conclude that reasonable bid-preparation costs may be recovered if the rejected
bidder promptly sought but was denied a timely injunction to suspend the public-
improvement project pending resolution of the dispute and a court later
determines that the bidder was wrongfully rejected by the public authority but
                             SUPREME COURT OF OHIO




injunctive relief is no longer available because the project has already been started
or is completed under a contract awarded to another bidder. Therefore, we affirm
the judgment of the court of appeals and remand the matter for further
proceedings before the Court of Claims.
        {¶ 2} According to the complaint of Meccon, Inc., and Ronal Bassak,
appellees (“Meccon”), the University of Akron proposed to award plumbing, fire-
protection, and heating, ventilation, and air-conditioning (“HVAC”) contracts for
public-improvement work in its football stadium. Meccon submitted a bid for the
separate HVAC project, as did other contractors.         Another contractor, S.A.
Comunale, submitted four bids: one for each of the stand-alone fire-protection,
plumbing, and HVAC contracts and a combined bid to perform all three contracts.
        {¶ 3} When the bids were opened, S.A. Comunale’s combined bid was
the lowest of the combination bids submitted. S.A. Comunale’s bid was $1.2
million less than the next-lowest combination of bids. S.A. Comunale was also
the low bidder for each of the stand-alone fire-protection, plumbing, and HVAC
contracts. Meccon submitted the second-lowest bid for the HVAC work.
        {¶ 4} Thereafter, S.A. Comunale withdrew its combined bid and its
stand-alone plumbing bid. The university awarded the stand-alone fire-protection
and HVAC contracts to S.A. Comunale. After the university rebid the stand-
alone plumbing contract and S.A. Comunale was once again the low bidder, S.A.
Comunale also won that contract.
        {¶ 5} Meccon alleges that the university’s award to S.A. Comunale of
the three stand-alone contracts, after S.A. Comunale had withdrawn both its
combined bid and its plumbing bid, was in violation of the university’s own
“Instructions to Bidders” documents and comparable provisions within Ohio
statutes.   Meccon filed suit in the Court of Claims, seeking a temporary
restraining order, a declaratory judgment, preliminary and permanent injunctive
relief, damages for its bid-preparation costs, and any other appropriate legal and




                                          2
                                      January Term, 2010




equitable relief resulting from the university’s failure to award the HVAC
contract to Meccon.
         {¶ 6} In response, the university filed a motion to dismiss for lack of
subject-matter jurisdiction. It argued that disappointed bidders were entitled only
to injunctive relief and that Meccon’s claim for bid-preparation costs and other
money damages was not cognizable.                     The Court of Claims granted the
university’s motion, concluding that only the court of common pleas had
jurisdiction because Meccon’s remaining claim was only for equitable relief. On
the same basis, the Court of Claims also denied the motion for a temporary
restraining order, denied all other motions as moot, and dismissed the complaint.
         {¶ 7} Meccon appealed to the Tenth District Court of Appeals, and the
court reversed the Court of Claims with respect to the jurisdiction question. 182
Ohio App.3d 85, 2009-Ohio-1700, 911 N.E.2d 933. The court concluded that
disappointed bidders can recover bid-preparation costs and that because such
costs are monetary damages, the Court of Claims does have subject-matter
jurisdiction to hear all of Meccon’s claims. Id. at ¶ 26. The court also determined
that Meccon’s argument that the Court of Claims erred when it failed to consider
Meccon’s motion for a temporary restraining order was moot. Id. at ¶ 27, 29. We
accepted the university’s appeal under our discretionary jurisdiction. 122 Ohio
St.3d 1502, 2009-Ohio-4233, 912 N.E.2d 107.1
         {¶ 8} The university contends that Cementech, Inc. v. Fairlawn, 109
Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24, controls the disposition of this
case. In Cementech, a public authority solicited bids for a public project. In the
process of awarding the contract, the public authority unlawfully rejected
Cementech’s bid. The trial court awarded Cementech bid-preparation costs but


1. At this stage of the proceedings, the only question presented to this court is the availability of
money damages. The questions pertaining to the legality of the awarding of the contracts at issue
have not been addressed.




                                                 3
                               SUPREME COURT OF OHIO




denied lost profits. Cementech appealed the trial court’s order limiting damages
to the bid-preparation costs. The appellate court reversed and allowed the lost
profits.
           {¶ 9} In reversing the appellate court, this court held: “When a
municipality violates competitive-bidding laws in awarding a competitively bid
project, the rejected bidder cannot recover its lost profits as damages.” Id. at
paragraph one of the syllabus. The holding was founded on the principle that
“punishing government entities through lost-profit damages to rejected bidders in
effect punishes the very persons competitive bidding is intended to protect — the
taxpayers.” Id. at ¶ 12. We also explained that the purposes of competitive
bidding, which are to prevent excessive costs and corrupt practices and to provide
open and honest competition in bidding for public-improvement contracts, clearly
militate against allowing lost-profit damages to wrongfully rejected bidders. Id.
at ¶ 9. Allowing such damages harms taxpayers by forcing the taxpayers to bear
extra costs, which include both the unjustifiably higher prices paid to the
wrongfully chosen bidder for the public contract and, if awarded, the damages
established by the disappointed bidder that did not perform the work, including
lost profits, which are often speculative and significant. Id. In that setting, we
concluded that injunctive relief and the resulting delays in commencing the
project serve as a sufficient deterrent to a public authority’s violation of
competitive-bidding laws. Id. at ¶ 11.
           {¶ 10} According to the university, Cementech holds that bid-preparation
costs and other money damages cannot be recovered by a rejected bidder for a
public project and that injunctive relief is the only available remedy.         The
university further asserts that since the remaining relief requested in Meccon’s
action is equitable, the Court of Claims has no jurisdiction over that claim and the
Court of Claims properly granted the university’s motion to dismiss.
Correspondingly, the university argued before the appellate court that Meccon’s




                                          4
                                   January Term, 2010




appeal to that court was also moot because injunctive relief requested by Meccon
had been denied earlier in the proceedings.
        {¶ 11} The issue of whether bid-preparation costs could be recovered by a
wrongfully rejected bidder was not answered in Cementech.2 Upon consideration
of the arguments in this case on the availability of reasonable bid-preparation
costs as damages, we decline to extend the holding in Cementech to this
circumstance.
        {¶ 12} We reach this conclusion because the reasons articulated in
Cementech for denying recovery of lost profits as damages do not carry over to
the circumstances in which bid-preparation costs are sought after denial of a
timely application for injunctive relief. A significant distinguishing factor in
those circumstances is the lack of any other remedy for a public authority’s
wrongful conduct. If, for instance, a rejected bidder alleges that a public authority
failed to comply with competitive-bidding laws and promptly seeks injunctive
relief to delay the public-improvement project pending resolution of the dispute,
denial of the requested injunctive relief means that determination of the allegation
of wrongful conduct by the public authority will not take place until much later in
the litigation.     Under our precedent, once the public-improvement work
commences or is completed, the rejected bidder will not be able to perform the
public contract even if the bidder demonstrates that its bid was wrongfully
rejected. Cementech, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24, ¶ 13.
        {¶ 13} In such circumstances, the wrongfully rejected bidder is left with
no remedy for the public authority’s unlawful conduct, and injunctive relief will
no longer serve to deter the public authority’s unlawful conduct. Thus, we hold
that when a rejected bidder establishes that a public authority violated state
competitive-bidding laws in awarding a public-improvement contract, that bidder

2. There was no cross-appeal filed by the public authority in Cementech questioning the trial
court’s award of bid-preparation costs. 160 Ohio App.3d 450, 2005-Ohio-1709, 827 N.E.2d 819.




                                             5
                             SUPREME COURT OF OHIO




may recover reasonable bid-preparation costs as damages if that bidder promptly
sought, but was denied, injunctive relief and it is later determined that the bidder
was wrongfully rejected and injunctive relief is no longer available.
       {¶ 14} By requiring a wrongfully rejected bidder to first seek injunctive
relief and allowing the bidder to be awarded reasonable bid-preparation costs only
if erroneously denied timely relief, we are applying a form of the well-established
principle of mitigation of damages. For if injunctive relief is timely granted, then
a wrongfully rejected bidder will have avoided the damages that would otherwise
flow from the public authority’s wrongful conduct by preventing the improper
awarding of the contract or by suspending the contract before it has been
performed to such an extent that the bid award is no longer subject to timely
correction.
       {¶ 15} However, when the wrongfully rejected bidder pursues injunctive
relief in a timely and good-faith manner but is erroneously denied the relief by the
trial court, and the award of the contract to another bidder and the performance by
that bidder have progressed beyond the point of correction, then the bidder should
be able to recover the reasonable cost it incurred in the preparation of its bid. But
for the noncompliance with the competitive-bidding laws by the public authority,
the bid would have been accepted, and the contract would have been awarded to
the complaining bidder.
       {¶ 16} This rule, together with the rule prohibiting recovery of the more
speculative lost-profit damages, seems best calculated to strike a balance between
protecting the public from incurring extra cost due to the misconduct of the public
authority, ameliorating the damages sustained by the lowest and best bidder in its
good-faith participation in the competitive-bidding process, and deterring the
public authority from violations of the competitive-bidding law.
       {¶ 17} The appellate court also recognized the distinction between bid-
preparation costs and lost profits as damages: “There are good public-policy




                                         6
                                January Term, 2010




reasons favoring [the recovery of bid-preparation costs]. First, without some
penalty, there is little deterrent to a public entity who fails to follow the
competitive-bidding statutes. Second, contractors may be reluctant to bid on
public projects when they suspect the competitive bidding will not be conducted
fairly. Ultimately, refusal to bid harms the public as the pool of qualified bidders
shrinks. Any harm to the public from these types of damages is de minimus when
compared to the harm to the public from recovery of lost profits. Allowing
recovery of bid-preparation costs will serve to enhance the integrity of the
competitive-bidding process.”      182 Ohio App.3d 85, 2009-Ohio-1700, 911
N.E.2d 933, at ¶ 24.
       {¶ 18} We hold that in appropriate circumstances, as delineated above,
reasonable bid-preparation costs are recoverable as money damages.
       {¶ 19} When Meccon filed its action for money damages and injunctive
relief against the university, it filed it in the Court of Claims. The Court of
Claims has exclusive, original jurisdiction over civil suits that request money
damages against the state even when ancillary relief, such as an injunction or
declaratory judgment, is also sought. R.C. 2743.03(A)(1) and 2743.03(A)(2);
State ex rel. Blackwell v. Crawford, 106 Ohio St.3d 447, 2005-Ohio-5124, 835
N.E.2d 1232, ¶ 20. Therefore, the Court of Claims had jurisdiction to hear
Meccon’s claim for bid-preparation costs.
       {¶ 20} Injunctive relief must be promptly sought as a precondition to
those damages, however. The university contends that Meccon waited two full
months after the bids were opened to seek injunctive relief. Meccon states that it
requested injunctive relief four business days after it learned that the university
had awarded the plumbing, fire-protection, and HVAC contracts in violation of
the state’s competitive-bidding laws. Whether Meccon was timely in its pursuit
of injunctive relief satisfying this precondition for an award of its bid-preparation




                                         7
                            SUPREME COURT OF OHIO




costs as damages is a matter that has not yet been addressed by any court.
Consequently, a remand to the Court of Claims to consider this matter is required.
       {¶ 21} Accordingly, the judgment of the court of appeals is affirmed, and
the matter is remanded to the Court of Claims for further proceedings.
                                                               Judgment affirmed
                                                             and cause remanded.
       PFEIFER,    LUNDBERG      STRATTON,     O’CONNOR,      O’DONNELL,      and
LANZINGER, JJ., concur.
       BROWN, C.J., not participating.
                              __________________
       Thompson Hine, L.L.P., Peter D. Welin, and Andrew R. Fredelake, for
appellees.
       Richard Cordray, Attorney General, Benjamin C. Mizer, Solicitor General,
Alexandra T. Schimmer, Chief Deputy Solicitor General, Emily S. Schlesinger,
Deputy Solicitor, and William C. Becker and Lisa J. Conomy, Assistant Attorneys
General, for appellant.
       Schottenstein, Zox & Dunn Co., L.P.A., Stephen L. Byron, Rebecca K.
Schaltenbrand, and Stephen J. Smith; and John Gotherman, urging reversal for
amici curiae, Ohio Municipal League, County Commissioner Association of
Ohio, and Ohio Township Association.
                           ______________________




                                         8