Strahm v. Buckeye Pipe Line Co., L.P.

Court: Ohio Court of Appeals
Date filed: 2011-03-14
Citations: 2011 Ohio 1171
Copy Citations
1 Citing Case
Combined Opinion
[Cite as Strahm v. Buckeye Pipe Line Co., L.P., 2011-Ohio-1171.]




                      IN THE COURT OF APPEALS OF OHIO
                          THIRD APPELLATE DISTRICT
                               ALLEN COUNTY



ROBERT C. STRAHM, ET AL.,                                          CASE NO. 1-10-60

   PLAINTIFFS-APPELLANTS,

  v.

BUCKEYE PIPE LINE COMPANY, L.P.,                                     OPINION

   DEFENDANT-APPELLEE.



                  Appeal from Allen County Common Pleas Court
                           Trial Court No. CV 2009 1319

                       Judgment Reversed and Cause Remanded

                            Date of Decision: March 14, 2011




APPEARANCES:

        Bernard K. Bauer for Appellant

        Paul J. Coval for Appellee
Case No. 1-10-60




WILLAMOWSKI, J.

       {¶1} Plaintiffs-Appellants, Robert C. Strahm and Donna J. Strahm

(“Appellants” or “the Strahms”), appeal the decision of the Allen County Court of

Common Pleas granting partial summary judgment in favor of Defendant-

Appellee, Buckeye Pipe Line Company, L.P. (“Buckeye”). The Strahms maintain

that the pipe line easements across their land did not contain any explicit language

that would permit Buckeye to clear all the trees, shrubs and vegetation from the

easements without providing compensation. For the reasons set forth below, the

judgment is reversed.

       {¶2} The Strahms filed an action for declaratory judgment and damages

regarding a dispute concerning the duties and responsibilities of the parties under

four pipe line easements affecting two adjacent parcels of property owned by the

Strahms. The dispute in question began when Buckeye cleared all of the trees,

shrubs and vegetation from an area on the Strahms’ two properties which

included, but may not have been limited to, the pipeline rights-of-way.

       {¶3} In 1984, Mr. Strahm purchased two parcels of land (the “northern

parcel” and the “southern parcel”) in Richland Township. At the time of purchase,

each piece of property was subject to separate pipe line easements originally

granted to Sohio Pipe Line Co. (“Sohio”) and Trans-Ohio Pipeline Co. (“Trans-



                                        -2-
Case No. 1-10-60



Ohio”).      Buckeye is the successor in interest to the Sohio and Trans-Ohio

easements.

          {¶4} In 1947, Sohio obtained blanket easements over both parcels to “lay,

maintain, operate, repair, replace and remove a pipe line and all necessary fixtures,

equipment and appurtenances thereto ***.” The easements also specified the

rights to the premises that were reserved to the grantors of the right-of-way and

their successors:

          Grantor and Grantor’s heirs and assigns reserve the right fully
          to use and enjoy the said premises except insofar as such use and
          enjoyment shall be inconsistent with the exercise by the Grantee
          of the rights herein granted to it.

(Sohio 1947 Easement.) The Sohio easements also provided for compensation to

the landowner in the event of damages as a result of exercising the easement

rights:

          The Grantee *** agrees to bury said pipe line so that it will not
          interfere with the cultivation of the land and also to pay any
          damages to crops, buildings, drain tile, fences and timber arising
          from the exercise by the Grantee of any of the rights herein
          conferred upon it.

(Id.)

          {¶5} Sometime later, in 1973, Trans-Ohio also obtained two separate

easements to “construct, lay, maintain, operate, alter, repair, remove, change the

size of, and replace a pipe line and appurtenances thereto ***” over both the

northern and southern parcels.      These easements provided for a right-of-way

                                         -3-
Case No. 1-10-60



which extended 15 feet on each side of the pipe line. The Trans-Ohio easements

also specified the rights of the landowners as to their use and enjoyment of the

easements, although they contained somewhat different wording than the Sohio

easements as to the Grantors’ retained rights and the provisions for compensation.

        Grantors are to fully use and enjoy the said premises, except for
        the purposes granted to the said Grantee and provided that the
        said Grantors shall not construct nor permit to be constructed
        any house, structures or obstructions on or over, or that will
        interfere with the construction, maintenance or operation of, any
        pipe line or appurtenances constructed hereunder, and will not
        change the grade over such pipe line.

(Trans-Ohio 1973 Easement.) These easements specified that Trans-Ohio would

be responsible for the payment of damages to “crops, timber, or fences” from the

construction of the pipe lines and, thereafter:

        to pay such damages which may arise to growing annual crops
        or fences from the maintenance, alteration, repair, removal,
        change of the size, or replacement thereof.

(Id.)

        {¶6} After he purchased the properties, Mr. Strahm entered into an

agreement with the National Conservation Reserve Program to plant trees and

shrubs on his property in order to create a wildlife habitat and help preserve

natural resources. Between 1988 and 1994, Mr. Strahm planted specified grasses

as well as dogwoods, white pines and ash trees, pursuant to the recommendations




                                         -4-
Case No. 1-10-60



of the conservation organization. The Strahms did not believe that their plantings

were inconsistent with their rights to use their land according to the easements.

       {¶7} However, on November 14, 2001, Buckeye’s Regional Right-of-Way

Agent, Martin White (“Mr. White”) sent Mr. Strahm a letter documenting the fact

that the easements contained substantial pine and hardwood trees. The letter

stated that Buckeye had attempted to clear the right-of way in 1997 and again in

2001, but that the Strahms had refused to allow the work to be done. The letter

stated that “[t]rees are a non-permitted use of the right-of-way as they are

substantial impediments for access to and workspace around the pipe lines during

either routine or emergency pipe line maintenance work.” (Plaintiff’s Ex. 4 to the

2009 Dep. of Mr. White.) Mr. White was going to “review the easements more

thoroughly” and complete a report before the end of the year.

       {¶8} On November 21, 2001, and again on July 30, 2002, Mr. Strahm sent

letters to Mr. White asking Buckeye to send him “all easements relating to [my

properties] including all restrictions and regulations involving these easements.”

In his deposition, Mr. White testified that he did not recall that he had ever

provided Mr. Strahm with the information he had requested.

       {¶9} On October 1, 2007, Buckeye sent the Strahms a letter informing them

of Buckeye’s intention to clear the trees and vegetation from the 30-foot wide

easements (15 feet on each side of the pipe line) by the latter part of the month,


                                         -5-
Case No. 1-10-60



stating that “Buckeye cannot access or maintain its pipe line under present right-

of-way conditions.”    (Plaintiffs’ Complaint, Ex. 5.)    In the letter, Mr. White

acknowledged that he had capitulated to the Strahms’ objections in the past, but

that current easement conditions inhibited Buckeye’s ability to maintain regulatory

compliance, including patrolling the corridor by air in search of pipe line failure.

The letter stated:

       You purchased this property subject to Buckeye’s easement
       rights. A ‘nature preserve,’ Pheasants Forever habitat, and
       commercial tree nursery activities are contrary to the spirit and
       intent of the easement grant and as such are non-permitted uses
       of the right of way. *** Consequently, the trees/vegetation have
       grown into substantial impediments for the safe and practical
       operation and maintenance of the pipe line.

(Id.) The letter stated that it was intended as a “courtesy notification,” not as “a

negotiation or debate of easement rights.” (Id.)

       {¶10} On October 23 and 24, 2007, Buckeye removed all of the trees and

brush, and completely mowed the fields in the easements to prevent the potential

regrowth of seedlings.       Mr. White explained why they mowed all of the

vegetation, in addition to just removing the trees and shrubs:

       Right of way clearing is preventive maintenance. The longer we
       delay, the worse it becomes; and so, we wanted to mow this at
       this point in time -- as a matter of vegetation maintenance.

(White Dep. at pp. 23-24.)




                                         -6-
Case No. 1-10-60



         {¶11} The Strahms filed a complaint1 for declaratory judgment and

damages. The Strahms maintained that Buckeye’s complete clearing of the entire

area of the easements went beyond the rights granted by the explicit language of

the easements. The Strahms also claimed that Buckeye cleared and damaged land

and property that was not within the easements, specifically, that Buckeye cleared

a path in excess of 30 feet at some points (up to 100 feet wide); that Buckeye left

ruts in the land; and that Buckeye destroyed a small bridge that was not within the

easement. Buckeye denies these claims. The complaint for declaratory judgment

asked the court to resolve the controversy as to whether the easements permitted

Buckeye to enter the properties “to clear vegetation” and not “to construct, lay,

maintain, operate, alter, repair, remove, change the size of, [or] replace” a pipe

line. The Strahms also requested compensation, claiming that Buckeye removed

and damaged trees and shrubs having a total replacement value of over $222,000,

and that Buckeye caused additional damages on and off the rights-of-way totaling

$16,500.

         {¶12} Buckeye denied all of the Strahms’ assertions and filed a motion for

partial summary judgment on June 15, 2010.2 Buckeye argued that the easements


1
  The Strahms originally filed their complaint on September 17, 2008, Case No. CV 2008 1361. However,
they referenced only the Trans-Ohio easements in that complaint. After discovering the omission of the
Sohio easements, the Strahms voluntarily dismissed that complaint and re-filed this Case No. CV 2009
1319 on December, 11, 2009, seeking essentially the same relief based on the same allegations.
2
  On March 12, 2010, the trial court entered its pre-trial order setting the case schedule. Cross-motions for
summary judgment were to be filed by June 15, 2010, with any responses filed within 30 days after any
motions were filed.

                                                    -7-
Case No. 1-10-60



permitted Buckeye to remove timber during maintenance and otherwise permitted

Buckeye to remove obstructions, including trees, shrubs, and vegetation, that

interfered with its right to access and maintain its pipe lines. Buckeye asserted

that the language of the respective easements, along with Ohio law, established

Buckeye’s rights to clear the easements. Buckeye maintained that the easements

contemplated such removal because it is “reasonably necessary and convenient” to

facilitate Buckeye’s access and maintenance of the pipe lines, and that the removal

of vegetation facilitated compliance with Federal requirements. (Buckeye’s Mtn.

for Sum. Judgmt., pp. 7-8.) Buckeye asserted that the trees, shrubs, and vegetation

were removed because they constituted “substantial impediments for the safe and

practical operation and maintenance” of the respective pipe lines. (Id. at 9.)

Buckeye further proposed that even if the easements did not explicitly give

Buckeye the right to remove the vegetation from the rights-of-way, the

surrounding circumstances and consideration of what is “reasonably necessary and

convenient” supports the conclusion that Buckeye is permitted to remove those

items within its rights-of-way. (Id.) Furthermore, the terms of the easements did

not require Buckeye to compensate the Strahms for the removal of such

“obstructions.”




                                        -8-
Case No. 1-10-60



           {¶13} The Strahms responded with a cross-motion for partial summary

judgment on July 15, 2010,3 arguing that the explicit language contained in the

respective easements did not unambiguously permit Buckeye to remove trees,

shrubs and vegetation from its rights-of-way without compensation to the Strahms.

The Strahms argued that Buckeye’s actions were improper because the mowing of

the easements was not done in conjunction with laying, maintaining, operating,

repairing, replacing or removing a pipe line. In addition to the absence of explicit

language giving Buckeye the right to clear the easements for the sake of clearing

them, the Strahms also asserted that there was no prohibition against planting trees

in the rights-of-way because the language in the easements only prohibited the

construction of a house, structure, or obstruction in the rights-of-way, but it did

not prohibit the planting of trees. The Strahms also asserted that Buckeye’s

acquiescence to the presence of the trees over a period of years may be considered

an estoppel. And finally, the Strahms maintained that federal regulations did not

give Buckeye the implicit right to remove the trees, shrubs and vegetation.

           {¶14} On August 2, 2010, the trial court issued its decision granting partial

summary judgment in favor of Buckeye, finding that (1) both easements gave

Buckeye the right to remove trees, shrubs and other vegetation from the rights-of-

way as an exercise of their “maintenance” rights; and, (2) the Trans-Ohio



3
    Buckeye maintains that the Strahms’ cross-motion for summary judgment was untimely. See fn. 2.

                                                   -9-
Case No. 1-10-60



easements did not require Buckeye to compensate the Strahms for the removal of

trees when exercising its rights under the easements. However, because the Sohio

easements required Buckeye to compensate the Strahms for the removal of trees in

the easements when exercising its rights, there remained a genuine issue of

material fact as to (1) whether the Strahms’ conduct constituted an “interference or

obstruction” with Buckeye’s rights, in which case compensation is not required;

and, (2) whether Buckeye exceeded its rights under the easement or otherwise

unlawfully entered upon the Strahms’ property and caused damages.

       {¶15} The Strahms timely appeal and raise the following two assignments

of error for our review.

                            First Assignment of Error

       The Trial Court committed error prejudicial to the [Strahms] as
       a matter of law, by entering a declaratory judgment in favor of
       [Buckeye] which permitted it to remove trees, shrubs and
       vegetation to facilitate aerial inspection of pipeline rights of way,
       without compensation, when the Trans-Ohio easements which
       granted rights to it did not contain any explicit language
       regarding its proposed right of way clearing work.

                           Second Assignment of Error

       The Trial Court committed error prejudicial to the [Strahms] as
       a matter of law, by entering a declaratory judgment in favor of
       [Buckeye] which permitted it to remove trees, shrubs and
       vegetation to facilitate aerial inspection of pipeline rights of way,
       when the Sohio easements which granted rights to it did not
       contain any explicit language regarding its proposed right of
       way clearing work.


                                       -10-
Case No. 1-10-60



       {¶16} The arguments in the Strahms’ two assignments of error assert that

the explicit language in the Trans-Ohio easements (first assignment of error) and

the Sohio easements (second assignment of error) did not permit Buckeye to enter

upon the easements for the sole purpose of clearing vegetation. We shall address

both assignments of error together, as they raise essentially the same issues.

       {¶17} Appellate courts review decisions on summary judgment de novo,

viewing the facts as most favorable to the non-moving party and resolving any

doubt in favor of that party. Grafton v. Ohio Edison Co., 77 Ohio St.3d 102, 105,

1996-Ohio-336, 671 N .E.2d 241.          Because it is a procedural device that

terminates litigation, summary judgment must be awarded with caution. Ormet

Primary Aluminum Corp. v. Employers Ins. of Wausau, 88 Ohio St.3d 292, 2000-

Ohio-330, 725 N.E.2d 646.

       {¶18} Summary judgment is appropriate where there are no genuine issues

as to any material fact and the moving party is entitled to judgment as a matter of

law. Civ.R. 56(C). “Summary judgment shall not be rendered unless it appears

*** that reasonable minds can come to but one conclusion and that conclusion is

adverse to the party against whom the motion for summary judgment is made

***.” Civ.R. 56(C); Temple v. Wean United, Inc. (1977), 50 Ohio St.2d 317, 364

N.E.2d 267. “The purpose of summary judgment is not to try issues of fact, but is

rather to determine whether triable issues of fact exist.” Schnippel Constr., Inc. v.


                                        -11-
Case No. 1-10-60



Profitt, 3d Dist. No. 17-09-12, 2009-Ohio-5905, ¶10, quoting Lakota Loc. Schools

Dist. Bd. of Edn. v. Brickner (1996), 108 Ohio App.3d 637, 643, 671 N.E.2d 578.

      {¶19} The party moving for summary judgment bears the initial burden of

informing the trial court of the basis for the motion and identifying those portions

of the record that demonstrate the absence of a genuine issue of material fact on an

essential element of the nonmoving party's claims. Dresher v. Burt, 75 Ohio St.3d

280, 293, 1996-Ohio-107, 662 N.E.2d 264. The moving party does not discharge

this initial burden under Civ.R. 56 by simply making a conclusory allegation that

the nonmoving party has no evidence to prove its case. Id.; Vahila v. Hall, 77 Ohio

St.3d 421, 1997-Ohio-259, 429, 674 N.E.2d 1164. “Rather, the moving party must

be able to specifically point to some evidence of the type listed in Civ.R. 56(C)

which affirmatively demonstrates that the nonmoving party has no evidence to

support the nonmoving party's claims.” (Emphasis sic.) Dresher at 293, 662

N.E.2d 264.

      {¶20} If the moving party meets this burden, the non-moving party then has

a reciprocal burden to establish the existence of genuine issues of material fact.

Id. “When reviewing a trial court's ruling on summary judgment, the court of

appeals conducts an independent review of the record and stands in the shoes of

the trial court. Mergenthal v. Star Banc Corp. (1997), 122 Ohio App.3d 100, 103,

701 N.E.2d 383.


                                       -12-
Case No. 1-10-60



       {¶21} In this case, both parties agree with the undisputed fact that both the

Trans-Ohio and the Sohio easements give Buckeye the right to “maintain” the pipe

lines. The dispute arises from a difference in the parties’ understanding as to what

it means to “maintain” the pipe lines. The primary issue is whether that language

in the easements gives Buckeye the right to clear all trees, shrubs, and vegetation

over the entire area of the easements even when such clearing is not done in

conjunction with any other work on the pipe line. And, if it does, is Buckeye

required to compensate the Strahms for the removal of the timber from the Sohio

easement?

       {¶22} An easement is an interest in the land of another that entitles the

owner of the easement (the dominant estate) to a limited use of the land (the

servient estate). Crane Hollow, Inc. v. Marathon Ashland Pipe Line, LLC (2000),

138 Ohio App.3d 57, 66, 740 N.E.2d 328; Alban v. R.K. Co. (1968), 15 Ohio St.2d

229, 231, 239 N.E.2d 22, 23-24. When an easement is created by an express

grant, as in this case, the extent and limitations upon the dominant estate's use of

the land depend upon the language in the grant. See Alban at 232, 239 N.E.2d at

24; Columbia Gas Transm. Corp. v. Bennett (1990), 71 Ohio App.3d 307, 318,

594 N.E.2d 1, 7-8. When the terms in an easement are clear and unambiguous, a

court cannot create a new agreement by finding an intent not expressed in the clear

language employed by the parties. Alexander v. Buckeye Pipe Line Co. (1978), 53


                                       -13-
Case No. 1-10-60



Ohio St.2d 241, 246, 374 N.E.2d 146, 150.         The language of the easement,

considered in light of the surrounding circumstances, is the best indication of the

extent and limitations of the easement. Lakewood Homes, Inc. v. BP Oil, Inc., 3rd

Dist. No. 5-98-29, 1999-Ohio-851, citing Apel v. Katz, 83 Ohio St.3d 11, 17,

1998-Ohio-420, 697 N.E.2d 600.           However, courts have held that normal

developmental changes and new inventions could entitle an easement holder to

vary the mode of enjoyment and use of the easement. See, e.g., Crane Hollow,

138 Ohio App.3d at 67.

      {¶23} In their complaint, the Strahms allege that the explicit language in

the easements grants Buckeye the right to utilize the easements to “maintain *** a

pipe line.” (Emphasis added.) However, there is no explicit language giving

Buckeye the right to maintain the easements or to enter upon the right-of-way for

purposes other than those specified.      Even Mr. White acknowledged that the

easements do “not contain any explicit language regarding Buckeye’s proposed

right-of-way clearing work.” (Complaint, Ex. 5; see also White Dep., p. 30.) It

was undisputed that no maintenance or operational work was being done on the

pipe lines when the clearing was done.

      {¶24} However, Buckeye maintains that the removal of all of the trees and

vegetation from the entire easement area is necessary for its proper maintenance of

the pipe line.   Mr. White has indicated that clearing vegetation is part of


                                         -14-
Case No. 1-10-60



Buckeye’s standard practice of “preventative maintenance” and was a matter of

“vegetation maintenance.” (White Dep., p. 23-24.)

       {¶25} The question as to what constitutes maintenance of a pipe line under

the Trans-Ohio and Sohio easements appears to raise a genuine issue of material

fact that would preclude summary judgment. In fact, the trial court even noted in

its judgment entry that “as the Third District stated in Voisard v. Marathon

Ashland Pipe Line, these are factual inquiries ***. (Aug. 2, 2010 J.E., pp. 6-7,

Voisard v. Marathon Ashland Pipeline, LLC., 3d Dist. No. 9-05-49, 2006-Ohio-

6926, ¶7, stating “the issues presented in this type of case are questions of fact,

which must be resolved on a case-by-case basis.”)

       {¶26} Buckeye has set forth numerous arguments as to why it should be

permitted to clear the easements as it wishes. However, we do not find that

Buckeye has pointed to any admissible facts in the record to support the

contention that such clearing constitutes necessary “maintenance” under the terms

of the relevant easements and the facts in this case. Although not necessarily

required to do so, neither party submitted any affidavits or other types of Civ.R. 56

evidence. Even the depositions of Mr. Strahm and Mr. White were not filed in this




                                        -15-
Case No. 1-10-60



case -- copies were merely attached to Buckeye’s motion for summary judgment.4

Buckeye’s arguments, along with unsubstantiated, conclusory opinions stated by

Mr. White in letters to the Strahms, do not constitute evidence that would entitle

Buckeye to summary judgment.

         {¶27} For example, Buckeye has asserted that the trees had to be removed

because their roots could interfere with the pipe line. While that might certainly

be one reason to justify Buckeye’s removal of the trees, we did not find any

evidence anywhere in the record as to how deep the pipe lines were buried, how

deep the roots of the trees extended, or whether there was any actual or likely

infringement upon the pipe line by any tree roots. In fact, none of Buckeye’s

assertions were supported by the type of admissible summary judgment evidence

that would establish the necessity of clearing the easements as a function of

“maintaining a pipe line.”

         {¶28} Buckeye also made many legal arguments, citing cases where courts

determined that a pipe line company was entitled to remove trees and vegetation

from the rights-of-way in order to maintain the pipe lines. However, many of


4
  Civ.R. 56(C) states that “judgment shall be rendered forthwith if the pleadings, depositions, answers to
interrogatories, written admissions, affidavits, transcripts of evidence, and written stipulations of fact, if
any, timely filed in the action, show that there is no genuine issue as to any material fact and that the
moving party is entitled to judgment as a matter of law. No evidence or stipulation may be considered
except as stated in this rule.” (Emphasis added.) But, see, e.g., Whanger v. Grange Mut. Cas. Co., 7th Dist.
No. 06-JE-18, 2007-Ohio-3187, ¶9 (unfiled deposition was not proper summary judgment evidence, but it
was within the trial court’s discretion to consider the conforming summary judgment evidence when no
objection was made by the parties.) The parties did not object in this case. However, we note that some of
the photographic exhibits referenced in the depositions were not included anywhere in the record.

                                                    -16-
Case No. 1-10-60



these cases were decided after a trial wherein both sides had an opportunity to

present their evidence and the courts’ decisions were based upon factual

testimony, often from expert witnesses. See, e.g., Andrews v. Columbia Gas

Transm. Corp. (C.A.6, 2008), 544 F.3d 618, 622 (summary judgment was denied

and case proceeded to trial).

       {¶29} Furthermore, other cases cited by Buckeye were distinguishable in

that the relevant facts and issues were different and/or the controlling language in

the easements was different. For instance, in Voisard v. Marathon, supra, this

Court held that Marathon could maintain the pipe line as it believed was

necessary.   2006-Ohio-6926 at ¶8.     However, the language in that particular

easement provided Marathon “‘the right of way to lay, maintain, operate and

remove a pipe line, if the same shall be thought necessary by said grantee[.]’”

(Emphasis sic.) Id. Buckeye’s easements do not contain such broad language. In

another case, the easement originally contained language similar to that in the

easements before us now. However, several decades later, an amended easement

was negotiated and the new language prohibited the planting or permitting of any

trees or non-shrubbery woody growth anywhere over the specified right-of-way.

Panhandle Eastern Pipeline Co. v. Howey, 6th Dist. No. L-01-1037, 2001 WL

1155838, 1. The Strahms’ easements have not been renegotiated to include any

language prohibiting trees and non-shrubbery growth. And, in a case highly relied


                                       -17-
Case No. 1-10-60



upon by Buckeye, the language of the easement also contained the word “inspect,”

which is absent from the terms in this case. Rueckel v. Texas Eastern Transm.

Corp. (1981), 3 Ohio App.3d 153, 156, 444 N.E.2d 77 (the easement conveyed the

right to “lay, operate, renew, alter, inspect and maintain a pipe line ***.”)

       {¶30} Buckeye points to some cases where courts permitted tree removal in

order to allow for aerial inspection of the pipe line.         See, e.g., Voisard v.

Marathon, supra. But, see, Lakewood Homes v. B.P., 1999-Ohio-851 (“[the pipe

line company] did not present any evidence to the trial court that demonstrates that

its maintenance and inspection could not be carried out in a manner which did not

impose additional burdens on Lakewood Homes’ servient property.”) While we

acknowledge that the necessity of aerial inspection may, under certain

circumstances, require a pipe line company to clear some trees from an easement,

the testimony concerning that need in this case was ambiguous and raised

questions of fact. Mr. White stated that they “have to patrol” the pipe line, and it

could be accomplished by walking it or by aerial inspection. (White Dep., pp. 24-

25.) Aerial inspection was just one of “several reasons” why Buckeye maintained

the rights-of-way. (Id.) There was also testimony that another pipe line company

also had an easement through the Strahms’ properties and that company had not

cut down trees in order to patrol their pipe line. (Id.)




                                         -18-
Case No. 1-10-60



       {¶31} Buckeye also cited several cases for the proposition that it was

entitled to do what was “reasonably necessary and convenient” to maintain the

rights-of-way.   However, the cases cited using that language involved situations

in which the width or dimensions of the right-of-way was not specified in the

language of the easement, and that was the standard used by the courts to

determine what the size of the easement should be.         See, e.g., Pomante v.

Marathon Ashland Pipe Line L.L.C., 187 Ohio App.3d 731, 2010-Ohio-1823, 933

N.E.2d 831, ¶10 (when establishing the dimensions of an easement, the trial court

must consider what is “reasonably necessary and convenient” to serve the purpose

for which the easement was granted.) See, also, Voisard v. Marathon, supra;

Crane Hollow, 138 Ohio App.3d at 67-68, 740 N.E.2d at 334. In those cases, the

trial courts heard evidence as to what was “reasonably necessary and convenient”

in order to determine what were the equitable limitations of the dimensions of the

easement; not necessarily what was “reasonably necessary and convenient” as to

the utilization of the easement.

       {¶32} And, concerning the issue of the appropriate dimensions of an

easement, we do not find where the width of the 1947 Sohio right-of-way was

delineated in the easement. This is an issue of fact that the trial court must

determine in order to ascertain whether Buckeye removed trees and vegetation

beyond the bounds of the easements if those boundaries were not specified. See,


                                      -19-
Case No. 1-10-60



e.g., Crane Hollow, 138 Ohio App.3d at 67, 740 N.E.2d at 334 “(when the

intended dimensions of an easement are not expressed in the grant itself,

determining the dimensions becomes largely a question of fact ***.”)

       {¶33} Buckeye asserts that the easements not only give Buckeye the right

to remove timber during the construction of the pipe line, but that Buckeye may

also remove timber during maintenance of the pipe line. We agree. However, the

record clearly shows that Buckeye was not doing any maintenance on the pipe line

at the time of the clearing. Many of the cases relied upon by Buckeye held that it

was permissible to remove trees from an easement, but they involved issues that

arose when the easement grantee sought to repair or do specific maintenance on a

pipe line. See, e.g., Crane Hollow, supra, (where the grantee wanted to repair and

reopen a pipe line which had been capped several years earlier); Rueckel v. Texas

Eastern Transm. Corp., 3 Ohio App.3d at 156, 444 N.E.2d at 80 (the trees did not

create a problem until November 1977, when Texas Eastern was engaged in the

installation of a cathodic protection system designed to protect the pipe lines from

corrosion.)

       {¶34} We also note that the trial court prefaced its summary judgment

decision with the statement that “It should be noted that this case is not and should

not be decided in a vacuum or in isolation. Rather, we are a nation dependent

upon oil. ***” (Emphasis added.) The trial court then referenced the Gulf of


                                        -20-
Case No. 1-10-60



Mexico BP oil spill and a recent spill into the Kalamazoo River, commenting that

pipe line companies do not have an easy job of inspecting and maintaining pipe

lines. However, for the purposes of summary judgment, Civ.R. 56(C) does require

that the decision be made utilizing only the specific summary judgment evidence

set forth in the rule. “No evidence or stipulation may be considered except as

stated in this rule. A summary judgment shall not be rendered unless it appears

from the evidence or stipulation, and only from the evidence or stipulation, that

reasonable minds can come to but one conclusion ***.”         (Emphasis added.)

Civ.R. 56(C). Buckeye alluded to the necessity of clearing the easement so that it

could quickly and easily access its pipe line for maintenance or in the event of

emergency. But again, there was no actual evidence in the record as to how often

a company might need to access its pipe line (for either routine work or emergency

purposes), how much of the pipe line would need to be accessed, whether the

presence of vegetation on the right-of-way would actually cause a significant

problem, and how large of an area was reasonably necessary to be cleared for

those purposes.

      {¶35} If there was evidence in the record that the vegetation on the

easements was interfering with Buckeye’s actual maintenance of the pipe line,

Buckeye would have the right to remove the offending vegetation. However, we

do not grant summary judgment on mere speculation. The burden of showing that


                                      -21-
Case No. 1-10-60



no genuine issue exists as to any material facts falls upon the moving party.

Without uncontroverted evidence that it was necessary for Buckeye to clear all

vegetation from all areas of the easements in order to “maintain” its pipe line,

summary judgment was not proper. Appellants’ first and second assignments of

error are sustained.

       {¶36} Having found error prejudicial to the appellant herein in the

particulars assigned and argued, we reverse the judgment of the trial court and

remand for further proceedings consistent with this opinion.

                                       Judgment Reversed and Cause Remanded

PRESTON, J., concurs.

/jnc

ROGERS, P.J., concurs separately.

       {¶37} I concur with the majority opinion, but write separately to stress my

position that pipeline cases in Ohio have given too much latitude to the pipeline

companies to unilaterally interpret and expand their “rights” under easements.

The usual standards for interpretation of the contracts for easements should be

applied in all such cases and not expanded without compensation simply because

some new Federal regulation imposes new duties upon the companies. Nor should

the right to clear trees and brush be expanded without compensation simply

because some new invention, such as an airplane, makes inspection easier and/or


                                       -22-
Case No. 1-10-60



more economical if done in a manner not contemplated by those who executed the

contract. As I stated in my dissent in Voisard v. Marathon:

      I am troubled by what I perceive to be a departure from general
      contract principles in pipeline cases.          In general, these
      departures routinely favor pipeline companies and grant rights
      which were clearly not within the reasonable contemplation of
      property owners at the time the easements were signed. One of
      the cornerstones of contract law is to ascertain the intent of the
      parties at the time they entered into the contract. I do not
      believe that, at the time these parties entered into the agreement,
      either contemplated federal regulation of gas companies to the
      extent that they are regulated today. Nor do I believe the parties
      contemplated the use of aerial surveillance to achieve the
      regulatory mandates. On that issue, I would follow this court's
      holding in Lakewood Homes, Inc. v. BP Oil, Inc., 3d Dist. No. 5-
      98-29, 1999 Ohio 851.

Voisard v. Marathon Ashland Pipeline, LLC., 3d Dist. No. 9-05-49, 2006-
Ohio-6926, ¶12 (Rogers, J., Dissenting).




                                       -23-