[Cite as Campbell v. George J. Igel & Co., Inc., 2013-Ohio-3584.]
IN THE COURT OF APPEALS OF OHIO
FOURTH APPELLATE DISTRICT
HOCKING COUNTY
WILLIAM M. CAMPBELL, :
Plaintiff-Appellant, :
Case No. 13CA4
vs. :
DECISION AND
GEORGE J. IGEL & CO., INC., : JUDGMENT ENTRY
Defendant-Appellee. : RELEASED 08/14/2013
APPEARANCES:
Abigail M. Saving, Lilley & Saving Co., L.P.A., Logan, Ohio, for Plaintiff-Appellant.
Christopher J. Weber, Kegler, Brown, Hill & Ritter, LPA, Columbus, Ohio, for Defendant-
Appellee.
Hoover, J.
{¶ 1} Plaintiff-appellant, William M. Campbell (“appellant”), appeals from the judgment
of the Hocking County Court of Common Pleas that granted the motion for summary judgment
of defendant-appellee, George J. Igel & Co., Inc. (“appellee”), as to the appellant’s claim for
breach of contract. For the reasons set forth below, we reverse the judgment of the trial court
and remand for further proceedings.
{¶ 2} Appellant raises two assignments of error for review.
First Assignment of Error:
THE TRIAL COURT ERRED AS A MATTER OF LAW WHEN IT GRANTED
DEFENDANT’S MOTION FOR SUMMARY JUDGMENT.
Second Assignment of Error:
Hocking App. No. 13CA4 2
THE TRIAL COURT ERRED AS A MATTER OF LAW WHEN IT DENIED
PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT.
{¶ 3} The record reveals the following facts and procedural history. Appellant owns real
property at 19577 State Route 664, Logan, Ohio (the “Property”). In the summer of 2011, the
Ohio Department of Transportation (“ODOT”) was preparing a construction project to realign
State Route 664 adjacent to Old Man’s Cave State Park (the “Project”). On June 20, 2011, a
representative of appellee, Jon Pulcheon, met with appellant to inform him that appellee intended
to submit a bid on the Project. That same day, appellant and appellee executed a Construction
Site Agreement (the “Agreement”). Mr. Pulcheon presented the Agreement, which appears to be
a pre-printed form contract with certain additional handwritten terms, to appellant.
{¶ 4} Under the terms of the Agreement, appellant gave appellee “permission to
establish a staging area [on the Property] for basing operations associated with the construction
project including storage of materials, equipment and other pertinent items of work.” The
Agreement also gave appellee “the right of ingress and egress to the [P]roperty in locations
selected by the [appellee] for all purposes necessary to complete the fulfillment of this
agreement.”
{¶ 5} In exchange for the permission to use the Property, appellee agreed to “place [an]
embankment [of] approx. 120,000 cy [cubic yards],” to “strip and replace topsoil,” to “grade and
seed all disturbed areas,” to “provide positive drainage as needed,” and to “place aggregate up to
the building site.” The Agreement also contains a provision labeled “Lump Sum Payment
$50,000.00,” requiring appellee to pay appellant Twenty-Five Thousand Dollars ($25,000.00) “at
start,” and Twenty-Five Thousand Dollars ($25,000.00) “upon completion and acceptance.”
Hocking App. No. 13CA4 3
{¶ 6} After the parties executed the Agreement, appellee submitted its bid to ODOT and
was awarded the Project in July 2011. In January 2012, appellee notified appellant that it would
not be using the Property to stage its operations on the Project or to dump fill dirt excavated from
the Project site. Appellee then proceeded to dump fill dirt from the Project on property owned
by the State of Ohio. The Property was never used, nor was it ever disturbed during appellee’s
completion of the Project. Appellee never paid the Fifty Thousand Dollars ($50,000.00) to
appellant.
{¶ 7} Appellant filed a complaint in the Hocking County Court of Common Pleas
against appellee for breach of contract alleging damages of Fifty Thousand Dollars ($50,000.00),
plus interest and costs. Appellee filed a motion for judgment on the pleadings. Appellant
responded with a memorandum contra and a motion for summary judgment. The trial court
converted appellee’s motion for judgment on the pleadings to a motion for summary judgment.
The trial court ultimately entered judgment on January 4, 2013, overruling appellant’s motion for
summary judgment and sustaining appellee’s motion for summary judgment. The trial court
found, inter alia, that a “review of the language of the contract leads to the conclusion that the
intent of the parties was that the $50,000.00 was not due until and unless the property was used.”
Appellant timely appealed the judgment of the trial court.
{¶ 8} Because appellant’s two assignments of error are interrelated, we will address
them together.
{¶ 9} Both assignments of error challenge the trial court’s rulings on the parties’ motions
for summary judgment. We review the trial court’s decision on a motion for summary judgment
de novo. Smith v. McBride, 130 Ohio St.3d 51, 2011-Ohio-4674, 955 N.E.2d 954, ¶ 12.
Hocking App. No. 13CA4 4
Accordingly, we afford no deference to the trial court’s decision and independently review the
record and the inferences that can be drawn from it to determine whether summary judgment is
appropriate. Harter v. Chillicothe Long-Term Care, Inc., 4th Dist. No. 11CA3277, 2012-Ohio-
2464, ¶ 12; Grimes v. Grimes, 4th Dist. No. 08CA35, 2009-Ohio-3126, ¶ 16.
{¶ 10} Summary judgment is appropriate only when the following have been
established: (1) that there is no genuine issue as to any material fact; (2) that the moving party is
entitled to judgment as a matter of law; and (3) that reasonable minds can come to only one
conclusion, and that conclusion is adverse to the nonmoving party. Civ.R. 56(C); DIRECTV,
Inc. v. Levin, 128 Ohio St.3d 68, 2010-Ohio-6279, 941 N.E.2d 1187, ¶ 15. In ruling on a motion
for summary judgment, the court must construe the record and all inferences therefrom in the
nonmoving party’s favor. Civ.R. 56(C). The party moving for summary judgment bears the
initial burden to demonstrate that no genuine issues of material fact exist and that they are
entitled to judgment in their favor as a matter of law. Dresher v. Burt, 75 Ohio St.3d 280, 293,
662 N.E.2d 264 (1996). Once that burden is met, the nonmoving party then has a reciprocal
burden to set forth specific facts to show that there is a genuine issue for trial. Id.
{¶ 11} Furthermore, in order to succeed on a breach of contract claim, the plaintiff must
demonstrate that: (1) a contract existed; (2) the plaintiff fulfilled his obligations; (3) the
defendant breached his obligations; and (4) damages resulted from this breach. Chaney v.
Ramsey, 4th Dist. No. 98CA614, 1999 WL 217656, *5 (Apr. 7, 1999), citing Doner v. Snapp, 98
Ohio App.3d 597, 600, 649 N.E.2d 42 (2nd Dist.1994). “ ‘[B]reach,’ as applied to contracts is
defined as a failure without legal excuse to perform any promise which forms a whole or part of
a contract, including the refusal of a party to recognize the existence of the contract or the doing
of something inconsistent with its existence.” Natl. City Bank of Cleveland v. Erskine & Sons,
Hocking App. No. 13CA4 5
Inc., 158 Ohio St. 450, 110 N.E.2d 598 (1953), paragraph one of the syllabus. “ ‘When the facts
presented are undisputed, whether they constitute a performance or a breach of a written
contract, is a question of law for the court.’ ” Koon v. Hoskins, 4th Dist. No. 95CA497, 1996
WL 30018, *7 (Jan. 24, 1996), fn. 5, quoting Luntz v. Stern, 135 Ohio St. 225, 20 N.E.2d 241
(1939), paragraph five of the syllabus.
{¶ 12} Here, both parties agree that the Agreement is clear and unambiguous. It is
further undisputed that appellee did not utilize appellant’s land in the performance of its Project
duties despite appellant having made the Property available for use. Thus, whether appellant
may enforce the payment obligation (“Lump Sum Payment” provision) through this breach of
contract action rests upon a determination of whether, as a matter of law, the language of the
Agreement contained a condition precedent to performance, or alternatively, a mutual exchange
of promises.1
{¶ 13} If the Agreement contains an exchange of promises, then appellant may pursue a
remedy for its breach. Where, however, the formation of a contract is dependent upon a
condition precedent, such condition must be performed before the agreement becomes effective.
“A condition precedent is an occurrence that must take place before a contractual obligation
becomes effective.” Karr v. JLH of Athens, Inc., 4th Dist. No. 01CA16, 2001 WL 688543, *13
(June 12, 2001). Thus, “[i]f a condition precedent is not met, a party is excused from performing
the duty promised under the contract.” Id. “The determination of whether a contractual
provision ‘is a condition precedent or merely a promise to perform is a question of the parties’
1
The interpretation of a written contract is a matter of law. Karr v. JLH of Athens, Inc., 4th Dist.
No. 01CA16, 2001 WL 688543, *13 (June 12, 2001), fn. 30. In construing a written contract,
the primary objective is to ascertain the intent of the parties. Hoskins, 1996 WL 30018 at *5. “If
a contract is clear and unambiguous, then its interpretation is a matter of law and there is no issue
of fact to be determined.” Id.
Hocking App. No. 13CA4 6
intent.’ Intent is best determined ‘by considering the language of a particular provision, the
language of an entire agreement, or the subject matter of an agreement.’ ” Adkins v. Bratcher,
4th Dist. No. 07CA55, 2009-Ohio-42, ¶ 32, quoting Hiatt v. Giles, 2nd Dist. No. 1662, 2005-
Ohio-6536, ¶ 23. “ ‘Condition precedents are not favored by the law, and whenever possible
courts will avoid construing provisions to be such unless the intent of the agreement is plainly to
the contrary.’ ” Id.
{¶ 14} Appellee argues that use of appellant’s Property is a condition precedent to its
obligation to pay under the Agreement. Appellant, on the other hand, contends that nothing in
the Agreement made the payment obligation contingent upon actual use of the Property. Instead,
appellant argues that the Agreement unambiguously imposed a legal duty on appellee to make
payment under the Lump Sum Payment provision upon his making of the Property available for
appellee’s use.
{¶ 15} The trial court determined that appellee was not required to pay under the
Agreement unless or until it actually made use of the Property. The trial court then concluded
that because appellee chose not to use the Property, the Agreement had not been breached.
{¶ 16} In support of its argument that its obligation to pay under the Agreement was
conditioned upon the use of the Property, appellee points to two provisions. First, it points to
paragraph one of the Agreement which states: “The Land Owner grants to the Contractor
permission to establish a staging area for basing operations associated with the construction
project including storage of materials, equipment and other pertinent items of work.” (Emphasis
added.) Appellee contends that use of the word “permission” demonstrates the parties’ intent
that it was permitted, not required or obligated, to use the Property. Next, appellee points to the
Hocking App. No. 13CA4 7
Lump Sum Payment provision, and argues that the words making payment due “at start” and
“upon completion” create express conditions precedent to its payment obligations.
{¶ 17} Appellee also contends that the subject matter of the Agreement supports a
finding of condition precedent, because fulfillment of the agreement “contemplated significant
use, disruption and alteration to [appellant’s] property had [appellee] used the Property.”
Appellee contends that interpreting the Agreement to require appellee to pay appellant despite
never having used, disturbed, or altered the Property would make the agreement unfair and
unreasonable; and would give the Agreement no meaning or purpose.
{¶ 18} In contrast, appellant argues that the four corners of the Agreement contains no
conditional language; but rather, clearly and unambiguously defines the contractual obligations
of the parties. Appellant also disputes that the use of the words “1/2 at start $25,000”, and “1/2
upon completion and acceptance $25,000” creates an express condition precedent. Appellant
contends that placement of this language under a section of the Agreement labeled “Lump Sum
Payment” “speaks solely to the timing of the payment of the contract price.” Appellant also
argues that appellee mischaracterizes the use of the word “permission”; and alleges that the word
is actually used to describe his obligations, not to modify the obligations of appellee. In support,
appellant points to the surrounding provisions and notes that the two paragraphs immediately
following the paragraph in which the word “permission” is used, relate solely to the obligations
of the appellant and have no bearing on the obligations of appellee.
{¶ 19} Applying the rules of interpretation set forth above, we conclude that the trial
court erred when it determined that appellee was not obligated to perform under the Agreement
until or unless the Property was used. As an initial matter, we reject appellee’s argument that the
Hocking App. No. 13CA4 8
Lump Sum Payment provision of the Agreement expressly made the use of the Property a
condition precedent to its payment obligation. Rather, we read the provision as an unambiguous
obligation of appellee to make payment in exchange for appellant making his Property available
for use during the duration of the ODOT Project. Put another way, the Lump Sum Payment
provision sets forth an unconditional promise by the appellee to perform – i.e., a promise to
make payment of Fifty Thousand Dollars ($50,000.00). The words “at start” and “upon
completion,” merely set forth the time that appellee was required to make payment. Had the
parties intended to make payment conditional upon appellee’s actual use of the Property, they
easily could have inserted language to that effect. We find that the Lump Sum Payment
provision is not explicit enough to indicate that the parties intended to create a condition
precedent.
{¶ 20} We also reject appellee’s argument that use of the word “permission,” in
paragraph one of the Agreement, demonstrates the parties’ intent to create a conditional contract.
As appellant points out in its reply brief, paragraph one is contained in a portion of the
Agreement that sets forth the duties and obligations of appellant. Thus, it is clear when reading
the provision in the context of the entire contract that use of the word “permission” is not
intended to grant appellee discretion in deciding whether to use the Property; but rather to
expressly set forth the promise of appellant to make the Property available to appellee.
{¶ 21} Moreover, a review of the entire Agreement further evidences an intent of the
parties to create an unconditional contract. For instance, the express terms of the Agreement
requiring appellee to place an embankment of 120,000 cubic yards, to strip and replace topsoil,
to grade and seed all disturbed areas, to provide positive drainage, and to place aggregate up to
building site, are all drafted as assurances and declarations. There is no language modifying
Hocking App. No. 13CA4 9
these obligations or evidencing an intent to make the obligations conditional. In fact, nowhere in
the Agreement will one find language that is typical of a conditional contract; i.e., nowhere in the
Agreement can be found the words “condition” or “conditional,” “contingent,” “subject to,”
“unless,” and etc…
{¶ 22} Finally, we also disagree with appellee’s argument that the subject matter of the
Agreement evidences an intent of the parties’ that the Agreement be conditional. The
Agreement is titled “Construction Site Agreement.” The introductory recital states that the
Agreement concerns “a certain construction contract between the [George J. Igel & Co., Inc.]
and Ohio Dept. of Transportation in Hocking County, Ohio, designated as ODOT 110417.” The
Agreement was clearly executed with the understanding that use of appellant’s Property was
necessary in order for appellee to fulfill its Project obligations with ODOT. Accordingly, the
subject matter of the agreement evidences an intent that the Agreement was unconditional, and
of vital importance to appellee’s ability to perform its contract with ODOT.
{¶ 23} Appellee also advances the argument that the timing of the Agreement execution
evidences the parties’ intent to create a conditional contract. More specifically, appellee argues
that the parties’ could not have intended that appellee was obligated to use the Property because
at the time the Agreement was executed, appellee had yet to even bid on the ODOT contract. In
essence, appellee is asking the court to consider parol evidence in support of its contention that
its obligations under the Agreement were conditioned upon use of the Property.
{¶ 24} “ ‘While parol evidence is inadmissible to vary the unambiguous terms of a
written contract, it is admissible to establish a condition precedent to the existence of a contract.’
” Hiatt, 2005-Ohio-6536 at ¶ 31, quoting Riggs v. Std. Slag Co., 9th Dist. No. 16199, 1993 WL
Hocking App. No. 13CA4 10
473817, *1 (Nov. 10, 1993). However, “[e]ven a condition precedent may not be shown by
parol evidence when the condition is inconsistent with the express terms of the writing. When
the subject matter of a condition precedent is dealt with in the written instrument, in any form,
the condition may not be shown by parol evidence to be different from the manner in which it is
expressed in the writing.” Id. at ¶ 32. Here, we have already determined that the Agreement
unambiguously imposes on appellee a contractual duty to perform. Because the Agreement
speaks specifically to the duties of the parties’, any parol evidence offered to prove a contingent
relationship would contradict the express terms of the Agreement. Even more, the Agreement
contains an integration clause which states that: “It is agreed that the terms and conditions of this
agreement are fully covered in the foregoing and that any oral or written statements made by
either party or agents, not set forth herein, are not binding on the parties and are not considered
as part of this agreement.” As such, reliance upon parol evidence is inappropriate in the case at
hand.
{¶ 25} In sum, we find that use of the Property was not a condition precedent to
appellee’s duty to perform under the Agreement. A contract existed; appellant fulfilled his
obligations under the contract; and appellee undisputedly failed to perform its obligations under
the contract. However, we believe that genuine issues of material fact exist with respect to
whether damages resulted from the breach. The trial court did not commit error by denying
appellant’s motion for summary judgment as damages still need to be proven to succeed on a
breach of contract claim. However, the trial court did err in granting appellee’s motion for
summary judgment. The trial court’s judgment is hereby reversed and this cause is remanded so
that a hearing may be held regarding damages.
Hocking App. No. 13CA4 11
{¶ 26} Based upon the foregoing, we sustain appellant’s first assignment of error and
overrule appellant’s second assignment of error. We reverse the judgment of the Hocking
County Court of Common Pleas; and we remand this matter to the trial court so that further
proceedings may be held regarding the damages.
JUDGMENT REVERSED AND CAUSE REMANDED.
Hocking App. No. 13CA4 12
JUDGMENT ENTRY
It is ordered that the JUDGMENT IS REVERSED and that the CAUSE IS REMANDED.
Appellee shall pay the costs herein taxed. The Court finds there were reasonable grounds for this
appeal.
It is ordered that a special mandate issue out of this Court directing the Hocking County
Common Pleas Court to carry this judgment into execution.
Any stay previously granted by this Court is hereby terminated as of the date of this
entry.
A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the
Rules of Appellate Procedure.
Harsha, J.: Concurs in Judgment and Opinion.
McFarland, P.J.: Dissents.
For the Court
By:
Marie Hoover, Judge
NOTICE TO COUNSEL
Pursuant to Local Rule No. 14, this document constitutes a final judgment entry and the
time period for further appeal commences from the date of filing with the clerk.