J-A02017-14
2014 PA Super 184
VINCENT P. NERTAVICH, JR. IN THE SUPERIOR COURT OF
PENNSYLVANIA
v.
PPL ELECTRIC UTILITIES, KTA, KTA-
TATOR, INC.,
KTA/SET ENVIRONMENTAL, S-E
TECHNOLOGIES, INC.,
ALEXANDER ANDREW, INC., D/B/A
FALLTECH, ALEXANDER
ANDREW, INC., FALLTECH, THOMAS &
BETTS CORP.,
THOMAS & BETTS CORP., D/B/A OR T/A
MEYER STEEL STRUCTURES, F/K/A I.T.T.
- MEYER
INDUSTRIES, F/K/A MEYER INDUSTRIES,
MEYER
STEEL STRUCTURES F/K/A I.T.T.- MEYER
INDUSTRIES,
F/K/A MEYER STEEL STRUCTURES, ITT-
MEYER INDUSTRIES,
MEYER INDUSTRIES, MEYER MACHINE,
INC. AND WINOLA
INDUSTRIAL, INC.
APPEAL OF: PPL ELECTRIC UTILITIES
CORPORATION
No. 3415 EDA 2012
Appeal from the Judgment Entered December 5, 2012
In the Court of Common Pleas of Philadelphia County
Civil Division at No(s): No. 2316 Sept. Term 2009
BEFORE: FORD ELLIOTT, P.J.E., OTT, J., and STRASSBURGER, J.*
____________________________________________
*
Retired Senior Judge assigned to the Superior Court.
J-A02017-14
OPINION BY OTT, J.: FILED AUGUST 27, 2014
$2,494,542.35, entered December 5, 2012, in the Philadelphia County Court
of Common Pleas, in favor of Vincent P. Nertavich, Jr., for the injuries he
sustained when he fell 40 feet while working as the employee of an
independent contractor1 2
On
appeal, PPL argues the trial court erred in failing to grant judgment
notwithstanding the verdict (j.n.o.v.) or a new trial. For the reasons set
forth below, we conclude that PPL was entitled to the grant of j.n.o.v., and,
accordingly, reverse the judgment entered in favor of Nertavich.
The facts underlying this appeal are summarized by the trial court as
follows:
Defendant PPL owns 90-foot-high, 10-foot-in
circumference tubular steel electric transmission poles. Some of
these poles need to be repainted from time to time to prevent
structural decay. PPL contracted with QSC [Painting,
contract called for
work to begin in August 2007 and be completed by November
____________________________________________
1
2
and Thomas & Betts Corp., were either dismissed by the trial court or settled
prior to trial. Thomas & Betts was the manufacturer of both the electric
transmission pole and ladder upon which Nertavich was working when he
sale of the pole was dismissed pretrial by summary judgment. His claim
with respect to the ladder proceeded to trial, but the jury found Thomas &
Betts was not negligent.
-2-
J-A02017-14
That PPL Specification document contained a variety of
detailed requirements about the job. It prescribed each step
how to paint the poles.
....
While the workmen painted, power might continue to
surge through the lines attached to the poles. As a result, the
insulators, making sure that paint does not splatter or drip onto
off the insulators. Also, PPL maintained control over the
known as a contract field representative, for the project who was
materials, quality assurance, general safety, work procedures
a
the circuit breakers so that the workers would not be
PPL representative would not allow workers on the poles until
the lines were set.
the contractor to ensure that safety requirements of the contract
involving a direct threat or imminent danger, the field
Repre
ordered from Defendant Thomas & Betts, with PPL establishing
their specifications. The pole specifications included the
dimensions of the pole, its paint, and the number and type of
attachment points. PPL was aware that the poles would need
repainting every 15 to 20 years. PPL did not specify that the
poles should have any vangs[, i.e., pieces of metal,] welded onto
anyard or other suspension device could
attach to the pole. The only attachment points on the poles,
besides those at the top of the poles and on the arms for
electrical wires, were a series of brackets running up one side of
-3-
J-A02017-14
That PPL Specification document contained a variety of
detailed requirements about the job. It prescribed each step
how to paint the poles.
....
While the workmen painted, power might continue to
surge through the lines attached to the poles. As a result, the
insulators, making sure that paint does not splatter or drip onto
off the insulators. Also, PPL maintained control over the
known as a contract field representative, for the project who was
materials, quality assurance, general safety, work procedures
a
the circuit breakers so that the workers would not be
PPL representative would not allow workers on the poles until
the lines were set.
the contractor to ensure that safety requirements of the contract
involving a direct threat or imminent danger, the field
Repre
ordered from Defendant Thomas & Betts, with PPL establishing
their specifications. The pole specifications included the
dimensions of the pole, its paint, and the number and type of
attachment points. PPL was aware that the poles would need
repainting every 15 to 20 years. PPL did not specify that the
poles should have any vangs[, i.e., pieces of metal,] welded onto
anyard or other suspension device could
attach to the pole. The only attachment points on the poles,
besides those at the top of the poles and on the arms for
electrical wires, were a series of brackets running up one side of
-3-
J-A02017-14
[Nertavich] lost 3 inches in height as his body literally
compacted from the fall.
Trial Court Opinion, 6/14/2013, at 2-6 (footnotes and record citations
omitted).
Nertavich initiated this personal injury/products liability action by writ
of summons on September 23, 2009. After filing a complaint and first
amended complaint, Nertavich filed a second amended complaint on April
Falltech, Thomas & Betts, and Winola Industrial, Inc. which designed,
manufactured, and/or sold fall protection equipment, the electric
transmission poles, and the single-rail ladders4
PPL and KTA/Set Environmental, the owner of the utility poles and an
engineering consulting company hired to oversee the painting work,
respectively. Nertavich raised claims of general negligence, professional
negligence, strict liability, and breach of warranty, as well as sought punitive
damages.
PPL filed a motion for summary judgment on July 5, 2011, which the
trial court denied on September 1, 2011.5 The case proceeded to a jury
____________________________________________
4
5
The other defendants also filed motions for summary judgment. Relevant
to this appeal, Thomas & Betts filed a motion for partial summary judgment,
products liability claim with respect to the
manufacture and design of the transmission pole was barred by the statute
(Footnote Continued Next Page)
-5-
J-A02017-14
the pole. These brackets served as attachment points for
removable single-
wobble, frightening workers. There was no place for a worker
climbing the pole to attach a lanyard or lifeline, except for
somewhere on these ladders. There were two types of ladders.
Both consisted of a central metal beam with metal pegs
protruding out to the left and right. The first, termed a working
ladder, had parallel pegs on each side to give the appearance of
a straight bar across the rail so that a worker could stand level.
The second type, the climbing ladder, had alternating pegs
staggered at regular intervals up each side of the rail. The
ladders came from the manufacturer with two bolts that attach
through their bottom to secure them to the pole. QSC, not
having another means of lifting its workers into place to paint
the pole, asked PPL for the removable ladders. PPL provided
QSC with the ladders, but not with the bolts.
On September
ground working on a PPL pole. More experienced workers were
painting the pole above him. He was standing on one of the
climbing ladders. QSC provided [Nertavich] with a pole belt, a
body harness, and two lanyards. One lanyard was to attach to
the pole belt, and the other was to attach to the body harness to
serve as a lifeline. [Nertavich] used only the pole belt and one
lanyard. He testified at trial that on previous jobs he had used
only the pole belt and one lanyard, and that no one told him he
had to use the harness as well.[3] The one lanyard he used was
coated in dried paint. [Nertavich] tied the paint-coated lanyard
to the ladder above him, a working ladder, by looping it around a
left peg. [Nertavich], holding on to the lanyard, leaned out to
his left to slap paint on a hard-to-reach spot on the back of the
pole. The ladder above him to which he was tied off wobbled
several inches to the left. The lanyard unlooped. [Nertavich] fell
40 feet, landing on his feet. The fall fractured his feet,
dislocated his ankles, fractured his knee, his right femur, his
right hip, and burst several of his lumbar spine disks.
____________________________________________
3
Indeed, Nertavich admitted that his body harness was in his truck on the
day of his accident. N.T., 3/1/2012, at 129-130.
-4-
J-A02017-14
trial, commencing in February of 2012. PPL moved for a nonsuit at the
-in-chief, and a directed verdict at the close of
all testimony, both of which were denied by the trial court.6 On March 9,
2012, the jury returned a verdict in favor of Nertavich in the amount of
$4,613,150.00. However, the jury found PPL 51% causally negligent for
injuries. The jury also found that the ladder designed by Thomas & Betts
was not defective.7
Both parties sought post-trial relief. On March 13, 2012, Nertavich
filed a motion for delay damages, and, on March 19, 2012, PPL filed post-
trial motions seeking j.n.o.v. or a new trial. The trial court granted
motion, and, on April 9, 2012, entered a molded verdict in the
amount of $2,494,542.35 in favor of Nertavich and against PPL.8 Thereafter,
-trial motion, and on
_______________________
(Footnote Continued)
of repose. See 42 Pa.C.S. § 5536. The trial court agreed, and dismissed
that claim. See Order, 9/1/2011.
6
The trial court did, howe
7
Accordingly, Thomas & Betts has not filed a brief in this appeal.
8
The molded verdict reflects both a reduction in the total award based upon
-6-
J-A02017-14
December 5, 2012, judgment was entered on the verdict. This timely appeal
followed.9
PPL raises the following four issues on appeal:
(1) Is PPL entitled to judgment notwithstanding the verdict for
injuries sustained by an employee of an independent
contractor when controlling Pennylvania law, as reflected
in Beil v. Telesis Construction, Inc., 608 Pa. 273, 11 A.3d
456 (Pa. 2011), requires that PPL exercise significant
control over the manner, methods, means, and operative
that is specifically related to the accident, and the evidence
at trial established that the independent contractor itself
directed and exercised control over its work?
(2) Is PPL entitled to a new trial on liability when the Court
improperly permitted Nertavich to introduce evidence of
including such things as
onsite safety representative, and a common law duty to
hire competent contractors when those purported duties
are inconsistent with Beil or otherwise inapplicable under
the law?
(3) Is PPL entitled to a new trial on liability when the Court
instructed the jury contrary to Beil?
(4) Is PPL entitled to judgment notwithstanding the verdict
when the evidence established that Nertavich assumed the
risk of his fall?
-4. Because we conclude that PPL is entitled to j.n.o.v. on its
first issue, we need not address its remaining claims.
____________________________________________
9
The trial court did not direct PPL to file a concise statement of errors
complained of on appeal pursuant to Pa.R.A.P. 1925(b).
-7-
J-A02017-14
not responsible for the acts or omissions of such independent contractor or
Beil, supra, 11 A.3d at 466 (emphasis supplied).
This foundational law is based upon the long-standing notion
that one is not vicariously liable for the negligence of an
independent contractor, because engaging an independent
manner of doing the work contracted for. How can the other
party control the contractor who is engaged to do the work, and
who presumably knows more about doing it than the man who
by contract authorized him to do it? Responsibility goes with
Silveus v. Grossman, 307 Pa. 272, 278, 161 A.
362, 364 (1932).
Id.
However, this general rule is subject to certain exceptions. Relevant
414 of the Restatement (Second) of Torts:
One who entrusts work to an independent contractor, but who
retains the control of any part of the work, is subject to liability
for physical harm to others for whose safety the employer owes
a duty to exercise reasonable care, which is caused by his failure
to exercise his control with reasonable care.
Restatement (Second) of Torts § 414 (1965).
The Beil Court discussed the degree of control necessary to hold an
owner liable for injuries suffered by an employee of an independent
contractor under Section 414:
The primary question in many premises cases, as is the
issue before us, is whether the property owner hirer of the
independent contractor retained sufficient control of the work to
be legally responsible for the harm to the plaintiff. Comment c
to Section 414 provides the most commonly used test for
determining whether an employer/landowner retained sufficient
control. More precisely, comment c speaks to the degree of
-9-
J-A02017-14
First, PPL contends it is entitled to j.n.o.v. because Nertavich failed to
establish that it retained control over the manner, methods, means, and
overcome the general rule that an owner owes no duty to the employees of
an independent contractor.
be entered upon two bases: (1) where the movant is
entitled to judgment as a matter of law; and/or, (2) the evidence was such
that no two reasonable minds could disagree that the verdict should have
Egan v. USI Mid-Atl., Inc., 92 A.3d 1, 19-
decision granting or denying a post-trial motion for j.n.o.v. is well-
established:
When a court reviews a motion for judgment n.o.v., the
reviewing court considers the evidence in the light most
favorable to the verdict winner, who must receive the benefit of
every reasonable inference of fact arising therefrom, and any
conflict in the evidence must be resolved in his or her favor. A
judgment n.o.v. should only be entered in a clear case.
Beil v. Telesis Const. Inc., 11 A.3d 456, 462 (Pa. 2011) (citations
omitted). Further, we will not substitute our judgment for that of the fact
finder when it comes to questions of credibility and weight of the evidence.
Egan, supra, 92 A.3d at 20 (citation omitted).
In Beil, the case upon which PPL relies for support of its appeal, the
-8-
J-A02017-14
not responsible for the acts or omissions of such independent contractor or
Beil, supra, 11 A.3d at 466 (emphasis supplied).
This foundational law is based upon the long-standing notion
that one is not vicariously liable for the negligence of an
independent contractor, because engaging an independent
manner of doing the work contracted for. How can the other
party control the contractor who is engaged to do the work, and
who presumably knows more about doing it than the man who
by contract authorized him to do it? Responsibility goes with
Silveus v. Grossman, 307 Pa. 272, 278, 161 A.
362, 364 (1932).
Id.
However, this general rule is subject to certain exceptions. Relevant
414 of the Restatement (Second) of Torts:
One who entrusts work to an independent contractor, but who
retains the control of any part of the work, is subject to liability
for physical harm to others for whose safety the employer owes
a duty to exercise reasonable care, which is caused by his failure
to exercise his control with reasonable care.
Restatement (Second) of Torts § 414 (1965).
The Beil Court discussed the degree of control necessary to hold an
owner liable for injuries suffered by an employee of an independent
contractor under Section 414:
The primary question in many premises cases, as is the
issue before us, is whether the property owner hirer of the
independent contractor retained sufficient control of the work to
be legally responsible for the harm to the plaintiff. Comment c
to Section 414 provides the most commonly used test for
determining whether an employer/landowner retained sufficient
control. More precisely, comment c speaks to the degree of
-9-
J-A02017-14
because the poles were energized, and there were no other
attachment points on the poles to rig other climbing devices.
QSC had to request these ladders from PPL to climb the poles.
These facts, especially the way in which PPL dictated how
QSC workers were to perform their painting work coupled with
evidence of control over safety and access, evince the quality of
control that the Supreme Court found lacking in Beil. The
qualitative element being present, it was for the jury to
determine if the quantity of control necessary to make PPL liable
existed. There were ample facts in evidence, including the
to determine that the necessary quantum of control existed as
they did.
Id. at 16-17 (footnote omitted).
Conversely, PPL argues the type of control Nertavich claims it retained
over the jobsite in this case is the same type of control the Supreme Court
found insufficient in Beil
-run Beil through a so-
matter of law. We agree.
Beil
decision on the issue of landowner liability for injuries sustained by the
employee of an independent contractor. A discussion of the facts and
disposition in Beil will be helpful to our resolution of the present case. They
are as follows.
Lafayette Colleg
Telesis subcontracted the roofing work to Kunsman Roofing and Siding
also
- 12 -
J-A02017-14
restore stonework on the exterior of the building. On the day of the
accident, Beil was installing flashing on the roof. He used scaffolding erected
by MPS, after consultation with the College, to access the roof. While
ascending the ladder with 15 pounds of flashing, he fell 30 feet, and
sustained serious injuries. Beil subsequently filed a personal injury action
against the College, Telesis, and MPS. A jury awarded damages of $6.8
million, and apportioned liability as follows: Telesis 50% liable, the College
35% liable, MPS 10% liable and Beil 5% liable. The College appealed, and
this Court reversed and remanded for the entry of j.n.o.v. in favor of the
College. Beil then petitioned the Supreme Court for allowance of appeal.
See Beil, supra, 11 A.3d at 458-462. On appeal, the Supreme Court
retain sufficient control of the premises to subject it to liability pursuant to
Id. at 472.
retained control of the premises in two broad categories: safety and access.
Id. at 46
Id. He presented the following evidence in support of that claim: (1)
Telesis was contractually obligated to comply with the safety directives of
-site project manager was consulted as to
- 13 -
J-A02017-14
because the poles were energized, and there were no other
attachment points on the poles to rig other climbing devices.
QSC had to request these ladders from PPL to climb the poles.
These facts, especially the way in which PPL dictated how
QSC workers were to perform their painting work coupled with
evidence of control over safety and access, evince the quality of
control that the Supreme Court found lacking in Beil. The
qualitative element being present, it was for the jury to
determine if the quantity of control necessary to make PPL liable
existed. There were ample facts in evidence, including the
to determine that the necessary quantum of control existed as
they did.
Id. at 16-17 (footnote omitted).
Conversely, PPL argues the type of control Nertavich claims it retained
over the jobsite in this case is the same type of control the Supreme Court
found insufficient in Beil
-run Beil through a so-
matter of law. We agree.
Beil
decision on the issue of landowner liability for injuries sustained by the
employee of an independent contractor. A discussion of the facts and
disposition in Beil will be helpful to our resolution of the present case. They
are as follows.
Lafayette Colleg
Telesis subcontracted the roofing work to Kunsman Roofing and Siding
also
- 12 -
J-A02017-14
restore stonework on the exterior of the building. On the day of the
accident, Beil was installing flashing on the roof. He used scaffolding erected
by MPS, after consultation with the College, to access the roof. While
ascending the ladder with 15 pounds of flashing, he fell 30 feet, and
sustained serious injuries. Beil subsequently filed a personal injury action
against the College, Telesis, and MPS. A jury awarded damages of $6.8
million, and apportioned liability as follows: Telesis 50% liable, the College
35% liable, MPS 10% liable and Beil 5% liable. The College appealed, and
this Court reversed and remanded for the entry of j.n.o.v. in favor of the
College. Beil then petitioned the Supreme Court for allowance of appeal.
See Beil, supra, 11 A.3d at 458-462. On appeal, the Supreme Court
retain sufficient control of the premises to subject it to liability pursuant to
Id. at 472.
retained control of the premises in two broad categories: safety and access.
Id. at 46
Id. He presented the following evidence in support of that claim: (1)
Telesis was contractually obligated to comply with the safety directives of
-site project manager was consulted as to
- 13 -
J-A02017-14
a post-accident email that the roofers were working in a potentially unsafe
expert testimony that the College controlled safety at the site. Id. With
certain are
Id. at 469. In support of this contention, he produced evidence that: (1)
the College denied the roofers access to certain areas of the building; (2) the
subcontractors had to obtain written permission to enter the building; and
(3) the College hired MPS, whose scaffolding was used, and the College was
consulted as to where to place the scaffolding. Id. at 469-470.
However, the Supreme Court held that a property owner may retain a
certain degree of authority over safety issues, as well as regulate the use of
retaining a certain degree of authority over safety issues, such as
supervising and enforcing safety requirements, and even imposing its own
safety requirements at a work site, does not constitute control for purposes
Id. at 469 (footnote omitted). Rather, a property
public policy. Id. at 468.
subs
- 14 -
J-A02017-14
Id. at 471. Rather, the Court
explained,
[did] not directly relate to the decis
equipment, which Kunsman contracted to provide, and Telesis
contracted to ensure was safe. While MPS permitted the
Kunsman roofers to use its scaffolding, Telesis did not anticipate
or rely upon the use of MPS scaffolding for access to the roof,
and access was for Kunsman to determine.
Id. Accordingly, the Beil
exercised certain authority regarding safety and regulated access to, and
use of, certain areas of the premises, this is not the type of conduct that
Id. at 472.
In the present case, however, the trial court opined that the facts
ly the way in which PPL dictated how QSC
workers were to perform their painting work coupled with evidence of control
over safety and access, evince the quality of control that the Supreme Court
found lacking in Beil 17 (footnote
actual exercise
to be sufficient in the present case] are the very same theories of control
- 15 -
J-A02017-14
rejected by Beil and its ancestors.
follow, we agree.
With respect to the contract provisions,10 the trial court first found that
which included such details as the specific
type of paint to use, how to apply the paint (i.e., by concealing brush marks,
without runs, by applying a uniform finish and thickness, etc.), and the
11
- constituted control
specifications had nothing
directed QSC workers how to tie off to the pole, how to climb the pole, or
____________________________________________
10
rpretation is to ascertain the intent
of the contracting parties. In cases of a written contract, the intent of the
Lesko v. Frankford Hospital-Bucks County,
15 A.3d 337, 342 (Pa. 2011) (quotation omitted).
11
See Contract, 8/30/2007, Attachment A, at 2, ¶ 17.
- 16 -
J-A02017-14
Id. at 1062.
In the present case, the contract provided quality specifications for the
painting of the transmission poles.13
to do with these quality specifications. Rather, Nervatich fell when the
ladder he tied off on wobbled, and the single lanyard he used as fall
protection slid off the rung.14 Moreover, Nertavich has failed to identify any
contractual provisions that instructed QSC how to climb the poles safely
to complete the painting work.15 Rather, the contract specifically provided
ing
equipment necessary to complete this painting contract in an efficient
____________________________________________
13
Gallus Wukitsch, who at the time of the accident was a senior engineer in
P -
-in-chief. He explained why the contract
Keeler and Long product, you d
understand that the paint we were specifying had certain requirements by
Id. at 53.
14
nyard attached which is how he had been working
-226
15
As we will discuss infra, Nertavich also contends that PPL actually
controlled how QSC climbed the poles.
- 19 -
J-A02017-14
A, at 3, ¶¶ 23 and 26. As
specifications set forth in the contract did not establish that
accident.16
Secondly, with regard to the terms of the contract, the trial court also
See Trial
Court Opinion, 6/14/2013, at 16-17. Specifically, the court noted that (1)
the contract specified safety provisions to be followed, and (2) created the
position of a PPL contract field supervisor, Wayne Grim, whose duty it was to
monitor safety conditions at the work site and hold daily safety meetings.17
____________________________________________
16
f the operational
the contract provided specific, detailed painting specifications. However,
how QSC was to achieve those specifications was up to the company, itself.
at 146; Videotaped Deposition of John Pateras, 7/22/2010, at 31. More
importantly, as discussed supra, the contract did not specify how QSC was
.
17
As became evident during trial, Mr. Grim had no training or experience
climbing steel transmission poles. N.T., 2/29/2012, at 154. However, he
Id. at
170. Indeed, Nertavich confirmed that no one from PPL directed the
painters as to how to do their jobs, and QSC had its own foreman, Mike
Healy, who rotated between three or four QSC painting crews on the PPL
(Footnote Continued Next Page)
- 20 -
J-A02017-14
Id. at 1062.
In the present case, the contract provided quality specifications for the
painting of the transmission poles.13
to do with these quality specifications. Rather, Nervatich fell when the
ladder he tied off on wobbled, and the single lanyard he used as fall
protection slid off the rung.14 Moreover, Nertavich has failed to identify any
contractual provisions that instructed QSC how to climb the poles safely
to complete the painting work.15 Rather, the contract specifically provided
ing
equipment necessary to complete this painting contract in an efficient
____________________________________________
13
Gallus Wukitsch, who at the time of the accident was a senior engineer in
P -
-in-chief. He explained why the contract
Keeler and Long product, you d
understand that the paint we were specifying had certain requirements by
Id. at 53.
14
nyard attached which is how he had been working
-226
15
As we will discuss infra, Nertavich also contends that PPL actually
controlled how QSC climbed the poles.
- 19 -
J-A02017-14
A, at 3, ¶¶ 23 and 26. As
specifications set forth in the contract did not establish that
accident.16
Secondly, with regard to the terms of the contract, the trial court also
See Trial
Court Opinion, 6/14/2013, at 16-17. Specifically, the court noted that (1)
the contract specified safety provisions to be followed, and (2) created the
position of a PPL contract field supervisor, Wayne Grim, whose duty it was to
monitor safety conditions at the work site and hold daily safety meetings.17
____________________________________________
16
f the operational
the contract provided specific, detailed painting specifications. However,
how QSC was to achieve those specifications was up to the company, itself.
at 146; Videotaped Deposition of John Pateras, 7/22/2010, at 31. More
importantly, as discussed supra, the contract did not specify how QSC was
.
17
As became evident during trial, Mr. Grim had no training or experience
climbing steel transmission poles. N.T., 2/29/2012, at 154. However, he
Id. at
170. Indeed, Nertavich confirmed that no one from PPL directed the
painters as to how to do their jobs, and QSC had its own foreman, Mike
Healy, who rotated between three or four QSC painting crews on the PPL
(Footnote Continued Next Page)
- 20 -
J-A02017-14
at 17.
However, the Beil Court made clear that a property owner who retains
enforcing safety requirements, and even imposing its own safety
requirements at a work site, does not constitute control for purposes of
imposing liabil Beil, supra, 11 A.3d at 469. Moreover, the terms of the
contract in the present case clearly placed responsibility for job site safety
upon QSC. The contract explicitly provided:
responsibilities under this Contract while performing Work on
for safety-related reasons, these actions are for the primary
purpose of protecting Company personnel and property.
Contractor shall remain solely responsible for the safe
performance of the Work under this Contract. The
provisions of this article shall be interpreted and construed in a
contractor.
Contract, 8/30/2007, at 6-7, ¶ M (emphasis supplied). See id. at 5, ¶¶ D
_______________________
(Footnote Continued)
job. N.T., 3/1/2012, at 161- -worker Ryan Wheeler
testified that Healy would yell at the painters if they were not using fall
protection on a pole. See N.T., 2/27/2012, at 132; Videotaped Deposition
of Ryan Wheeler, 7/21/2010 at 90.
- 21 -
J-A02017-14
18
shall take all reasonable precautions for the
safety of all Contractor personnel engaged in the Work and shall
See also id. at
be safely painted in [their] entirety prior to start of work on that
to provide all personal protecti
19
-related reason that
type of safety oversight was the same which the Supreme Court found
permissible in Beil. See Beil, supra
property owner retaining a certain degree of authority over safety issues,
such as supervising and enforcing safety requirements, and even imposing
its own safety requirements at a work site, does not constitute control for
See also LaChance, supra, 869 A.2d at
1060- ised to assure
itself that [independent contractor] performed its work safely, as [it] had
____________________________________________
18
Painting
19
See Contract, 8/30/2007, at 5-6, ¶ F.
- 22 -
J-A02017-14
agreed in its contract, did not make [landowner] the guarantor of the safety
Moreover, with respect to the contract, the trial court also found PPL
fied that this
areas of any questions, materials, quality assurance, general safety, work
Moreover, the t
to as GSP-19, which stated that the contract field representative was to
cedures, Section 19 (Revised-
establishment of the position of contract field representative demonstrated
Nerta
However, in , 911 A.2d
1264 (Pa. 2006), the Supreme Court rejected a similar claim that a
-site safety supervisor established that the
landowner retained control over the worksite.
- 23 -
J-A02017-14
of a section of an expressway in western Pennsylvania. PTC also hired
responsible to administer and oversee several projects, as well as monitor
the safety procedures of the other contractors. Id. at 1268. Farabaugh, an
employee of NESL, was fatally injured when he drove a loaded, off-highway
dump truck up a hill and the haul road he was traveling on collapsed due to
instability in the hill. His Estate argued at trial that the haul road did not
comply with safety measures. Id. at 1269. The trial court granted
summary judgment in favor of PTC and Trumbull, and the Commonwealth
Court reversed. Id. at 1270-1271.
20
at PTC
safety orientation videotape to all those employed on the jobsite, (2) by
____________________________________________
20
reversal of summary judgment with respect to Trumbull, concluding:
[u]nder the relevant contract
of care to Decedent based upon its contractual obligation to
perform safety inspections and other monitoring functions. A
determination of the scope of the duty and whether this duty
was breached, however, requires further development of the
proximate cause of the accident.
Id. at 1267. Unlike in the present case, Trumbull was contractually
obligated to monitor safety on the job site.
- 24 -
J-A02017-14
employing an on-site safety inspector, and (3) by contracting with Trumbull
to provide construction management services. Id. at 1273-1274. However,
LaChance
dictates that [a landowner] monitor the safety of its highway construction
Id.
at 1275, quoting LaChance, 869 A.2d at 1064. Furthermore, the
Farabaugh Court held:
It would likewise disserve public policy to impose liability
on PTC for going one step further and hiring a contractor
specifically to supervise safety issues on site in addition
to requiring its general contractor to be responsible for
safety under its own contract with PTC. Instead, we
ct with PTC, PTC turned over
control of the worksite to its general contractor, NESL, and did
of a Section 414 analysis.
Id. at 1275.
tract field
representative, responsible for, inter alia
practices, did not evidence its retention of control over all matters of work
for th
8/30/2007, at 7 ¶ M.
misplaced. The GSP internal company documents that set forth safety
- 25 -
J-A02017-14
-51. In
particular, while GSP 19, which governs contractor safety, states that the
ontractor to ensure that
Section 19 (Revised January 2005) at ¶¶ 5.4, 7.2. See also id. at ¶ 7.1.
Therefore, although GSP 19 encourages PPL employees to monitor the safety
safety matters on the job site. Moreo
internal documents, which are not provided to the independent contractors
or their employees. N.T., 2/29/2012, at 136. Accordingly, we conclude that
te based
See Beil, supra, 11
A.3d at 467.
Turning to the second part of the Beil control test, PPL may still be
based on its actual conduct. Id.
21
sufficient to find it liable for
____________________________________________
21
Trial Court Opinion, 6/14/2013, at 17.
- 26 -
J-A02017-14
s to
-rail
ladders; and (3) by providing these ladders to QSC without the necessary
bolts to secure them to the transmission poles. See Trial Court Opinion,
6/14/2013, at 17, 21. PPL argues, conversely, that none of this evidence
demonstrated its retention of control over the job site.
it wa
engineer, Wukitsch described the procedure as follows:
Green tag procedure allows us to work on facilities. And what
contacts a line or some other thing, the lines trip out and
automatically reclose.
cker real fast. Lines trip and
With a green tag permit, we actually go to the end points
at the substations, at the circuit breakers. We change the
condition of those circuit breakers so that if at any time those
electrical lines would trip for any reason, they would
N.T., 2/29/2012, at 14- ephen Estrin,
testified that the procedure was necessary to ensure that QSC workers were
- 27 -
J-A02017-14
the job site:
QSC was not given unfettered discretion of when, where and
how to work. They had to get this tag before they could work.
So if they arrived on the job site at 0700 and PPL had not issued
the green tag, they could not access the pole and perform work.
They would have to wait till [PPL] issued them the tag.
Id. at 105.
PPL contends, however, that this argument is similar to the controlled
access claim rejected by the Supreme Court in Beil. In Beil, the College
ted with MPS as to where to
erect its scaffolding, which Beil later used to access the roof. Nonetheless,
the Beil
ontrol
over the manner, method, means, or operative detail in which the work is
Beil, 11 A.3d at 471. The Court opined:
They are tangential to the substantive work of the contractor,
and subcontractor. Simply stated, the College did not control
the way the workers did their work.
does not directly relate to the decision of
scaffolding instead of [its] own equipment, which [it]
contracted to provide, and [the general contractor]
contracted to ensure was safe. While MPS permitted the
[subcontractor] roofers to use its scaffolding, [the general
contractor] did not anticipate or rely upon the use of MPS
scaffolding for access to the roof, and access was for [the
subcontractor] to determine.
Id. (emphasis supplied and record citation omitted).
- 28 -
J-A02017-14
Similarly, here, the green tag permit simply indicated to QSC that the
pole was not energized, and it was safe for QSC to perform its painting work,
pursuant to the contract, by whatever means it saw fit. Indeed, the permit
procedure did not directly relate to the decision of QSC concerning how its
employees would climb the poles. As the Beil
novel, if not absurd, interpretation of Section 414 if an independent
Id. at 470. Furthermore, the
issuance of a green tag permit for the pole had nothing to do with the
22
Accordingly, we find that the green tag permit
Second, the trial court also
to the poles by limiting the available ways to scale the poles to the use of
single rail ladders. Trial Court Opinion, 6/14/2013, at 17. Indeed, Nertavich
t any other means for
This finding, however, ignores the specific terms of the contract that
____________________________________________
22
Had Nertavich been electrocuted as a result of the improper issuance of a
green tag permit, we would be inclined to conclude that PPL maintained
control over that aspect of the job site, and was subject to liability.
- 29 -
J-A02017-14
equipmen
Contractor to field locate the structu
Id. at 1. The contract also stated that the
ot be safely
Id.
at 2, ¶ 12. Accordingly, the terms of the contract placed all responsibility for
determining how to access the transmission poles upon the knowledgeable
independent contractor, QSC.
QSC, the experienced contractor, not PPL, determined how to climb the
Deposition of John Pateras, 7/22/2010, at 31. He confirmed that the
-rail ladders, to access
23
Id. at 32. See also N.T., 2/27/2012, at
____________________________________________
23
We note that Nertavich argues PPL was negligent for not questioning QSC
Program (Revision No. 3), 11/27/1995, at 61. However, the above
(Footnote Continued Next Page)
- 30 -
J-A02017-14
co-
. However, this
argument ignores the reality that QSC was the expert painting contractor,
with 16 years of experience in industrial painting, and most of its experience
working for power companies, such as PPL. N.T., 2/28/12, at 146;
Videotaped Deposition of John Pateras, 7/22/2010, at 14-15. In fact,
Wukitsch testified that all of the contractors who attended the pre-bid
meeting, including QSC, understood that they would be accessing the
rs told him
they had used them before. N.T., 2/29/2012, at 110-111. PPL provided the
job specifications, and deferred to the specialized expertise of the contractor
to determine how to safely complete the work. Accordingly, we conclude
suggest or provide alternative means to access the
transmission poles is not evidence of its retention of control over the job
site.
_______________________
(Footnote Continued)
was entitled to rely on the expertise of the independent contractor it hired to
perform this specialized work.
- 31 -
J-A02017-14
supplying the single-rail ladders to QSC. The cour
supply their ladders only after it was unable to obtain them itself. Pateras
But I do remember in the bidding process that originally we were
supposed to furnish the climbing devices. I called the company
furnish it. Then I believe I had spoke[n] to PP&L and told them
about the problem. And PP&L furnished some climbing devices.
N.T., 2/28/12, at 146; Videotaped Deposition of John Pateras, 7/22/2010, at
71. Pateras testified that he was at the warehouse when his employees
Id. at 73. Moreover, Wukitsch
testified that after PPL located the single-rail ladders,
[w]e showed [QSC] what we had and said: We would make
these available for your use.
working order. They were the ones who picked them up and
took them out to the job site, installed them.
N.T., 2/29/2012, at 35 (emphasis supplied). Indeed, Wukitsch testified that
for all c
Id. at 114-115. See also Contract, 8/30/2007, Attachment
A at 3, ¶ 23. He explained that the language was added to make clear that
- 32 -
J-A02017-14
he ladders, carry them, put them on,
Id. at 115.
Therefore, while PPL made available to QSC the actual ladders the
contractor used to climb the transmission poles, we do not find that, by
PPL only made the ladders
available when QSC was unable to obtain them on its own. Significantly,
there was no evidence that PPL mandated that QSC use these particular
ladders to climb the transmission poles. Indeed, the language of the
contract was cle
rigging equipment necessary to complete this painting contract in an
after inspection of the ladders, was free to reject them, or choose a different
means to climb the poles. Accordingly, we conclude the trial court erred in
-rail ladders Nertavich used
the climb the transmission poles established its retention of control over the
job site.24
____________________________________________
24
We do not find that the decision of the Pennsylvania Supreme Court in
Byrd v. Merwin, 317 A.2d 280 (Pa. 1974), mandates a different result. In
that case, Byrd was an employee of an electrical subcontractor hired to
contractor on the job.
was installing electrical wiring. The usual procedure in such situations was
to install the staircase prior to wiring the house. Id. at 518.
(Footnote Continued Next Page)
- 33 -
J-A02017-14
Because we conclude that the evidence, viewed in the light most
favorable to Nertavich, did not establish that PPL retained sufficient control
over the job site, based on the contract provisions and actual control, to
subject it to liability
motion for j.n.o.v.
presented evidence that PPL was directly liable for his injuries. He argues
Beil direct liability when the landowner,
_______________________
(Footnote Continued)
Byrd sued both Olin and Merwin, and a jury returned a verdict in his
Section 414 of the Restatement. On appeal, the Supreme Court reversed,
Id. at 282. Further, Merwin, the general
Id.
must be remembered that it was Olin who ordered electrical work started
b Id.
First, we note that Byrd was a plurality decision, with three justices
joining the majority, two justices concurring in the result, and one justice
dissenting. In addition, the facts in Byrd were clear that the owner retained
control of the work site and actually instructed the subcontractor when and
where to begin his work. There is no such degree of control in the present
case.
- 34 -
J-A02017-14
as here, engages in its own, independent negligent conduct that directly
of law, we conclude that his claims of direct negligence in the present case
fail.25
Nertavich claims PPL was directly liable for his injuries based on the
the Restatement (Second) of Torts, because PPL provided single-rail ladders,
____________________________________________
25
We note that both the trial court and Nertavich cite Chenot v. A.P. Green
Services, Inc., 895 A.2d 55 (Pa. Super. 2006), for the proposition that a
land owner may be directly liable to the employee of an independent
contractor for its own negligent acts. Trial Court Opinion, 6/14/2013, at 20
we disagree that Chenot stands
for such a broad principal of law. Indeed, the Chenot Court simply found
In that case, Chenot was exposed to asbestos dust while working as
an employee of Philip Carey, an independent contractor retained by Koppers
Company to install new insulation in one of its manufacturing facilities.
Chenot later contracted mesothelioma as a result of this exposure. Chenot,
supra, 895 A.2d at 58. In concluding that Koppers owned a duty of care to
of a danger on his premises has a duty to warn an independent contractor of
that danger, whether or not the contractor exercises full control over the
premises. Id. at 64.
Therefore, rather than stand for the broad proposition that a
landowner may be directly liable to the employee of an independent
doctrine, a doctrine which the trial court found inapplicable in the present
case. See
- 35 -
J-A02017-14
without accompanying bolts to secure the ladders to the transmission poles,
and provided an unqualified contract field representative to monitor safety
practices on the job site; (2) negligent design of the transmission poles,
because PPL failed to require the pole manufacturer to include lifeline
26
and the
National Electric Safety Code (NESC). For the reasons that follow, we
conclude that none of these theories should have been presented to the
jury.
Section 323 of the Restatement (Second) of Torts, commonly known as the
27
imposes liability when one gratuitously undertakes
to perform a service for another:
One who undertakes, gratuitously or for consideration, to render
services to another which he should recognize as necessary for
the protection of the other's person or things, is subject to
liability to the other for physical harm resulting from his failure
to exercise reasonable care to perform his undertaking, if
(a) his failure to exercise such care increases the risk of such
harm, or
(b) the harm is suffered because of the other's reliance upon the
undertaking.
Restatement (Second) of Torts § 323 (1965).
____________________________________________
26
Occupational Safety and Health Act, 29 U.S.C. § 651 et seq.
27
Filter v. McCabe, 733 A.2d 1274, 1276 (Pa. Super. 1999), appeal
denied, 758 A.2d 1200 (Pa. 2000).
- 36 -
J-A02017-14
QSC with the single-rail ladders, it did so negligently when it failed to also
provide the bolts to secure the ladders to the transmission poles. We
increased the risk of harm to Nertavich or that Nertavich, or, in fact, QSC,
with the single-rail ladders supplied by PPL, and, indeed, had requested
were aware that the ladder could be secured to the transmission pole with a
bolt. For example, another QSC painter, Donald Thompson, testified that he
ladders in question. N.T., 3/7/2012, at 157. He explained that he had
painted more than 5,000 poles, and while some had ladders permanently
attach Id. at 157-
158. He also testified why he never used bolts when he installed the single-
rail ladders:
gets hard. The red primer was 6000 primer. It sets in there,
and you have to sometimes beat them out to get it to come back
out.
Id.
as their use on the PPL job. Id. Moreover, Nertavich, himself, testified that
prior to the PPL job, he had painted approximately two dozen similar
- 37 -
J-A02017-14
including the one in question. N.T., 3/1/2012, at 23, 25-26. He testified he
had never seen a bolt attaching the ladder to the poles on any job. Id. at
36-37.
ularly, when his
own co-worker acknowledged that QSC never used bolts to attach the
single-rail ladders to the poles in a temporary application, and Nertavich,
himself admitted he never saw a bolt attaching the ladder to the pole on any
job. Moreover, bec industrial painting
expert, he cannot establish that his accident resulted from
Second, Nertavich argues PPL was directly liable for his injuries when it
chose to provide an on-site contract field representative to ensure job site
safety procedures were being followed, but then negligently appointed Grim
to the position, who had no training or experience on the proper way to
climb and tie-off on a transmission pole. We conclude, however, this
argument runs counter to the dictates of Beil, Farabaugh, and LaChance,
As our sister court stated in LaChance
LaChance,
supra, 869 A.2d at 1064. Furthermore, in Farabaugh, the Supreme Court
- 38 -
J-A02017-14
concluded that
safety issues at the job site. Farabaugh, supra, 911 A.2d at 1275.
Moreover, in Beil, the Supreme Court reiterated that a property owner who
supervising and enforcing safety requirements, and even imposing its own
safety requirements at a work site, does not constitute control for purposes
Beil, supra, 11 A.3d at 469 (footnote omitted). To
hold that an owner who designates an, albeit inexperienced, on-site safety
representative may be held liable under Section 323 of the Restatement,
would undercut the case law cited above, as well as the general rule that a
landowner is generally not responsible for the acts or omissions of his
independent contractor.28 Id. at 466.
Furthermore, the imposition of liability under these circumstances
contract provided for the designation of a contract field representative, who
____________________________________________
28
Our conclusion might be different if there was any evidence that Grim
provided instructions or directions to Nertavich or the other QSC employees.
However, the testimony was undisputed that Grim provided no direction at
all.
- 39 -
J-A02017-14
questions, materials, quality assurance, general safety, work procedures and
29
solely
responsible
Contract, 8/30/2007, at 7, ¶ M (emphasis supplied). Therefore, we conclude
Next, Nertavich claims PPL was directly liable for his injuries because it
failed to require the transmission pole manufacturer, Thomas & Betts, to
include lifeline attachment points, or vangs, on the poles. He argues:
PPL was responsible to advise Thomas & Betts of any attachment
points it wanted on its poles because PPL was in the best
position to know what it needed to do on its poles by way of
access and maintenance. PPL knew that its poles would need to
be repainted. PPL knew that workers would need to access its
poles to paint them. PPL, by ordering the ladders to access and
work on its poles, knew that workers would need to climb the
should have known, that QSC prohibited the use of single rail
ladders. PPL knew or should have known that such ladders did
not provide adequate safe tie-offs for the lifelines needed by the
workers to perform their duties safely and were also proscribed
by OSHA.
transmission pole, attempts to end-
determination that the statute of repose barred any claim based upon the
____________________________________________
29
Contract, 8/30/2007, Attachment A, at 2, ¶ 6.
- 40 -
J-A02017-14
court granted
or manufacture of the transmission pole was barred by the statute of repose,
42 Pa.C.S. § 5536. The statute mandates, in relevant part, that any action
observation of construction, or construction of any improvement to real
property must be commenced within 12 years after completion of
30
42 Pa.C.S. § 5536(a). Therefore,
any challenge to design of the pole should be similarly barred.31
____________________________________________
30
Wukitsch testified that the transmission pole that Nertavich was painting
the mid- at 17. Therefore, it had been in
place more than 20 years on September 23, 2007, the date of the accident.
31
was tainted by hearing evidence of the defective pole, which was not an
issue in the case. He claims that the only evidence he produced regarding
asserted the pole was defective
n.7. However, PPL did not assert a claim against Thomas & Betts claiming
that the pole was defective. Rather, its counterclaims asserted only
allegations of joint and several liability and contribution/indemnification.
See
Second Amended Complaint, May 11, 2011, at ¶¶ 119-120.
- 41 -
J-A02017-14
that under Pennsylvania law the defendants could owe
plaintiff a duty of care. It is important to reiterate that to use
the OSHA regulation as evidence here is not to apply the OSHA
for use as evidence of the standard of care owed to plaintiff.
This is precisely how the Pennsylvania state courts had
employed OSHA regulations. See e.g. Brogley v.
, 306 Pa.Super. 316, 452 A.2d 743,
746 (1982).
Id. at 1014 (emphasis supplied). Therefore, the Third Circuit concluded
evidence of the violation of an OSHA regulation was relevant to the issue of
the standard of care, only after the court first determined that the
defendant owed a duty of care to the plaintiff.
In that case, the Court found that Kane owed a duty to Rolick pursuant
possessor of land must exercise reasonable care to protect invitees from
non- Id. at 1011. The Court
recognized that,
[a]lthough the duty owed to an independent contractor varies
depending upon the control the possessor maintains over
the work
still use reasonable care to make the premises safe or give
adequate and timely warning of dangers known to him but
unknown to the contractor....
Id. (citation omitted and emphasis supplied). Section 343, however, is
inapplicable in the present case because none of the purported causes of
Nert i.e., the failure to use a second lanyard, the use of a
constituted dangers known to PPL, but unknown to
Nertavich or his employer, QSC. Moreover, as discussed supra, we conclude
- 44 -
J-A02017-14
that the evidence presented by Nertavich
we conclude that PPL owed no duty to Nertavich, the employee of an
independent contractor, it would have been improper for the jury to consider
Therefore, because we conclude that PPL was entitled to judgment as
post trial motion for j.n.o.v. See Egan, supra. Accordingly, we reverse the
judgment entered against PPL, and remand for the entry of j.n.o.v. Because
our dispositi
remaining claims.
Judgment reversed. Case remanded for entry of j.n.o.v. Jurisdiction
relinquished.
Strassburger, J., files a Dissenting Opinion.
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 8/27/2014
- 45 -