ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Certified Construction Company of ) ASBCA No. 58782
Kentucky, LLC )
)
Under Contract No. W9124D-06-D-0001 )
APPEARANCES FOR THE APPELLANT: Thomas E. Roma, Jr., Esq.
G. Alan Oliver, Esq.
Ackerson & Yann, PLLC
Louisville, KY
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
CPT Tyler L. Davidson, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE TING
ON GOVERNMENT'S PARTIAL MOTION TO DISMISS
Certified Construction Company of Kentucky, LLC (Certified or appellant)
submitted a $839,052.31 request for equitable adjustment (REA) in September 2012.
After the contracting officer (CO) denied the REA, Certified submitted a claim. The
CO denied the claim and Certified appealed. The government moves to dismiss a
portion of appellant's claim for lack of Contract Disputes Act (CDA), 41 U.S.C.
§§ 7101-7109, jurisdiction, arguing that it accrued six years prior to appellant's claim
submission. Certified maintains that its REA was a claim and that the Board has
jurisdiction over a larger portion of appellant's claim than the government asserts. We
grant the government's motion and dismiss the portion of the appeal pertaining to
costs incurred prior to 22 March 2007.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. Effective 20 October 2005, Fort Knox Directorate of Contracting (Army or
the government) awarded Contract No. W9124D-06-D-0001 to Certified. The
requirements-type contract was for concrete placement, asphalt surface treatments and
pavement markings at Fort Knox, Kentucky, for a period of performance from
1 November 2005 through 31 October 2006. The contract included a one-year option
period. (R4, tab 1)
2. The government exercised the first option year by Modification No. P00005
extending the contract through 31 October 2007 (R4, tab 7 at 1-2) and extended that
option through 30 April 2008 by Modification No. P00009 (R4, tab 11 at 1). The
government also modified the contract multiple times to adjust line item pricing (R4,
tabs 8-10, 12-14). The final estimated value of the contract was$ 3,166,308.90 (R4,
tabs2, 14).
3. The contract contained Alternate I of the Disputes clause, FAR 52.233-1,
DISPUTES (JUL 2002)-ALTERNA TE 1 (DEC 1991 ).
4. During the course of performance, appellant alleges, "the cost of certain
petroleum products substantially increased in a manner unanticipated at the time
Appellant entered into the contract" (comp I. ~ 7). Certified sent a letter, dated
17 September 2012, to the CO with the subject line "Requirements Type Contract for
Concrete and Asphalt-W9l24D-06-D-OOO1." The letter stated:
We are making a Request for Equitable Adjustment to this
contract. ...
During the contract we incurred additional expenses due to
the extreme rise in petroleum products used in this
contract. The product that had the greatest impact to our
costs was Liquid Asphalt.. .. The CLIN's that were
affected by this cost impact are 0072, 0073, 1072 and
1073. We have estimated our request using the Kentucky
Transportation Cabinet, Department of Highways Standard
Specifications for Road and Bridge Construction,
Section 109.07.01, Price Adjustments for Liquid Asphalt.
We have attached the worksheets we used in the
determination of the cost impact for this request and the
REA is based on the KY Asphalt Index, KAPI at the time
of the contract bid, versus the KAPI at the time of
production and installation.
The total amount requested for the REA is listed below for
the Asphalt Base and Asphalt surface items we used for the
duration of the contract.
Total Request for Equitable Adjustment $ 839,052.31
2
In summary, this request is for adjustment to contract
pnce.
(R4, tab 15 at 1-2)
5. The 17 September 2012 letter included the following certification, signed by
Certified' s president:
I certify that this request is made in good faith, and that the
supporting data is accurate and complete to the best of my
knowledge and belief.
(R4, tab 15 at 2)
6. The 17 September 2012 letter included two calculation tables, one for each
grade of asphalt used during construction: 4.8% and 5.6%. Both tables were
structured similarly. For each month of contract performance, appellant compared the
price of asphalt, as set by the Kentucky Average Price Index (KAPI), at the time of
production and installation to the price of asphalt, as set by the KAPI, at the time of its
bid, made a determination whether a price adjustment was appropriate for each
respective month and calculated the alleged amount of the adjustment. For example,
for the months of May and June 2006, it made the following calculations:
PC QUANTITY TONS T A PL c T*A/IOO*PL*(C-5)
MO./YEAR KY FOR PAY ITEM % PRICE %CHANGE
~SPHALT FOR MONTH ASPHALT INDEX IN INDEX ~DJUSTMENT
INDEX I st TO End of Month AT LETTING PLUS/MINUS 5%
May-06 312.7 4.8% $220.63 36.730% NO ADJ
Jun-06 355.2 1993.130 4.8% $220.63 55.990% $11,818.22
The tables include calculations for every month from January 2006 through December
2009. 1 (R4, tab 15 at 3-6)
7. The Kentucky Transportation Cabinet releases the KAPI price monthly (app.
supp. R4, passim).
8. In response to appellant's 17 September 2012 letter, the government sent a
letter, dated 19 October 2012, denying appellant's request for equitable adjustment
(R4, tab 16).
9. Certified sent a second letter, dated 22 March 2013, to the CO with the
subject line "Request for Contracting Officer's Decision." The letter stated:
1
There is no adjustment claimed for the month of March 2007 (R4, tab 15).
3
On September 17, 2012, Certified requested an equitable
adjustment to the Contract to compensate for the increased
cost of performance resulting from the unprecedented
increase in the price of Liquid Asphalt.... By letter dated
October 19, 2012, the Department of the Army denied
Certified's request for equitable adjustment.
... Certified submits that the Department's denial of Claim
for Equitable Adjustment was improper and requests a
decision by the Contracting Officer that it is entitled to the
$839,052.31 difference between petroleum costs at the
time the contract was bid, and the [sic] at the time of
production and installation, calculated using the Kentucky
Asphalt Index.
(R4, tab 17 at 1-2) The 22 March 2013 letter included the following certification,
signed by Certified's president:
I certify that this claim is made in good faith; that the
supporting data are accurate and complete to the best of
my knowledge and belief; that the amount requested
accurately reflects the contract adjustment for which
Certified believes the Government is liable; and that I am
duly authorized to certify the claim on behalf of Certified.
(Id. at 2)
10. The CO issued a CO's final decision (COFD), by letter dated 31May2013,
denying Certified's claim (R4, tab 18). Certified appealed the COFD to this Board by
letter dated 16 July 2013 (R4, tab 19).
DECISION
The government moves to dismiss "the portion of this appeal that pertains to
'additional expenses' incurred prior to March 22, 2007" arguing that "recovery for
such expenses is barred under the [CDA's] six-year statute of limitations" (gov't mot.
at 1). Appellant argues that only the portion of the claim that "accrued more than
six years before its letter of September 17, 2012" is not within the Board's jurisdiction
(app. resp. at 3 n. l ).
4
The CDA' s statute of limitation requires that a contractor's claim against the
government "shall be submitted within 6 years after the accrual of the claim."
41 U.S.C. § 7103(a)(4)(A). As of January 2005, FAR 33.201 defined accrual of a
claim in pertinent part as: "the date when all events, that fix the alleged liability of
either the Government or the contractor and permit assertion of the claim, were known
or should have been known."
Where a claim is inherently susceptible to being broken down into a series of
independent and distinct events or wrongs, each having its own associated damages,
the doctrine of continuing claim will apply. Gray Personnel, Inc., ASBCA No. 54652,
06-2 BCA il 33,378 at 165,476-77 (citing Friedman v. United States, 159 Ct. Cl. 1
( 1962)). In the instance of a continuing claim "the statute of limitations runs on each
distinct liability-creating event having its own associated damages." Fluor
Corporation, ASBCA No. 57852, 14-1 BCA il 35,472 at 173,930.
Appellant's claim was inherently susceptible to being broken down into a series
of distinct events, namely the monthly release of the KAPI and, therefore, the
continuing claim doctrine applies. Appellant's price adjustment claim is founded on
the comparative price of asphalt at the time of asphalt production against the price of
asphalt at the time of the bid, where the prices are established by the KAPI (SOF ilil 4,
6). Each release of the KAPI for a particular month ofCertified's performance was an
independent and distinct event having its own associated damages. For each month,
appellant determined whether a price adjustment was allegedly owed and calculated
damages independently for each month (SOF il 6). The government's potential
liability could not be fixed until the Kentucky Transportation Cabinet released the
KAPI each month. Accordingly, appellant's claim was a continuing claim and the
statute of limitations runs distinctly on each month's release of the KAPI between
January 2006 through December 2009.
The government argues that:
[B]ecause the time between the dates on which ... portions
of the claim accrued and March 22, 2013, the date
appellant submitted the claim, was more than the CDA's
six-year statute of limitations allows, the Board must
dismiss the portions of the appeal related to claims which
accrued prior to March 22, 2007.
(Gov't mot. at 5-6) Appellant, in its response, does not refute the argument that
portions of its claim accrued each month (app. resp. at 2). However, appellant argues
that its claims were first submitted to the CO by its 17 September 2012 letter (app.
resp. at 3).
5
The CDA does not define the term claim; however, the FAR defines a claim as:
[A] written demand or written assertion by one of the
contracting parties seeking, as a matter of right, the
payment of money in a sum certain, the adjustment or
interpretation of contract terms, or other relief as arising
under or relating to the contract.
FAR 2.101. It is established that while a claim need not be submitted in any particular
form or use any particular wording, a proper CDA claim must include "( 1) adequate
notice of the basis and amount of a claim and (2) a request for a final decision."
M Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1328 (Fed. Cir. 2010).
The request for a final decision can be explicit or implied. See James M Ellett
Construction Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996); see also
Environmental Safety Consultants, Inc., ASBCA No. 54995, 06-1BCAii33,230 at
164,666 (holding that the contractor impliedly requested a CO's decision when it
resubmitted its REA with an unsigned CDA certification where the amount in dispute
was less than $100,000). Additionally, claims over $100,000 must be certified in
accordance with 41 U.S.C. § 7103(b)(l). TMS Envirocon, Inc., ASBCA No. 57286,
12-2 BCA ii 35,084 at 172,296. "We employ a common sense analysis in evaluating
on a case by case basis whether a demand constitutes an effective claim." Zafer
Taahhut Insaat ve Ticaret A.S., ASBCA No. 56770, 11-2 BCA ii 34,841 at 171,391
(citing Transamerica Insurance Corp. v. United States, 973 F.2d 1572, 1579 (Fed. Cir.
1992)).
Appellant's 17 September 2012 letter was not a claim but was in fact an REA.
The 17 September 2012 letter failed to request a CO' s decision, a foundational
requirement for any contractor claim. See Maropakis, 609 F.3d at 1328. At no point
did Certified explicitly request a COFD and nothing in the letter implied that a request
for a COFD was being made. The 17 September 2012 letter consistently referenced
that it was an REA. (SOF ii 4) Furthermore, appellant's letter was not certified as a
CDA claim but was certified in accordance with DF ARS 252.243-7002, REQUESTS
FOR EQUITABLE ADJUSTMENT (MAR 1998) (SOF ii 5). The contents of the
17 September 2012 letter is wholly consistent with the submission of an REA and,
therefore, there is nothing to imply a request for a COFD. The totality of the record
further supports the conclusion that when appellant submitted its 17 September 2012
letter, it intended to submit an REA. The CO treated the 17 September letter as an
REA when it denied it rather than issuing a COFD, and Certified did not object
(SOF ii 8). In fact, at all points after the submission of the 17 September 2012 letter,
Certified consistently refers to and treats the letter as an REA, not a claim. The
22 March 2013 letter referenced the 17 September 2012 letter and characterized it as
an REA (SOF ii 9) and appellant's complaint refers to the 17 September 2012 letter as
an REA (com pl. ii 10 ). Appellant's first attempt to characterize the 17 September
6
2012 letter as a claim occurred only after the government filed its partial motion to
dismiss (app. resp. at 3). However, despite its recent assertions to the contrary,
appellant did not submit a claim until 22 March 2013 when it converted the
I 7 September 2012 REA to a CDA claim by providing a CDA certification and
requesting a COFD (SOF ii 9).
As appellant did not submit a claim until 22 March 2013, the portion of
appellant's claim accruing prior to 22 March 2007 was not submitted to the CO within
six years after accrual. Therefore, we have no jurisdiction to consider that portion of
appellant's claim. See 41 U.S.C. § 7103(a)(4)(A).
CONCLUSION
The government's partial motion to dismiss the portion of appellant's claim
accruing prior to 22 March 2007 is granted. The appeal is dismissed for lack of
jurisdiction to the extent it relates to alleged costs incurred between January 2006 and
March 2007. The Board has jurisdiction of the appeal as it relates to costs incurred
after March 2007. 2
Dated: 8 July 2014
... b
PETER D. TING
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
~a&l_I. 6~
&~~
Administrative Judge
MICHAEL T. PAUL
Administrative Judge
Acting Chairman Acting Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
2
The Board does not consider what day of the month the claim accrued because appellant
does not claim an adjustment for the month of March 2007 (SOF ii 6 n. l ).
7
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 58782, Appeal of Certified
Construction Company of Kentucky, LLC, rendered in conformance with the Board's
Charter.
Dated:
JEFFREYD. GARDIN
Recorder, Armed Services
Board of Contract Appeals
8