December 23 2014
DA 14-0196
Case Number: DA 14-0196
IN THE SUPREME COURT OF THE STATE OF MONTANA
2014 MT 332
SHERIDAN ELECTRIC CO-OP, INC.,
a Montana rural electric cooperative,
Plaintiff and Appellee,
v.
MONTANA-DAKOTA UTILITIES,
a corporation,
Defendant and Appellant.
APPEAL FROM: District Court of the Fifteenth Judicial District,
In and For the County of Daniels, Cause No. DV 10-2013-2
Honorable David Cybulski, Presiding Judge
COUNSEL OF RECORD:
For Appellant:
Jeffery J. Oven, Steven R. Milch, Crowley Fleck PLLP; Billings, Montana
For Appellee:
Maxon R. Davis, Davis, Hatley, Haffeman & Tighe, P.C.; Great Falls,
Montana
Loren O’Toole, II, O’Toole Law Firm; Plentywood, Montana
Submitted on Briefs: September 24, 2014
Decided: December 23, 2014
Filed:
Clerk
Justice Michael E Wheat delivered the Opinion of the Court.
¶1 Montana-Dakota Utilities (MDU) appeals from the judgment of the Fifteenth Judicial
District Court, Daniels County, granting Sheridan Electric Co-op, Inc.’s (Sheridan) motion
for summary judgment and denying MDU’s motion for summary judgment.
FACTUAL AND PROCEDURAL BACKGROUND
¶2 The material facts are not in dispute. Sheridan is a Montana rural electric cooperative.
MDU is an electric services provider. Both serve customers in the Madoc/Scobey area in
Daniels County. Cahill Seeds, Inc. (Cahill) is a farm and seed retail business located
approximately six miles east of Scobey, near the intersection of Highway 5 and North Madoc
Road.
¶3 In 2011, Cahill began planning the construction of a new seed washing plant and
submitted initial requests for electric service to MDU and Sheridan. The request stated that
Cahill would require three-phase Wye power to operate the plant.
¶4 When Cahill made its request Sheridan had an existing distribution line carrying
three-phase Wye power approximately 1.33 miles north of the Cahill site. Meanwhile, MDU
had an existing line carrying three-phase Wye power located approximately 6.5 miles west of
Cahill. MDU also had an existing transmission line carrying three-phase Delta power
running along Highway 5, and a distribution line connected to that transmission line at its
Madoc Substation, near the junction of Highway 5 and North Madoc Road, approximately
300 feet from Cahill.
2
¶5 Sheridan responded to Cahill’s request, stating that it could provide three-phase Wye
power with the construction of a 1.33 mile line extension connecting its distribution line to
Cahill. MDU told Cahill that it could not provide three-phase Wye power.
¶6 In September 2011, Cahill began building the seed washing plant. To provide power
during construction, MDU installed a pole-mount transformer along the distribution line and
extended a 285 foot single-phase service line to Cahill.
¶7 During 2012 and 2013, as construction neared completion and Cahill began to install
equipment requiring three-phase Wye power, MDU upgraded its transmission and
distribution systems near Cahill. MDU replaced the transformer at the Madoc substation
with a Wye transformer, added a fourth “neutral” wire to the distribution line, replaced the
pole mount transformer on the distribution line with a three-phase padmount transformer,
and replaced the single-phase service line with three-phase service line. These upgrades
allowed MDU to provide three-phase Wye power to Cahill.1 After completing its upgrades,
MDU began providing three-phase Wye power to Cahill.
¶8 On January 14, 2013, prior to MDU completing its upgrades, Sheridan filed a
complaint in District Court. Sheridan alleged that MDU violated the Montana Territorial
Integrity Act (MTIA) when it extended power to Cahill. Sheridan argued that under the
priority provisions of the MTIA it had the exclusive right to serve Cahill because it had a line
capable of delivering three-phase Wye power located 1.33 miles away from Cahill, while
MDU’s closest capable line was 6.5 miles away from Cahill. According to Sheridan,
1
An MDU employee testified that the fourth wire was a common addition to three-phase Wye lines
but not a necessity.
3
MDU’s nearby distribution line did not meet the requirements of the MTIA because
substantial upgrades to MDU’s distribution system were required to send three-phase Wye
power along the line.
¶9 MDU responded, arguing that the MTIA only required that the “line” itself need have
the capacity to carry the requisite load. MDU pointed out that the line itself had the physical
capacity to carry three-phase Wye power, and only the transformers needed to be upgraded
to provide three-phase Wye to Cahill.
¶10 Both sides moved for summary judgment. The District Court ruled in favor of
Sheridan, finding that the 1.33 mile distance from Sheridan’s three-phase Wye transmission
line to Cahill gave Sheridan priority over MDU, whose three-phase line was 6.5 miles away.
MDU appeals.
STANDARDS OF REVIEW
¶11 We review a district court’s grant of summary judgment de novo. Scentry
Biologicals, Inc. v. Mid-Continent Cas. Co., 2014 MT 39, ¶ 23, 374 Mont. 18, 319 P.3d
1260. We review a district court’s interpretation of a statute for correctness. State v.
Madsen, 2013 MT 281, ¶ 8, 372 Mont. 102, 317 P.3d 806.
DISCUSSION
¶12 We restate the issue as follows:
¶13 1. Did the District Court err in finding that Sheridan had the right to serve Cahill
under the priority provisions of the MTIA?
4
¶14 MDU asks us to reverse the District Court for three reasons. First, because MDU had
the exclusive right to serve Cahill under § 69-5-105(1), MCA, by virtue of having the line
nearest to Cahill with the capacity to serve Cahill. Second, because MDU added Cahill to its
service territory when it began delivering single-phase construction power to Cahill in
September 2011, and therefore Sheridan was prohibited from serving Cahill by § 69-5-104,
MCA. Third, because granting priority to Sheridan would violate public policy and the
legislative intent of the MTIA.
¶15 We will address each argument in turn.
When Cahill submitted its request for three-phase Wye power, did MDU have
priority to serve Cahill under § 69-5-105(1), MCA?
¶16 We first address the question of when a provider’s facilities are measured for purposes
of determining priority for serving new consumers under the MTIA. Timing is important
where, as in this case, an electric facilities provider is upgrading its facilities during the
pendency of a dispute. The District Court implicitly held that priority should be determined
at the time Cahill approached Sheridan and MDU about providing electric services. We
agree.
¶17 Section 69-5-105(1), MCA, “Service to new consumers,” states:
Except as provided in 69-5-106 and 69-5-113, the electric facilities provider
that has a line nearest the premises and that has the capacity to serve the
premises, as measured in accordance with subsection (2), shall provide electric
service facilities to the premises initially requiring service after May 2, 1997.
Without a premises in existence the statute would have no meaning. Furthermore, the statute
clearly contemplates new premises, that is, premises that have recently come into existence.
MTIA defines “premises” as “a building, residence, structure, irrigation pump, or facility to
5
which electrical service facilities are provided or are to be installed.” Section 69-5-102(12),
MCA. When Cahill solicited bids for electrical services in early 2011, the plant became a
“facility to which electrical services . . . [were] to be installed” which is to say a premises.
The need to evaluate each party’s electrical service facilities arose at that time. Thus in
assessing priority we will consider only the electric service facilities each party had in place
when Cahill made its request for electrical service.
¶18 Having determined that we will only consider a provider’s electrical service facilities
already in place in early 2011, we turn to the question of which party had priority under the
MTIA. The answer to this question hinges upon the meaning of § 69-5-105(1), MCA.
¶19 MDU contends that the term “capacity” as used in § 69-5-105(1), MCA, refers to the
physical capacity of the line as defined by § 69-5-102(11), MCA. “‘Line’ means any
material that is used to convey electrical energy and that is normally energized between
2,400 volts phase to ground and 14,400 volts phase to ground.” Section 69-5-102(11),
MCA. Under MDU’s interpretation of the statute, MDU had priority because, at the time
Cahill submitted its request for power, the line itself had the capacity to deliver three-phase
Wye power, despite the fact that MDU’s nearby substation did not have the capacity to send
three-phase Wye power down the line.
¶20 An alternative interpretation is that the statute requires the electric facilities provider
to have the capacity to actually send the load down the line. “‘Electric facilities provider’
means any utility that provides electric service facilities to the public.” Section 69-5-102(6),
MCA. “‘Electric service facilities’ means any distribution or transmission system or related
facility necessary to provide electricity to the premises, including lines.” Section
6
69-5-102(7), MCA. Under this interpretation, Sheridan would have priority because its
nearest distribution system, including line, was actually carrying three-phase Wye when
Cahill made its request, while MDU’s distribution system required a substation upgrade in
order to carry three-phase Wye.
¶21 The plain language of § 69-5-105(1), MCA, supports the latter interpretation. The
sentence comprising § 65-5-105(1) contains two relative clauses: “that has a line nearest the
premises,” and “that has the capacity to serve the premises.” Each clause begins with the
relative pronoun “that.” The meaning of the statute rests on which noun, “electric facilities
provider” or “line,” is antecedent to which relative pronoun. Under MDU’s interpretation
“electric facilities provider” is antecedent to the first and “line” is antecedent to the second.
However, the statute states: “the electric facilities provider that has a line nearest the
premises and that has the capacity to serve the premises. . . .” Section 65-5-105(1), MCA
(emphasis added).2
¶22 Here, the “and” is dispositive. Its placement in the sentence compels the conclusion
that “electric facilities provider” is antecedent to both relative pronouns and therefore is the
subject of each relative clause. Thus it is the “electric facilities provider” that must “[have] a
2
As part of its argument, MDU notes that the statute does not define “capacity” and correctly states
that when a term is not defined by statute we consider that term to have its plain and ordinary
meaning. In support of its position that the term “capacity” refers only to the line itself, MDU
quotes Webster’s Third New International Dictionary, defining “capacity” as “the power or ability to
hold, receive, or accommodate.” This definition is indeed appropriate when referring to the capacity
of an electrical line. However, another equally plain and ordinary meaning of “capacity” is “the
ability to . . . process . . . manufacture, or produce.” Webster’s Third New International Dictionary
330 (1961). This definition is appropriate when referring to the capacity of an electrical facilities
provider. The “plain and ordinary meaning” doctrine as applied to the term “capacity” does not lend
support to either interpretation.
7
line nearest the premises” and it is the “electric facilities provider” that must “[have] the
capacity to serve the premises.”
¶23 Therefore, under § 69-5-105(1), MCA, an electric facilities provider that has the line
nearest the premises and that has the distribution system (including lines) with the capacity
to provide electricity to the premises “shall provide electric service facilities to the
premises. . . .” Section 69-5-105(1), MCA.
¶24 While it is undisputed that MDU’s distribution line had the capacity to supply
three-phase Wye power, we conclude that MDU did not meet the requirements of
§ 69-5-105(1), MCA, because its distribution and transmission facilities did not have the
capacity to provide three-phase Wye without a significant upgrade to its nearby substation.
When Cahill made its request for three-phase Wye power in 2011, MDU’s nearest line with
the distribution and transmission facilities necessary to provide three-phase Wye were more
than six miles away, while Sheridan had a line with the necessary facilities less than two
miles away. Therefore, the District Court did not err when it determined that Sheridan had
priority to serve Cahill under § 69-5-105(1), MCA.
Did Cahill become part of MDU’s “service territory” when it provided single-phase
electricity to Cahill during the construction of the facility?
¶25 MDU argues that when it provided single-phase construction power to Cahill in
September 2011, it added Cahill to its service territory, thus precluding Sheridan from
providing electricity to Cahill pursuant to § 69-5-104, MCA. That statute states that “a
utility may not provide electricity supply service to premises in another utility’s service
territory.” § 69-5-104(1), MCA. A “service territory” is defined as “premises receiving
8
distribution service from a utility on January 1, 2011, and premises added pursuant to Title
69, chapter 5.” Section 69-5-102(14), MCA.
¶26 Because MDU was not providing distribution service to Cahill on January 1, 2011,
Cahill could only be made a part of MDU’s service territory if it was added pursuant to Title
69, chapter 5. Under Title 69, chapter 5, priority for service to new customers is determined
by § 69-5-105(1), MCA. We have already concluded that Sheridan had priority in providing
electric services to Cahill under that section.3 Hence, when MDU extended single-phase
electrical service to Cahill, it did not do so pursuant to Title 69, chapter 5. Thus, MDU
providing construction power to Cahill did not result in Cahill being added to MDU’s service
territory. Section 69-5-104(1), MCA, therefore, grants no priority to MDU and does not
prohibit Sheridan from providing electricity supply service to Cahill.
Would granting Sheridan priority to serve Cahill violate the legislative intent
behind the MTIA?
¶27 MDU urges us to reverse the District Court because granting Sheridan priority to
serve Cahill would violate the legislative intent behind the MTIA. In interpreting a statute
“the office of the judge is simply to ascertain and declare what is in terms or in substance
contained therein, not to insert what has been omitted or to omit what has been inserted.”
§ 1-2-101, MCA. If the language of the statute is unambiguous “no further interpretation is
required, and we will resort to legislative history only if legislative intent cannot be
determined from the plain wording of the statute.” Clarke v. Massey, 271 Mont. 412, 416,
897 P.2d 1085, 1088 (1995).
3
See supra, ¶¶ 15-23.
9
¶28 Because we have found that the language of § 69-5-105(1), MCA, unambiguously
grants priority to the electric facilities provider that has both the line nearest the premises and
the capacity to serve the premises we will not look to legislative history in interpreting the
statute further. The statute clearly grants priority to Sheridan.
CONCLUSION
¶29 We conclude that the language of § 69-5-105(1), MCA, unambiguously grants priority
to Sheridan because it had the line closest to Cahill and the distribution system capacity to
serve Cahill. Based on that finding, we determine that MDU did not add Cahill to its service
territory pursuant to Title 69, chapter 5, when it extended single-phase construction power to
Cahill in September 2011. We decline to resort to an examination of legislative history
where the statute in question is unambiguous.
¶30 For the foregoing reasons, we hold that the District Court did not err in finding that
Sheridan has the right to serve Cahill under the priority provisions of the MTIA.
¶31 Affirmed.
/S/ MICHAEL E WHEAT
We Concur:
/S/ JAMES JEREMIAH SHEA
/S/ PATRICIA COTTER
/S/ BETH BAKER
/S/ JIM RICE
10