ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
DODS, Inc. ) ASBCA No. 59510
)
Under Contract No. SPM4A 7-09-M-8426 )
APPEARANCE FOR THE APPELLANT: Mr. David Storey
President
APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq.
DCMA Chief Trial Attorney
Douglas R. Jacobson, Esq.
Trial Attorney
Defense Contract Management Agency
Bloomington, MN
OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
PURSUANT TO BOARD RULE 12.3
INTRODUCTION
Appellant, DODS, Inc. (DODS), seeks $18,470.53 in termination settlement
costs, appealing from the deemed denial of its I May 2014 certified claim for that sum
certain. DODS has elected to proceed pursuant to Board Rule 12.3, and the parties
have elected to proceed without a hearing, pursuant to Board Rule 11. We sustain the
appeal in part and award $2,792.55, plus interest.
SUMMARY FINDINGS OF FACTS
In July 2009, DODS and the Defense Supply Center, Richmond, Virginia
(government), entered into Contract No. SPM4A 7-09-M-B426 for DODS to supply
"aircraft formers,'' including a first article for testing, for a total contract award of
$6,400 (R4, tab I at L 4 ). The first article was priced at $1,800 (id. at 9), and each of
the four aircraft formers that the contract contemplated DODS would deliver
subsequent to first article testing was priced at $ L 150 (id. at 8). DODS never
submitted a first article for approval (see app. supp. R4, tab A 184 ).
On 13 June 2011, the government terminated the contract for default (R4, tab 2
at 16). On 11 June 2012, we converted the termination for default to a termination for
convenience ofthe government. DODS, Inc., ASBCA 57667, 12-2 BCA ~ 35,078
at 172,281. On 18 December 2012, we denied the government's motion to reconsider
our decision to convert the termination. DODS, Inc., ASBCA 57667, 13 BCA
~ 35,203 at 172, 716.
On 11 March 2013, DODS submitted to the contracting officer a termination
settlement proposal (Standard Form 1435) requesting $18,470.53 (R4, tab 8). After
over a year of correspondence including regarding whether DODS had provided the
government sufficient information to support that request (R4, tabs 9, 11-17), on
1 May 2014, DODS submitted to the contracting officer a certified claim for
$18,470.53 (R4, tab 18; gov't br. at 16, ~ 56), the same amount set forth in the
11 March 2013 settlement proposal. Although the contracting officer never issued a
decision on the 1 May 2014 claim, the parties agree that they are at an impasse (Bd.
corr. file, 8 October 2014 memorandum of telephonic conference). We find that by
1 May 2014, when DODS submitted its certified claim to the contracting officer, the
parties had reached an impasse, establishing the Board's jurisdiction to entertain this
appeal. Cf Central Environmental, Inc., ASBCA No. 51086, 98-2 BCA ~ 29,912
at 148,080 (impasse including where 14 months had passed since appellant submitted
settlement proposal, and where appellant had requested contracting officer's final
decision 4 months after submitting proposal).
The contract includes Federal Acquisition Regulation (FAR) clause 52.249-1,
TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM)
(APR 1984) (R4, tab 1 at 15), which provides:
The Contracting Officer, by written notice, may
terminate this contract, in whole or in part, when it is in the
Government's interest. If this contract is terminated, the
rights, duties, and obligations of the parties, including
compensation to the Contractor, shall be in accordance
with Part 49 of the Federal Acquisition Regulation in effect
on the date of this contract.
DECISION
DODS bears the burden to prove by a preponderance of the evidence that it is
entitled to a greater termination settlement amount than that determined by the
contracting officer. See General Dynamics Land Systems, Inc., ASBCA No. 52283,
02-1 BCA ~ 31,659 at 156,411. Here, having not issued any decision, the contracting
officer did not determine a settlement amount; therefore, DODS bears the burden of
proving entitlement to any amount. A convenience termination converts a fixed-price
2
contract into a cost-reimbursement contract, entitling the contractor to recover its
allowable costs in accordance with the standards of reasonableness, allocability, and
regulatory cost principles, as applicable, plus profit. Id. Pursuant to FAR 49.207,
Limitation on settlements, "[t]he total amount payable to the contractor for a
settlement, before deducting disposal or other credits and exclusive of settlement costs,
must not exceed the contract price less payments otherwise made or to be made under
the contract."
Claimed Termination/or Convenience Settlement Costs
DODS seeks the following (R4, tab 8 at 41 ):
Metals: $880.00
Work-in-Progress: $2,679.25
Other Costs: $154.64
General & Administrative Expenses (G&A) $9,147.27
Profit: $1,905.98
Settlement Expenses: $3,791.39
Subtotal: $18,558.53
Less Disposal and Other Credits ($88.00)
Total: $18,470.53
Metals and "Other Costs"
DODS seeks $880 for four sheets of metal ($220 per sheet) paid for by TTF,
L.L.C. (TTF), (minus a 10%, $88.00 credit), as well as $154.64 in "Other Costs";
namely, the cost of delivery of those sheets to TTF by FedEx (R4, tab 8 at 41-50, 128).
We have found that "there is no practical distinction between TTF and DODS." DODS,
13 BCA ~ 35,203 at 172, 711. We further find that one of the sheets "was consumed in
the manufacturing process of the First Article" (app. supp. R4, tab A210), leaving
three sheets of residual equipment with a value of $660. The government invokes the
limitation in FAR 3 l.205-42(a), "Common items," that "[t]he costs of items reasonably
usable on the contractor's other work shall not be allowable unless the contractor
submits evidence that the items could not be retained at cost without sustaining a loss."
The burden is on a contractor to demonstrate that it could not retain the residual
equipment at cost for use on other work without sustaining a loss. FAR 31.205-42(a),
Termination costs; see Essex Electro Engineers, Inc., DOT CAB Nos. 1025, 1119,
81-1 BCA ~ 14,838 at 73,250 (citing former FPR 1-15.205-42(a) which was essentially
identical to FAR 3 l.205-42(a)), ajf'd on recon., 81-1BCA~15,109, ajf'd, 702 F.2d 998
(Fed. Cir. 1983). DODS makes no such showing. We award only the $220 cost of the
3
sheet that was consumed related to first article testing, as well as the $154.64 FedEx
delivery cost. 1
Work-in-Progress
DODS seeks $2,679.25 for "Work-in-Progress," consisting of direct labor costs
(R4, tab 8 at 41-42). The government does not dispute that those costs were incurred
performing work on the contract, but contends that they are not reasonable, including
because DODS did not even produce the first article, which was priced only at $1,800.
Indeed, the government invokes FAR 49 .207, Limitation on settlements, which provides
that "[t]he total amount payable to the contractor for a settlement, before deducting
disposal or other credits and exclusive of settlement costs, must not exceed the contract
price less payments otherwise made or to be made under the contract." However, $1,800
was not the price of the contract (the contract price was $6,400) but the price of one of
the contract's line items; namely, first article testing (R4, tab 1 at 1, 9). See Concord
Electric Co., ASBCA No. 31012, 85-3 BCA ~ 18,484 at 92,844-45.
Nevertheless, we agree that $2,679.25 in direct labor costs, given the
circumstances, is not reasonable. In its settlement proposal to the contracting officer
(Standard Form 1435), DODS proposed a 15% profit (R4, tab 8 at 41, line 11); from
that we infer that DODS contemplated earning 15% profit on the $6,400 contract
($960), leaving $5,440 for costs ($6,400 minus $960). In its settlement proposal,
DODS also proposed 257% G&A (R4, tab 8 at 42); from that we infer that DODS also
expected that it would incur $2.57 in indirect costs for each $1.00 in direct costs, or
1
Although neither party addresses it, the contract includes FAR 52.209-4, FIRST
ARTICLE APPROVAL - GOVERNMENT TESTING (SEP 1989) (R4, tab 1 at 13 ),
which provides, at paragraph (h):
Before first article approval, the acquisition of materials or
components for, or the commencement of production of,
the balance of the contract quantity is at the sole risk of the
Contractor. Before first article approval, the costs thereof
shall not be allocable to this contract for ( 1) progress
payments, or (2) termination settlements ifthe contract is
terminated for the convenience of the Government.
The record does not establish whether any of the residual three sheets of metal
was for production, or whether any exception to FAR clause 52.209-4(h)
applies. See Switlik Parachute Co., ASBCA No. 18024, 75-2 BCA ~ 11,434
at 4,438-40. For these reasons, we do not rely upon that clause.
4
approximately $3,920 in indirect costs and approximately $1,520 in direct costs for the
entire contract work; otherwise it would not have expected to earn 15% profit.
Because DODS spent $1,034.64 procuring metal for the work ($880.00 in material
plus $154.64 for its delivery), that leaves approximately $485 ($1,520 minus $1,035)
for direct labor costs. The contract work consisted of a first article and four aircraft
forms; DODS produced none of those yet spent $2,679.25 - approximately 552%
more ($2,679.25 divided by $485.00) than it must have contemplated spending on the
entire contract work - on direct labor costs. Without any evidence in the record
regarding what economies of scale DODS might have achieved had it passed first
article testing, we find, using a jury verdict approach, that awarding $300 in direct
labor costs is reasonable given the circumstances.
G&A
DODS seeks $9,147.27 in G&A expenses, consisting of 257% of the sum of $880
in materials and $2,679.25 in direct labor costs (R4, tab 8 at 41-42). There being no
evidence in the record demonstrating the calculation of that particular rate, but having
found that there is no practical difference between DODS and TTF, 13 BCA ~ 35,203
at 172,711, we adopt the comparable, 227.19% G&A rate computed for TTF's CY 2011
by the Defense Contract Audit Agency in Audit Report No. 01241-2012Wl 7100001,
which appears in the record (app. supp. R4, tabs A369, A384). 2 Applying that rate to the
materials and direct labor costs that we award, the result is an award of $1, 181.39 in
G&A expenses ($220 plus $300 equals $520 times 2.2719).
Profit
DODS seeks $1,905.98 in profit; that is, 15% of the sum of materials, direct
labor costs, and G&A (R4, tab 8 at 41-42). The government contends that no profit is
allowable, pursuant to FAR 49.203(a), Adjustment for loss, which provides for the
disallowance of profit "if it appears that the contractor would have incurred a loss had
the entire contract been completed." It does so appear. According to DODS's figures,
it spent $9,506.93, much more than the $6,400.00 contract price, without having
produced anything. Consequently, DODS is not entitled to profit.
2
Because we have found that "there is no practical distinction between TTF and
DODS." DODS, 13 BCA ~ 35,203 at 172,711, we include the audit report in
the Rule 4 file over the government's objection.
5
Settlement Expenses
DODS seeks $3,791.39 in "Settlement Expenses," consisting of $936.52 that
the government does not dispute (gov't br. at 28), and $2,854.87 in expenses spent
litigating ASBCA No. 57667 (R4, tab 8 at 43). The latter are not allowable, pursuant
to FAR 3 l.205-47(f)(l), Costs related to legal and other proceedings, because they
were incurred in connection with "[d]efense against Federal Government claims or
appeals or the prosecution of claims or appeals against the Federal Government." We
find that DODS is entitled to the $936.52 that the government does not dispute.
Termination/or Convenience Settlement Costs as Found by the Board
For the above reasons, we award DODS the following:
Metals: $220.00
Work-in-progress: $300.00
Other costs: $154.64
G&A $1,181.39
Settlement expenses: $936.52
Total: $2,792.55 3
CONCLUSION
The appeal is sustained in part and DODS is awarded $2,792.55, plus interest
pursuant to the Contract Disputes Act, 41 U.S.C. § 7109, from Monday, 5 May 2014,
the putative date that the contracting officer received DODS's 1 May 2014 claim, until
the date of payment.
Dated: 12 March 2015
Administr · tive Judge
Armed Services Board
of Contract Appeals
(Signature continued)
3
Because we do not allow the cost of the residual metal, we do not apply the
10% materials credit that DODS included in its claim (R4, tab 8 at 41, 43, 128).
6
I concur
RICHARD SHACKLEFORD
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 59510, Appeal of DODS,
Inc., rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN
Recorder, Armed Services
Board of Contract Appeals
7