J-A14022-15
NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
JOHN J. CALABRESE AND DEBORAH J. IN THE SUPERIOR COURT OF
SHRIK PENNSYLVANIA
Appellee
v.
P. THOMAS ZEAGER
Appellant No. 1849 MDA 2014
Appeal from the Judgment Entered October 14, 2014
In the Court of Common Pleas of Lancaster County
Civil Division at No(s): Cl-04-05070
BEFORE: BENDER, P.J.E., JENKINS, J., and STRASSBURGER, J.*
MEMORANDUM BY JENKINS, J.: FILED JUNE 01, 2015
Appellant P. Thomas Zeager appeals from the order of the Lancaster
County Court of Common Pleas granting summary judgment in favor of
Appellees John J. Calabrese and Deborah J. Shirk, entering judgment in
favor of Calabrese and Shirk, and awarding damages in the amount of
$158,667.22.1 We affirm the grant of Calabrese and Shirk’s motion for
summary judgment. We remand for the trial court to award an offset for
costs Calabrese and Shirk would have paid to connect to Zeager’s sewage
treatment plant.
____________________________________________
*
Retired Senior Judge assigned to the Superior Court.
1
The trial court awarded $50,372.83 in damages, $20,071.74 in statutory
interest, $3,378.25 in costs of litigation, and $84,844.40 in legal fees.
J-A14022-15
The trial court summarized the factual and procedural history as
follows:
In 1991, Edwin G. Hershey owned a hotel and restaurant
complex known as Hershey Farms on Route 896 in
Strasburg Township, Lancaster County. As public sewer
was not available in that area, Hershey built his own
sewage treatment plant on his property. Sanford M. Groff
owned an adjoining retail property. On November 22,
1991, Hershey and Groff entered into a Sanitary Sewer
Easement and Sewage Treatment Agreement (the
Agreement) which generally stated that Groff was
permitted to use the sewage plant located on Hershey’s
land in exchange for $25,000.00. Specifically, the
Agreement granted an easement across Hershey’s land for
the installation, repair, maintenance and operation of an
eight[-]inch sewer line which Groff could use to construct
sewer lines to connect to the plant at such time in the
future as Groff deemed necessary. The Agreement
between the parties had an explicit provision that it was
Hershey’s obligation to be physically and legally capable of
allowing Groff to hook into the facility “at all times and
under all conditions.” The Agreement also contained an
indemnification clause providing that should Hershey
breach the agreement, Groff would be entitled to all costs,
damages, and attorney’s fees resulting from the breach.
Subsequent to the Agreement, Groff sold his property to
Calabrese [and Shirk], and Hershey sold his land to
Zeager. At the time of sale, Groff had not connected to
the sewage treatment plant located on Hershey’s property.
Calabrese [and Shirk] and Zeager remained obligated by
the Agreement, however, which was binding on successors
in title to Groff and Hershey.
In the fall of 2003, Calabrese [and Shirk] entered into a
lease agreement with a new retail tenant which required
renovation and enlargement of [their] building. Calabrese
[and Shirk’s] existing on-lot septic system was incapable
of handling the required additional capacity generated by
the expansion. Therefore, Calabrese [and Shirk] decided
that [they] wished to tap into the sewer treatment plant
on the Zeager property. Calabrese [and Shirk] made
-2-
J-A14022-15
multiple attempts by telephone and letter to contact
Zeager to tell him that [they] now wanted to utilize the
sewer capacity that had been paid for years before by
Groff. Calabrese [and Shirk] eventually learned that
Zeager did not have the necessary legal approvals to add
Calabrese [and Shirk’s] discharge. Calabrese [and Shirk
were] then forced to construct a new “sand mound” septic
system on [their] own property at a total cost of
$34,275.33. [They] also incurred costs related to the
construction, such as lost rent and attorney’s fees.
Repeated requests were made to Zeager to pay all such
costs of the new system (as required by the
indemnification provision in the Agreement). Zeager
refused.
Calabrese [and Shirk] brought a breach of contract action
against Zeager on May 28, 2004, based upon the
Agreement entered into by their respective predecessors in
title. Both parties agreed that the Agreement permitted
Calabrese [and Shirk] to construct a pipe to connect with
Zeager’s sewage plant and required Zeager to accept and
treat the sewage. The parties disagreed, however,
regarding which party bore the responsibility under the
Agreement for obtaining the necessary government
approvals to allow Calabrese [and Shirk] to connect [their]
sewage pipe to Zeager’s plant. This apparently involved
the preliminary submission for approval of a sewage
module plan to Strasburg Township, pursuant to its
ordinances and to the regulations of the Pennsylvania
Department of Environmental Resources.
After the pleadings were closed, this matter was assigned
to the Honorable Paul K. Alison for a pretrial conference on
July 29, 2005. After four joint motions for trial
continuances by the parties, the case eventually proceeded
to a non-jury trial before Judge Allison on September 19
and 20, 2006. Following the filing of proposed findings of
fact and conclusions of law by the parties, Judge Allison
rendered a decision on January 25, 2007 (docketed on
January 26, 2007). The trial court concluded that, under
the terms of the Agreement, Calabrese [and Shirk] bore
the responsibility for obtaining official approval of the
connection to Zeager’s sewage plant, and judgment was
entered in Zeager’s favor.
-3-
J-A14022-15
Calabrese [and Shirk] filed a timely post[-]trial motion,
which was denied by Judge Allison on March 19, 2007.
Thereafter, Calabrese [and Shirk] appealed the trial court’s
ruling to the Superior Court. On May 22, 2009, a three-
judge panel of the Superior Court reversed the trial court
in a published opinion.
The appellate court held that “the trial court misinterpreted
the terms of the Agreement and that the Agreement
unambiguously assigns to Zeager the responsibility for
obtaining the governmental approval for connecting
Calabrese and Shirk’s sewage line to Zeager’s sewage
treatment facility.”
Zeager filed an application for reconsideration on June 5,
2009, which was denied by the Superior Court on August
4, 2009. No petition for allowance of appeal was filed with
the Supreme Court of Pennsylvania, and the case was
thereafter remanded to the trial court.
Following the remand, Calabrese [and Shirk] filed a motion
for judgment on September 13, 2011, to which Zeager
responded with a cross motion for judgment on October 3,
2011. Zeager also filed on October 31, 2011, a motion to
amend his answer to the complaint to plead actual
planning and construction costs for a new sewage
treatment plant built in 2009, following the remand of this
case, as an offset to any of Calabrese [and Shirk’s]
damages. Finally, a motion for post remand evidentiary
hearing was filed by Zeager on October 31, 2011.
These matters were assigned to the Honorable Jeffery D.
Wright on December 15, 2011, following Judge Allison’s
retirement from the bench. Following a status conference
on February 27, 2012, Judge Wright sent the parties to
mediation through the Lancaster Bar Association. The
mediation concluded without a successful resolution. Two
subsequent attempts at mediation by Judge Wright in
September and October of 2012 ended again without
success.
This case was then reassigned to the Honorable Louis J.
Farina. Following a case management conference on
January 23, 2013, Judge Farina entered an order docketed
on January 25, 2013, which allowed Zeager to amend his
answer to plead a claim for offset damages related to the
-4-
J-A14022-15
post[-]trial construction of his new sewer plant, set a
discovery schedule, and invited dispositive motions. The
Order further noted, in an apparent response to Zeager’s
motion for a post[-]remand evidentiary hearing, that
“[a]ny bench trial will be limited only to a determination of
the amount of damages to which [Calabrese and Shirk are]
entitled resulting from [Zeager’s] breach of contract.
[Zeager’s] liability to [Calabrese and Shirk] for breach of
contract was finally determined by the judgment of the
[S]uperior [C]ourt. The only remaining issue is damages,
allowable attorney’s fees and costs.”
On November 12, 2013, Calabrese [and Shirk] filed a
motion for summary judgment. Following the filing of
briefs by the parties, the case was reassigned to this
[c]ourt on May 9, 2014. Oral argument on the summary
judgment motion was scheduled for August 4, 2014, and
then rescheduled, upon request of Zeager, to September
19, 2014. On October 14, 2014, I entered an [o]rder
granting Calabrese [and Shirk’s] [m]otion for [s]ummary
[j]udgment and entered judgment in favor of Calabrese
[and Shirk] and against Zeager as follows: (1) damages in
the amount of $50,372.83; (2) statutory interest from
March 23, 2007, through November 12, 2013, in the
amount of $20,071.741 (3) costs of litigation in the
amount of $3,378.25; and (4) legal fees through
November 12, 2013, totaling $84,844.40. The total
judgment was $158,687.22, before additional legal fees
and interest to be awarded in an amount to be determined
upon submission of a supplemental bill of costs and fees by
Calabrese within ten days of the [o]rder. Calabrese [and
Shirk’s] supplemental bill of costs was filed on October 23,
2014.
The same date, Zeager filed a post[-]trial motion
challenging the [c]ourt’s order granting summary
judgment. However, because Pa.[]R.Civ.P. 227.1(a) states
that a post[-]trial motion does not apply to summary
judgment motions, Zeager then filed a direct appeal to the
Superior Court on November 3, 2014.
Trial Court Opinion, 12/16/2014, at 1-7. Both Appellant and the trial court
complied with Pennsylvania Rule of Appellate Procedure 1925.
-5-
J-A14022-15
Zeager raises the following claims on appeal:
A. Did the [t]rial [c]ourt incorrectly determine that, post-
remand, it was precluded from reviewing the issue of
whether [Calabrese and Shirk] gave Zeager sufficient
notice of [Calabrese’s and Shirk’s] desire to connect, the
evidence of record establishing that [Calabrese and Shirk]
did not give Zeager reasonable notice under the governing
circumstances?
B. Where the trial court acknowledged that damages
offsets existed, was it error for the [t]rial [c]ourt to not
reduce its damages award by the amount of the offsets, in
particular offsets relating to the contractual liability
[Calabrese and Shirk] would have had for new plant
reconstruction had [Calabrese and Shirk] connected to the
old plant?
Appellant’s Brief at 4.
“[S]ummary judgment is appropriate only in those cases where the
record clearly demonstrates that there is no genuine issue of material fact
and that the moving party is entitled to judgment as a matter of law.”
Summers v. Certainteed Corp., 997 A.2d 1152, 1159 (Pa.2010) (quoting
Atcovitz v. Gulph Mills Tennis Club, Inc., 812 A.2d 1218, 1221
(Pa.2002)). A “trial court must take all facts of record and reasonable
inferences therefrom in a light most favorable to the non-moving party” and
“must resolve all doubts as to the existence of a genuine issue of material
fact against the moving party.” Id. (citing Toy v. Metropolitan Life Ins.
Co., 928 A.2d 186, 195 (Pa.2007)). Therefore, a trial court “may only grant
summary judgment ‘where the right to such judgment is clear and free from
all doubt.’” Id. (quoting Toy, 928 A.2d at 195). This Court “may reverse a
grant of summary judgment if there has been an error of law or an abuse of
-6-
J-A14022-15
discretion.” Id. (quoting Weaver v. Lancaster Newspapers, Inc., 926
A.2d 899, 902–03 (Pa.2007)).
Zeager maintains that although this Court in the prior appeal found
that he breached the Agreement, it did not address his affirmative defense
that it was impossible for him to comply with the Agreement because
Calabrese and Shirk provided insufficient notice of their desire to use his
plant. Appellant’s Brief at 14-15, 15 n.2. Zeager maintains this Court
“recognize[d] Calabrese and Shirk’s notice (or lack thereof) as an issue,” but
“made no pronouncement as to whether Calabrese and Shirk did or did not
provide sufficient notice to Zeager.” Appellant’s Brief at 14-15. Zeager
argues the trial court erred when it failed to address the notice issue
following remand from our May 22, 2009 decision. We find the law of the
case doctrine prohibited the trial court from considering this issue.
The law of the case doctrine “provides that if an appellate court has
considered and decided a question on appeal, neither that court nor any trial
court may revisit that question during another phase of the same case.”
Gateway Towers Condominium Assoc. v. Krohn, 845 A.2d 855, 861
(Pa.Super.2004).2 “The doctrine is designed to promote judicial economy,
____________________________________________
2
The distinct rules that make up the law of the case doctrine are:
(1) upon remand for further proceedings, a trial court may
not alter the resolution of a legal question previously
decided by the appellate court in the matter; (2) upon a
second appeal, an appellate court may not alter the
(Footnote Continued Next Page)
-7-
J-A14022-15
uniformity of decision making, protect the settled expectations of the
parties, maintain the consistency of the litigation and end the case.” Id.
(quoting Peden v. Gambone Bros. Dev. Corp., 798 A.2d 305, 310
(Pa.Cmwlth.2002)).
The Agreement contained the following provision regarding
government approvals:
[2. Acceptance and Treatment of Sewage.]
(c) At the Plant, [Zeager] shall treat [Calabrese and
Shirk’s] Discharge in accordance with all federal, state,
and local laws and regulations applicable thereto, and in
accordance with standards established by the United
States Environmental Protection Agency (‘EPA’), and the
Pennsylvania Department of Environmental Resources
(‘DER’), as such standards are from time to time
promulgated, sufficient to permit discharge into the waters
of the Commonwealth of Pennsylvania, and [Calabrese and
Shirk]’s Discharge shall be so discharged. Further,
[Zeager] shall assure that all wastewater treated at the
Plant is treated in accordance with all federal, state, and
local laws and regulations applicable thereto, and in
accordance with standards promulgated by the EPA and
DER, sufficient to permit discharge into the waters of the
Commonwealth of Pennsylvania. At all times and under
all conditions, [Zeager] shall assure that the Plant
has sufficient treatment capacity to treat (and shall
_______________________
(Footnote Continued)
resolution of a legal question previously decided by the
same appellate court; and (3) upon transfer of a matter
between trial judges of coordinate jurisdiction, the
transferee trial court may not alter the resolution of a legal
question previously decided by the transferor trial court.
In re Estate of Elkins, 32 A.3d 768, 776 (Pa.Super.2011) (quoting
Commonwealth v. Starr, 664 A.2d 1326, 1331 (Pa.1995)).
-8-
J-A14022-15
reserve sufficient treatment capacity), shall be
capable of so treating, and shall be legally
authorized to so treat [Calabrese and Shirk]’s
Discharge.
Sanitary Sewer Easement and Sewer Treatment Agreement, dated Nov. 26,
1991, at p.3 (“Agreement”) (emphasis added).
In the prior appeal, this Court found Zeager breached the Agreement.
Calabrese v. Zeager, 976 A.2d 1151, 1151-52 (Pa.Super.2009). It further
found:
Both parties agree that the Agreement permitted
Calabrese and Shirk to construct a pipe to connect with
Zeager’s sewage plant and required Zeager to accept and
treat the sewage. The parties disagree, however,
regarding which party bore the responsibility under the
Agreement for obtaining the necessary government
approvals to allow Calabrese and Shirk to connect their
sewage pipe to Zeager’s plant (specifically, an “approved
sewer module” from the Pennsylvania Department of
Environmental Resources). The trial court decided that
Calabrese and Shirk bore this responsibility and entered
judgment in Zeager’s favor.
We find that the highlighted portion of paragraph 2(c)
unambiguously requires Zeager to have legal authorization
in place to accept Calabrese and Shirk’s sewage discharge.
The highlighted portion further makes clear that this
obligation required Zeager to maintain this legal
authorization “at all times and under all conditions,” and,
therefore, when Calabrese and Shirk notified Zeager that
they intended to connect a sewage pipe to Zeager’s plant,
it was Zeager’s responsibility under paragraph 2(c) to
obtain the required approvals from the DER. Paragraph
2(c) plainly requires Zeager to treat the Calabrese and
Shirk discharge in accordance with all federal, state, and
local laws and regulations, and it would not be possible for
Zeager to do so without obtaining the required “approved
sewer module” from the DER.
Id. at 1155-56.
-9-
J-A14022-15
In the prior appeal, Zeager stated in his appellate brief:
Zeager joins in the portion of the Statement of the Case
related to the procedural history in this matter set forth on
page 6 and through the first full paragraph on page 7 of
the Calabrese Brief. It should also be noted that, at trial,
evidence on additional issues was presented, the issues
including:
1. Did Calabrese give sufficiently timely notice to Zeager of
his desire to connect the Calabrese property to the Zeager
sewage plant?
2. If Zeager was found to be in breach of the 1991
Sanitary Sewer Easement and Sewage Treatment
Agreement (the “Agreement”), what damages did
Calabrese incur?
3. Must any or all of Calabrese’s damages be offset by
amounts Calabrese saved by not hooking up to the Zeager
sewage plant?
Because the [t]rial [c]ourt found Zeager did not breach the
Agreement, the [t]rial [c]ourt did not need to address the
above issues.
Appellee Brief, filed 8/27/2007, at 2. Zeager further wrote:
Alternatively, if this Court is persuaded that the [t]rial
[c]ourt did commit some error in interpreting the
Agreement, this Court must remand this matter to the
[t]rial [c]ourt for such additional proceedings on the
contract interpretation issue as this Court orders, as well
as the issues raised before the [t]rial [c]ourt but not
decided by the [t]rial [c]ourt as stated in the Procedural
History (Part II. A.) of this Brief (timeliness of Calabrese
notice, damages, and damages offset).
Id. at 16. Zeager also discussed the evidence he believed established
Calabrese and Shirk failed to provide notice, e.g., the permit process would
take 6-12 months, Calabrese and Shirk did not write to Zeager until
- 10 -
J-A14022-15
November 2003, and Calabrese and Shirk submitted plans for an onsite
sewer maintenance system. Id. at 4-6.
Calabrese and Shirk’s appellate brief in the prior appeal discussed the
evidence of the notice they provided in the course of arguing that Zeager
breached the contract because he failed to obtain the legal authorization.
Appellant’s Brief, filed July 26, 2007, at 24-25.
This Court found Zeager breached the Agreement by failing to obtain
the necessary permits after Calabrese and Shirk notified him they would use
his sewer plant. Calabrese, 976 A.2d at 1156. Before reaching this
decision, we reviewed the arguments relating to notice or lack thereof in the
parties’ briefs. Further, we conducted a plenary review of the record,
including the trial transcripts, which contained testimony regarding the
notice provided, and the Agreement, which provided that Zeager shall be
legally authorized to treat Calabrese and Shirk’s discharge “[a]t all times and
under all conditions.” Because we considered and decided the notice issue
on the prior appeal, the law of the case doctrine precluded the trial court
from revisiting this issue and Zeager’s claim lacks merit.
Zeager also challenges the trial court’s damages calculation, arguing
Calabrese and Shirk saved money when they used an on-site system rather
than Zeager’s sewage treatment plant because they did not have to pay
connection costs or maintenance and operation costs. Appellant’s Brief at
27. He further claims Calabrese and Shirk saved the costs they would have
- 11 -
J-A14022-15
owed Zeager for the “re-construction” of Zeager’s sewer management
system had they connected to the system. Id. at 28.
The Supreme Court of Pennsylvania has stated:
Where one party to a contract without any legal
justification, breaches the contract, the other party is
entitled to recover, unless the contract provided otherwise,
whatever damages he suffered, provided (1) they were
such as would naturally and ordinarily result from the
breach, or (2) they were reasonably foreseeable and within
the contemplation of the parties at the time they made the
contract, and (3) they can be proved with reasonable
certainty.
Helpin v. Trustees of Univ. of Pa., 10 A.3d 267, 270 (Pa.2010) (quoting
Ferrer v. Trustees of the University of Pennsylvania, 825 A.2d 591,
610 (Pa.2002)). A damage award should “place the non-breaching party ‘as
nearly as possible in the same position [it] would have occupied had there
been no breach.’” Id. (quoting Lambert v. Durallium Products Corp., 72
A.2d 66, 67 (Pa.1950)). “The measure of damages for breach of contract is
compensation for the loss sustained. The aggrieved party can recover
nothing more than will compensate him.” Id. (quoting Lambert, 72 A.2d at
67 (emphasis deleted)).
Zeager claims the damages award should be offset by the amount
Calabrese and Shirk saved by not connecting to Zeager’s plant, including the
operation and maintenance costs (also referred to as sewage process
charges) and the connection costs (also referred to as trenching costs).
Appellant’s Brief at 29-31.
- 12 -
J-A14022-15
Calabrese and Shirk are paying operational and maintenance costs
associated with the sewage treatment facility they constructed when unable
to access Zeager’s plant. They did not include the operational and
maintenance costs in the damages sought. Because Calabrese and Shirk are
paying operational and maintenance costs, and such costs were not part of
the damages award,3 the trial court properly declined to deduct these costs
from the damages award.
Zeager next claims the damages award should be offset by the
connection costs Calabrese and Shirk would have spent had they connected
to Zeager’s plant. We agree.
The Agreement provided:
[Calabrese and Shirk] shall be permitted to construct
within the above-described easement sanitary sewer lines
and other facilities to transport wastewater from
[Calabrese and Shirk’s] Real Estate to the Plant, and
[Zeager] shall connect such sewer lines to the Plant.
Agreement at ¶ 2(a). Further, at trial Calabrese testified that if he
connected to Zeager’s plant, the Agreement required him to install the
sewage line and he would bear the cost of such installation. N.T.,
9/19/2006, at 99.
____________________________________________
3
Operation and maintenance costs do not appear on the list of damages
claimed. See Joint Trial Exhibit No. 53.
- 13 -
J-A14022-15
Zeager’s breach of the Agreement forced Calabrese and Shirk to
construct their own treatment facility. By building their own treatment
facility, however, they saved the costs they would have owed for connecting
to Zeager’s sewage plant. Therefore, to make them whole for Zeager’s
breach, they are entitled to the cost they spent on their facility, less the
connection costs they would have owed had they connected to Zeager’s
plant.
Calabrese and Shirk argue they still are entitled to connect to Zeager’s
plant. Therefore, if the connection costs are deducted now, and Calabrese
and Shirk later connect to Zeager’s plant, they would be paying those costs
twice. Appellee’s Brief at 8. This argument, however, is speculative, as it is
unclear whether Calabrese and Shirk will seek to connect to Zeager’s plant
in the future.4 Moreover, whether Calabrese and Shirk will connect to
Zeager’s plant is made even more speculative because Zeager replaced the
original sewage treatment plant with a new sewage treatment facility at a
new location. See Opinion, 12/15/2014, at 17, 16 n.10; Appellant’s Brief at
28, 33-35. Therefore, we find the court erred in not deducting the
connection costs from the damages award. We leave it to the trial court to
calculate the connection costs offset on remand.
____________________________________________
4
We need not address whether Calabrese and Shirk would be entitled to
reimbursement of the connection costs offset in the event they later connect
to Zeager’s plant.
- 14 -
J-A14022-15
Zeager also maintains Calabrese and Shirk are liable for re-
construction costs. We disagree.
The Agreement provided:
After connection of the sewer lines and other facilities
installed to transport the [Calabrese’s and Shirk’s]
discharge to the Plant, [Calabrese and Shirk] shall pay to
[Zeager] a share of repair, reconstruction, and equipment
replacement expenses incurred directly in connection with
the operation of the plant and which are of a character
that must be capitalized under generally accepted
accounting standards (“Capital Improvements”), but such
Capital Improvements shall not include improvements,
additions and repairs initially made in order to
accommodate and treat the [Calabrese’s and Shirk’s]
Discharge or to increase the Sewer Plant’s capacity for
treatment.
Agreement, at 6.
In 2008-2009, after trial, Zeager replaced his sewer treatment plant.
He claims the amount Calabrese and Shirk allegedly would have owed had
they been connected to Zeager’s plant ($78,000.00) should be offset against
the damages award. Appellant’s Brief at 28-29. This claim fails. Calabrese
and Shirk never connected to the plant and, therefore, this provision, which
applies only following connection to the plant, is inapplicable.
Further, a new plant is not a “capital improvement.” As the trial court
stated:
[S]uch “capital improvements” do not encompass a brand
new multi-million dollar sewer treatment facility at a
completely new and separate site distinct from the location
of Zeager’s original treatment plant. This was not a repair,
reconstruction, or restoration of the old facility as
envisioned by the Agreement. Zeager’s counsel
- 15 -
J-A14022-15
acknowledged at the trial in this matter that Zeager was
“building a new plant” that was separate and distinct from
the “old plant.” It is disingenuous and incongruous of
Zeager to continually refer to the “reconstruction” of a
“new sewage treatment plant.”
Trial Court Opinion, 12/15/14, at 17 (internal citations omitted).
Moreover, even if it were a “capital improvement,” Calabrese and Shirk
would not have been responsible for the cost. Pursuant to the agreement,
Calabrese and Shirk are not responsible for capital improvements that
increase the capacity of the plant. Agreement at ¶ 4(d). Applying this
provision, the trial court reasoned:
Zeager’s expert engineer, McCorkle, testified that the new
plant was necessary for the growth of Zeager’s business,
Hershey Farms, and Sight & Sound Theater, another
adjoining property which also contracted for the use of the
sewage treatment facility. Post[-]trial discovery further
revealed that Zeager had granted the right to access and
utilize the new plant to Keystone Custom Homes for an
entirely new residential development. The new plant more
than tripled the capacity of the original plant from 35,000
gallons per day of discharge to 110,000 gallons of sewage
per day. Clearly, the new plant was constructed for the
purpose of significantly increasing the amount of treatment
capacity that Zeager controlled. Thus, pursuant to
subparagraph 4(d) of the Agreement, Calabrese [and Shirk
are] not obligated to contribute to the costs of such
“improvements, additions and repairs” to increase the
plant’s capacity.
Opinion, 12/15/14, at 17-18.
- 16 -
J-A14022-15
Order affirmed in part and reversed in part. Remanded for the trial
court to offset damages in the amount of costs Calabrese and Zeager would
have paid to connect to Zeager’s plant. Jurisdiction relinquished.
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 6/1/2015
- 17 -