J-A04005-15
NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
LISA GARDNER AND MARK MONAHAN, IN THE SUPERIOR COURT OF
PENNSYLVANIA
Appellees
v.
LEE BRUDER, T/D/B/A BRUDER
CONSTRUCTION CO.,
Appellant No. 672 WDA 2014
Appeal from the Judgment Entered March 31, 2014
In the Court of Common Pleas of Allegheny County
Civil Division at No(s): AR-12-001706
BEFORE: BOWES, OLSON, and STRASSBURGER,* JJ.
MEMORANDUM BY BOWES, J.: FILED JULY 10, 2015
Lee Bruder t/d/b/a/ Bruder Construction Co. appeals from the
judgment entered on the non-jury verdict in favor of Lisa Gardner and her
husband, Mark Monahan (collectively referred to as “Appellees”), in the
amount of $21,655. We affirm in part, reverse in part, and remand with
instructions.
On March 26, 2011, Appellees entered a written contract with
Appellant to demolish an existing garage behind Appellees’ home in the
Mexican War Streets neighborhood of Pittsburgh, Pennsylvania, and build a
new two-car garage. Pursuant to the written accord, a form contract
published by the American Institute of Architects (“AIA”), Appellees would
____________________________________________
*
Retired Senior Judge assigned to the Superior Court.
J-A04005-15
compensate Bruder $27,475, subject to additions and deductions as
provided by the agreement.1
According to the scope of work document attached to the written
agreement, the original plan was to build a detached one-level carriage-
house style2 garage with a pitched roof. Those plans outlined a garage
constructed of 620 square feet of masonry block with brick veneer covering
the front and rear walls from ground to the gutter. The front side of the
garage incorporated a wood-clad two-bay garage door. The rear of the
structure had an additional single car garage door, a window, and a door for
pedestrian access. The contract amount included the cost to build a 6’ x 12’
trussed roof with appropriate weatherization, shingles, gutters, and
downspouts. While not expressly included in the scope of work that
Appellant presented to Appellees prior to executing the construction
contract, the agreement also covered several items that had been previously
agreed upon. That work included connecting the garage to the existing
electrical supply in the residence, installing an electric garage door opener,
____________________________________________
1
The parties employed the 1987 edition of AIA Document A107 entitled
“Abbreviated Form of Agreement Between Owner and Contractor.”
2
A carriage-house style of garage generally refers to a detached garage with
living space above the garage area. In order to save money on construction
cost, the initial construction plan omitted the second-floor living space
completely. However, as discussed in the body of this memorandum,
Appellees ultimately settled on a one-and-one-half-story structure in that
style.
-2-
J-A04005-15
digging a trench for the installation of PEX water supply lines, and grading
the back yard for proper drainage. Prior to signing the construction
agreement, Mr. Monahan listed the omitted tasks on a Post-It note in
Appellant’s presence and affixed that note to the scope of work that
Appellant had prepared. Appellant eventually executed a change order
(Change Order No. 2) that acknowledged those tasks as included in the
original contract.
The demolition phase started as scheduled and construction
progressed for approximately one month. On April 28, 2011, the parties
agreed to amend the scope of work to include a stripped-down one-half
story addition for $6,750.3 To facilitate the alterations, Appellant drafted
Change Order No. 1 that read, “Build additional ‘1/2 story’ onto garage of
725 SF of 8[”] block. Included are two dormer openings; one at yard and
one at street side.” Defendant’s Exhibit C. Appellant signed the change
order and presented it to Appellees for approval.
Concerned that the change order was too vague and that Appellant
had, again, omitted agreed upon tasks, Mr. Monahan drafted a revised
change order that specified the height of the one-half story addition (six
feet), the pitch of the roof (6’ x 12’), and the composition of the window or
____________________________________________
3
The revisions did not include a staircase or any interior framing. The one-
half-story interior was essentially a shell that Appellees could finish in the
future.
-3-
J-A04005-15
door to be placed in the two dormer openings. In addition, the revised
change order included cutting and installing a window in the south facing
gable and additional brick veneer covering the front, rear, and exposed side
of the structure. As Appellees interpreted their agreement with Appellant as
including these items, the revised change order did not alter the expected
increase of $6,750 to the contract price.
Appellees executed their version of the change order and mailed it to
Appellant along with a $5,000 progress payment and the $6,750 advance
payment that Appellant requested to construct the addition. Appellant did
not sign the amended change order, but he accepted both payments and
continued to perform the construction work according to the revised design.
In the ensuing months, Appellees became dissatisfied with Appellant’s lack
of progress and the quality of the work he performed. They also were
unhappy with Appellant’s failures to repair damage that his employees
caused to the neighboring property or to execute the revised Change Order
No. 1. Appellant never repaired the damage satisfactorily or executed the
revised Change Order No. 1. Indeed, the scope of the work contained in
that change order was contested at trial and it remains a central contention
on appeal.
Ultimately, it became apparent that the parties disagreed about the
scope of Change Order No. 1. and the additional costs associated with
Appellees’ proposed alteration of the planned electrical system. As it relates
to the substantial electrical alterations, on July 18, 2011, Appellees paid
-4-
J-A04005-15
Appellant $1,500, which they believed covered the cost of permits and
materials. On July 20, 2011, Appellant prepared Change Order No. 3 in the
amount of $4,500. The change order, which Mr. Monahan denied receiving,
purportedly covered the following:
1. Add 100A[4] electrical panel in the garage [and] 100A service
at exterior.
2. Add 8 receptacles in conduit on interior walls.
3. Provide City of Pittsburgh electrical inspection.
Defendant’s Exhibit L. Appellant completed portions of the electrical
alterations, but the extent of Appellant’s performance under the proposed
change order is unclear from the certified record. Conversely, the record
reveals that Appellant’s proposed $4,500 increase under Change Order No. 3
did not include Appellees’ prior $1,500 payment. See Defendant’s Exhibit S.
After communications soured, the pace of work slowed, and Appellant
eventually stopped performing. By August 17, 2011, Appellees had paid
Appellant $28,250 toward the contract price of $34,225. Appellees
requested a refund for work that was not completed. Appellant countered
with demands for payment for work he performed beyond the scope of the
contract prior to Appellees’ decision to terminate the contract, i.e., the
additional brick veneer and the expanded electrical work.
____________________________________________
4
The ampere, also identified and “A” or “amp,” is the base unit for
measuring electric current.
-5-
J-A04005-15
On March 13, 2012, Appellees filed a civil complaint against Appellant
seeking $21,655 in damages. Appellant eventually filed a counter claim for
unjust enrichment totaling $14,775.5 The matter was assigned to
compulsory arbitration, and the board of arbitrators awarded Appellees the
damages they requested. Appellant appealed the award, and the case
proceeded to a nonjury trial de novo on September 17, 2013.
During trial, Mr. Monahan testified on behalf of Appellees. He
presented documentation of a $670 payment to a third party to repair the
damage that Appellant caused to a neighboring property and to perform
masonry work on the garage. In addition, Mr. Monahan submitted two
estimates outlining the projected cost to fix Appellant’s work and to
complete construction. The two estimates projected the total remaining
costs to be $27,000 and $17,056 respectively.
Mr. Bruder testified on his own behalf. Essentially, he attested that
the $6,750 increase in the contract price, as outlined in his Change Order
No. 1, only covered the expense of constructing the one-half story addition
out of masonry block. He explained that his quote did not include the
additional cost to affix brick veneer to the masonry block on the one-half
story addition, to purchase and install windows in the newly created dormer
openings, or to cut an opening and install a window under the south-facing
____________________________________________
5
Appellant initially leveled multiple legal theories; however, the claim for
unjust enrichment was the only count to withstand preliminary objections.
-6-
J-A04005-15
gable. He also challenged Appellees’ evidence regarding the extent of his
performance under the contract, the accuracy of the estimated expense of
completing the tasks envisioned in the contract, and the uncontested
portions of the two change orders.
As it relates to his counter claim, Mr. Bruder adduced evidence that,
after applying Appellees’ prior payments in the amount of $28,250 and
crediting Appellees $3,5006 for work that Appellant admittedly failed to
perform under the contract, Appellees still owed him $14,275 for work that
he completed. The bulk of that amount was $7,300 for the brick veneer that
Appellant affixed to the one-half story addition and $4,500 for the expanded
electrical work.
On September 19, 2013, the trial court entered a non-jury verdict in
favor of Appellees and against Appellant in the amount of $21,655. It
rejected Appellant’s counterclaim. Thereafter, the trial court denied post-
trial relief, and on March 31, 2014, it entered judgment on the verdict. This
timely appeal followed.
Appellant presents one question: “Whether the verdict is so
outrageous that it is shocking to a sense of fairness and justice so as to
warrant a new trial?” Appellant’s brief at i. Our well-ensconced standard of
____________________________________________
6
Appellant admitted that he failed to install roofing shingles, gutter and
downspout, window sills, and the pedestrian door. See Defendant’s
Exhibit S.
-7-
J-A04005-15
review from a non-jury trial verdict is as follows: We must “determine
whether the findings of the trial court are supported by competent evidence
and whether the trial court committed error in any application of the law.”
Allegheny County Housing Authority v. Johnson, 908 A.2d 336, 340
(Pa.Super. 2006) As with all questions of law, the trial court’s legal
conclusions “are not binding on an appellate court because it is the appellate
court's duty to determine if the trial court correctly applied the law to the
facts of the case.” Id. (internal citation omitted). However, we give great
deference to the trial court’s factual findings, which “must be given the same
weight and effect on appeal as the verdict of a jury.” Id. Finally, “We
consider the evidence in a light most favorable to the verdict winner [and]
we will reverse the trial court only if its findings of fact are not supported by
competent evidence in the record or if its findings are premised on an error
of law.” Id.
Appellant challenges the trial court’s determination that he was
responsible for Appellees’ costs to complete the work that he never agreed
to perform. His claim is two-fold. The initial aspect of Appellant’s argument
concerns the scope of Change Order No. 1 and the second component
affects the calculation of Appellees’ damages in relation to the value of the
work that he allegedly performed without compensation. We address these
positions seriatim.
First, Appellant contends that the version of Change Order No. 1 that
he submitted to Appellees accurately reflected the scope of the work that he
-8-
J-A04005-15
envisioned in his $6,750 quote regarding the addition, i.e., constructing a
one-half-story addition using 725 square feet of eight-inch masonry block
and building opposing dormer openings in the roof of the structure.
Appellant continues that all of the remaining work that he completed on the
one-half-story addition at Appellees’ directives, including installing the
additional brick veneer and performing the expanded electrical work, was
outside the scope of the contract and that he should not be required to bear
the substantially increased costs associated with his performance.
Accordingly, Appellant contends that he is entitled to payment from
Appellees for the value of the extra work. Appellant also argues that the
evidence that Appellees submitted regarding the cost of completion did not
reflect the parties’ written agreements. He posits, Appellees “presented
estimates at trial of what it would cost to finish a building that was larger
and more elaborate than the building referenced in the signed contract [and]
[Appellant] never agreed to build the structures reflected in the estimates.”
Appellant’s brief at 10.
The only contract document that both parties admittedly executed is
the A107 form contract. Additionally, the parties agreed to Change Order
No. 2, which memorializes the Post-It note that Appellees affixed to the
written contract before signing it. The crux of this dispute is the scope of
Change Order No. 1 regarding the construction of the one-half story addition
and the extent of the revised electrical work. As noted, the parties
submitted countervailing interpretations of the two versions of Change Order
-9-
J-A04005-15
No. 1 and never fixed the cost of the revised electrical alterations that
Appellant completed.
In discounting Appellant’s position, the trial court concluded that
Change Order No. 1 included, inter alia, the cost to procure and install three
windows and 513 square feet of brick veneer on the exposed portions of the
one-half story addition. While the court made an express finding as to the
brick veneer, there was no definite finding as to the three windows.
Nevertheless, in light of the fact that the trial court included the omitted
windows in its calculation of the damages Appellees incurred as a result of
Appellant’s incomplete performance, the trial court necessarily determined
that the three windows were within the scope of Change Order No. 1. As we
highlight infra, the certified record supports both aspects of the court’s
conclusion. Accordingly, we do not disturb it.
During the nonjury trial, Mr. Monahan testified that he and his wife,
Ms. Gardner, contracted with Appellant to build the distinctive carriage-
house style garage behind his home. N.T., 9/17/13, at 16-17. As Mr.
Monahan was uneasy with the lack of specificity in the scope of work
outlined in the contract documents that Appellant presented, he affixed a
Post-It note to the contract that listed four additional tasks that Appellant
agreed to perform but had omitted from the written instrument. Id. at 19-
20. After construction started, Mr. Monahan spoke with Appellant about
building a one-half-story shell on top of the the planned structure. Id. at
22-23. Thereafter, Appellant proffered a $6,750 quote to construct what
- 10 -
J-A04005-15
was then envisioned as a one-and-one-half-story garage and he produced a
change order to that effect. Id. at 24. Mr. Monahan believed that the
proposed Change Order No. 1 was “extremely vague and [did not] reflect
the conversations that we had had about [the garage] that were more
specific than that.” Id. Accordingly, Mr. Monahan prepared a revised
change order that identified “specifics about the roof pitch[,] . . . [verified]
that each window opening would have either a door . . . or window[,] . . .
[a]nd . . . added a line about [the] front, rear and exposed side [having]
brick veneer.” Id. at 25. At trial, he explained that the initial contract for
the one-story garage only encompassed brick veneer on the front and rear
of the building, but since the exposed portions of the revised structure would
be visible from the street, it had to be covered by brick veneer to comply
with the neighborhood’s historic codes. Id. at 25-26.
While Appellant failed to sign Mr. Monahan’s revised change order, he
never advised him that the windows and brick veneer were not included in
the new contract price. Id. at 28-29, 31. Additionally, as it relates to the
veneer, Appellant constructed the one-half story to accommodate the
application of the brick veneer. Id. at 29. Mr. Monahan explained,
the side [of the garage] facing my neighbor's garage, which is a
single story, is constructed of eight-inch wide block. And so at
the point where it was going to become exposed above my
neighbor's garage, it transitioned from eight-inch wide block to
four-inch wide, which allows for the four inches of the brick next
to it.
- 11 -
J-A04005-15
So for the remainder for the exposed side you've got four-
inch wide block and four-inch wide brick running up the rest of
the side.
Id. at 29. Indeed, as noted supra, Appellant eventually applied the brick
veneer to all of the exposed sides of the building that were visible from the
street. Id. at 74, 76. Appellant did not indicate that the veneer was an
extra cost until after he substantially competed that portion of the job. Id.
Thus, the certified record supports the trial court’s finding regarding the
scope of the original contract and Change Order No. 1
Having found that the record sustains the court’s determination that
the installation of additional brick veneer and dormer windows were included
in the new contract price of $34,225, we next examine the record regarding
Appellant’s performance of the modified contract. The focus of our review is
upon whether Appellant performed as expected. For the reasons that follow,
we find the record proves that he did not.
During the trial, Mr. Monahan introduced photographs depicting
Appellant’s incomplete and unsuitable performance. For example, the
photographs illustrated that Appellant framed the roof improperly and that
the misaligned roof created large gaps where the roof met the dormers and
the masonry blocks. See Plaintiff’s Exhibit 13, Photographs #11 and #18.
The condition was aggravated by the fact that Appellant’s masonry work was
incomplete on one side of the garage insofar as it did not ascend the entire
height of the structure. Id. Appellees also documented that Appellant
constructed the opposite wall at the incorrect pitch. N.T., 9/17/13, at 61;
- 12 -
J-A04005-15
Plaintiff’s Exhibit 13, Photograph #16. Additionally, since the roof was
framed improperly, no overhang existed to use with the gutter system,
which, along with the shingles and fascia board, Appellant neglected to
install. Id. at 58-59; Photograph #13. Thus, as Mr. Monahan testified, “any
precipitation would run down the wall rather than out into a gutter.” Id. at
58. Other photographs demonstrated Appellant’s failure to complete the
brick veneer, lay the PVC conduit for the electrical lines, hang the electrical
panel, and install the rear-facing garage door and windows in both of the
dormer frames and the south-facing gable. Id. at 55-57, 59, 61-62; Exhibit
13; Photographs # 8, #9, #13, #16, and #18. Additionally, the masonry
arch on the dormer was incomplete and Appellant did not install window sills
on any of the windows. Id. at 75. All of the foregoing items, including the
basic electrical work, were within the contract as expanded by Change Order
No. 1. Finally, the record revealed that Appellant abandoned his scaffolding
and pump jacks on Appellees’ property. Id. at 56, 60; Photograph # 15.
Mr. Monahan testified that, even after he and Ms. Gardner hired a crew to
dismantle the equipment, Appellant neglected to remove it from Appellees’
property for approximately one year. Id. at 56, 60.
As it relates to the physical damage that Appellant caused to the
neighboring properties, Mr. Monahan stated that Appellant failed to repair
either of the walkways that he and his employees damaged. N.T., 9/17/13,
at 30. Likewise, Appellant neglected to fix the damage that he caused to
Appellees’ gate, fencepost, and porch steps or mend the damage that his
- 13 -
J-A04005-15
mason caused to the roof of a neighboring garage. Id. 46, 57; see also
Plaintiff’s Exhibit 13, Photograph # 12. In fact, when questioned about the
repairs to Appellees’ property, Appellant feigned ignorance about the
fencepost, opined that rehanging the gate was not within the scope of the
contract, and characterized the porch stairs that his company accidently
demolished with a backhoe as “deficient” in the first place. N.T., 9/17/13, at
97-98, 100. Appellant did not contest Appellees’ assertion that none of the
repairs was performed.
Concerning Appellant’s imperfect performance, Appellant conceded
that he neglected to complete the roof and gutter work, hang the barn door
at the rear of the garage, install a seal on the garage door, dig the trench for
the electrical and water lines, grade the yard for drainage, and finish the
masonry arch on the ground-level rear window. Id. at 97-99, 100.7 He
characterized that work as minimal and he estimated that the tasks could be
completed for approximately $3,500. Id. at 95; Defendant’s Exhibit S. For
____________________________________________
7
Appellant acknowledged that he installed only one of four windows, but he
reiterated his position that the windows that he declined to install were not
included in the contract price. N.T., 9/17/13, at 95-97. Similarly, he
asserted that the contract had not budgeted for him to cut the window
opening under the gable, lay veneer around that window, attach wood
cladding to the garage door, and paint any portion of the structure. Id. at
88-89, 97, 99, 101. He claims that all of these items are outside the scope
of his contract with Appellees. Id. at 88-89, 97, 99, 101. However, as
noted in the body of this writing, the trial court found, either expressly or
implicitly, that these items were included in the contract price, and with the
exception of Appellant’s alleged responsibility to paint the garage, the record
sustains that finding.
- 14 -
J-A04005-15
example, Appellant opined that it would cost $75 to complete the masonry
work and $150 to correct the framing issue. N.T., 9/17/13, at 100.
Notwithstanding Appellant’s protestations to the contrary, the
foregoing evidence demonstrates that Appellant failed to perform as
expected under the contract. Appellant performed certain tasks and
neglected others. Moreover, some of the work was only partially complete
and aspects of the work that Appellant did perform were not done in
workmanlike manner. The roof was unfinished and poorly framed.
Appellant neglected to install shingles, fascia board, or a gutter and
downspout system. He failed to complete the required masonry work and
preliminary electrical work under the contract, and he damaged Appellees’
property and the property of their neighbors. Stated simply, the evidence
sustains the trial court’s findings regarding Appellant’s lack of performance
under the modified contract. Thus, for all of the foregoing reasons, we find
the trial court did not err in framing the scope of Appellant’s performance
under the contract and in determining that certain aspects of the work
Appellant was required to perform under the contract were either ignored,
incomplete, or deficient. Hence, Appellant is responsible for the natural and
ordinary costs associated with completing the garage that Appellant agreed
to build.
The second cog in Appellant’s reasoning challenges the trial court’s
calculation of the damages it awarded to Appellees. Preliminarily, Appellant
complains that the two estimates that Appellees adduced to establish their
- 15 -
J-A04005-15
damages related to a “vastly expanded project that [he] never agreed to
complete.” Appellant’s brief at 8. While Appellant’s brief does not elaborate
upon this position fully, it is clear from his testimony and legal position
throughout the litigation that he believes that the scope of the construction
project was limited to his interpretations of the contract and Change Order
No. 1. That is to say, from Appellant’s perspective, the only items that were
included in the modified contract following the change order were the
construction of (1) the one-half-story addition from 725 square feet of
masonry block; and (2) a roof with two dormer window openings. As noted
supra, however, the record supported the trial court’s findings that Change
Order No. 1 included, inter alia, the installation of three windows and
additional brick veneer over the exposed portions of the structure. Thus, we
rebuff Appellant’s current line of argument for the identical reason that we
rejected his earlier contention.
The remaining component of Appellant’s argument, which challenges
the logic of the trial court’s damage award, is more nuanced. Appellant
argues that the verdict has no support in the law or facts of this case. We
disagree with the overly simplistic perspective that the damage award is
utterly without support. However, our review revealed signficant
irregularities in the trial court’s rationale.
Where the issue is not derived from a question of law, we review a
challenge to the calculation of damages for an abuse of discretion. J.J.
DeLuca Co., Inc. v. Toll Naval Associates, 56 A.3d 402, 417 (Pa.Super.
- 16 -
J-A04005-15
2012). As our Supreme Court reiterated in Helpin v. Trustees of
University of Pennsylvania, 10 A.3d 267, 270 (Pa. 2010) (quoting Ferrer
v. Trustees of the University of Pennsylvania, 825 A.2d 591, 610 (Pa.
2002)),
Where one party to a contract without any legal
justification, breaches the contract, the other party is entitled to
recover, unless the contract provided otherwise, whatever
damages he suffered, provided (1) they were such as would
naturally and ordinarily result from the breach, or (2) they were
reasonably foreseeable and within the contemplation of the
parties at the time they made the contract, and (3) they can be
proved with reasonable certainty.
The High Court continued, “The purpose of a damage award is to place the
non-breaching party ‘as nearly as possible in the same position it would have
occupied had there been no breach.’” Id. (quoting Lambert v. Durallium
Products Corporation, 72 A.2d 66, 67 (Pa. 1950)). Indeed, “[t]he
measure of damages for breach of contract is compensation for the loss
sustained [and] [t]he aggrieved party can recover nothing more than [what]
will compensate him.” Id. (citation omitted) (emphasis in original).
The fact-finder may not render a verdict based upon conjecture;
however, it may use a measure of deductive reasoning in estimating
damages. See J.J. DeLuca Co., Inc., supra, at 417. “The fact-finder may
make a just and reasonable estimate of the damage based on relevant data,
and in such circumstances may act on probable, inferential, as well as direct
and positive proof.” Id. at 417-418.
- 17 -
J-A04005-15
Herein, Appellant failed to complete the following tasks pursuant to the
original contract and Change Order No. 1: (1) correct the roof framing and
install sheathing, shingles, gutters, fascia boards, and downspout; (2) install
three windows; (3) hang garage door in rear; (4) clad, seal and install large
garage door; (5) dig trenches for electrical and plumbing conduits; (6) rough
grade the back yard for drainage; (7) install window sills; and (8) complete
the masonry arch over the yard-facing window. In addition, Appellant is
responsible for Appellees’ expenditures to fix the roof of their neighbor’s
garage, repair the wooden gate, fence post, and shared walkway on their
property, and to replace the missing porch steps that were obliterated by
Appellant’s backhoe. Accordingly, the trial court’s award of damages must
reflect the sum of the costs to complete, repair, or replace these items.
Instantly, the trial court explained the calculation of its $21,665
damage award in favor of Appellees as follows:
The parties had originally contracted for services from
Bruder to construct a carriage house in the agreed upon amount
of $27,475.00. Subsequently, the plaintiffs requested
construction of an additional one-half story for the carriage
house and, pursuant to code, required brick veneer on all
exposed outside surfaces of the entire structure. That change
increased the initial cost of the contract by $6,750.00, resulting
in a total cost of completion of $34,225.00. Plaintiffs paid
$28,225.00 to Bruder toward that total cost. When Bruder failed
to complete the work, Plaintiffs expended $27,000.00 to finish
the project within the scope of the amended agreement and paid
an additional $670.00 to cure damage allegedly occasioned by
Bruder's negligence to a neighboring property in the course of
his performance.
....
- 18 -
J-A04005-15
The plaintiffs were required to take the project to completion and
to meet additional costs that, but for Bruder's failure to perform,
would not have been incurred. The cost of completion was
established at trial to be $27,670.00. That figure was pursuant
[to] an estimate of $27,000.00 not only to complete the project
but also to correct mistakes attributed to Bruder and by an
additional $670.00 repair estimate for damage done to the
adjacent property.
The cost incurred by the plaintiffs was $55,895, which is
the sum of the amount paid to Bruder and the amount required
to complete the project after Bruder had ceased to perform:
[$]28,225 + [$]27,670. Plaintiffs acknowledge that the total
contract price with Bruder would have been $34,255.00. That
amount was not, in fact, paid in full to Bruder, but plaintiffs
concede that that sum would have been paid to Bruder had he
completed the project. The damages due to the plaintiffs is the
cost of the completed project less the sum Bruder would have
received from plaintiffs had he fully performed the contract; that
is, $58,895 less $34,225 or $21,670. The Court awarded
$21,665; the amount pled.
Trial Court Opinion, 7/22/15, at 4-5 (footnote omitted).
At the outset, we observe that the certified record supports the trial
court’s calculation of the $670 that Appellees paid to Mike and Mark
Geissinger for repairs to their neighbor’s roof and Appellant’s inadequate
masonry work. See Exhibit 14. Accordingly, we do not disturb that aspect
of the court’s calculation.
The only evidence that Appellees proffered during the trial relating to
the cost of completing construction were two estimates, Plaintiff’s Exhibits
- 19 -
J-A04005-15
15 and 16, respectively.8 Exhibit 15 is an email exchange between Mr.
Monahan and Bob Cullen, a prospective contractor, wherein Mr. Cullen
____________________________________________
8
Both estimates were submitted in response to the following bullet-point list
of work that Mr. Monahan believed was required to complete the garage
renovation:
• Install rectangular, double hung, wood framed windows on
front, back, side (3 total)[;]
• Finish roof framing to give proper overhang[;]
• Install fascia boards on gable sides of balding (1x10)[;]
• Install half-round gutters and round downspouts[;]
• Install shingles on roof to match house[;]
• Paint and hang sliding wood “barn” doors on track in yard-
facing opening[;]
• Re-hang wood gate at end of pathway to alley[;]
• Dig trench between garage and house and install “conduit” for
plumbing supply lines[;]
• Pull circuit through existing conduit to provide power for
garage door opener and an outlet[;]
• Repair damaged fence (post leaning due to concrete base
being exposed)[;]
• Replace missing wood steps from yard to deck[;]
• Re-grade yard for proper drainage to pathways and alley[;]
• Install seal on existing 16' garage door[;]
• Attach wood (cedar . . . ) cladding to 16' Masonite door to
replicate older-style wood doors[;]
(Footnote Continued Next Page)
- 20 -
J-A04005-15
responded to Appellees’ bullet-list of tasks by submitting a rough estimate of
$27,000. Conversely, Exhibit 16 was an itemized proposal submitted by
Horn Corporation (“Horn”) that set forth a thorough description of the
precise work that it would perform for an estimated cost of $17,056.00.
The trial court neglected to explain why it adopted Mr. Cullen’s rough
calculation of $27,000 over Horn’s quote to perform the work for
$17,056.00. In fact, other than a brief reference to Appellant’s argument,
the trial court failed to acknowledge the existence of the lower estimate.
That omission is especially problematic in light of the fact that Mr. Cullen’s
appraisement conceded that the project was “very hard to estimate,” see
Exhibit 15, and Horn submitted a detailed quote setting forth each task
individually. See Exhibit 16.
During the trial, Mr. Monahan testified that Mr. Cullen’s approximation
was a more accurate depiction of his damages because Horn’s estimate did
not include some of the items on his bullet-point list. N.T., 9/17/13, at 65.
_______________________
(Footnote Continued)
• Finish masonry
o . . . finish bottom of yard-facing garage door opening to allow
garage door to land properly
o Finish brick jack arch above ground level yard-facing window
Plaintiff’s Exhibit 15. The only responsibility identified in the itemized list
that was not expressly or implicitly included in the contract documents is
painting the large barn doors at the rear of the garage. Accordingly, that
cost is not attributable to Appellant.
- 21 -
J-A04005-15
While Mr. Monahan did not identify which jobs were omitted from Horn’s
quotation, our review of Exhibit 16 reveals that the quote did not include the
costs to repair Appellees’ fence, grade the back yard, transfer the main
electrical supplying wire to the new pole on top of the garage, supply the
negligible amount of bricks to complete the masonry arch over one window,
or paint the barn doors. These five enumerated tasks that Horn omitted
from its quote do not explain the $10,000 variance between the two
estimates.
First, as noted in footnote eight on pages 20-21, Appellant was not
responsible for painting the barn doors so that cost was properly omitted
from the quote. Conversely, since Mr. Cullen’s estimate appears to include
painting, the court’s reliance upon that aspect of the estimate in calculating
Appellees’ damages is improper. Additionally, we observe that Mr. Cullen’s
estimate excludes at least one item that was included in Horn’s quotation,
the decorative cladding for the garage door, and consistent with Horn’s
quotation, Mr. Cullen’s estimate also excluded the costs associated with the
masonry work. N.T., 9/17/13, at 63; Exhibit 15. For these reasons, the
exclusions noted in the Horn quotation fail to explain why Mr. Cullen’s
estimate exceeded Horn’s quotation by approximately $10,000. The record
simply does not sustain Mr. Monahan’s characterization of the Cullen
estimate as a more accurate assessment of damages.
While the trial court was free to reject all, any, or none of Appellees’
evidence relating to damages, including Horn’s estimate of the cost to
- 22 -
J-A04005-15
complete the garage, the certified record must nevertheless sustain the
court’s decision to adopt the Mr. Cullen’s estimate in toto. See J.J. DeLuca
Co., supra (“the fact-finder may not render a verdict based on sheer
conjecture or guesswork”). Instantly, nothing in the certified record begins
to explain the substantial disproportion of projected costs in the two
estimates, and the trial court did not attempt to reconcile that disparity.
Moreover, Mr. Cullen’s express qualifications that the project that was
difficult to evaluate and that his appraisal was a rough estimate thwarts any
potential inference that his assessment was intrinsically accurate,
particularly when Horn presented a categorical proposal to perform the work
for approximately $10,000 less.
Thus, mindful of the unexplained variance between the two estimates,
and the fact that Mr. Cullen’s estimate included costs associated with a task
that was not Appellant’s responsibility to complete, we find that the record
does not support the court’s wholesale adoption of Mr. Cullen’s estimate of
$27,000. At a minimum, assuming the accuracy of all remaining aspects of
Mr. Cullen’s approximation, the trial court’s estimate of Appellees’ damages
must be reduced by the projected cost of painting the barn doors.
In addition to the foregoing discrepancies, the trial court’s calculation
of damages also ignores Appellant’s performance of the electrical work
beyond the original contract and Change Order No. 1. As noted supra,
during construction, Appellees expanded the scope of the electrical work to
be performed on the garage. While the extent of Appellant’s performance is
- 23 -
J-A04005-15
unclear, it is apparent from the certified record that: (1) Appellant
completed a portion of the expanded electrical work; (2) four days prior to
discontinuing their relationship with Appellant, Appellees conceded that they
owed Appellant money for that work beyond the initial payment of $1,500;
and (3) the trial court did not adjust the damage award to account for that
debt. N.T., 9/13/15, at 45, 48, 70; Defendant’s Exhibit L, at 2 (“Upon
completion on or by [August 29] we will make final payment of the
remaining $6,195 plus the remainder due for the electrical work.”)
(emphasis added).
Herein, the trial court based its calculation of damages upon Appellees’
payment of $28,250, including the $1,500 payment for electrical work,
toward the $34,225 contract price. However, since the trial court did not
account for any electrical work beyond what was originally envisioned, it
neglected to determine the cost of Appellant’s performance of the expanded
electrical alterations and it omitted that figure from its calculation. Thus, in
order to make the parties whole, the trial court was required to increase the
contract price in the amount equal to Appellant’s cost of performance,
presumably an amount between $1,500 and $4,500 based upon the
evidence submitted at trial, before it could compute Appellees’ damages. As
the trial court omitted the value of Appellant’s performance from its
equation, Appellees received a windfall equal to that amount.
Accordingly, for all of the preceding reasons we affirm the trial court’s
determination that Appellant was contractually obligated to perform in
- 24 -
J-A04005-15
accordance with Appellees’ interpretation of Change Order No. 1 and that he
is liable for the reasonably foreseeable costs to repair his mistakes and
complete construction of the garage consistent with the contract documents.
However, we vacate the judgment entered on the $21,655 verdict and
remand for a new calculation of damages that is an accurate estimation of
the cost to complete Appellant’s contractual obligation and accounts for
Appellant’s performance of the expanded electrical work.
Affirmed in part, reversed in part, and remanded with instructions.
Jurisdiction relinquished.
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 7/10/2015
- 25 -