Third District Court of Appeal
State of Florida
Opinion filed July 22, 2015.
Not final until disposition of timely filed motion for rehearing.
________________
No. 3D14-1592
Lower Tribunal No. 14-1007
________________
Aspen Air Conditioning, Inc.,
Appellant,
vs.
Safeco Insurance Company of America, et al.,
Appellees.
An Appeal from the Circuit Court for Miami-Dade County, Daryl E.
Trawick, Judge.
Lynne S. K. Ventry (Delray Beach); Clifford A. Wolff (Fort Lauderdale),
for appellant.
Mills Paskert Divers and Alberta Adams Campbell and Matthew G. Davis
(Tampa), for appellee Safeco Insurance Company of America.
Before WELLS, ROTHENBERG, and LAGOA, JJ.
ON MOTION FOR ATTORNEY’S FEES
LAGOA, J.
Pursuant to Florida Rule of Appellate Procedure 9.410 and section
57.105(1), Florida Statutes (2014), Appellee, Safeco Insurance Company of
America (“Safeco”), seeks an award of attorney’s fees—incurred defending
against allegedly baseless assertions contained in the Appellant’s Initial Brief—as
a sanction against Appellant, Aspen Air Conditioning, Inc. (“Aspen”), and its
counsel, Lynne S.K. Ventry, Esq. (“Ventry”) and Clifford A. Wolff, Esq.
(“Wolff”). Because we find that Aspen’s allegations are without a good faith
basis, sanctions against Aspen and its counsel are warranted under both section
57.105 and Rule 9.410.
I. FACTUAL AND PROCEDURAL HISTORY
This appeal arises from a construction project of a nursing and rehabilitation
center in Coral Gables (the “Project”). DooleyMack Constructors of South
Florida, LLC (“DooleyMack”), was the general contractor for the Project. The
Project’s owner and developer was Victoria Management, LLC (“Victoria”). On
November 13, 2007, Safeco issued payment and performance bonds naming
DooleyMack as principal and Victoria as an obligee.
On May 22, 2009, DooleyMack entered into a subcontract with Aspen (the
“Subcontract”) to construct and install the HVAC components for the Project. At
the conclusion of Aspen’s work, Aspen was owed a balance on the Subcontract.
On January 23, 2012, Aspen served DooleyMack and Safeco with its notice of
bond claim in accordance with the terms of the Subcontract and payment bond.
Safeco filed suit against Aspen on June 22, 2012, in the United States
District Court for the Southern District of Florida (the “Federal Litigation”).
2
Safeco sought, inter alia, indemnity for any claims arising out of the Department
of Labor’s (“DOL”) assessments against Aspen and its subcontractors for alleged
wage violations. Aspen brought a counterclaim, asserting a claim on the payment
bond, as well as a third-party complaint against DooleyMack. Safeco, Aspen, and
DooleyMack thereafter entered into a Tolling Agreement in which Safeco agreed
to dismiss the Federal Litigation without prejudice, and the parties agreed that the
statute of limitations for any claims arising out of the Subcontract, the bond, and/or
the Project would be tolled until October 1, 2013. The parties subsequently
executed an Agreement Extending Tolling Agreement and a Second Agreement
Extending Tolling Agreement (the “Tolling Agreement”) to extend the deadline
through January 15, 2014. The Tolling Agreement contains a forum selection
clause providing:
5) The Parties further agree that should any further
litigation be filed by Aspen against DooleyMack, and/or
Safeco or by DooleyMack and/or Safeco against Aspen,
arising out of or related to the Subcontract, the Bond or
the Project, said litigation shall be filed in the United
States District Court for the Southern District of Florida.
On January 14, 2014, Aspen filed suit against Safeco and DooleyMack in
the Circuit Court for Miami-Dade County, alleging that Safeco and DooleyMack
breached the bond and Subcontract in failing to pay Aspen for its work. Safeco
moved to dismiss Aspen’s Complaint, and later its Amended Complaint for
improper venue. In response, Aspen contended that venue was proper in state
court due to an already existing case in
3
the Circuit Court for Miami-Dade County regarding the Project (the “Parallel
Action”). In the Parallel Action, Victoria had filed suit against Safeco and
DooleyMack in October 2013 for alleged Project construction defects. Victoria,
however, did not name Aspen as a defendant, nor did Aspen attempt to intervene.
On May 27, 2014, the trial court held a hearing on Safeco’s Motion to
Dismiss Aspen’s Amended Complaint for improper venue based on the forum
selection clause in the parties’ Tolling Agreement. On June 1, 2014, the trial court
entered an order dismissing Aspen’s Amended Complaint, finding that the forum
selection clause required Aspen to file the action in federal court. Aspen filed its
notice of appeal on June 30, 2014, and on February 18, 2015, we affirmed the trial
court’s dismissal of Aspen’s Amended Complaint. Aspen Air Conditioning, Inc.
v. Safeco Ins. Co. of Am., No. 3D14-1592, 2015 WL 691642 (Fla. 3d DCA Feb.
18, 2015) (table).
In Section III of its Initial Brief, Aspen asserted that Safeco’s counsel made
misleading statements to the trial court at the hearing on the Motion to Dismiss.1
Specifically, Aspen alleged that the statements of Safeco’s counsel, Alberta
Campbell (“Campbell”), misled the trial court about the substance and status of the
“Parallel Action.”2 According to Aspen, Campbell downplayed the HVAC defects
1 Prior to filing its Initial Brief, Aspen made a similar argument before this Court in
its Motion to Relinquish Jurisdiction, which this Court denied. In its Opposition to
Aspen’s Motion to Relinquish Jurisdiction, Safeco provided documentary evidence
illustrating that each of the statements made by Safeco’s counsel were, in fact,
supported by then-existing communications and documents.
4
at issue in the Parallel Action, misrepresented to the trial court that the Parallel
Action was close to resolution, and mischaracterized Aspen’s involvement in the
issues raised in the Parallel Action. The relevant statements made by Safeco’s
counsel, Campbell, at the hearing on the Motion to Dismiss are as follows:
THE COURT: Let me ask this. This case that was filed in state
court, Victoria Management, LLC v. Safeco Insurance, et al., what’s
the subject matter of that case?
MS. CAMPBELL: Sure. That case involves two different issues. The
largest is the flooring. What they’re alleging is really the
bathrooms—they’re alleging that the shower pan liners that were put
in these ADA showers—so if you can imagine, it’s one of those big,
open bathrooms, like you’d see in a hospital. This is a fully staffed—
full-time nursing facility for elderly people.
You roll the wheelchair in, and you’ve got the toilet right there .
. . . That has nothing to do with Aspen. That has to do with Aspen’s
work. That’s another two other contractors called Flooring World and
Everlast, who are parties to that suit with Victoria Management.
Victoria had alleged in that lawsuit a small issue with the
HVAC, that there were negative pressure issues throughout the
building, but they had not complied with the 558 process—that’s
2 Specifically, in Section III of its Initial Brief, Aspen argued:
At the May 27, 2014 hearing on SAFECO’s Motion to Dismiss,
counsel for SAFECO made misleading statements about the status and
substance of the Parallel Action, to induce the trial court to grant its
motion. As noted in the proposed Motion to Vacate attached to
ASPEN’s Motion to Relinquish Jurisdiction, SAFECO’s attorney
advised the trial court that the HVAC defects alleged in the Parallel
Action were minor, and further claimed that the entire case was close
to resolution . . . .
The statements made by SAFECO’s attorney may have been
motivated by zealous advocacy, but they were also false when made.
SAFECO’s counsel knew or should have known that the statements
would be misleading. The trial court was left with an incorrect
impression regarding the significance of ASPEN’s work in the
Parallel Action, and the commonality of both facts and issues in the
two cases.
5
provided under the Florida Statutes—which says, [b]efore you can run
out as an owner and sue the contractor and the surety for a
construction defect, you have to give us a chance to investigate and
try to fix it.
And so we argued to the judge there that they had to do that,
and the judge agreed with us. And so all the portion of that case that
relates to Aspen’s work has been stayed, and we’re going through the
558 process. We agreed with Victoria to hire an independent guy to
go out and test the system that Aspen had installed.
And that the process has been completed, and he thinks that it
can be fixed by doing an adjustment of the controls—I’m probably
telling you more than you want to know—but we’ve sent an offer to
Victoria to pay for that, and I’m supposed to get a response back from
them this week.
If I’m able to work that out with Victoria, there will be no issue
in that lawsuit that involves Aspen whatsoever.
THE COURT: Okay.
After complying with the relevant safe harbor requirements of section
57.105 and Rule 9.140, on December 18, 2014, Safeco filed a Motion for
Sanctions with our Court after Aspen declined to withdraw Section III of its Initial
Brief.
On March 23, 2015, Aspen filed its response to Safeco’s Motion for
Sanctions, arguing that sanctions are not appropriate when a party’s actions have a
good faith basis and that it “merely pointed out in good faith” Aspen’s claim
regarding Campbell’s arguments to the trial court, and that Aspen’s “arguments are
supported by the facts.” For the reasons discussed below, we find Aspen’s
arguments without merit.
6
II. ANALYSIS
Section 57.105(1)(b) provides for sanctions when the application of then-
existing law to material facts does not support a claim or defense,3 and Rule
9.410(a), (b)(1), provides for sanctions for the filing of any brief that is deemed to
be frivolous.4 On appeal, both section 57.105 and Rule 9.410 provide a basis for
3 Section 57.105(1) provides:
(1) Upon the court’s initiative or motion of any party, the court shall
award a reasonable attorney’s fee, including prejudgment interest, to
be paid to the prevailing party in equal amounts by the losing party
and the losing party’s attorney on any claim or defense at any time
during a civil proceeding or action in which the court finds that the
losing party or the losing party’s attorney knew or should have known
that a claim or defense when initially presented to the court or at any
time before trial:
(a) Was not supported by the material facts necessary to establish the
claim or defense; or
(b) Would not be supported by the application of then-existing law to
those material facts.
4 Rule 9.410(a), (b)(1), provides:
(a) Court’s Motion. After 10 days' notice, on its own motion, the
court may impose sanctions for any violation of these rules, or for the
filing of any proceeding, motion, brief, or other paper that is frivolous
or in bad faith. Such sanctions may include reprimand, contempt,
striking of briefs or pleadings, dismissal of proceedings, costs,
attorneys' fees, or other sanctions.
(b) Motion by a Party.
(1) Applicability. Any contrary requirements in these rules
notwithstanding, the following procedures apply to a party seeking an
award of attorneys' fees as a sanction against another party or its
7
attorney’s fees as a sanction. See, e.g., Visoly v. Sec. Pac. Credit Corp., 768 So.
2d 482, 490 (Fla. 3d DCA 2000) (“In Florida, appellate attorney’s fees may be
assessed against a party and their counsel for filing a frivolous appeal pursuant to
[section 57.105] and [Rule 9.410].”). As we previously stated,
An appeal is defined as frivolous if it presents no justiciable
question and is so devoid of merit on the face of the record that there
is little prospect it will ever succeed.
We recognize that to some extent, the definition of “frivolous”
is incapable of precise determination. Nevertheless, a review of
Florida caselaw reveals there are established guidelines for
determining when an action is frivolous. These include where a case is
found: (a) to be completely without merit in law and cannot be
supported by a reasonable argument for an extension, modification or
reversal of existing law; (b) to be contradicted by overwhelming
evidence; (c) as having been undertaken primarily to delay or prolong
the resolution of the litigation, or to harass or maliciously injure
another; or [(d)] as asserting material factual statements that are false.
Id. at 490-91 (citations and footnote omitted). Because we conclude that Section
III of Aspen’s Initial Brief is frivolous when analyzed under these established
guidelines, we impose attorney’s fees as sanctions. Cf. Morton v. Heathcock, 913
So. 2d 662, 668 (Fla. 3d DCA 2005) (“It has long been recognized that use of the
word ‘shall’ in section 57.105, ‘evidences the legislative intention to impose a
mandatory penalty in the form of a reasonable attorney's fee . . . .’” (quoting
Wright v. Acierno, 437 So. 2d 242, 244 (Fla. 5th DCA 1983))).
Here, Campbell’s statements to the trial court were supported by
documentation and correspondence between the parties in the Parallel Action, and
counsel pursuant to general law.
8
both Safeco’s Opposition to Aspen’s Motion to Relinquish Jurisdiction and its
Motion for Attorney’s Fees contained documents establishing the veracity of
Campbell’s statements regarding the Parallel Action with Victoria. These
documents, therefore, establish that Aspen’s claims in Section III of its Initial Brief
were without factual or legal support.5
Significantly, in a letter dated September 15, 2014, Safeco informed Aspen’s
counsel of the baseless accusations before Aspen filed its Motion to Relinquish
Jurisdiction.6 At the least, Aspen’s counsel knew or should have known from the
documents Safeco attached to its Opposition to Aspen’s Motion to Relinquish
Jurisdiction that Aspen did not have a factual basis for its misrepresentation claims
made in its Initial Brief. Yet, Aspen and its counsel subsequently decided to
include the false allegations made in Section III despite the documents establishing
that the allegations were baseless. The unambiguous terms of both Rule 9.410 and
section 57.105 are in place to protect Safeco and its attorneys from such action.
5 For example, correspondence exchanged between Safeco and Victoria reveal that
Victoria accepted—subject to certain provisions—Safeco’s offer to have the
building’s HVAC system tested and potentially balanced, if needed. Thus, in
direct contradiction to Aspen’s assertions in its Initial Brief, Safeco’s counsel
could not have known at the time of the hearing on its Motion to Dismiss that
Victoria would later reject the offer to balance the HVAC system. Similarly, the
correspondence between Campbell and Victoria establish that Campbell’s
statements made at the hearing on the status of negotiations between Safeco and
Victoria were completely accurate based on the information Safeco and Campbell
had at the time.
6Prior to filing its Motion to Relinquish Jurisdiction in this Court, Aspen sent a
copy of the motion to Safeco for review.
9
See Martin Cnty. Conservation Alliance v. Martin Cnty., 73 So. 3d 856, 858-59
(Fla. 1st DCA 2011).
Moreover, we find Aspen’s assertion that it made the statements in good
faith to be without merit, as Aspen relies primarily on documents exchanged with
Safeco and Campbell dated after the hearing on Safeco’s Motion to Dismiss in
making this argument. These documents were not in existence at the time of the
hearing, and our review is limited to the record made before the trial court.
Konoski v. Shekarkhar, 146 So. 3d 89, 90 (Fla. 3d DCA 2014); Altchiler v. State,
Dep’t of Prof’l Regulation, 442 So. 2d 349, 350 (Fla. 1st DCA 1983).
Accordingly, we are compelled to grant Safeco’s Motion for Attorney’s Fees as a
sanction against Aspen and its counsel.
III. CONCLUSION
Because we conclude that Safeco’s counsel did not make any
misrepresentation to the trial court but accurately relayed the facts and status of the
Parallel Action involving Victoria that she knew at the time of the hearing on
Safeco’s Motion to Dismiss, we find that Section III of Aspen’s Initial Brief is
wholly without factual or legal basis. Accordingly, we award a reasonable
attorney’s fee, including pre-judgment interest, to be paid to Safeco in accordance
with section 57.105(1) and Rule 9.410, and remand to the trial court.
Motion granted; remanded with instructions.
10