Opinion issued May 3, 2001
In The
VÉâÜà Éy TÑÑxtÄá
For The
Y|Üáà W|áàÜ|và Éy gxåtá
NO. 01-00-00143-CV
____________
VALERO MARKETING & SUPPLY COMPANY, Appellant
V.
KALAMA INTERNATIONAL, LIMITED LIABILITY COMPANY, Appellee
On Appeal from the 129th District Court
Harris County, Texas
Trial Court Cause No. 97-49288
OPINION
This is an appeal from a summary judgment disposing of a breach of contract
complaint, rendered in favor of appellee, Kalama International, LLC. (“Kalama”).
Appellant, Valero Marketing and Supply Company (“Valero”), complains the trial
court erred in (1) granting Kalama’s summary judgment motion and denying Valero’s
summary judgment motion; (2) considering “usage of trade” evidence and ignoring
the existence of a fact issue on “usage of trade”; and (3) not finding Kalama was
required under the Uniform Commercial Code to notify Valero of the requirement that
a methanol dedicated or methanol clean barge was necessary to take delivery of
methanol. We affirm.
Background Facts
Justice Oliver Wendell Holmes warned, “In most contracts men take the risk
of events over which they have imperfect or no control.” Ferry v. Ramsey, 277 U.S.
88, 95, 48 S. Ct. 443, 444, (1928). The undisputed facts of this case illustrate this
admonition.
After negotiating a price, a third-party broker brought together Valero, a refiner
and marketer of petroleum products, and Kalama, a marketer of various chemicals.
Valero and Kalama subsequently entered into a contract, drafted by Valero, dated June
16, 1997, wherein Kalama agreed to sell Valero 20,000 barrels of methanol ASTM D
11552-891 at $.59 per gallon. The contract specified Valero would take delivery of
1
This type of methanol is 99.85% pure methanol. Methanol is defined as “a
colourless, volatile, poisonous liquid with a pungent odour which is produced
mainly by the high-pressure reduction of carbon monoxide or dioxide with
hydrogen and is used as an intermediate in the synthesis of formaldehyde, as
a solvent, and as a denaturant for ethyl alcohol.” THE COMPACT OXFORD
2
the methanol between June 23, 1997 and June 30, 1997 “via Valero’s barge, at
Plaquemine, LA.”
The designated point of delivery and loader of the methanol was Georgia Gulf
Corporation, a third-party chemical company located in Plaquemine, Louisiana.2 The
parties also jointly hired a third-party inspection company, SGS Consulting and
Inspection, Inc. (“SGS”), to inspect the barge upon its arrival at the port; Valero and
Kalama split the costs of the inspection. Thus, SGS was a contract inspector working
for both Valero and Kalama.
Valero hired the Genie Cenac, a third-party barge, to take delivery of the
methanol. On June 18, 1997, Valero sent a nomination to Kalama detailing the
volume of product and designating the Genie Cenac as the barge to receive delivery.
The nomination also listed the prior cargo of the Genie Cenac as unleaded gasoline.
Kalama received the nomination; no objection was made.
On June 30, 1997, before the Genie Cenac docked at Georgia Gulf, SGS
inspected the barge and rejected it for “cleanliness to carry: Methanol”; this was the
last date on which delivery could occur under the terms of the contract. The Genie
ENGLISH DICTIONARY 1072 (2d ed. 1991).
2
Kalama stored methanol at Georgia Gulf, a corporation separate and apart from
Kalama.
3
Cenac had been cleaned prior to docking, but despite that cleaning, gasoline vapors
and puddles remained on the barge from its prior cargo of unleaded gasoline. Georgia
Gulf refused to load the barge because it could only load the methanol onto a
methanol dedicated or methanol clean vessel.3
After this rejection, Kalama agreed to extend the time allowed for delivery until
July 2, 1997, and Valero agreed to pay for the cleaning of the Genie Cenac.4 Valero
subsequently took the Genie Cenac to be cleaned again and have it “stripped and
blown dry.” On July 1, 1997, the Genie Cenac again attempted to load at Georgia
Gulf, but SGS rejected the barge a second time, noting the same problems that existed
on the first inspection.
On July 2, 1997, Kalama sent a letter to Valero terminating the contract because
Valero “had failed to produce a suitable barge to load the methanol within the
3
Georgia Gulf did not have the required permit from the State of Louisiana to
recover gasoline vapors, which would have been necessary if Georgia Gulf had
loaded the methanol with the presence of gasoline puddles and vapors. Thus,
loading the Genie Cenac would have violated Georgia Gulf’s permit and would
have risked potentially contaminating Georgia Gulf’s entire plant and shutting
it down because the barge was not methanol dedicated or methanol clean.
4
We do not address the issue of contract modification as we may not consider
any ground not expressly presented to the trial court by written motion, answer,
or other response to the motion for summary judgment. See TEX. R. CIV. P.
166a (c); City of Houston v. Clear Creek Basin Auth., 589 S.W.2d 671, 676
(Tex. 1979); Hussong v. Schwan’s Sales Enters., Inc., 896 S.W.2d 320, 323
(Tex. App.—Houston [1st Dist.] 1995, no writ).
4
contractual deadline.” When Kalama terminated the contract, Valero was forced to
cover at a higher price. Valero sent a letter to Kalama demanding to be paid damages
in the amount of $82,135.52.5
Although Kalama was not aware before this incident that Geogia Gulf did not
have a permit to recover gasoline vapors, Kalama was aware Georgia Gulf required
barges accepting delivery of methanol to be methanol dedicated or methanol clean.
Danny Oliver, a Valero employee who drafted the agreement in question,
testified that he did not know Georgia Gulf required methanol clean or methanol
dedicated barges. However, Cathy Cazes, a Georgia Gulf employee, testified that
Georgia Gulf had previously loaded methanol onto Valero barges “more than once or
twice” and that Valero would have used a methanol dedicated or methanol clean barge
because Georgia Gulf has always required methanol dedicated or methanol clean
barges.6 Valero claimed in its summary judgment motion and in its appellate brief that
5
Valero’s alleged damages include the cost of cover, various incidental and
consequential damages, and attorney’s fees. The actual amount sought by
Valero in this suit is $82,277.40.
6
Cazes testified in her deposition as follows:
Q Has Georgia Gulf loaded methanol onto any Valero barges in the
past that you can recall?
A Yes, sir, we have.
5
the president of Georgia Gulf, Frank Vendt, testified Valero “had no prior dealings
with Georgia Gulf”; however, this is not what Vendt said. The record shows Vendt
either could not remember or did not personally know of Valero or any prior dealings
between Valero and Kalama.7 Thus, his testimony does not contradict Cazes’
Q And, I know this is a difficult question, do you have any idea how
many times?
A No, sir.
Q Would it be more than once or twice?
A Yes, sir, I think it’s more than once or twice.
Q Would they have had to use a dedicated barge or a clean barge at
that time also?
A Yes, sir, all barges have to be cleaned.
7
Vendt testified in his deposition as follows:
Q And just to try to clear something up; in your mind’s eye, can you
recall any particular time when Valero may have purchased
methanol from the Georgia Gulf facility in the past?
A I couldn’t tell you in the past, no. I couldn’t tell you. Any time
or dates or anything. Or by what means.
Q I’m sorry, I didn’t get the last part?
A Or by what means. I couldn’t tell you how - - if we ever did, or
how it was loaded into what vessel, or what kind of vessel, what
mode.
6
testimony.
Peggy Pane, a Valero supply coordinator, testified that Valero had previously
used methanol dedicated or clean barges and that two Valero refineries preferred
methanol to be transported in methanol dedicated or clean barges. She sometimes
called these refineries to see whether they would accept a barge with another previous
cargo. Pane also explained that the inspection company represents both the buyer and
the seller, who split the cost of the inspection, and that the inspection company
inspects the barge to see whether any puddles are in the barge and whether it is in
good shape for loading.
Procedural Background
Valero filed suit against Kalama seeking damages for breach of contract.
Kalama answered with a general denial, and further pleaded several alternative
defenses, including: (1) Valero caused the incident and damages as a result of its own
negligence, actions, omissions, and failure to act; (2) Valero failed to provide a
suitable container to transport the methanol; (3) Valero’s failure to provide a suitable
container to transport the methanol was a breach of the contract, excusing further
Q But can you recall whether they have or not, just in general?
A Honestly, the first time that I ever heard of Valero was this
incident right here.
7
performance by Kalama; (4) the actions of third parties rendered performance
impossible; (5) the contract was modified; and (6) the incident and damages were
caused solely by the acts and conduct of parties over whom Kalama had no control.
Kalama moved for summary judgment claiming there was no evidence Valero
tendered performance because Valero failed to provide a suitable barge to receive the
methanol and, thereby, breached the contract. Kalama contended proof of Valero’s
breach was demonstrated by: (1) the custom and usage of trade in the methanol
business; (2) Valero’s actual or constructive knowledge that a methanol dedicated or
a properly cleaned barge was necessary to load Methanol ASTM D1152-89; (3) two
failed barge inspections; and (4) Valero’s failure to meet the product quality
specifications in its nominations.
Valero replied by filing its own motion for summary judgment. Valero asserted
the trial court could determine as a matter of law Kalama breached the contract
because Kalama did not deliver the methanol as required under the contract and failed
to notify Valero of “special requirements necessary to take delivery” pursuant to
section 2.503(a) of the Texas Business and Commerce Code. TEX. BUS. & COMM.
CODE ANN. § 2.503(a) (Vernon 1994). Valero asserted that “[d]ue to [Kalama and
Georgia Gulf’s] prior dealings, Kalama was aware that Geogia Gulf had special
requirements for barges.” Valero claimed it tendered performance when the Genie
8
Cenac arrived at Georgia Gulf’s facility, but Kalama “did not deliver the product as
required by the contract.” Moreover, Valero maintained that it “had no prior dealings
with Georgia Gulf.” Valero blamed Kalama for the failure of delivery, asserting that
Kalama was obligated to inform Valero of the necessity of a methanol dedicated or
methanol clean barge and that “[a] buyer cannot be expected to furnish facilities with
special requirements if it does not know what the special requirements are.”
The trial court rendered summary judgment for Kalama.8
Summary Judgment Standard of Review
The purpose of the summary judgment rule is to provide a method of summarily
terminating a case when it clearly appears that only a question of law is involved and
there is no genuine issue of fact. Gaines v. Hamman, 163 Tex. 618, 626, 358 S.W.2d
557, 563 (1962). The basic standards for reviewing a motion for summary judgment
are well established. Nixon v. Mr. Property Management Co., 690 S.W.2d 546,
548-49 (Tex. 1985). The Supreme Court of Texas has mandated the following
standards:
1. The movant for summary judgment has the burden of showing
that there is no genuine issue of material fact and that it is entitled
to judgment as a matter of law.
8
The trial judge signed a general judgment, not specifying the grounds for
rendering the summary judgment.
9
2. In deciding whether there is a disputed material fact issue
precluding summary judgment, evidence favorable to the
non-movant will be taken as true.
3. Every reasonable inference must be indulged in favor of the
non-movant and any doubts resolved in its favor.
Id. When a defendant is the movant, as in the present case, we must be alert to
additional rules controlling summary judgment practice. The question on appeal, as
well as in the trial court, is not whether the summary judgment proof raises fact issues
with reference to the essential elements of the plaintiff's cause of action, but, rather,
whether the summary judgment proof establishes as a matter of law there is no
genuine issue of fact as to one or more of the essential elements of the plaintiff’s cause
of action. Gibbs v. General Motors Corp., 450 S.W.2d 827, 828 (Tex. 1970).
When a party moves for summary judgment under Texas Rule of Civil
Procedure 166a(i), on the ground that there is no evidence of one or more essential
elements of the non-movant’s claims upon which the non-movant would have the
burden of proof at trial, the movant does not bear the burden of establishing each
element of its own claim or defense. TEX. R. CIV. P. 166a(i). Rather, the non-movant
must present evidence raising a genuine issue of material fact on the challenged
elements. Id.
A no-evidence summary judgment is essentially a pretrial directed verdict, and
we apply the same legal sufficiency standard when reviewing a no-evidence summary
10
judgment as we apply when reviewing a directed verdict. Jackson v. Fiesta Mart,
Inc., 979 S.W.2d 68, 70 (Tex. App.—Austin 1998, no pet.). Our task as an appellate
court is to ascertain whether the non-movant produced any evidence of probative force
to raise a fact issue on the material questions presented. See id. We consider all the
evidence in the light most favorable to the party against whom the no-evidence
summary judgment was rendered, disregarding all contrary evidence and inferences.
Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp., 994 S.W.2d 830,
834 (Tex. App.—Houston [1st Dist.] 1999, no pet.).
A no-evidence summary judgment is improperly rendered if the non-movant
presents more than a scintilla of probative evidence to raise a genuine issue of material
fact. Greathouse v. Alvin Indep. School Dist., 17 S.W.3d 419, 423 (Tex.
App.—Houston [1st Dist.] 2000, no pet.). “More than a scintilla of evidence exists
when the evidence . . . ‘rises to a level that would enable reasonable and fair-minded
people to differ in their conclusions.’” Merrell Dow Pharms., Inc. v. Havner, 953
S.W.2d 706, 711 (Tex. 1997) (citations omitted). When the issue is one of no
evidence or conclusive evidence, the issue is a question of law. Crim Truck & Tractor
Co. v. Navistar Int’l Transp. Corp., 823 S.W.2d 591, 594 (Tex. 1992).
When both parties move for summary judgment, we review the summary
judgment evidence presented by both sides and grant the relief the trial court should
11
have granted. See Commissioners Court v. Agan, 940 S.W.2d 77, 81 (Tex. 1997).
Where, as here, the summary judgment order does not specify the grounds relied
upon, we will affirm the summary judgment if any of the grounds presented in the
motion are meritorious. See Carr v. Brasher, 776 S.W.2d 567, 569 (Tex. 1989).
Kalama’s No-Evidence Motion for Summary Judgment
In its first point of error, Valero contends the trial court erred by rendering
summary judgment for Kalama and denying summary judgment for Valero. Kalama’s
summary judgment motion claims there was no evidence Valero tendered performance
under the contract because Valero failed to provide “facilities reasonably suited to the
receipt” of the methanol. See TEX. BUS. & COM. CODE ANN. § 2.503(a)(2) (Vernon
1994). Conversely, Valero contends it did tender performance and, in its third point
of error, that Kalama was required to notify Valero that a methanol dedicated or
methanol clean barge was necessary to take delivery of the methanol.
We address the tender of performance and notification issues together because
these issues directly relate to each other and are dispositive of the case.
A. Breach of Contract
The essential elements of a breach of contract action are: (1) the existence of
a valid contract; (2) performance or tendered performance by the plaintiff; (3) breach
of the contract by the defendant; and (4) damages sustained by the plaintiff as a result
12
of the breach. Hussong, 896 S.W.2d at 326 (emphasis added). When the evidence is
undisputed regarding a person’s conduct under a contract, the court as a matter of law
determines whether the conduct shows performance or breach of a contract obligation.
Lafarge Corp. v. Wolff, Inc., 977 S.W.2d 181, 186 (Tex. App.—Austin 1998, pet.
denied).
Pursuant to the contract, Valero arranged for the Genie Cenac to pick up the
methanol at Plaquemine, Louisiana. However, SGS rejected the barge two times
because of a strong gasoline odor and standing liquid in the barge, and thus, Georgia
Gulf refused to load the methanol onto the Genie Cenac.
We must determine, under the undisputed facts, whether Valero performed or
tendered performance under the contract when the Genie Cenac arrived at Georgia
Gulf.
B. Application of the Uniform Commercial Code
The contract between Valero and Kalama is silent as to what type of barge is
required to take delivery of the methanol, so in determining whether Valero’s
production of the Genie Cenac on June 30, 1997 at Geogia Gulf constituted
performance or a tender of performance, we turn to the Uniform Commercial Code
(“U.C.C.”). See TEX. BUS. & COM. CODE ANN. §§ 2.101-2.725 (Vernon 1994 & Supp.
2001). Chapter 2 of the U.C.C. governs this contract because it is a contract for the
13
sale of goods. See TEX. BUS. & COM. CODE ANN. §§ 2.102, 2.105(a) (Vernon 1994).
The U.C.C. defines a “contract” as “the total legal obligation which results from
the parties’ agreement as affected by [the U.C.C.] and any other applicable rules of
law.” TEX. BUS. & COM. CODE ANN. § 1.201 (11) (Vernon Supp. 2001). Under the
U.C.C., “the obligation of the seller [Kalama] is to transfer and deliver and that of the
buyer [Valero] is to accept and pay in accordance with the contract.” TEX. BUS. &
COM. CODE ANN. § 2.301 (Vernon 1994) (emphasis added). In the absence of a
specified place for delivery, “the place for delivery of goods is the seller’s place of
business,” but in a contract for the sale of identified goods which the parties know at
the time of contracting are in some other place, “that place is the place for their
delivery.” TEX. BUS. & COM. CODE ANN. § 2.308 (1), (2) (Vernon 1994). Thus,
Valero, as the buyer, had the obligation to accept the methanol at Georgia Gulf.
“Tender of delivery requires that the seller put and hold conforming goods at
the buyer’s disposition and give the buyer any notification reasonably necessary to
enable him to take delivery.” TEX. BUS. & COM. CODE ANN. § 2.503(a) (Vernon
1994) (emphasis added). Kalama instructed Georgia Gulf to hold the methanol and
deliver it to Valero. During oral argument, Valero claimed this was an “imperfect”
tender because Kalama failed to notify Valero of the necessity of a methanol dedicated
or methanol clean barge. We disagree. “The manner, time, and place for tender are
14
determined by the agreement and [the U.C.C.] . . . .” TEX. BUS. & COM. CODE ANN.
§ 2.503(a) (Vernon 1994) (emphasis added). Because the material facts are not
disputed, “manner of tender,” which is the real issue in this case, is a question of law
to be decided by the court.
Pursuant to the U.C.C., “unless otherwise agreed[,] the buyer “must furnish
facilities reasonably suited to the receipt of the goods.” TEX. BUS. & COM. CODE
ANN. §2.503(a)(2) (Vernon 1994) (emphasis added).9 This obligation of the buyer,
Valero, is “no part” of the seller’s, Kalama’s, tender. TEX. BUS. & COM. CODE ANN.
§ 2.503(a)(2) cmt. 4 (Vernon 1994) (emphasis added). “‘Receipt’ of goods means
taking physical possession of them.” TEX. BUS. & COM. CODE ANN. § 2.103(a)(3)
(Vernon Supp. 2001) (emphasis added). Therefore, Valero, as a matter of law, had the
responsibility of supplying a vessel suited to taking physical possession of the
methanol.
Furthermore, “‘tender’ connotes such performance by the tendering party as
puts the other party in default if he fails to proceed in some manner.” TEX. BUS. &
COM. CODE ANN. § 2.503(a) cmt. 1 (Vernon 1994) (emphasis added). Here, Kalama
9
Facilities are defined as “[t]hat which promote the ease of any action, operation,
transaction, or course of conduct. . . . As applied to carriers, means everything
necessary for . . . the safety and prompt transportation of freight.” BLACK’S
LAW DICTIONARY 705 (4th ed. 1968) (emphasis added).
15
had Georgia Gulf hold the methanol and requested delivery to Valero; Kalama could
do no more. Kalama’s tender put Valero in default when Valero failed to physically
take possession of the methanol. Valero’s production of the Genie Cenac at Georgia
Gulf did not constitute a tender of performance because Valero was unable to take
physical possession of the methanol. Thus, Valero’s performance did not put Kalama
in default. See id.
Valero’s argument that Kalama had the responsibility to notify Valero that a
methanol dedicated or methanol clean barge was necessary to load the methanol is
without merit. Under the general definitions of the U.C.C., a person has “notice” of
a fact when:
(A) he has actual knowledge of it; or
(B) he has received a notice or notification of it; or
(C) from all the facts and circumstances known to him at the time in
question he has reason to know that it exists.
TEX. BUS. & COM CODE ANN. § 1.201(25) (Vernon Supp. 2001). A “[p]erson”
includes an “organization,” which in turn includes a “corporation.” TEX. BUS. & COM
CODE ANN. §§ 1.201(30), (28) (Vernon Supp. 2001).
We hold, under the undisputed facts of this case, that notice by Kalama to
Valero of Georgia Gulf’s methanol dedicated or methanol clean barge requirement
was not “reasonably necessary” because (1) such a barge was already needed to take
16
delivery of the methanol specified in the contract, and (2) Valero, at the very least, had
reason to know a methanol dedicated or methanol clean barge could be required. See
TEX. BUS. & COM CODE ANN. § 1.201(25)(C).
The contract in question called for the methanol to be 99.85% pure. Valero
claims it was willing to waive the required specification because it did not really
matter to Valero whether the methanol was 99.85% pure.10 However, 99.85% pure
methanol is what Valero contracted for, and, in the context of what notice was
reasonably necessary, this contract specification is dispositive.
The summary judgment proof showed that, if the methanol were loaded onto
an unclean barge, the methanol would have deviated from the contracted for
specifications. Harinder B.S. Jalli, vice president of Kalama, testified, “Valero’s barge
was contaminated with unleaded gasoline. The slightest bit of unleaded gasoline or
10
Specifically, Valero contends any contamination from gasoline remaining on
the Genie Cenac did not matter because the contract provided that “[q]uality
determination shall be made on representative samples of product taken from
the shore tank prior to delivery” and that title shall pass to Valero before the
methanol reached the barge, “at the flange connection between the vessel’s
permanent manifold connection and the shore line at Plaquemine, LA.” Valero
argues any contamination after that point would not have been Kalama’s
responsibility and would not have put Kalama in breach of the contract. This
is true, but unpersuasive. Valero does not contend Kalama knew or should
have known before this problem arose that Valero did not actually need 99.85%
pure methanol. Valero ordered that particular product, and it was reasonable
for Kalama to assume that Valero needed it as ordered and would be prepared
to receive it as ordered, rather than in a contaminated state.
17
hydrocarbon vapor would make the Methanol ASTM D1152-89 off specifications.”
Although Oliver stated in an affidavit that “insignificant levels of a different
product–for example, the gasoline puddles on the Genie Cenac–seldom cause the
methanol to be off-specification once loaded on a barge,” he testified in his deposition
that loading methanol onto a barge that was not dedicated could potentially disturb the
quality of the methanol.11 Also, Pane testified, “If you are loading methanol behind
any other cargo than methanol, it will throw the methanol off spec [sic] for pure
methanol usage.”
Logic dictates that mixture of another substance with 99.85% pure methanol
will dilute the methanol. Therefore, a methanol dedicated or methanol clean barge
was necessary to maintain the specifications contracted for by Valero regardless of the
requirements of Georgia Gulf. Why should Kalama be required to notify Valero that
Georgia Gulf required the use of a methanol dedicated or methanol clean barge when
in fact such a barge was necessary for Valero to take possession of the contracted for
99.85% pure methanol? Such notice was not “reasonably necessary.”
Additionally, Valero should have known a methanol dedicated or methanol
clean barge could be required to take delivery of the contracted for methanol. The
11
Oliver’s statement in his affidavit does not contradict his deposition because in
both he recognizes the possibility of contamination of the methanol if it is
loaded onto an unclean barge.
18
undisputed testimony of Cazes shows that Valero had dealt with Georgia Gulf prior
to this incident and that Georgia Gulf has always required the use of a methanol
dedicated or methanol clean barge to take delivery of methanol. Moreover, the
uncontradicted testimony of Pane reveals that Valero itself had previously used
methanol dedicated or methanol clean barges to transport methanol; that two of
Valero’s own refineries prefer using methanol dedicated or clean barges to transport
methanol; and that she sometimes called these refineries to check whether a barge
with another previous cargo was acceptable.
These facts, coupled with the fact that a methanol dedicated or methanol clean
barge was necessary to take possession of the methanol specifically contracted for,
demonstrate Valero had reason to know at the time in question that such a barge could
be required to take delivery of the methanol. Therefore, under the undisputed facts
of this case, we hold Kalama had no duty to notify Valero of Georgia Gulf’s
requirement that barges must be methanol dedicated or methanol clean to take delivery
of methanol. Valero had the legal responsibility of supplying a barge suited to taking
possession of the methanol, and it failed to supply a suitable barge.
Accordingly, there is no evidence to support a tender of performance by Valero,
one of the necessary elements to maintain a cause of action for breach of contract.
The trial court correctly granted Kalama’s no-evidence motion for summary
19
judgement and properly denied Valero’s motion for summary judgment. We overrule
Valero’s first and third points of error.
Because we base our holding on the undisputed facts of this case without
considering usage of trade evidence, we do not address Valero’s second point of error.
Conclusion
Although Oliver, the Valero employee who drafted the contract in question,
testified he did not know of Georgia Gulf’s requirement of a methanol dedicated or
methanol clean barge, the undisputed facts show such a barge was necessary for
Valero to take delivery of the methanol contracted for regardless of Georgia Gulf’s
requirements. Additionally, from all the facts and circumstances known to Valero at
the time, Valero had reason to know such a barge could be required. It would
contradict the U.C.C. and common sense to require Kalama to notify Valero of that
which it, as a corporation, had reason to know. To put Justice Holmes’s admonition
in full context:
As a matter of law there is nothing new in charging a party with
knowledge of what is his duty to know . . . . But the essential thing is
that whether in a roundabout or a perfectly natural way [a] statute has
said if you take the office you must take the consequences of knowledge
whether you have it or not. In most contracts men take the risk of events
over which they have imperfect or no control.
Ferry, 48 S. Ct. at 444, 277 U.S. at 95.
We affirm the judgment.
20
Terry Jennings
Justice
Panel consists of Justices Cohen, Jennings, and Duggan.12
Publish TEX. R. APP. P. 47.
12
The Honorable Lee Duggan, Jr., retired Justice, Court of Appeals, First District
of Texas at Houston, participating by assignment.
21