TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
NO. 03-05-00565-CV
CenterPoint Energy Houston Electric, LLC and
Texas Genco, LP, Appellants
v.
Public Utility Commission of Texas and
City of Houston, Appellees
FROM THE DISTRICT COURT OF TRAVIS COUNTY, 126TH JUDICIAL DISTRICT
NO. GN402478, HONORABLE SCOTT H. JENKINS, JUDGE PRESIDING
O P I N I O N
CenterPoint Energy Houston Electric, LLC and Texas Genco, LP (collectively "CenterPoint"), successors to a former integrated utility serving the Houston area, (1) appeal a district-court judgment that affirmed an order of the Public Utility Commission in a fuel reconciliation proceeding under the Public Utility Regulatory Act (PURA). (2) See Tex. Util. Code Ann. § 36.203 (West 1998). In its order, the Commission disallowed the recovery of certain fuel expenses because they were not reasonable and necessary. We affirm the judgment.
The Controversy
A fuel reconciliation proceeding is the means by which a regulated utility's reasonable and necessary fuel and purchased power expenses are finalized. Because a regulated utility, such as CenterPoint, is not permitted under PURA to automatically pass through to ratepayers its fuel and purchased power costs, it must reconcile its fuel revenues and expenses to avoid over- or under-recovery of the costs set by the Commission in the form of a fixed fuel factor.
This appeal concerns CenterPoint's request for recovery of purchased power costs under a Joint Operating Agreement ("JOA") that CenterPoint entered into with City Public Service of San Antonio ("CPS"), San Antonio's municipally owned utility, arising out of litigation and then settlement between the parties over the management of the South Texas Nuclear Project ("STP"). CenterPoint urges that the Joint Operating Agreement enabled CenterPoint and CPS to reduce their costs and that CenterPoint carried its burden in the proceedings to demonstrate that its fuel expenses during the reconciliation period were reasonable and necessary. The Commission and intervenor City of Houston contend that (i) the purpose of the Joint Operating Agreement was to settle litigation over CenterPoint's imprudent mismanagement of the South Texas Nuclear Project, (ii) the benefits of the Joint Operating Agreement are overstated, and (iii) these costs are not recoverable through CenterPoint's fuel factor and should be disallowed.
The Nature of a Fuel Reconciliation Proceeding
Instead of allowing a regulated utility to pass its actual fuel costs through to its
customers, the Commission designs a rate for the utility that takes into account projected fuel costs
in the form of a fixed "fuel factor." Tex. Util. Code Ann. § 36.203. The Commission periodically
adjusts this factor and reconciles fuel costs the utility charged using the factor against fuel costs the
utility actually incurred. See id. Section 36.203 provides for the timely adjustment of a utility's fuel
factor, with or without a hearing, and the reconciliation of a utility's fuel costs. Id. In a fuel
reconciliation proceeding, the utility carries the burden of proving that its eligible fuel expenses
during the reconciliation period were "reasonable and necessary expenses" to provide reliable service
to its customers. 16 Tex. Admin. Code § 25.236(d)(1)(A) (2004). (3)
The scope of the proceeding
includes "any issue" related to determining the reasonableness of the electric utility's fuel expenses
during the reconciliation period. Id. § 25.236(d)(2). This is CenterPoint's final fuel reconciliation, and the final fuel balance will be
included in its true-up proceeding. See Tex. Util. Code Ann. § 39.202(c) (West Supp. 2005). The
final balance from the true-up proceeding will be applied to the rates charged by CenterPoint as the
transmission and distribution provider affiliated with the former integrated utility. Id. § 39.262
(West Supp. 2005). FACTUAL AND PROCEDURAL BACKGROUND On July 1, 2002, CenterPoint filed a petition to reconcile its revenues collected under
the fuel factors with the actual fuel and purchased power costs incurred for the period August 1,
1997, through January 20, 2002. The Commission referred the application to the State Office of
Administrative Hearings for a contested case hearing before an administrative law judge. Several
parties, including the City of Houston, intervened in the proceeding, challenging CenterPoint's
claimed expenses. The parties filed a stipulation resolving certain of the claimed expenses, leaving
in dispute a total of $202 million over four issues, which were reserved for a hearing. These remaining expenses related to the recovery of CenterPoint's purchased power
costs under the JOA that CenterPoint had entered into with CPS in 1996. The Joint Operating Agreement The terms and the allocation of savings arising from the joint operations of
CenterPoint and CPS are at the core of this dispute. The JOA arose out of CPS's claim against
HL&P over its operation of the STP in which CPS had an interest. The agreement between CPS and
HL&P was executed on July 1, 1996, and resulted in CenterPoint as successor maintaining joint
operations with CPS. The JOA provided for the joint operation of the two utilities' electrical
generating systems in order to serve their combined load as a single service area. Under this joint
dispatch arrangement, excess capacity from one utility could be used to serve the other utility's
customers. At the end of each month, CPS and CenterPoint would calculate the net flow of
energy from one utility to the other. Compensation for energy used was to have two separate
components: the Production Cost Adjustment ("PCA") and a benefit-sharing payment. The PCA
was created to reimburse the party providing the energy for its costs of producing the electricity. The
benefit-sharing payment allocated a pre-determined share of the benefits of joint operation between
the parties. Under the terms of the JOA, CPS and CenterPoint were required to calculate their
individual cost of operating in the joint system and compare the joint system costs to the costs that
would have occurred had the two parties operated separately, thus determining the savings arising
from their joint operations. Joint system costs were calculated on the basis of a study designated
"Study J"; stand-alone costs were calculated on the basis of "Study S." (4) The JOA defined the total
joint operation benefit as the difference between the parties' actual costs under the joint operations
and their stand-alone costs. Under this negotiated sharing arrangement, CPS would receive 90% of
the calculated total benefit, while CenterPoint received 10%. The 90/10 allocation would continue
until CPS received $150 million in benefit payments. CenterPoint would avoid the payment of $150
million in settlement payments if the JOA produced savings in that amount for CPS. (5) In January
2000, the parties modified the benefit split for short-term transactions from 90/10 to 50/50. At the hearing, CenterPoint contended that the JOA provided it and CPS with fuel
savings through the combined economic dispatch of all the generating units owned and operated by
the two parties. Carla J. Mitcham, then President of the Texas Region for Reliant Resources, Inc.,
a majority-owned subsidiary of Reliant Energy, Inc., testified: Dispatching the systems jointly results in operational efficiencies and economies of
scale, allowing the parties to meet their respective obligations at a lower fuel cost
than would have been realized had they dispatched their systems independently. The
resultant savings in fuel costs are shared by CPS and [CenterPoint]. For the
reconciliation period, [CenterPoint]'s customers have realized a savings of
$31,415,272 due to the JOA. Mitcham explained that savings are achieved through the joint dispatch process because CenterPoint
"commits and dispatches the most economical units from both parties' available resources to meet
the joint obligations of the two systems." By jointly dispatching the two systems, both companies
are able to achieve savings in fuel and related costs. Illustrating the economic theory underlying the
joint operation of the two utility systems, she described the numerous mechanisms for achieving cost
savings through the JOA: [T]he most significant savings are realized through the increased utilization of CPS's
coal-fired units. As a general rule, coal-fired units, due to their lower fuel price, have
a much lower marginal production cost than gas-fired units. For example, if there are
two units with identical efficiency, yet one is burning coal at a price of $1.50/MMbtu
and the other is burning natural gas at $3.24/MMbtu, then the marginal cost of the
gas-fired generation is more than twice as much as the coal-fired generation. Typical
values for this example would show the coal-fired marginal cost to be $15.00/MWH
and the gas-fired marginal cost to be $32.50/MWH. During certain low load
conditions, such as the middle of the night or during the more moderate weather
months, CPS has an excess of coal-fired generation above their load obligations.
During the CPS low load periods, [CenterPoint]'s load obligations are typically high
enough that the marginal cost for [CenterPoint]'s generation portfolio is still
determined by a gas-fired unit. Using the previous marginal cost values from above,
the most economical and efficient decision is to transfer the $15.00/MWH power
from San Antonio to Houston and not generate the $32.50/MWH power. Indeed, this
is exactly what happens in the Economic Dispatch process. The resultant savings in
this example of $17.50/MWH ($32.50/MWH - $15.00/MWH) for every coal-generated MWH transferred from San Antonio to [CenterPoint] is shared by the two
parties. Under the energy planning process of the JOA, a computerized program modeling the HL&P and
CPS systems operated on an hourly basis to determine and select the most economical mix of
generating units to serve the load requirements of the companies. CenterPoint demonstrated that
both companies saved money because they had the ability to utilize power from the other's
generation facilities. When CPS was not utilizing its coal plants at full capacity, CenterPoint could
and did purchase electricity from CPS's coal plants rather than running its own gas-fired plants. Mitcham explained that savings were achieved through the JOA in other ways. From
August 1, 1997, to July 30, 2001, the rules and protocols of the Electric Reliability Council of Texas
(ERCOT) allowed CPS and CenterPoint as members to reduce their total responsive reserve
obligations by dispatching their respective control areas as one. (6) For this portion of the fuel
reconciliation period then, dispatching jointly and sharing responsive reserve obligations saved
CenterPoint's customers over $31 million of fuel costs. By the agreement, the parties agreed to "operate their respective electrical generating
systems jointly as a single control area in a manner that preserves the autonomy of the individual
utilities to serve native load while achieving savings in fuel and related costs which will benefit the
customers of both systems." The parties agreed to take no action that would frustrate the purposes
of the agreement, provided, however, that they were not restricted "from responding to external
forces or situations beyond [their] reasonable control, such as the requirements of [their] native load
or regulatory changes, in a commercially reasonable manner," giving due consideration to the
purposes and benefits of joint operation. The JOA also allowed CPS and CenterPoint to buy and sell power with third parties
and to use the jointly operated system to serve those transactions, which were categorized as either
"short-term" or "long-term." Short-term transactions were those entered into at or near the actual
time of the purchase or sale of power. Long-term transactions were those entered into with more
advance planning and often covered purchases over an extended period of time. Margins from short-term transactions were shared by CPS and CenterPoint under the JOA, while margins from long-term
transactions were kept by the party making the purchase or sale. The different treatment was based
on the assumption that short-term transactions were economical only because of the lower cost of
joint operations; otherwise, a party would have entered into the transaction in advance, based on its
own costs, and captured the entire benefit. The short-term transactions were originally subject to the
90/10 savings split. Effective January 2000, the parties agreed to share equally the profits or losses
from short-term transactions without regard to whether the $150 million in savings had been met. CenterPoint incurred, and sought to recover, $480 million in costs and benefits it paid
CPS during the reconciliation period under the JOA. This amounted to approximately $35.70/MWh.
Of the $480 million, $320 million represented CPS's fuel expenses and operation and maintenance
expenses for producing the power sold to CenterPoint. The remaining $160 million represented
CPS's 90% share of the $191 million in savings that had been achieved as a result of the joint
operations pursuant to JOA calculations. CenterPoint purchased power from approximately ninety different entities during the
fuel reconciliation period. Less than half of its power was purchased from CPS. The average price
per megawatt hour for all CenterPoint's purchased power was $35.20. Although the City did not
challenge as excessive the $35.70/MWh of the power purchased from CPS, it questioned the savings
claimed by CenterPoint through the JOA's joint dispatch process. Because the JOA was the product of a settlement of claims made by CPS against
HL&P regarding its management of the construction of the STP, the City urges that "the true purpose
of the JOA was to settle litigation over CenterPoint's imprudent management of [STP]" and to fund
its settlement with non-recoverable expenses cloaked as fuel expenses. The City assumes that any
benefit to the utility from the JOA necessarily comes at the expense of its ratepayers. The City
asserts that CenterPoint should have negotiated and received under the JOA more than 10% of the
savings, arguing that the inequitable split was the result of CenterPoint's use of the JOA to settle its
litigation with CPS. Accordingly, the City urged that the savings recognized under the JOA should
be reduced. After the hearing, the ALJ issued a proposal for decision that recommended
disallowance of $67.1 million of the $160 million that CenterPoint had paid to CPS as CPS's share
of JOA savings. The proposed disallowance was based on (i) a change and recalculation of the 90/10
split required under the JOA to a 67/33 split of the savings and (ii) a $46.8 million reduction in other
savings recognized under the JOA. The Commission's Decision The Commission issued a final order accepting this portion of the ALJ's proposal for
decision, finding that CenterPoint failed to prove that $67.1 million of its claimed expenses were
prudent and that it should not be recovered as reasonable and necessary fuel expense. Although the
Commission made no findings that the negotiated savings split was caused or influenced by the STP
settlement, the Commission found that the parties to the JOA overstated the agreement's actual
benefits and that CenterPoint paid more than it reasonably should have through the benefit-sharing
payments. The $67.1 million disallowance resulted from three adjustments to the benefits CPS
and CenterPoint had estimated under the JOA. First, the Commission found that the 90/10 split of
the relative share of the benefits was unfairly disproportionate and therefore flawed. It disregarded
the JOA allocation and reallocated the split to a 67/33 basis, with 67% allocated to CPS and 33%
to CenterPoint. This change in the split affected only the portion of the savings that, under the JOA,
were shared 90/10, leaving unaffected the equal split of short-term transactions that began on January
1, 2000. The other two adjustments of the $67.1 million concerned the total amount of joint
benefits and reduced the JOA savings by $46.8 million. The $46.8 million deduction consisted of
two parts: a $30.6 million deduction and a $16.2 million deduction. With respect to the $30.6
million, the Commission found that the JOA overstated the joint benefits attributed to short-term
sales. This figure was based on estimated benefits of short-term energy transactions that the JOA
required to be treated as joint, shared benefits. In finding of fact no. 82, the Commission determined
that it was "reasonable" to adjust CenterPoint's benefit calculation, treating these transactions as
stand-alone savings rather than as savings arising from the JOA "to reflect that benefits of short-term
energy transactions . . . were erroneously excluded" from Study S. The third adjustment relating to the total amount of joint benefits was a $16.2 million
deduction based on the finding that at certain points in time the costs of block-power purchases from
the ERCOT market were lower than the costs of operating CenterPoint's own gas-fired plants. Thus,
the Commission found that CPS and CenterPoint overestimated their Study S costs because their
calculations ignored the "probability" that they would have purchased energy in the ERCOT
wholesale market under a stand-alone operation: finding of fact no. 80 stated, "Without the JOA,
CenterPoint had opportunities to purchase economy energy from other suppliers within ERCOT." ANALYSIS By three issues, CenterPoint urges that the Commission acted arbitrarily and
capriciously and without supporting substantial evidence with regard to three aspects of the JOA:
(i) the Commission's disregard of the negotiated 90/10 split of the JOA and its reallocation to a
67/33 split; (ii) the Commission's refusal to recognize $30.6 million of savings under the JOA
because the agreement included short-term transactions in joint savings; and (iii) the Commission's
refusal to recognize $16.2 million of the savings under the JOA by finding that CenterPoint should
have calculated its stand-alone costs on the basis of block-power purchases from the ERCOT market
whenever those purchases were less than the costs of running CenterPoint's own gas-fired plants. Standard of Review This case turns on our application of the standard of review in an administrative
appeal governed by section 2001.74 of the Texas Government Code. See Tex. Gov't Code Ann.
§ 2001.174 (West 2000). We first inquire into the nature of the proceeding and the applicable
burden of proof. CenterPoint seeks to reverse findings and conclusions made by the Commission
relating to one of its core functions: the assessment of the reasonableness of a utility's claimed
expenses. A utility is entitled to recover from its ratepayers those fuel and purchased power
expenses that are "reasonable and necessary expenses incurred to provide reliable electric service
to retail customers." 16 Tex. Admin. Code § 25.236(d)(1)(A); see Tex. Util. Code Ann. § 36.051
(West 1998) (7); see also Cities for Fair Util. Rates v. Public Util. Comm'n, 924 S.W.2d 933, 935 (Tex.
1996). The parties agree that a utility seeking to pass fuel expenses to ratepayers bears the burden
of proving the reasonableness of those expenses. 16 Tex. Admin. Code § 25.236(d)(1)(A). The
Commission contends, and we agree, that in filing its petition to reconcile its fuel-related revenues
and expenses, CenterPoint assumed the obligation of demonstrating the prudence of expenses
incurred. The scope of the proceeding below allows consideration of "any issue related to
determining the reasonableness of the electric utility's fuel expenses during the reconciliation
period." Id. § 25.236(d)(2) (emphasis added). CenterPoint has challenged the Commission's decision as violative of the governing
statute and rules, as arbitrary and capricious, and as not reasonably supported by substantial
evidence. Tex. Gov't Code Ann. § 2001.174(2)(A), (D), (E), (F). Although a decision not supported
by substantial evidence may be deemed to be arbitrary and capricious, a decision may be supported
by substantial evidence and yet still be arbitrary and capricious. City of El Paso v. Public Util.
Comm'n, 883 S.W.2d 179, 184 (Tex. 1994); Starr County v. Starr Indus. Servs., Inc., 584 S.W.2d
352, 355 (Tex. Civ. App.--Austin 1979, writ ref'd n.r.e.). Under the substantial evidence rule, we give significant deference to the agency in
its field of expertise. Railroad Comm'n of Texas v. Torch Operating Co., 912 S.W.2d 790, 792
(Tex. 1995). We presume that the agency's findings, inferences, conclusions, and decisions are
supported by substantial evidence and the agency order is valid. Texas Health Facilities Comm'n
v. Charter Med.-Dallas, Inc., 665 S.W.2d 446, 453 (Tex. 1984); Southwestern Pub. Serv. v. Public
Util. Comm'n, 962 S.W.2d 207, 215 (Tex. App.--Austin 1998, pet. denied). In conducting a
substantial evidence review, we must evaluate the whole record and determine whether the evidence
as a whole, taking into account both the supporting and detracting evidence, is such that reasonable
minds could have reached the conclusion the agency must have reached in order to take the disputed
action. Texas State Bd. of Dental Exam'rs v. Sizemore, 759 S.W.2d 114, 116 (Tex. 1988). We
afford the agency's expertise substantial deference in interpreting the facts, and we may not
substitute our judgment for that of the agency on the weight of the evidence on questions committed
to agency discretion. Tex. Gov't Code Ann. § 2001.174; Cities of Abilene, San Angelo, & Vernon
v. Public Util. Comm'n, 146 S.W.3d 742, 748 (Tex. App.--Austin 2004, no pet.); City of El Paso
v. Public Util. Comm'n, 916 S.W.2d 515, 522 (Tex. App.--Austin 1995), appeal dism'd by agr.,
1996 Tex. App. LEXIS 1010 (Tex. App.--Austin Mar. 13, 1996) (Commission has broad discretion
to determine recovery of expenses in ratemaking proceeding); Southern Union Gas Co. v. Railroad
Comm'n, 692 S.W.2d 137, 141-42 (Tex. App.--Austin 1985, writ ref'd n.r.e.). CenterPoint also urges that the agency decision should be reversed because it is
arbitrary and capricious. An agency decision may be found arbitrary and capricious if it is based on
legally irrelevant factors or if legally relevant factors were not considered. City of El Paso v. Public
Util. Comm'n, 883 S.W.2d 179, 184 (Tex. 1994); Consumers Water, Inc. v. Public Util. Comm'n,
774 S.W.2d 719, 721 (Tex. App.--Austin 1989, no writ). So long as there is a rational connection
between the facts found and the agency's decision, we may not overturn the agency's action as
arbitrary or capricious. But the agency's discretion is not unbridled, and its conclusions must be drawn from
the facts. Section 2001.174 speaks of the four different ways in which an agency finding, inference,
conclusion, or decision may require reversal: the relevant action may be arbitrary, capricious,
characterized by abuse of discretion, or characterized by a clearly unwarranted exercise of discretion.
Tex. Gov't Code Ann § 2001.174(F). We reverse only when we are able to conclude from the record
as a whole that the agency did not base its finding or conclusion on a consideration of the factors
implicated in the case by applicable law or, in the alternative, that the agency did consider the
relevant factors but its choice was a clear error of judgment. The existence of the JOA does not relieve CenterPoint of its burden of demonstrating
that its fuel and purchased power expenses were reasonable and necessary. Nor does it augment this
burden. The limited nature of our inquiry underscores the burden to be borne by the utility and the
latitude in implementation and interpretation by the agency that the legislature intended in a fuel
reconciliation proceeding. This latitude, however, does not relieve us of our role in the review
process to ensure that the agency take the hard look--lest the deferential review required of us
insulates the Commission from judicial review. Reallocation of JOA 90/10 Split CenterPoint urges that the Commission acted illegally, arbitrarily and capriciously
or without substantial evidence in disallowing amounts it paid to CPS through the 90/10 JOA sharing
scheme because the agreement resulted in savings to ratepayers and therefore the expenses were
reasonable as a matter of law. The Commission responds that the evidence reflects no real savings
and fails to provide any basis for such a disproportionate sharing of benefits. The Commission
argues that it disallowed those payments that exceeded CPS's reasonable share of the benefits of
joint operation and then disregarded the JOA's savings allocation, adjusting the benefit split to
67/33. We may not ignore the elephant in the room: the controversy concerning the 90/10
split is grounded in the origins of the JOA. The Commission argues that the 90/10 split is
"inherently suspect" because the JOA was conceived for the purpose of settling the existing litigation
between CPS and CenterPoint over the STP. The Commission acknowledges that there is no finding
to this effect, but that this fact is "beyond dispute." The Commission urges that the evidence reflects
no real savings and "shows that the primary purpose for the lopsided division under the JOA was
not to save ratepayers money, but to settle existing litigation between CPS and CenterPoint."
(Emphasis added). CenterPoint urges that a contract that results in comparative savings of this amount
to ratepayers is prudent as a matter of law, particularly when the utility had no obligation to enter
into a contract of that type. It urges that it prudently negotiated and administered its contracts.
CenterPoint contends that the Commission's "fine-tuning" is inconsistent with its "limited role" in
a fuel reconciliation proceeding, and that the proceeding allows only a "narrow inquiry" to adjust
the fuel factor for the "anomalies resulting from actual, fluctuating fuel prices" that occur. See GTE
S.W., Inc. v. Public Util. Comm'n, 978 S.W.2d 161, 168 (Tex. App.--Austin 1998, pet. denied)
(Powers, J., dissenting) (contrasting fuel-reconciliation proceedings with rate cases). The ALJ characterized it thus: City of Houston contends, and CenterPoint does not necessarily dispute, that it
entered into the JOA to settle litigation claims by CPS against [CenterPoint] for
mismanagement of the construction and operation of the South Texas Nuclear Project
in the 1980's and early 1990's. City of Houston maintains that it is improper for
[CenterPoint] to recover the payments because it requires that ratepayers be required
to pay for litigation settlement costs related to HL&P's mismanagement of STP, and
the lack of verification of the costs and benefits underlying these payments. The Commission found that CenterPoint failed to justify amounts paid to CPS under
the "disproportionate 90/10 sharing scheme." In findings of fact, the Commission found that (i)
"[t]he 90/10 benefit split was based on the expectation that most of the benefits of the joint dispatch
would come from dispatching CPS's coal units," (ii) of the $191 million of benefits during the
reconciliation period, only $109.7 million--or 57%--could be attributed to CPS's coal generation,
(iii) CenterPoint "relied too heavily on the use of CPS's excess coal-fired energy in agreeing to the
90/10 benefit split," and (iv) because the 90/10 split overwhelmingly benefitted CPS, it would have
been reasonable to track the source of the benefits on a regular basis to verify the accuracy of the
split and that its inaccuracy should have been apparent from the beginning because it was based on
an incorrect assumption, i.e., the exclusion of short-term energy transactions. The Commission
found that CenterPoint was only justified in paying CPS 67% of the total benefit. CenterPoint acknowledges that the JOA arises as a result of litigation between
CenterPoint and CPS. In response to a request for information concerning the circumstances that
gave rise to the JOA, Carla Mitcham stated: As mentioned in [a prior response], the JOA was entered into as part of an agreement
by HL&P and City Public Service Board (CPS) to settle certain claims brought by
CPS against HL&P related to the South Texas Project. By jointly dispatching the
two systems, both CPS and HL&P can achieve savings in fuel and related costs for
the benefit of customers on both systems. The JOA provides significant savings
primarily through the increased utilization of CPS's coal-fired units. . . . [B]y
dispatching the systems jointly, the JOA provided savings to HL&P's ratepayers,
while also creating sufficient benefit for CPS to permit settlement and avoid the risks
of costly and protracted litigation. CenterPoint urges and the Commission found that the JOA provided CenterPoint and
CPS with fuel savings through the combined economic dispatch of the generating units owned and
operated by CenterPoint and CPS. Because the agreement brought undisputed savings to ratepayers,
CenterPoint urges that it was a reasonable contract as a matter of law, and the expenses incurred
under it were reasonable as well. The Commission responds that when CenterPoint agreed to the
JOA, it consequently assumed the obligation of demonstrating the prudence of all expenses under
the agreement and failed to do so. Because CenterPoint was engaging in an unconventional purchase
of power, and the price it would ultimately pay was not based on a typical dollars-for-megawatt-hours exchange, the Commission suggests that this series of complex calculations allowed
CenterPoint to disproportionately share benefits from the combined operations. CenterPoint's
application to reconcile its expenses thus required the Commission to review the expenses,
"including the expenses incurred each month under the JOA." The Commission urges that whether
the utility has met the burden of proving the reasonableness of its expenses is a matter within the
Commission's discretion. See Tex. Util. Code Ann. § 36.051 (authorizing the Commission to
establish rates that cover a utility's "reasonable and necessary" operating expenses.) We first address the role of the JOA in this proceeding. We agree with the
Commission's assertion that CenterPoint's expenses are not shielded from scrutiny because they
were incurred under a contract. But neither shall the expenses and consequent savings be subjected
to heightened scrutiny because they were incurred in a contract arising out of a settlement agreement
between the parties. Indeed, the existence of the agreement is a neutral fact that does not relieve
CenterPoint from its obligation to demonstrate that its expenses were reasonable and necessary and
to account for those expenses. Nor does it allow the Commission to disregard a prudently negotiated
and administered contract in which reasonable and necessary expenses were incurred. Mitcham testified that CenterPoint's fuel expenses were reasonable and necessary
expenses and that its contract negotiations produced the lowest cost of fuel to CenterPoint's
ratepayers. She explained how "dispatching the systems jointly results in operational efficiencies
and economies of scale, allowing the parties to meet their respective obligations at a lower fuel cost
than would have been realized had they dispatched their systems independently." Mitcham testified
that the JOA did not affect the manner in which CenterPoint performed its Energy Planning Process
or operated its system: The JOA has served to enhance [CenterPoint's] ability to reduce fuel expenses for
its customers. The integration of the two systems into a joint dispatch arrangement
creates an opportunity for both systems to maximize efficiency, thus reducing fuel
costs. The JOA is essentially an automated sales and purchase arrangement between
the two companies, although neither is actually obligated to sell or purchase energy
from the other. The Energy Planning Process and EMACS includes both CPS's and
[CenterPoint's] system demand and generating resources, and dispatch is governed
by the economics of the joint electrical systems. The increased efficiencies in
operation attained through the JOA could not be realized by the two parties operating
separately. She testified that, for the fuel reconciliation period, dispatching jointly and sharing responsive
reserve obligations saved CenterPoint's ratepayers over $31 million in fuel costs. She also testified that the JOA was modified to account for operational experience
and a change in methodology for sharing the benefits of third party transactions. Although section
5.3 of the JOA provided that the benefit-sharing ratio would change from 90/10 to 50/50 once CPS
received benefit payments totaling $200 million, the parties agreed to modify the agreement in
January 2000 due to concerns raised in previous fuel reconciliation proceedings. Because of these
concerns regarding the 90/10 split, CenterPoint and CPS agreed to modify the benefit sharing for
third-party marketing transactions. The benefit sharing remained at the contractually agreed upon
ratio of 90/10 for benefits realized from dispatching the systems jointly, "primarily because the bulk
of the benefits from the JOA are due to CPS's excess coal generation." The parties agreed to alter
the benefit sharing of third-party short-term marketing transactions on a 50/50 basis effective January
1, 2000. Thus, effective January 1, 2000, the benefit-sharing for third-party transactions was
recalibrated: the benefit realized by dispatching each party's generation portfolio in a joint manner
while meeting their combined obligations continued to be shared on a 90/10 ratio; the benefit
realized from each party's third-party marketing transactions was shared on a 50/50 ratio. The Commission's findings rest on the testimony of Scott Norwood, an electrical
engineer with experience in the electric utility industry, who testified on behalf of intervenor City
of Houston. Norwood testified that the JOA "appears to have been devised by HL&P as a means
to have ratepayers fund a $150 million guaranteed settlement payment to CPS in order to resolve
claims related to [CenterPoint's] mismanagement of the construction and operations of STP."
Norwood concluded that the 90/10 division was "inherently suspect" because of its origin in
litigation and that CenterPoint "likely would not have been able to recover these litigation settlement
costs through rates, and particularly not through the fuel reconciliation process." He characterized
the benefit calculations as unverified, "fundamentally flawed," and "significantly overstated." He
testified: The JOA appears to have been devised by HL&P as a means to recover STP
litigation settlement costs that otherwise would not have been recoverable from
ratepayers in light of the nature of the claim underlying these costs and the fact that
the Commission has previously disallowed a significant amount of HL&P's share of
such costs. The benefits of the JOA are estimated by HL&P using a complex
modeling process that has not been approved by the Commission. [CenterPoint]
should have sought approval of this transaction before entering into the JOA. (8) Norwood urged the Commission to address the "impropriety of charging retail customers for costs
to settle claims related to HL&P's past mismanagement of the construction and operation of STP
. . . ." Because of the "impropriety of asking ratepayers to pay for litigation settlement costs related
to HL&P's mismanagement of STP as eligible fuel, and the lack of verification of costs and benefits
underlying these payments," Norwood recommended that a 67/33 benefit-sharing ratio, with 67%
to CPS, would be more equitable. In response to a request for clarification of testimony on the issue of the 90/10 split
and Mitcham's testimony at the hearing that only 57% of the JOA benefits were actually derived by
dispatching CPS's coal units, CenterPoint responded, "At the time [CenterPoint] entered the JOA
. . ., [it] reasonably believed that a 90/10 split of JOA savings would properly reflect the anticipated
contribution of the CPS coal units." CenterPoint acknowledged that an "after-the-fact estimate"
showed that CPS coal units accounted for 57% of the total JOA benefits, but that the decision was
reasonable when made. There is no suggestion that CenterPoint sought to conceal the origin of the agreement.
The agreement itself states that it is entered into "pursuant to the settlement agreement between the
parties." That the JOA originated as a means of settling a lawsuit between the contracting parties
does not alone make it suspect, or render its terms unreasonable. CenterPoint, on the other hand, argues that a contract that results in savings to
ratepayers is prudent as a matter of law, "particularly when the utility had no obligation to enter into
a contract of that type." We do not agree that the very existence of savings renders expenses
reasonable and necessary. As CenterPoint asserts in its reply brief, "Had there been no savings but
merely a reasonable price for power purchased from CPS, CenterPoint would have been entitled to
recover these expenses as reasonable and necessary." The issue, then, is whether the fuel expenses
were reasonable and necessary and whether CenterPoint carried its burden. It is undisputed that if there had been no JOA at all, the costs to CenterPoint would
have been higher. However, a contract that results in some savings when additional savings were
available may not be prudent. The Commission's decision to reallocate the sharing benefit was
based on its conclusion that a 67/33 split was reasonable. CenterPoint urges that there is no evidence
that CPS would have agreed to terms more favorable than the JOA. Nor is there evidence that
CenterPoint could have--or should have--negotiated a similar agreement with some other utility.
The JOA is a binding agreement that CenterPoint entered into with an unaffiliated third party. Prudence does not contemplate the acceptability of a single manner of conducting
business or the reasonableness of a single price for fuel. Prudence has two components relevant
here: (i) judgment in selecting from a range of reasonable options and (ii) a timing element. It
simply cannot be--and we do not understand the Commission to argue--that CenterPoint has no
latitude in exercising its business judgment along a continuum of acceptable choices. Just as this
Court may not substitute its judgment for that of the agency, the scope of review cabins the
discretion of the agency itself to the range of "reasonable and necessary" choices--not a single
decision or even the most reasonable one. Likewise, judgment is not exercised in a vacuum, but in context. The existence of
the contract does not eliminate the reasonableness requirement but simply makes the analysis more
complex. It would place an unprecedented burden on CenterPoint to show that it could not have
negotiated a better deal. There is no evidence in the record that CPS would have agreed to anything
other than the terms of the JOA. To rely solely on the wisdom of hindsight renders the analysis
necessarily speculative. Because the reconciliation process is necessarily backward-looking,
however, CenterPoint is not relieved of its obligation to carry its burden of establishing
reasonableness; it is not shielded from the Commission's inquiry. It is incumbent on CenterPoint,
then, to carry its burden to prove that its expenses were "reasonable and necessary." That CenterPoint must establish that its fuel expenses were reasonable and necessary
does not require it to prove that it negotiated the best possible split of savings, but only that its
choices fell within a range of options within which an expense is considered reasonable and
necessary. It is not charged with knowledge of the distribution of prices in advance. To recover its
eligible fuel expenses, CenterPoint must demonstrate that such expenses were reasonable and
necessary. See 16 Tex. Admin. Code § 25.236(d)(1)(A). Utility expenses cannot be deemed
reasonable and necessary unless the utility was prudent in incurring the expenses it seeks to pass on
to its rate payers. See Gulf States Util. Co. v. Public Util. Comm'n, 841 S.W.2d 459, 466 (Tex.
App.--Austin 1992, pet. denied). The "reasonable and necessary" standard thus incorporates a
prudence review. Nucor Steel v. Public Util. Comm'n, 26 S.W.3d 742, 748 (Tex. App.--Austin
2000, pet. denied). Although we do not conclude, as CenterPoint urges, that a contract that results
in savings to ratepayers is prudent as a matter of law, neither do we conclude that the Commission
may second-guess rational decision-making aided only by its hindsight analysis. The applicable
standard "does not require perfection." Id. at 749. The parties cite to Texas Utilities Electric Co. v. Public Utility Commission, 881
S.W.2d 387 (Tex. App.--Austin 1994), rev'd in part, 935 S.W.2d 109 (Tex. 1996), in support of
their respective arguments. In Texas Utilities, the Commission reviewed TXU's fuel contracts with
its affiliates and disallowed some of the costs under those contracts. 881 S.W.2d at 412-14.
Affiliate contracts, however, are subject to greater scrutiny than other fuel and power purchase
contracts. Utilities must show "that the price to the utility is no higher than prices charged by the
supplying affiliate to its other affiliates or divisions for the same item or class of items, or to
unaffiliated persons or corporations." Id. at 412; see Tex. Util. Code Ann. § 36.058(c)(2) (West
Supp. 2005). Affiliate transactions are not at issue here. And this higher level of scrutiny for
affiliates is not the standard applied to arm's length transactions with third parties such as CPS. The
record does not show--and the Commission does not argue--that power and fuel were purchased
from third parties when the fuel was not needed, the price was too high compared to other available
contracts for fuel or power, the affiliate rules were violated, or the prices paid included charges that
were not related to the price of the power. (9) In Texas Utilities, this Court affirmed the Commission's appropriate disallowance
of some of the costs incurred in two third-party contracts because the price was too high. The costs
under a gas purchase contract with Amoco were partially disallowed because the price was
"unreasonably high given the spot price of gas at the time." Texas Utils., 881 S.W.2d at 414.
Similarly, some of the costs under a gas contract with Delhi were disallowed because the utility had
misconstrued the contract as requiring it to buy fuel when the purchase was not required and cheaper
fuel was readily available. Id. at 415. In neither of these instances did the Commission engage in
an analysis, as here, as to whether the utility could have negotiated a better price with Amoco or
Delhi. Instead, it examined purchase costs in relation to the costs of other alternative fuels available.
Thus, it based its decision on evidence of market prices in other contracts, which indicated that the
utility had unnecessarily increased customer fuel costs. Here, the elephant in the room is the Commission's conclusion that the JOA
inaccurately allocated costs between CenterPoint and CPS because it included settlement of claims
that CPS had against CenterPoint regarding its operation of the STP. Although the Commission's
Order contains no findings that give any weight to the fact that the STP claims were settled as part
of the agreement, the ALJ concluded in the PFD adopted by the Commission that the 90/10 split
concept was inextricably intertwined with the JOA: [I]t appears that initially [CenterPoint] recognized that the 90/10 split may have been
overstated because the percentages would be reduced from 90/10 to 50/50 after the
total estimated benefits exceeded $200 million. This provision supports City of
Houston's argument that the motivation for the 90/10 split was to ensure that the
JOA would provide the primary source of funding for the $150 million payment that
HL&P's shareholders were obligated to pay CPS to settle the STP litigation claims. The Commission concluded that the amount of total JOA benefits supplied from CPS
coal-fired generation, which was the original basis for the 90/10 sharing agreement, was closer to
57%. The Commission found that, of the $191 million in alleged joint benefits, only $109.7 million
or 57% could be attributed to CPS's generation. The Commission's reallocation to a 67/33 sharing
basis had a basis in the record and was not unreasonable. For its conclusion that the 67/33 split was
reasonable, the Commission relied on the testimony of Scott Norwood who testified on behalf of the
City of Houston. Norwood based his 67% allocation of benefits to CPS on his determination that
only 57% of JOA savings were derived from dispatching CPS's coal units. He concluded that the
67/33 split "more reasonably reflects the contribution of CPS coal-fired [plants] to the estimated
joint dispatch benefits." In responding to Norwood's testimony, Mitcham disputed that the actual
benefits would not support a 90/10 split. She testified that CenterPoint's reasonable expectations
had been "largely" confirmed by actual practice. Using CenterPoint's estimate of the CPS coal
benefits, Mitcham concluded that the resulting split was even closer to the 90/10 split--87½%. She
concluded, "In either case, however, the difference between HL&P's original expectations and
estimates of actual benefits is relatively small, further indicating that HL&P was relying on
reasonable expectations when it negotiated the 90/10 split." The issue is whether CenterPoint carried its burden to demonstrate that its expenses
were reasonable and necessary. CenterPoint was not required to show that it could have negotiated
a better deal, but it was required to show that the 90/10 split was reasonable under the circumstances.
We conclude that CenterPoint did not carry its burden of establishing that the 90/10 split was
reasonable. We further conclude that the evidence in the record is consistent with the Commission's
conclusion that the split should be "adjusted." The Commission's disregard of the 90/10 savings
allocation and its reallocation to a 67/33 sharing of the savings is supported by substantial evidence,
and its decision is not arbitrary or capricious. We overrule CenterPoint's first issue. Disallowances Related to Short-term Transactions and Block-Power Purchases The Commission also reduced the amount of savings attributed to the JOA by $46.8
million, composed of $30.6 million for short-term transactions and $16.2 million for block-power
purchases. CenterPoint urges that the Commission acted arbitrarily, capriciously, and without
substantial evidence in disallowing these amounts. Specifically, CenterPoint contends that the
disallowances are inconsistent with the Commission's finding that the benefits attributable to the
JOA were $191 million. 1. Short-term Transactions As to the short-term transactions, the Commission relied upon Scott Norwood's
testimony to find that the benefits calculated under the JOA should be reduced by $30.6 million for
short-term energy transactions that were erroneously excluded from the Study S stand-alone scenario.
These sales were considered "benefits" of the joint operation, and were thus "shared" under the
benefit-sharing arrangement. The Commission found that CenterPoint should have expected these
short-term sales of power under independent operations and that CenterPoint had no basis for
excluding them from its model. Because excluding these margins from Study S resulted in an
overestimation of joint benefits, the Commission disallowed the joint benefit amount. The evidence presented during the hearing on the merits establishes that CenterPoint,
in estimating the costs and benefits of the JOA, used a production cost model to compare the
hypothetical productions costs of the two systems under two scenarios, including Study J, which
simulated the joint operations of the two systems, and Study S, which simulated the production costs
of the two systems operating separately assuming that neither system made short-term energy
purchases or sales. Under the JOA, the cost differences between these two scenarios--Study S
minus Study J--were defined as benefits of joint operations and attributed entirely to the JOA. Although both CenterPoint and CPS engaged in separate short-term energy sales, it
is undisputed that income from short-term sales was excluded from Study S. Because the JOA
benefits calculation did not include short-term transactions (sales or purchases) in Study S and did
include them in the Study J scenario, the entire benefits of the transactions were attributed to the
JOA with 90% of the benefits assigned to CPS. It is also undisputed that CenterPoint had previously
engaged in such short-term energy transactions. Norwood testified that it was unreasonable for CenterPoint to exclude these
transactions from Study S given CenterPoint's historical sales of excess power and that by including
them in Study J but not Study S, CenterPoint overstated the benefits derived from the JOA. He
concluded that there should be an adjustment to total JOA benefits to remove the estimated margins
attributable to the short-term transactions. The Commission reasons that CenterPoint witness Carla
Mitcham conceded on cross examination that the JOA excluded these sales revenues despite
CenterPoint's expectation they would occur. She testified: Q: Now since we've already established that you've had some short-term
purchases, you're not here and [CenterPoint's] not saying that it didn't have or
wouldn't have expected any short-term purchases in a stand-alone dispatch, but
simply did not model for that? A: I think the answer to that is yes. In normal stand-alone operations, there were
generally purchases or sales. The JOA did not have that modeled in the
calculation, yes. Q: And I believe we talked yesterday to the extent that those are not in the Model
S, and therefore all of the benefits or savings would be attributable to the JOA,
you're essentially overstating to some extent the savings from the JOA? A: If you look at it very narrowly mathematically, yes. Q: If you look at it the way I just described it, the answer would be yes? A: Yes. Mitcham explained that she believed the exclusion was immaterial: "What you get in return for
entering into the JOA, if you look at the whole agreement, is all of these thousands of transactions
with San Antonio that in my mind produced greater savings than those separate transactions could
have produced on their own." CenterPoint urges, then, that the JOA produced savings; the
Commission urges that the benefits were overstated. In its findings of fact, the Commission found that: 75: With the onset of competition, CenterPoint had knowledge that the market
would become more active and short-term transactions would be common. 76: Before entering into the JOA, in April 1994 through March 1996, [CenterPoint]
had significant short-term economy energy sales and purchases. 78: HL&P's assumption not to include short-term energy transactions in Study S
was not reasonable given that HL&P had engaged in short-term energy
transactions before the JOA. 82: It is also reasonable to adjust [CenterPoint's] benefit calculation by $30.6
million (the amount of estimated benefits of short-term energy transactions
HL&P included in the Study J case) to reflect that benefits of short-term energy
transactions that were erroneously excluded from the Study S case. 89: Adjusting the benefit split to 67/33 is reasonable, and the adjustment reduces the
JOA expenses by a total of $67.1 million. This adjustment incorporates the
$46.8 million adjustment recommended for CenterPoint's failure to include
short-term energy transactions in the Study S [stand-alone] scenario. Because in findings of fact 77 and 84, the Commission found benefits attributable to the JOA were
$191 million, CenterPoint urges that the existence of these savings are inconsistent with the
Commission's other findings. Again, the issue turns on whether CenterPoint carried its burden to demonstrate that
an expense was reasonable and necessary. By Mitcham's testimony, CenterPoint sought to discredit
Norwood's testimony as to the definition and calculation of savings under the agreement. Contrary
to CenterPoint's assertion that Mitcham's testimony was a mere--and slight--mathematical
overstatement of benefits, the disallowance resulted from a conceptual disagreement of the parties
over the nature of the savings, a dispute the Commission is well-suited to resolve. We are
particularly mindful here that the APA expressly prohibits the re-weighing of the evidence presented
to the Commission, and we may not substitute our judgment for that of the agency on the weight of
the evidence on questions presented to the Commission's discretion. Tex. Gov't Code Ann.
§ 2001.174. The Commission did not abuse its discretion in assigning weight and credibility to
Norwood's testimony in light of the record as a whole. We conclude that substantial evidence
supports the Commission's decision regarding the short-term transactions and that its decision is not
arbitrary or capricious. Because it began equally sharing the benefits in January 2000, CenterPoint argues that
the change cures any harm from treating the transactions as joint benefits. In response to the
Commission's assertion that CenterPoint waived this point by raising it for the first time on appeal,
CenterPoint argues that this ground is encompassed within its overarching motion for rehearing. The
purpose of a motion for rehearing is to provide notice to the agency that the moving party is
dissatisfied with its final order and that an appeal will be pursued if the ruling is not altered. The
motion should therefore be sufficiently definite to apprise the agency of the error claimed. Suburban
Util. Corp. v. Public Util. Comm'n, 652 S.W.2d 358, 365 (Tex. 1983) (mere assertion in motion for
rehearing that finding unsupported by substantial evidence insufficient to preserve); Burke v. Central
Educ. Agency, 725 S.W.2d 393, 397 (Tex. App.--Austin 1987, writ ref'd n.r.e.) (mere citation to
generic statutory ground of "substantial evidence" or "arbitrary and capricious" insufficient).
Although we do not test the requisite specificity by the technical niceties of the pleading and practice
rules, the motion must (i) identify and set forth the specific fact finding, legal conclusion or ruling
complained of, and (ii) set forth the legal basis asserted by the moving party of the error that has been
committed by the agency. Hill v. Board of Trs. of the Ret. Sys., 40 S.W.3d 676, 678 (Tex.
App.--Austin 2001, no pet.). Because this ground was not raised in the motion for rehearing, the
general motion cannot be construed as encompassing or implying a complaint that the 50/50 change
cured any harm. CenterPoint failed to adduce proof that the 50/50 sharing eliminated any
overstatement of benefits. Thus, we conclude that this alleged error was not preserved for review. 2. Block-Power Purchases The Commission also found that the JOA overstated the cost of stand-alone
operations because it failed to consider the short-term wholesale power purchases CenterPoint would
have made in the stand-alone case and reasonably could have foreseen at the time the JOA was
adopted. The Commission contends that the JOA failed to take into account that the parties would
have engaged in additional third-party purchases in the wholesale market had they not entered into
the JOA and that the failure to consider such purchases resulted in an overstatement of JOA benefits.
CenterPoint asserts here, too, that the Commission's reasoning is a departure from the required
analysis for determining whether an expense is reasonable and necessary. The Commission based the disallowance on the testimony of Scott Norwood.
Norwood testified that the parties' decision to exclude short-term wholesale power purchases from
Study S was unrealistic because HL&P had a history of engaging in short-term purchases before
entering into the JOA. Thus, the profits or losses from these short-term, third-party energy
transactions should have been treated as a stand-alone benefit, that is, a profit or loss each utility
could have made on its own. Characterizing CenterPoint's modeling as "unrealistic," Norwood
testified: [T]hey've, for years and years and years, sold a lot of energy in the market and
purchased a lot of energy in the market when it's economical to do so. And what
they've done is reflected those in the joint case with the benefits of those in the joint
case and totally ignored them in terms of the short-term transactions in the stand-alone case. . . . [I]t's a very big error that blows these benefit numbers up and makes
this . . . in my view . . . unrealistic. Norwood testified that in the absence of the JOA, CenterPoint would have either produced energy
using its own gas generation units or it would have purchased the electricity on the wholesale market.
Norwood testified that in some months CenterPoint's own generation units would have been the
most cost-effective option. In other months, CenterPoint reasonably could have made money-saving
purchases from the wholesale market. These purchases were not considered in CenterPoint's Study
S analysis. Norwood calculated the $16.2 million adjustment by assuming that "the energy supplied
from CPS coal-fired generation in the joint operations case was replaced by CenterPoint's energy
purchases from the ERCOT market at average monthly on-peak prices." The Commission asserts
that this calculation resulted in a conservative estimate while CenterPoint asserts that his conclusions
are arbitrary and unreasonable. Because block-power purchases must be made in advance and in
fixed quantities for set hours over a set number of days and CenterPoint did enter into numerous
block-power purchases when the price was lower than the anticipated cost of generating the power
itself, CenterPoint urges that this does not negate that savings were achieved through the JOA. It is undisputed that the JOA gave CenterPoint access to the power available from
CPS's coal-fired plants and that it achieved savings. It is also undisputed that CenterPoint made
purchases on the wholesale market in addition to the energy it received from CPS. The Commission
concluded that a disallowance was appropriate because the parties did not include these purchases
in calculating Study S costs, the exclusion of which led to an overstatement of the benefit that
CenterPoint paid back to CPS. CenterPoint again asserts that the Commission's analysis is informed by hindsight;
the Commission concluded that, because CenterPoint had made such transactions prior to the JOA
and due to wholesale deregulation following the PURA amendments in 1995, the parties should have
anticipated that third-party purchases would have been available in increasing quantities under stand-alone operations. Thus, the Commission concluded that CenterPoint either was or reasonably should
have been aware of the facts and options at the time the agreement was entered into. Although
CenterPoint would not have known the precise amount of benefit that it could anticipate by
purchasing energy in the ERCOT market, the utility could have foreseen some increase in
transactions, and its failure to include these transactions in the stand-alone study was therefore
imprudent. We may not substitute our judgment for that of the agency and reweigh the evidence
presented to the Commission. We overrule CenterPoint's second and third issues. CONCLUSION Because the Commission's decision is supported by substantial evidence in view of
the reliable and probative evidence in the record as a whole, is not arbitrary or capricious, and
because we may not substitute our judgment for that of the agency as to the weight of the evidence,
we uphold the Commission's disallowances. In a fuel reconciliation proceeding, the utility is
seeking to avoid responsibility for fuel costs and pass them on to consumers. Thus, the burden rests
on the utility to establish that the utility itself acted reasonably. If the utility fails to carry its burden,
it cannot recover costs. The existence of savings alone does not satisfy CenterPoint's burden. The
existence of the JOA does not relieve CenterPoint of this burden. We conclude that the Commission
did not act arbitrarily and capriciously or without supporting substantial evidence in imposing the
disallowances. We overrule CenterPoint's issues and affirm the judgment of the district court. __________________________________________ Jan P. Patterson, Justice Before Justices B. A. Smith, Patterson and Puryear Affirmed Filed: June 2, 2006
1. CenterPoint Energy Houston Electric, LLC and Texas Genco, LP are successors to the
formerly integrated utility that served the Houston area and began the process of unbundling pursuant
to the Public Utility Regulatory Act in 2000. CenterPoint is now a transmission and distribution
utility and no longer generates or purchases power for resale. Texas Genco is an independent power
generation company that is no longer owned by CenterPoint. Other entities that composed the
former utility include Houston Lighting & Power Company ("HL&P"), CenterPoint Energy, Inc.,
and Reliant Energy, Inc.
2. Public Utility Regulatory Act (PURA), Tex. Util. Code Ann. §§ 11.001-66.017 (West 1998
& Supp. 2005).
3. The Rule provides for the following burden of proof and scope of proceeding in a fuel
reconciliation proceeding: (1) In a proceeding to reconcile fuel factor revenues and expenses, an electric utility has
the burden of showing that: (A) its eligible fuel expenses during the reconciliation period were reasonable and
necessary expenses incurred to provide reliable electric service to retail
customers; (B) if its eligible fuel expenses for the reconciliation period included an item or class
of items supplied by an affiliate of the electric utility, the prices charged by the
supplying affiliate to the electric utility were reasonable and necessary and no
higher than the prices charged by the supplying affiliate to its other affiliates or
divisions or to unaffiliated persons or corporations for the same item or class of
items; and (C) it has properly accounted for the amount of fuel-related revenues collected
pursuant to the fuel factor during the reconciliation period. (2) The scope of a fuel reconciliation proceeding includes any issue related to determining
the reasonableness of the electric utility's fuel expenses during the reconciliation
period and whether the electric utility has over- or under-recovered its reasonable fuel
expenses. 16 Tex. Admin. Code § 25.236(d)(1)-(2). 4. Study S included third-party transactions undertaken individually by either party, with the
party consummating the transaction retaining all the benefit of the transaction.
5. By the agreement, CenterPoint guaranteed to CPS "minimum annual payments of $10
million and a minimum in cumulative payments of $150 million for CPS's ninety percent share of
the benefits" of the agreement. The JOA provided for its term to extend for a term of ten years
"provided, however, in the event CPS has not received at least $150 million, made up of payments
for benefits of joint operation . . . then in that event joint operation will be continued. . . ." The
agreement then provided, "If CPS receives a cumulative benefit of $150 million from joint operation
prior to July 1, 2006, this Agreement shall remain in full force and effect, without any change in the
operating practices, procedures and understandings, for the remainder of the ten-year term, in order
to enable the Parties to continue to receive benefits from joint operation on the basis provided for
in this Agreement." If CenterPoint violated the agreement by selling its facilities or assets so as to
impair CPS's receipt of minimum annual and end-of-term payments, CenterPoint became
immediately liable for the $150 million minimum payment.
6. Because power is moved throughout the grid, to ensure reliability of the entire ERCOT
system, ERCOT requires connected utilities to maintain what is called "responsive" or "spinning"
reserve of generating capacity that can quickly provide power in response to a system disturbance.
To do this, utilities must have a certain amount of generating capacity up and running or "spinning"
but not actually serving customer load, thus maintaining a reserve.
7. PURA provides: "In establishing an electric utility's rates, the regulatory authority shall
establish the utility's overall revenues at an amount that will permit the utility a reasonable
opportunity to earn a reasonable return on the utility's invested capital used and useful in providing
service to the public in excess of the utility's reasonable and necessary operating expenses." Tex.
Util. Code Ann. § 36.051.
8. That CenterPoint failed to obtain advance approval of the JOA from the Commission is not
before us. Norwood asserted that CenterPoint was required to report the transaction pursuant to
PURA. See Tex. Util. Code Ann. § 14.101 (West Supp. 2005). But section 14.101 applies to
mergers and acquisitions of plants and does not apply to the JOA. See id. Moreover, the
Commission's order contains no findings regarding advance approval, and its decision cannot
therefore be upheld on this basis. See Sensitive Care, Inc. v. Texas Dep't of Human Servs., 926
S.W.2d 823, 829 (Tex. App.--Austin 1996, no writ) ("[A] reviewing court is forbidden to uphold
an agency's final decision based upon one conclusion of law when the agency rested its decision
upon a different conclusion of law stated in its final order.") In any event, CenterPoint did submit
the JOA to the Commission in a prior fuel reconciliation, but the Commission did not review it
because that proceeding was settled.
9. At an earlier point in the proceedings, CenterPoint settled an issue concerning capacity
costs, agreeing to a disallowance of $4.7 million of its purchased power costs as capacity payments.
Capacity costs are the costs of scheduling or reserving the right to obtain energy over a steady,
recurring, or predictable period of time.