NO. 07-01-0283-CV
IN THE COURT OF APPEALS
FOR THE SEVENTH DISTRICT OF TEXAS
AT AMARILLO
PANEL D
SEPTEMBER 20, 2001
______________________________
IN RE ENERGAS COMPANY, RELATOR
_________________________________
ON PETITION FOR WRIT OF MANDAMUS
Before BOYD, C.J., and QUINN and REAVIS, JJ.
In this original proceeding, relator Energas Company, seeks a writ of mandamus
requesting that we order the Honorable David L. Gleason, Judge of the 47th District Court
of Potter County, to vacate his order requiring relator to produce documents covering its
pipelines in the entire city of Amarillo for a 12-year period of time and documents relating
to the decision to cathodically protect pipelines within Amarillo for the past 30 years. For
the reasons set forth, we conditionally grant in part and deny in part the relief requested.
Relator, a public utility, is engaged in the business of supplying natural gas to
business and residential customers in the city of Amarillo and elsewhere. Forest Harvey
Miller, deceased, resided at an apartment located at 2713 West 9th Street in Amarillo. On
September 13, 1999, he was severely injured by an explosion at his apartment and died
sixteen days later as a result of burns received in the explosion. Contending that the
explosion was caused by a leaking gas main pipeline located approximately 17 feet from
the apartment, real party in interest, Mary Miller Speed, Dependent Administratrix of the
Estate of Forest Harvey Miller, Deceased (hereafter real party), filed suit in the 47th
District Court of Potter County styled Mary Miller Speed, Dependent Administratrix of the
Estate of Forest Harvey Miller, Deceased versus Energas Company, bearing cause
number 87-247-A, seeking to recover ordinary and exemplary damages. By her pleadings,
real party alleged that the injuries to Mr. Miller resulting in his death were proximately
caused by the negligence of relator as follows:
(A) failing to make sufficient inspections to discover the leaks in the main
before harm resulted to the decedent from these conditions.
(B) failing to maintain or properly utilize available monitoring equipment and
devices that would have alerted the Defendant of the dangerous gas leakage
by showing the existing gas pressure in the main.
(C) operating and maintaining the main in a dangerous and defective
condition.
(D) failure to perform proper repair and maintenance of the main.
(E) failure to stop the flow of gas through the main after learning of its
leaking condition, until the leaks could be repaired.
2
(F) failing to repair the main so as to prevent gas leaking from it, after
learning of its leaking condition.
(G) failing to warn the decedent of the peril or danger caused by the leaking
main, after learning of its leaking condition.
In addition to the allegations of ordinary negligence, real party also alleged that the
negligence of Energas was committed with malice and/or gross neglect.
In response to real party’s third request for production of documents, Energas
responded with objections on March 12, 2001.1 Real party filed her motion to compel
discovery on April 4, 2001. After a hearing, the trial court signed its order on June 7, 2001,
granting real party’s motion to compel and overruled Energas’s objections to discovery and
prayer for protection. As material here, Energas contends the trial court erred in
concluding that real party’s requests for discovery were narrowly tailored and relevant to
issues involved in the underlying case and in ordering Energas to produce documents
pertaining to the entire city of Amarillo for a 12-year period of time and documents relating
to the decision to cathodically protect2 lines within Amarillo for a 30-year period.
1
Energas complains about the ruling of the trial court on 22 requests for production.
Eleven of the requests are expressly based on 49 C.F. R. Part 192, Section 192.457 or
Section 192.465, and applicable Texas Railroad Commission Supplements, which
regulations contain provisions for cathodic protection of buried gas pipelines and pipeline
inspections to discover areas of corrosion. The remaining eleven requests relate to the
efforts of Energas to comply with the regulations.
2
Cathodic protection. A means of protecting a buried pipe against corrosion. A
current is directed onto the pipe by sacrificial annodes (metal ribbons) placed in the
ground, parallel to and connected to the pipe. Pipe will not corrode if sufficient current
flows onto the pipe. H. Williams, C. Meyers, P. Martin, B. Kramer, Oil & Gas Law, Vol 8,
3
Standard of Review
A writ of mandamus will only issue to correct a clear abuse of discretion or violation
of a duty imposed by law when there is no adequate remedy by appeal, and the relator has
the burden to present the appellate court with a record sufficient to establish the right to
mandamus. Walker v. Packer, 827 S.W.2d 833, 837-39 (Tex. 1992) (orig. proceeding).
With respect to factual matters committed to the trial court’s discretion, the appellate court
may not substitute its judgment for that of the trial court. Id. However, a review of a trial
court’s determination of controlling legal principles is entitled to much less deference. Id.
at 840. In our analysis, we “must focus on the record that was before the court and
whether the decision was not only arbitrary but also amounted ‘to a clear and prejudicial
error of law.’” In re Bristol-Myers Squibb Co., 975 S.W.2d 601, 605 (Tex. 1998).
As is common in original proceedings, the record presented here is not as complete
as a record presented after a trial on the merits. The record here consists only of (1) real
party’s original petition, (2) real party’s motion to compel responses to her third request for
production, with eight exhibits attached including Energas’s answers to some request for
admissions, objections to discovery requests, and Energas’s objections to the 22 requests
for production3 that Energas challenges here, (3) Energas’s response to real party’s motion
1998.
3
Energas challenges request numbers 4, 5, 6, 7, 8, 9, 10, 11, 13, 14, 15, 16, 17,
21, 22, 24, 30, 34, 36, 37, 38, and 41.
4
to compel, with the affidavit of David Gates, a vice president for Energas attached, (4) a
reporter’s record of the argument of counsel4 upon the presentation of the motion to
compel and Energas’s opposition to the motion, and (5) the trial court’s order.
By its sole issue, Energas contends the trial court abused its discretion in ordering
it to produce documents pertaining to the entire city of Amarillo for a 12-year period of time
and documents relating to the decision to cathodically protect lines within Amarillo for a
30-year period of time. In summary, Energas objected to production of the records
contending that the requested documents were not relevant, and were overly broad and
burdensome. Rule 192.3(b) of the Texas Rules of Civil Procedure5 provides:
(b) Documents and Tangible Things. A party may obtain discovery of the
existence, description, nature, custody, condition, location, and contents of
documents and tangible things (including papers, books, accounts,
drawings, graphs, charts, photographs, electronic or videotape recordings,
data, and data compilations) that constitute or contain matters relevant to the
subject matter of the action. A person is required to produce a document or
tangible thing that is within the person’s possession, custody, or control.
Because the rule requires that documents and tangible things must be relevant to the
subject matter of the action, we first address the question of relevance.
4
See Kern v. Gleason, 840 S.W.2d 730, 734 (Tex.App.--Amarillo 1992, no pet.)
(holding that argument of counsel is not evidence).
5
All rule references herein are to the Texas Rules of Civil Procedure.
5
Relevance
As summarized above, the underlying action was commenced following a gas
explosion at 2713 West 9th Street in Amarillo resulting in fatal injuries to Forest Harvey
Miller. By answers to request for admissions, Energas admitted:
• it owned and operated the low pressure steel main located at or near
2713 West 9th Street involved in the lawsuit;
• a leak detection survey performed in August 1998 on the system
which included the line at or near 2713 West 9th Street found over 80
leaks over an area of approximately three square miles;
• there was no cathodic protection and no effective external coating on
the low pressure steel main located at or near 2713 West 9th Street
on September 13, 1999;
• that on September 13, 1999, or within a day or two thereafter, the low
pressure steel main located at or near 2713 West 9th Street, was
found to have active external corrosion with holes and large-scale
pitting; and
• that soon after September 13, 1999, Energas replaced the low
pressure steel main located at or near 2713 West 9 th Street with
polyethylene pipe.
Although the first 11 of the challenged production requests expressly reference sections
192.457 and 192.465 of Title 49 of the Code of Federal Regulations,6 and the following
requests also seek documents within the context of cathodic protection and inspection of
buried lines, Energas did not object on the grounds that sections 192.457 and 192.465 did
not apply to the subject line or otherwise question the applicability of the regulations.
6
All regulation references herein are to Title 49 of the Code of Federal Regulations.
6
Although Energas contends here that relevant information is limited to the history of the
particular line serving 2713 West 9th Street, it does not argue or contend that records
relating to Energas operations in the context of section 192.457 entitled “External
corrosion control: Buried or submerged pipelines installed before August 1, 1971,” or
section 192.465 entitled “External corrosion control: Monitoring” are not relevant.
Moreover, based upon this record, records applying to “the particular line serving 2713
West 9th Street,” may include records of Energas operations as they relate to the
regulations. Considering the admissions of Energas and the absence of any objection or
evidence in this record questioning the applicability of the regulations, we conclude that
sections 192.457 and 192.465 are facially relevant to the claims of real party and,
accordingly, the trial court did not abuse its discretion in holding that the relevancy
requirement of Rule 192.3(b) was satisfied.
Overly Broad and Burdensome
The discovery rules do not contemplate the exclusion of relevant evidence unless
the evidence sought is unfairly prejudicial, privileged, or incompetent. Further,
discoverable information is also limited by legitimate interests of opposing parties such as
avoiding harassment or overly-broad requests. Kern v. Gleason, 840 S.W.2d 730, 736
(Tex.App.--Amarillo 1992, no pet.). While discussing the new discovery rules, in In re
Alford Chevrolet-Geo, 997 S.W.2d 173, 181 (Tex. 1999), the Court held:
7
A party resisting discovery, however, cannot simply make conclusory
allegations that the requested discovery is unduly burdensome or
unnecessarily harassing. The party must produce some evidence
supporting its request for a protective order.
Rule 192.4 allows the trial court to limit discovery if it determines that:
(a) the discovery sought is unreasonably cumulative or duplicative, or is
obtainable from some other source that is more convenient, less
burdensome, or less expensive; or
(b) the burden or expense of the proposed discovery outweighs its likely
benefit, taking into account the needs of the case, the amount in
controversy, the parties’ resources, the importance of the issues at stake in
the litigation and the importance of the proposed discovery in resolving the
issues.
The affidavit of David Gates is the only evidence provided by Energas to support its
objections to the requested discovery. As material here, the affiant states:
(a) In the City of Amarillo, Energas has approximately 5,062,906 total feet,
or 958.88 miles, of gas mains.
(b) Energas performs leak surveys on its pipe in the City of Amarillo as
frequently as twice per year ranging to a maximum time of five years
between surveys. The frequency of leak surveys depends upon the type of
pipe and the area being surveyed.
(c) Energas, in responses to discovery, has provided Plaintiff with
documents relating to leak surveys, leaks found and repaired reports, and
cathodic protection in an area with a 500 yard radius from 2713 West 9 th
Street, Amarillo, Texas, which is the site of the incident in question. To
require Energas to respond to Plaintiff’s requests aimed at the City of
Amarillo as a whole would burden Energas and its personnel, in that Energas
8
would incur travel expenses plus work time that is lost, in addition to the
expense of locating and copying thousands of pages of documents.
(Emphasis added). Significantly absent from the affidavit is any evidence that the
requested records are cumulative or duplicative or supporting the grounds for limiting
discovery set forth in Rule 192.4(b). Although the statement in (a) from Gates’s affidavit
constitutes a fact statement concerning the size of the Energas system in Amarillo, the
statement in (b) does not implicate Energas’s claims that the requests for production were
overly broad and burdensome. Moreover, the statement that pipe is inspected twice per
year is no evidence of Energas’s practice ten years before the explosion on September 13,
1999. The first portion of (c) of the affidavit does not address the question of
burdensomeness or that the requests are overly broad, and the emphasized portion of (c)
constitutes only a conclusory allegation that production of the requested documents would
be burdensome, contrary to In re Allford Chevrolet-Geo, 997 S.W.2d at 181. Further, the
affidavit does not address or discuss 49 C.F.R. § 192.465, which provides in part that:
(a) Each pipeline that is under cathodic protection must be tested at least
once each calendar year, but with intervals not exceeding 15 months . . . .
At least 10 percent of these protected structures, distributed over the entire
system must be surveyed each calendar year, with a different 10 percent
checked each subsequent year, so that the entire system is tested in each
10-year period.
It is significant to note that the regulation contemplates that “the entire system,” or as
presented here, the entire city of Amarillo, be inspected at least every ten years.
9
The fact that a discovery request is burdensome is not enough to justify protection;
“it is only undue burden that warrants nonproduction.” ISK Biotech Corp. v. Lindsay, 933
S.W.2d 565, 568 (Tex.App.--Houslton [1st Dist.] 1996, no pet.). See also In re Alford
Chevrolet-Geo, 997 S.W.2d at 181 (requiring demonstration of undue burden or
harassment). Accordingly, we conclude the trial court did not abuse its discretion in
directing that the records be produced covering the entire system of Energas in Amarillo.
We now turn to the question regarding the period of time for which record
production should be required. Most of the requests for production were tailored to require
production of records ten years prior to the explosion and from the date of the explosion
to the time of record production. However, requests 4, 17, and 24 did not contain any time
limitation for record production.7 As to requests 4 and 17, the trial court limited record
production to the ten years before the explosion. However, as to request 24, whether by
oversight or otherwise, the trial court did not impose any time limitation. Therefore, under
the order Energas is required to produce all documents regarding its decision to
cathodically protect lines within Amarillo that were installed prior to 1971 without any time
limitation.
7
Request number 30 does not expressly include a time limitation; however, the
deposition referenced in the request demonstrates that records since 1995 would be
sufficient to satisfy the request.
10
In Texaco, Inc. v. Sanderson, 898 S.W.2d 813, 815 (Tex. 1995), the plaintiffs
sought to prove a general “corporate strategy to ignore safety laws.” Although
acknowledging the plaintiffs’ rights to discover evidence of safety policies and practices,
the Court held that a request for records “without limitation as to time, place or subject
matter, is overbroad.” Then, in In re American Optical Corp., 988 S.W.2d 711, 713 (Tex.
1998), the Court held that requiring production of records for a 50-year period was an
abuse of discretion. Although the court recognized that parties must have some latitude
in fashioning discovery requests, the right is not unlimited and “[t]he trial court must make
an effort to impose reasonable discovery limits.” (Emphasis added). Id.
Considering that the trial court set a pattern of limiting record production to the ten
years prior to the explosion, and that 49 C.F.R. § 192.465(a) anticipates that the entire
system is to be tested during each 10 year period, we conclude the trial court abused its
discretion by not making an effort to impose reasonable discovery limits as to requests 24,
as it did with requests 4 and 17.
Accordingly, the writ of mandamus is conditionally granted in part and denied in
part. Although we have jurisdiction to direct the trial court to proceed to make an effort to
impose reasonable discovery limits, we may not tell the court what limits it should enter.
In re Martinez Ramirez, 994 S.W.2d 682, 684 (Tex.App.--San Antonio 1998, no pet.). The
trial court is directed to consider and determine, in the exercise of its discretion, the need
for reasonable discovery limits as to requests for production 24; otherwise, the writ is
denied. The writ will issue only if the trial court fails to comply with these instructions.
11
Don H. Reavis
Quinn, J., concurring. Justice
Publish.