Danny Vaughan and Kathleen Vaughan v. Ross Phillips D/B/A Ready-Homes & On-Site Construction

Court: Court of Appeals of Texas
Date filed: 2008-04-30
Citations:
Copy Citations
Click to Find Citing Cases
Combined Opinion
                                         NO. 07-06-0208-CV

                                  IN THE COURT OF APPEALS

                          FOR THE SEVENTH DISTRICT OF TEXAS

                                            AT AMARILLO

                                               PANEL D

                                       APRIL 30, 2008
                              ______________________________

                      DANNY VAUGHAN AND KATHLEEN VAUGHAN,

                                                                          Appellants

                                                    v.

                     ROSS PHILLIPS d/b/a READY-BUILT HOMES AND
                              ON-SITE CONSTRUCTION,

                                                          Appellee
                            _________________________________

               FROM THE 110TH DISTRICT COURT OF BRISCOE COUNTY;

                     NO. 3100; HON. JOHN R. HOLLUMS, PRESIDING
                              _________________________

                                      Memorandum Opinion
                                   ________________________

Before QUINN, C.J., and CAMPBELL and PIRTLE, JJ.

        This lawsuit involves the construction of a pre-built home by Ross Phillips /d/b/a

Ready-Built Homes and On-Site Construction (Phillips) for Danny and Kathleen Vaughan

(the Vaughans).1 When the Vaughans failed to pay Phillips the remainder due under the

contract, he filed a lien against the property and sued for breach of contract. The



        1
         The m ajority of the hom e was assem bled at Phillips’ work site and then m oved to property owned
in the country by the Vaughans where it was com pleted.
Vaughans counterclaimed alleging that Phillips failed to build and complete the home in

a good and workmanlike manner. Upon trial by a jury, judgment was entered effectively

denying all litigants the recovery of monetary damages.2 Both the Vaughans and Phillips

perfected an appeal. We reverse and remand in part and affirm in part.

       Vaughans’ Appeal

       Issue One

       The Vaughans initially contend that the jury’s answer to jury question two should be

disregarded. That question pertained to the identity of the litigant who first breached the

contract. The Vaughans believe that the answer should be disregarded because their

opponent judicially admitted, via his pleadings, that their breach occurred after his. We

overrule the issue.

       Through jury issue one of the charge, the trial court asked the jury to determine who

breached the construction contract. The choices given were Danny Vaughan, Kathleen

Vaughan, and Phillips; furthermore, all three were found to have materially breached the

agreement. Via the next question, the jury was asked to identify who materially breached

first. It found that both Vaughans did. This answer should be disregarded, according to

the Vaughans, because Phillips represented, in his live pleading that 1) “[o]n September

23, 2004, the Vaughans informed [him] that they would not allow [him] to continue

construction,” 2) he “fully performed his obligations under the Contract to the extent

allowed by” the Vaughans, and 3) “the Vaughans prevented [his] completion of his work

. . . by locking [him and his contractors] out” and representing that “no other work would be


       2
           The Vaughans were awarded an offset in the am ount of $51,680 against what they owed to Phillips.



                                                      2
allowed by Phillips on the Houses.” These averments purportedly constituted a judicial

admission that the Vaughans did not breach the agreement until September 23, 2004,

which date allegedly fell after the July 2004 conversation wherein Phillips stated that he

was ceasing work.

       That factual statements uttered in pleadings may constitute judicial admissions is

beyond doubt. See Horizon/CMS Healthcare Corp. v. Auld, 34 S.W.3d 887, 905 (Tex.

2000) (defining judicial admission as including factual statements in pleadings). Yet, to be

such an admission, the utterance must be clear, deliberate, and unequivocal. Id. If so,

then the admission pretermits the introduction of contrary evidence and relieves the jury

from having to address whether the admitted fact actually arose or occurred. Id. With that

in mind, we turn to the wording at issue and immediately note that it says nothing about

anyone breaching the contract first. Nor do the words suggest the absence of any other

breach committed by the Vaughans before September 23, 2004; indeed, any suggestion

to the contrary would be quickly dispelled by Phillips’ earlier averment regarding their

failure to make payments per the agreement. And, this allegation about payment is of

import given Phillips’ characterization of the breach as encompassing both his inability to

continue due to their action and their non-payment. So, when taken in context, we cannot

say that the allegations considered to be admissions by the Vaughans clearly, deliberately

and unequivocally illustrate that Phillips breached the contract first. So, those allegations

did not bar the trial court from submitting question two to the jury.




                                              3
       Issue Two

       Next, the Vaughans contend the trial court erred in denying them attorney’s fees.

They believed themselves entitled to same under §38.001 of the Civil Practice and

Remedies Code and §53.156 of the Property Code. We overrule the issue.

       As suggested by the Vaughans, a prevailing party may indeed recover attorney’s

fees under §38.001 of the Civil Practice and Remedies Code when suing upon a contract.

TEX . CIV. PRAC . & REM . CODE ANN . §38.001(8) (Vernon 1997). And, they did allege causes

of action against Phillips sounding in contract. However, the jury awarded them no

damages, and this is fatal to their issue. Green International v. Solis, 951 S.W.2d 384, 390

(Tex. 1997) (requiring the recovery of damages as a prerequisite to the recovery of

attorney’s fees under §38.001). And, we reject their proposition that because they need

not pay Phillips the remainder of the contract price they were effectively awarded damages.

The two are just not the same thing; escaping liability differs from obtaining affirmative

monetary relief.

       As for the request implicating the Property Code, §53.156 states that in a case to

foreclose on a lien or to declare a lien invalid, “the court may award costs and reasonable

attorney’s fees as are equitable and just.” TEX . PROP. CODE ANN . §53.156 (Vernon 2007)

(emphasis added). By use of the word “may,” however, the legislature made the award

discretionary on the part of the trial court; simply put, it need not award costs of fees even

to a prevailing party. Texas Wood Mill Cabinets, Inc. v. Butler, 117 S.W.3d 98, 107 (Tex.

App.–Tyler 2003, no pet.); World Help v. Leisure Lifestyles, Inc., 977 S.W.2d 662, 685

(Tex. App.–Fort Worth 1998, pet. denied). Given this, we cannot say that the trial court



                                              4
erred in denying the Vaughans such fees at bar, especially since the jury found that they

had indeed breached their contract with Phillips.

       Issue Three

       Finally, the Vaughans argue that the trial court erred in failing to submit a question

to the jury on detrimental reliance as an independent basis for recovering damages. We

overrule the issue.

       Noticeably absent from the Vaughans’ argument is citation to authority indicating

that detrimental reliance is an independent cause of action entitling one to damages. This

is especially troublesome because detrimental reliance normally does not constitute an

independent cause of action entitling one to monetary recovery. See University of Texas

Sys. v. Courtney, 946 S.W.2d 464, 468 (Tex. App.–Fort Worth 1997, writ denied) (stating

that detrimental reliance is not an independent tort). Rather, authorities treat it as an

equivalent to contractual promissory estoppel, id., or as an element of promissory estoppel.

Ludman v. Pacific Southwest Bank, F.S.B., No. 05-96-01128-CV, 1998 Tex. App. LEXIS

7516 (Tex. App.–Dallas 1998, no pet.) (not designated for publication). Moreover, the

Vaughans did not seek the submission of a question on promissory estoppel.

Consequently, we cannot say that the trial court erred in submitting the question.

       Phillips’ Appeal

       Issue One

       In the first of two issues, Phillips contended that the jury’s answer to a subsection

of Question No. 4 lacked evidentiary support, and because it did, the ultimate answer

provided by the jury was similarly deficient. We sustain the issue.



                                             5
       Through question four, the jury was asked to assess the amount of money that

would compensate Phillips for the damages suffered from the Vaughans’ breach of

contract. Among the various indicia it was directed to consider in arriving at the sum was

a provision asking the factfinder to determine the “reasonable and necessary cost of

complet[ing]” the construction project. The jurors found that sum to be $51,680. Phillips

questioned that finding since, in his view, no evidence appears of record illustrating that

the work and charges upon which the sum was based were reasonable and necessary.

       Completion costs must be reasonable and necessary to be recoverable. Mustang

Pipeline Co. v. Driver Pipeline Co., 134 S.W.2d 195, 200 (Tex. 2004). Furthermore,

evidence of what one paid or was charged to complete a project is no evidence that either

the payment or charge was reasonable and necessary. Id. at 200-201. And, therein lies

the problem here. The Vaughans proffered evidence that another contractor would charge

them approximately $75,000 to repair the deficiencies in construction and complete the

project. Yet, whether those charges were “reasonable” went undeveloped. The contractor

did not so testify; nor did anyone else familiar with the repairs purportedly needed to be

done. Again, the Vaughans merely tendered evidence of what one contractor would

charge them. And, if Mustang Pipeline is to be followed, we cannot but conclude that such

information constitutes no evidence of reasonableness.

       On the other hand, we cannot agree with Phillips’ proposition that he proved as a

matter of law that the reasonable and necessary expense of completion equaled $2500.

This is so because testimony appears of record illustrating that the work contemplated in

deriving that sum omitted other work thought necessary by other witnesses. For instance,



                                            6
witness Tillery opined that the home’s foundation had to be repaired as well, but that task

was omitted from the $2500 estimate provided by Phillips.3 Thus, the jury was free to

reject that sum as being indicative of the reasonable and necessary cost of completion.

        Given that one of the several elements upon which the jury’s answer to question

four depended lacked evidentiary support, we must conclude that the ultimate answer was

similarly deficient. And, because no evidence appears of record which would entitle us to

determine the accurate sum as a matter of law, we have no choice but to remand the topic.

So too must the issue of breach be remanded given that liability was disputed. TEX . R.

APP. P. 44.1(b) (stating that an appellate court cannot remand solely on the issue of

unliquidated damages if liability was disputed).

        Issue Two

        Through his second issue, Phillips contends that the trial court erred in denying him

attorney’s fees. Yet, in view of the record before us, we cannot say that he prevailed on

any claim entitling him to such fees at this point. Consequently, we overrule the issue.

        We reverse those portions of the judgment denying Phillips recovery against the

Vaughans for breach of contract and according the Vaughans an offset of $51,680,

remand the issues of whether the Vaughans breached the contract and the damages

arising from the breach to the trial court, and affirm the remainder of the judgment.



                                                                  Brian Quinn
                                                                  Chief Justice


        3
          W hile Tillery m ay not have been an “expert,” as argued at trial, one need not always be an expert
to proffer relevant inform ation about the necessity of house repairs. McGalliard v. Kuhlmann, 722 S.W .2d
694, 697 (Tex. 1986).

                                                     7