Verizon Corporate Services, Corp. F/D/B/A Verizon Logistics v. Kan-Pak Systems, Inc.

                                  NO. 07-08-0165-CV

                             IN THE COURT OF APPEALS

                      FOR THE SEVENTH DISTRICT OF TEXAS

                                     AT AMARILLO

                                        PANEL A

                                  JUNE 30, 2009
                         ______________________________

                 VERIZON CORPORATE SERVICES CORP. F/D/B/A
                       VERIZON LOGISTICS, APPELLANT

                                           V.

                        KAN-PAK SYSTEMS, INC., APPELLEE
                       _________________________________

            FROM THE 96TH DISTRICT COURT OF TARRANT COUNTY;

              NO. 96-223905-07; HONORABLE JEFF WALKER, JUDGE
                       _______________________________


Before CAMPBELL and HANCOCK and PIRTLE, JJ.


                                        OPINION


      Appellant, Verizon Corporate Services Corp., appeals the granting of summary

judgment in favor of appellee, Kan-Pak Systems, Inc. The judgment awarded Kan-Pak

actual damages in the amount of $97,464, attorney fees of $8,000, court costs, and post-

judgment interest at the rate of 8.25 percent per annum. Verizon further contends that the

trial court erred in denying Verizon’s motion for summary judgment. We reverse and

remand.
                                        Background


       In 1999, Verizon hired GLM to manage and oversee waste management at

Verizon’s Texas facilities. As part of the agreement by which Verizon hired GLM, Verizon

authorized GLM to review its current waste management and to negotiate leases with

vendors for waste management services. However, Verizon expressly denied GLM the

authority to enter into contracts on Verizon’s behalf. In addition, Verizon supplied GLM

with a letter of authorization to present to potential vendors that specified that GLM was

authorized to “act on behalf of Verizon to obtain information on waste removal and

recycling” and to “negotiate rates, service levels, and commodity rebates for the benefit of

Verizon.” However, this letter also expressly provided that, “GLM is not authorized to enter

into any agreement for service(s). Any negotiated rates, services levels, and commodity

rebates will be subject to review and final approval by [Verizon].”


       Between July 1999 and June 2002, a GLM employee negotiated and entered into

five rental contracts with Kan-Pak. According to these contracts, the GLM employee

entered into these contracts on behalf of Verizon. The five rental contracts were nearly

identical in their terms. Of particular relevance to the present appeal, each rental contract

was for a term of 60 months and contained an automatic renewal clause that would renew

the contracts for an additional 60 month period unless written notice of termination was

received by the other party no less than 60 days prior to the expiration of the current term.


       Kan-Pak supplied compactors to the five Verizon facilities covered under the

separate rental contracts. Either GLM or Verizon paid the monthly rental payments called


                                             2
for under the rental contracts until September 2006.          From September 2002 until

September 2006, Verizon received copies of all invoices covered by each of the five rental

contracts. In September 2004, Verizon contacted Kan-Pak about two of the locations

covered by the rental contracts requesting that half of the equipment be removed and that

the corresponding billing amount be decreased to reflect this change. Kan-Pak complied

with this request.


       In August 2006, Verizon informed Kan-Pak that it should submit its billing to Allied

Waste. Kan-Pak obliged and began to receive payments from Allied on four of the five

rental contracts.1 The reason for this change was that Verizon had terminated its waste

management consultation relationship with GLM and had retained Allied to perform this

task. As part of reviewing Verizon’s waste management, Allied discovered the rental

contracts that GLM had entered into with Kan-Pak. In December 2006, Allied forwarded

a copy of these rental contracts to Verizon. Verizon contends that the receipt of these

contracts in mid-December 2006 was when they became aware that such contracts existed

and was the first time that they saw the terms of the contracts. In February 2007, Verizon

contacted Kan-Pak by phone and advised Kan-Pak that Verizon had just discovered the

rental contracts and did not believe that it was bound by the contracts. Verizon asked Kan-

Pak to remove the compactors from all five facilities. Initially, Kan-Pak agreed, but, the day

before it was to remove the compactors, Kan-Pak told Verizon that it was going to stand

by the terms of the rental contracts. In a letter dated April 25, 2007, Verizon notified Kan-


       1
        There is some dispute regarding the extent to which Allied made payments under
the rental contracts, however, for purposes of this appeal, we conclude that this factual
issue is not material.

                                              3
Pak that it was to remove all equipment from the five sites covered by the rental contracts

and that these rental contracts were terminated.


       As a result of receiving Verizon’s termination letter, Kan-Pak filed the present action.

Kan-Pak’s petition alleges that Verizon breached the rental agreements because its

termination letter was received after each of the five rental agreements had automatically

renewed for new 60 month periods. After discovery, both parties moved for summary

judgment. In its motion, Kan-Pak contends that Verizon breached the rental contracts,

ratified the rental contracts, and is estopped from challenging the validity of the contracts.

By its motion, Verizon contends that the rental contracts are unenforceable against it

because GLM lacked either actual or apparent authority to contract on behalf of Verizon,

Verizon did not ratify the rental contracts, and Verizon is not estopped from challenging the

validity of the contracts. The trial court granted Kan-Pak’s summary judgment, denied

Verizon’s summary judgment, and awarded Kan-Pak $97,464, attorney fees of $8,000,

court costs, and post-judgment interest at the rate of 8.25 percent per annum.


       Following entry of summary judgment, Verizon filed a motion for new trial

challenging the amount of the award of actual damages assessed by the trial court as well

as whether Kan-Pak had established ratification or estoppel as a matter of law. As it

relates to the amount of damages awarded, Verizon contends that the award was improper

as a matter of law because future payments under the rental contracts were not discounted

to present value. The trial court denied Verizon’s motion.




                                              4
       On appeal, Verizon presents two issues. By its first issue, Verizon contends that

the trial court erred in granting summary judgment in favor of Kan-Pak and in failing to

grant summary judgment in favor of Verizon. By its second issue, Verizon contends that

the trial court erred in denying Verizon’s motion for new trial because Kan-Pak’s evidence

is legally insufficient to support the award of actual damages in the summary judgment.


                                    Summary Judgment


       Verizon contends that the trial court erred in granting Kan-Pak’s motion for summary

judgment and in denying Verizon’s motion for summary judgment. Specifically, Verizon

contends that the evidence raised a genuine issue of material fact as to each of the

grounds upon which Kan-Pak sought summary judgment: ratification and equitable

estoppel. Furthermore, Verizon contends that it is entitled to summary judgment because

it established, as a matter of law, that the rental contracts were not binding on Verizon and,

therefore, there was no enforceable contract upon which Kan-Pak could assert its breach

of contract action.


       When both parties to a suit move for summary judgment, each party bears the

burden of establishing that it is entitled to judgment as a matter of law. City of Garland v.

Dallas Morning News, 22 S.W.3d 351, 356 (Tex. 2000). When the trial court grants one

party summary judgment and denies the other, we review both parties’ summary judgment

evidence, determine all questions presented, and render the judgment the trial judge

should have rendered. FM Props. Operating Co. v. City of Austin, 22 S.W.3d 868, 872

(Tex. 2000). When the trial court does not specify the basis on which it granted summary


                                              5
judgment, the judgment will be affirmed on any meritorious ground expressly presented in

the motion and which is preserved for appellate review. State Farm Fire & Cas. Co. v.

S.S., 858 S.W.2d 374, 380 (Tex. 1993).


         Verizon moved for summary judgment on both traditional and no-evidence grounds,

while Kan-Pak’s motion asserted only traditional summary judgment grounds. See TEX .

R. CIV. P.166a. We review a summary judgment de novo to determine whether the movant

has established its right to summary judgment as a matter of law. See Dallas Cent.

Appraisal Dist. v. Cunningham, 161 S.W.3d 293, 295 (Tex.App.–Dallas 2005, no pet.). In

reviewing a summary judgment, we must examine the entire record in the light most

favorable to the nonmovant, indulging every reasonable inference and resolving any

doubts against the motion. See City of Keller v. Wilson, 168 S.W.3d 802, 824-25 (Tex.

2005).


Enforceability of the Rental Contracts


         Verizon contends that it is entitled to summary judgment because it established, as

a matter of law, that GLM had no authority to enter into contracts on Verizon’s behalf and,

therefore, the rental contracts are not enforceable against Verizon.2




         2
          We are aware that, even if the rental contracts are not enforceable against Verizon
based on GLM’s lack of authority, the rental contracts would be enforceable if Verizon
ratified the contracts or was equitably estopped from denying the validity of the contracts.
We will address those issues below. In this analysis, our review is limited to whether a fact
issue was raised as to whether GLM had the actual or apparent authority to bind Verizon
by entering into the rental contracts on its behalf.

                                              6
       An agent cannot bind a principal unless the agent has actual or apparent authority

to do so. See Lifshutz v. Lifshutz, 199 S.W.3d 9, 22 (Tex.App.–San Antonio 2006, pet.

denied). Actual authority arises when the principal intentionally confers authority upon the

agent or intentionally or by want of ordinary care allows the agent to believe he has

authority. See id. Apparent authority exists when the principal’s acts would lead a

reasonably prudent person to believe that the agent had authority to act on behalf of the

principal, the principal has either affirmatively held out the agent as possessing authority

or knowingly and voluntarily permitted the agent to act in an unauthorized manner, and the

party relying on the agent’s apparent authority must have ascertained the fact and scope

of the agent’s authority. See Tex. Cityview Care Ctr., L.P. v. Fryer, 227 S.W.3d 345, 353

(Tex.App.–Fort Worth 2007, pet. dism’d by agr.). Only the actions of the principal can give

rise to apparent authority; actions or representations of the agent have no effect on the

determination. See id. Under either theory, the party alleging agency has the burden to

prove its existence. Id. at 352.


       In the present case, there is no evidence in the record that would raise a fact issue

as to whether GLM had actual authority to contract on behalf of Verizon. The only

evidence relating to the actual authority that Verizon intentionally conferred on GLM is the

Waste Removal and Recycling Consultant Agreement between Verizon and GLM and a

letter of authorization that Verizon gave to GLM to present to potential vendors. Each of

these documents expressly provide that GLM was not authorized to enter into any

agreement or contract for services. Because this right was expressly denied GLM, we

cannot conclude that Verizon intentionally conferred authority to contract to GLM,


                                             7
intentionally allowed GLM to believe that it had authority to contract on behalf of Verizon,

or that Verizon failed to exercise the degree of care necessary to prevent GLM from

believing that it had authority to contract on behalf of GLM. Thus, we agree with Verizon’s

summary judgment contention that it established, as a matter of law, that GLM did not have

actual authority to contract on Verizon’s behalf and, thus, Kan-Pak’s breach of contract

claims cannot be founded on the basis of GLM’s actual authority to enter into the rental

contracts on Verizon’s behalf.


       As to GLM’s apparent authority, we are constrained to review only the evidence of

the actions of Verizon in determining whether Kan-Pak could reasonably believe that GLM

had authority to enter into the rental contracts on behalf of Verizon. See id. at 353. The

evidence of Verizon’s actions as it relates to whether they would lead a reasonably prudent

person to believe that GLM was acting on Verizon’s behalf is the letter of authorization that

specifically defines the scope of GLM’s agency and expressly prohibits GLM from

contracting on Verizon’s behalf. There is no evidence that Verizon held GLM out as having

authority to contract on its behalf. Most significantly, however, is that there is no evidence

that Kan-Pak ascertained the fact and scope of GLM’s authority, which is a required

element of a claim of apparent authority. See id. Kan-Pak was notified, by the letter of

authorization, that GLM did not have authority to bind Verizon to a contract and, further,

there is no evidence that Kan-Pak took any action to ascertain that GLM had been granted

greater authority than what was expressly identified in the letter of authorization. Because

there is no evidence to support one or more elements of a claim that Verizon is bound by

the rental contracts because GLM had apparent authority to contract on behalf of Verizon,


                                              8
Kan-Pak’s breach of contract claims may not rest on the apparent authority of GLM to

enter into the rental contracts on behalf of Verizon.


Ratification


       However, even though Verizon is not bound by the rental contracts based on the

actual or apparent authority of GLM to contract on Verizon’s behalf, Verizon would still be

bound by the contracts if it acted in a manner that ratified these contracts. In its motion for

summary judgment, Kan-Pak contends that Verizon ratified the rental contracts by directly

making 156 monthly payments under the rental contracts over the course of five to seven

years. Kan-Pak further cites evidence that GLM paid another 148 monthly payments. By

its summary judgment motion, Verizon contends that its actions were insufficient as a

matter of law to ratify the rental contracts and that it could not have ratified the rental

contracts before December 2006 because it was not aware of the material terms of the

contracts. Remaining mindful that this issue is presented in the context of competing

motions for summary judgment, we are required to examine the entire record in the light

most favorable to the nonmovant, indulging every reasonable inference and resolving any

doubts against the motion. See City of Keller, 168 S.W.3d at 824-25.


       Ratification of a contract occurs when a party recognizes the validity of the contract

by acting under the contract, performing under the contract, or affirmatively acknowledging

the contract. Stable Energy, L.P. v. Newberry, 999 S.W.2d 538, 547 (Tex.App.–Austin

1999, pet. denied). However, a party can only ratify a contract if, at the time of ratification,

it knew all of the material terms of the contract. See T & R Assocs., Inc. v. City of Amarillo,


                                               9
688 S.W.2d 622, 630 (Tex.App.–Amarillo 1985, writ ref’d n.r.e.). Thus, if a party acts in

a manner that recognizes the validity of a contract with full knowledge of the material terms

of the contract, the party has ratified the contract and may not later withdraw its ratification

and seek to avoid the contract. See Spellman v. Am. Universal Inv. Co., 687 S.W.2d 27,

29-30 (Tex.App.–Corpus Christi 1984, writ ref’d n.r.e.). Any retention of the beneficial part

of the transaction affirms the contract and bars rescission as a matter of law. Id. at 30.


       Kan-Pak contends that Verizon’s direct payment of 156 monthly payments on three

of the five contracts over the course of five to seven years coupled with GLM’s payment

of 148 monthly payments on the remaining contracts is sufficient evidence to establish that

Verizon ratified the rental contracts as a matter of law. However, there is no direct

evidence that, prior to December 2006, Verizon had any knowledge of all of the material

terms of the rental contracts. Certainly, there is no direct evidence that Verizon made

those payments with knowledge that the terms of the rental contracts included a 60 month

term that would be automatically renewed for an additional 60 month term if not terminated

in writing within 60 days of the expiration of the initial 60 month term. For Verizon to have

ratified the rental contracts, it would have to be shown that Verizon had knowledge of the

material terms of the contract at the time that it performed under the contract. Because,

prior to December 2006, there is no direct evidence that Verizon knew the material terms

of the rental contracts that it was performing under, we cannot conclude that Verizon

ratified the rental contracts as a matter of law by paying the monthly rental payments.3


       3
          Because we are reviewing Kan-Pak’s traditional motion for summary judgment, we
may not indulge reasonable inferences in Kan-Pak’s favor. Thus, while we conclude that
it is reasonable to infer that Verizon knew the material terms of the rental contracts prior

                                              10
       However, the evidence does establish that Verizon received copies of the rental

contracts in December 2006. Verizon made no direct monthly rental payments under the

rental contracts after it received copies of the rental contracts.4 Further, in February 2007,

Verizon contacted Kan-Pak and expressly repudiated the rental contracts.5 Looking at the

entire record and indulging all reasonable inferences in favor of Verizon, we conclude that

Verizon took no action after December of 2006 that ratified the rental contracts prior to its

express repudiation of those rental contracts in February 2007. Thus, Kan-Pak has failed

to establish that it was entitled to summary judgment on the basis that Verizon ratified the

rental contracts.


       Verizon contends, in support of its motion for summary judgment, that the evidence

establishes that it did not ratify the rental contracts as a matter of law. As discussed

above, Verizon received services and made monthly rental payments under the rental

contracts for five to seven years. Thus, Verizon retained some benefit under the rental

contracts and the retention of this benefit is some evidence of ratification. See Spellman,


to December 2006, that inference does not support Kan-Pak’s motion for summary
judgment.
       4
        However, we are aware that Verizon’s new waste management consultant, Allied,
did make monthly rental payments under the contracts after December 2006. However,
there is no evidence that Allied had the actual or apparent authority to bind Verizon.
Further, Allied’s payments were not made until after Verizon had expressly repudiated the
rental contracts. Thus, we do not conclude that Allied’s sporadic payments in 2007 was
evidence that Verizon ratified the rental contracts as a matter of law.
       5
          In its brief, Kan-Pak contends that Verizon did not repudiate the rental contracts
until its
 written notification of termination of the rental contracts was received in May 2007. While
the terms of the rental contracts required written notification of termination, an oral
repudiation of a contract is sufficient to show an intent to avoid the contract.

                                             11
687 S.W.2d at 30. Further, Verizon contends that GLM had no authority to contract on

Verizon’s behalf, yet Verizon acknowledges that it “knew that Kan-Pak had installed

compactors at its sites and what Kan-Pak was charging for each month’s rent.” We believe

that the presence of Kan-Pak’s compactors at five of Verizon’s Texas facilities and the

invoicing of monthly rental charges gives rise to a reasonable inference that a reasonably

prudent business would have investigated the basis of the monthly rental invoices and that,

in the exercise of ordinary diligence, such an investigation would have revealed the terms

of the rental contracts. While we cannot say that Verizon’s accepting of the benefits of the

rental contracts, without proof of its knowledge of the material terms of the rental contracts,

was a ratification of those contracts, we do conclude that Verizon’s conscious indifference

to discovering the terms of the rental contracts gives rise to a reasonable inference that it

knew or, at least, should have known the material terms of the rental contracts. As such,

we conclude that the evidence raises a genuine issue of material fact as to whether

Verizon ratified the rental contracts by making monthly rental payments under those

contracts. Therefore, we affirm the trial court’s denial of Verizon’s motion for summary

judgment.


Equitable Estoppel


       Finally, Kan-Pak contends that Verizon is equitably estopped from denying the

validity of the rental contracts based on its payment of the monthly rental charges.


       A claim of equitable estoppel requires proof of five elements: (1) a false

representation or concealment of material facts, (2) done with actual or constructive


                                              12
knowledge that the representation was false or that the concealed facts were material, (3)

made to a party without knowledge or the means to discover the facts, (4) with intent that

the other party act upon the representation or concealment, and (5) the other party

detrimentally relied on the representation or concealment. See Hausman v. Hausman, 199

S.W.3d 38, 43 (Tex.App.–San Antonio 2006, no pet.).


       However, in the present case, Kan-Pak has presented no evidence that would

establish, as a matter of law, that Verizon made any knowing false representation or

intentionally concealed any material facts relating to the rental contracts. As discussed

above, it is possible that Verizon had knowledge of the terms of the rental contracts and

continued to receive the benefit of those rental contracts, which might rise to the level of

an intentional concealment of material fact, but the evidence does no more than raise an

inference of that fact and, therefore, is insufficient to support Kan-Pak’s motion for

summary judgment. Because Kan-Pak has failed to establish as a matter of law that

Verizon is equitably estopped from denying the validity of the rental contracts, the trial court

could not have granted summary judgment on that basis.


Conclusion


       Because genuine issues of material fact are raised by the evidence as to each of

the grounds upon which Kan-Pak moved for summary judgment and because the evidence

does not establish that Verizon did not ratify the rental contracts as a matter of law, we

reverse the trial court’s grant of summary judgment in favor of Kan-Pak and affirm the trial

court’s denial of Verizon’s motion for summary judgment.


                                              13
                                         Damages


      Finally, Verizon contends that the trial court erred in denying its motion for new trial

because the trial court’s award of actual damages was not discounted to present value.

Because we have reversed the trial court’s summary judgment, the award of damages has

also been reversed. As such, the issue of the propriety of the trial court’s award of

damages is not before this Court. The “judicial power does not embrace the giving of

advisory opinions.” Gen. Land Office of Texas v. OXY U.S.A., Inc., 789 S.W.2d 569, 570

(Tex. 1990) (quoting Fireman’s Ins. Co. v. Burch, 442 S.W.2d 331, 333 (Tex. 1968)).


                                        Conclusion


      For the foregoing reasons, we reverse the trial court’s grant of summary judgment

in favor of Kan-Pak, affirm the trial court’s denial of Verizon’s motion for summary

judgment, and remand the cause to the trial court.




                                                  Mackey K. Hancock
                                                       Justice




                                             14