NUMBER 13-06-311-CV
COURT OF APPEALS
THIRTEENTH DISTRICT OF TEXAS
CORPUS CHRISTI - EDINBURG
AEP TEXAS CENTRAL COMPANY, ET AL., Appellants,
v.
PUBLIC UTILITY COMMISSION OF TEXAS, Appellee.
On appeal from the 261st District Court of Travis County, Texas.
OPINION
Before Chief Justice Valdez and Justices Yañez and Benavides
Opinion by Justice Benavides
On December 2, 2002, pursuant to section 39.202(c) of the Texas Utilities Code,
AEP Texas Central Company1 (“TCC”) filed an application for its final fuel reconciliation
with the Public Utility Commission of Texas (the “Commission”), for the period July 1, 1998
1
At the tim e it filed its final fuel reconciliation, TCC was known as Central Power & Light.
to December 31, 2001.2 See TEX . UTIL. CODE ANN . § 39.202(c) (Vernon 2007). Several
cities (the “Cities”),3 the Office of Public Utility Council (“OPC”), and Texas Industrial
Energy Consumers (“TIEC”) intervened and recommended various disallowances to TCC’s
petition. After hearings, the Commission issued its Order on Rehearing, the final order in
this case. TCC and the Cities appealed the Commission’s decision to the Travis County
District Court, which affirmed the decision in all respects.4
By six issues, TCC challenges the Commission’s decision and the district court’s
affirmance. TCC argues that the Commission erred by (1) extending the reconciliation
period; (2) not following prior reconciliation methodology; (3) improperly sharing off-system
margins; (4) arbitrarily treating TCC and its sister company differently regarding the load-
forecasting settlement in Docket No. 25755; (5) disallowing certain replacement power
costs; and (6) finding that certain TCC energy contracts contained implicit capacity costs.
Raising six issues, the Cities also appeal the Commission’s decision and the district
court’s affirmance. The Cities assert that the Commission erred by (1) including capacity
costs in eligible fuel expenses; (2) quantifying the amount of imputed capacity costs; (3)
failing to determine whether TCC paid an unreasonable price for firm energy; (4) failing to
exclude overcharges by the Department of Energy; (5) reconciling replacement fuel costs
2
See Application of Central Power and Light for Authority to Reconcile Fuel Costs, Public Utility
Com m ission Docket No. 27035 available at http://interchange.puc.state.tx.us/ (last visited 12/15/2008).
3
The Cities include the following: Alice, Aransas Pass, Big W ells, Cam p W ood, Carrizo Springs,
Corpus Christi, Dilley, Eagle Pass, Edinburg, Edna, Freer, Ganado, George W est, Goliad, Harlingen, Indian
Lake, La Feria, Laguna Vista, Laredo, Los Fresnos, Luling, Lyford, Mathis, McAllen, Mercedes, Odem , Orange
Grove, Palm Valley, Pearsall, Port Aransas, Port Isabel, Port Lavaca, Rancho Viejo, Refugio, Rockport, Rom a,
San Benito, Santa Rosa, Sinton, Taft, and Victoria.
4
See T EX . G O V ’T C OD E A N N §§ 2001.171, 2001.176 (Vernon 2008); T EX . U TIL . C OD E A N N . § 15.001
(Vernon 2007).
2
arising from imprudence at the South Texas Nuclear Project; and (6) allowing spot coal
costs that were imprudently incurred.
We affirm.
I. FACTUAL AND PROCEDURAL BACKGROUND
Through the Public Utility Regulatory Act, the Texas Legislature empowered the
Commission to regulate utilities. See TEX . UTIL. CODE ANN . §§ 11.001-66.017 (Vernon
2007 & Supp. 2008); Reliant Energy, Inc. v. Pub. Util. Comm’n of Tex., 101 S.W.3d 129,
133-34 (Tex. App.–Austin 2003), rev’d in part sub nom. CenterPoint Energy, Inc. v. Pub.
Util. Comm’n, 143 S.W.3d 81 (Tex. 2004). Under the utility code, each electric utility
operated as a monopoly in a designated service area, with regulated rates. Id.; see also
Office. of Pub. Util. Counsel v. Pub. Util. Comm’n of Tex., 104 S.W.3d 225, 227-28 (Tex.
App.–Austin 2003, no pet.).
The Commission set rates for the utilities that allowed the utilities to recoup their
prudently incurred costs and to receive a reasonable return on their investments. Reliant
Energy, Inc., 101 S.W.3d at 133. However, because the cost of fuel changes often, and
the Commission cannot hold rate proceedings to establish the rates utilities can charge
every single time the cost of fuel changes, the utilities code utilizes a “fuel factor.” See 16
TEX . ADMIN . CODE § 25.237 (2008). “Fuel factors are calculated by dividing the electric
utility's projected net eligible fuel expenses by the corresponding projected kilowatt-hour
sales for the period in which the fuel factors are expected to be in effect.” Office of Pub.
Util. Counsel v. Pub. Util. Comm'n of Tex., 185 S.W.3d 555, 561-62 (Tex. App.–Austin
2006, pet. denied).
3
In other words, the code permitted the electric utilities to charge rates that included
the recovery of fuel costs reasonably expected to be incurred. City of El Paso v. El Paso
Elec. Co., 851 S.W.2d 896, 898 (Tex. App.–Austin 1993, writ denied). Periodically,
through a proceeding before the Commission, the electric utilities had to reconcile the
revenues actually received with the expenses actually incurred. See TEX . UTIL. CODE ANN .
§ 36.203(e) (Vernon 2007); City of El Paso, 851 S.W.2d at 897-98. If the electric utility had
under-recovered its fuel expenses, it would recover the difference through a surcharge to
its customers. See 16 TEX . ADMIN . CODE § 25.236 (2001) (containing the Commission’s
fuel rules). If the electric utility had over-recovered its fuel expenses, it would refund that
amount to its customers. Id.
The legislature deregulated the retail electricity market in 1999. See TEX . UTIL.
CODE ANN . § 39.001 (Vernon 2007). Part of the transition to retail electricity competition
mandated by the legislature required the electric utilities to pursue a final fuel reconciliation
for the period ending the day before the date customer choice was introduced. TEX . UTIL.
CODE ANN . § 39.202(c). The electric utilities were to carry forward any under- or over-
recovery to a proceeding that would determine each electric utility’s “stranded costs” to be
passed on to ratepayers in that utility’s former designated service area. Id.
TCC filed its application for a final fuel reconciliation seeking to reconcile, among
other things, a total “Eligible Fuel Expense” of approximately $1.7 billion and “Fuel Factor
Revenues” of approximately $1.6 billion. Upon receipt of TCC’s petition for its final fuel
reconciliation, the Commission referred the application to the State Office of Administrative
Hearings for a contested case hearing, where administrative law judges (“ALJs”) received
4
evidence and heard testimony. The ALJs then recommended, with some disallowances,
that the Commission approve the application.
The Commission considered the ALJs’ proposal for decision and remanded the
case for the taking of additional evidence on the issue of whether some of TCC’s
purchased-power contracts contained embedded “capacity” costs, which were not costs
eligible for reconciliation. An ALJ issued a second proposal for decision, and the
Commission then issued an “Order on Rehearing” adopting the original proposal for
decision as modified on remand. TCC and the Cities appealed the Order on Rehearing
to the Travis County District Court, which affirmed the Commission’s order in all respects.
This appeal followed.5
II. TCC ISSUES NOS. 1 & 2: THE RECONCILIATION PERIOD AND METHODOLOGY
In its first issue, TCC alleges that the Commission violated the utility code by
extending the end of the reconciliation period. In its second issue, TCC contends that the
Commission violated its own rules by applying a different fuel reconciliation methodology
than that used in prior reconciliations. TCC claims that the prior methodology involved
reconciling expenses incurred in one month with revenues billed that same month.
A. Background
The legislature found implementing competitive electric markets to be in the public
interest and that the public interest requires that “electric services and their prices should
5
This appeal was transferred from the T hird Court of Appeals to the Thirteenth Court of Appeals
under a docket equalization order issued by the Suprem e Court of Texas. See T EX . G O V ’T C OD E A N N . §
73.001 (Vernon 2005). “In cases transferred by the Suprem e Court from one court of appeals to another, the
court of appeals to which the case is transferred m ust decide the case in accordance with the precedent of
the transferor court under principles of stare decisis if the transferee court’s decision otherwise would have
been inconsistent with the precedent of the transferor court.” T EX . R. A PP . P. 41.3.
5
be determined by customer choices and the normal forces of competition.” TEX . UTIL.
CODE ANN . § 39.001(a). Under the utilities code, the state implemented “on January 1,
2002, a competitive retail electric market that allows each retail customer to choose the
customer’s provider of electricity.” Id. § 39.001(b)(1); see CenterPoint Energy, 143 S.W.3d
at 90; Cities of Corpus Christi v. Pub. Util. Comm’n of Tex., 188 S.W.3d 681, 686 (Tex.
App.–Austin 2005, pet. denied). Chapter 39 of the utilities code was “enacted to protect
the public interest during the transition to and in the establishment of a fully competitive
electric power industry.” TEX . UTIL. CODE ANN . § 39.001(a).
With that underlying policy, the legislature instructed the Commission to hold a final
fuel reconciliation upon application by each utility. Section 39.202(c) commands each
formerly regulated monopoly to file a final fuel reconciliation “for the period ending before
the date customer choice is introduced.” Id. § 39.202(c). The utility code does not define
“the date customer choice is introduced.”
Customers who chose to switch to retail providers would be transferred to their
provider of choice after TCC completed a final meter read during January 2002. Thus,
even after January 1, 2002, when deregulation was set to begin, TCC continued providing
bundled-rate service to customers until the final meter read. TCC acknowledged that a
final meter read would be required before a customer could be switched to his provider of
choice and argued that customers could have arranged a special meter reading that would
have allowed customers to be switched prior to the time their normal meter read occurred.
In TCC’s final reconciliation, the Commission determined that the “date customer
choice is introduced” means the date that customers enter the competitive retail electric
market by choosing their own retail electric provider. TCC claims that the final fuel
6
reconciliation should include expenses and revenues incurred or received up to December
31, 2001, but not, as the Commission ordered, through the entire period that TCC
customers received bundled service. According to TCC, this allowed the Commission to
improperly include in TCC’s final fuel reconciliation certain expenses and revenues: those
incurred or received to provide service to customers under its “bundled” rate on and after
January 1, 2002, but prior to customers switching service to retail electric providers.8 See
TEX . UTIL. CODE ANN . § 39.202(c). Ultimately, this decision by the Commission required
TCC to reconcile $43,429,462.00 in revenues billed in 2002 and $10,591,133.00 in
expenses incurred in 2002, representing the amounts incurred up to the point customers
were switched to retail providers.
B. Standard of Review: Statutory Construction
We review questions of statutory construction de novo. State v. Pub. Util. Comm’n
of Tex., 246 S.W.3d 324, 332. Our goal is to determine and give effect to the legislature’s
intent. Id. We look to the statute as a whole, to determine legislative intent, and begin with
the plain language of the statute, applying its common meaning. Id. “Where the statutory
text is unambiguous, we adopt a construction supported by the statute’s plain language,
unless that construction would lead to an absurd result.” Id.
We are to give serious consideration to the Commission’s construction of statutes
it is charged with enforcing so long as the construction does not contradict the plain
wording of the statute and is reasonable. Tarrant Appraisal Dist. v. Moore, 845 S.W.2d
8
The “bundled” rate is the rate utilities charged custom ers for all service provided by the utility before
deregulation, while the utility was still a “bundled” utility (i.e., power generation com pany, retail electric
provider, and transm ission and distribution utility). See T EX . U TIL . C OD E A N N . § 39.051 (Vernon 2007)
(“Unbundling”).
7
820, 823 (Tex. 1993); Steering Comms. for the Cities Served by TXU Elec. v. Pub. Util.
Comm’n of Tex., 42 S.W.3d 296, 300 (Tex. App.–Austin 2001, no pet.). We “do not defer
to administrative interpretation in regard to questions which do not lie within administrative
expertise, or deal with a nontechnical question of law.” Rylander v. Fisher Controls Int’l,
Inc., 45 S.W.3d 291, 302 (Tex. App.–Austin 2001, no pet.). We are to give deference to
the Commission’s construction of its own rules, so long as that construction is reasonable.
Pub. Util. Comm’n of Tex. v. Gulf States Util. Co., 809 S.W.2d 201, 207 (Tex. 1991).
C. TCC’s Issue No. 1: Extending the Ending Date of TCC's Final Fuel
Reconciliation
In mandating retail electricity customer choice, the legislature required that “each
affiliated power generation company9 shall file a final fuel reconciliation for the period
ending the day before the date customer choice is introduced.” TEX . UTIL. CODE ANN . §
39.202(c) (emphasis added). The legislature chose not to define “the date customer
choice is introduced.” Id. According to TCC, the legislature’s intention is clear: the state
will “implement on January 1, 2002, a competitive retail electric market that allows each
retail customer to choose the customer’s provider of electricity.” Id. § 39.001(b)(1); see
CenterPoint Energy, 143 S.W.3d at 90; Cities of Corpus Christi, 188 S.W.3d at 686. TCC
argues that this is evidence that the legislature did not intend for the final fuel reconciliation
to include any revenue or expenses collected or incurred after December 31, 2001, for
rate-regulated service provided during the period in January 2002, while customers were
transferred to retail providers.
9
“‘Affiliated power generation com pany’ m eans a power generation com pany that is affiliated with or
the successor in interest of an electric utility certificated to serve an area.” T EX . U TIL . C OD E A N N . § 31.002(1).
8
The Commission, the Cities, and TIEC all assert that, by not specifically using
“December 31, 2001” in section 39.202(c), the legislature recognized that not all customers
would be provided with customer choice at midnight on December 31, 2001, and that by
using the more ambiguous phrase “the day before customer choice is introduced,” the
legislature intended for revenues and expenses received or incurred after December 31,
2001 to be included in the final fuel reconciliations. Even if all customers had used the
special meter read program, the record contains no evidence that every TCC customer
could have had his final meter read at 12:00 am on January 1, 2002. Such information
reinforces the Commission’s interpretation of the legislative intent behind using the phrase,
“the date customer choice is introduced.” Giving appropriate deference to the
Commission’s interpretation of the statutes it was created to enforce, we agree with the
Cities, the Commission, and TIEC.
Reading the statute as a whole,10 we see that the legislature could have used
“December 31, 2001” in section 39.202(c) had it intended for that date to be the end of the
period. Compare TEX . UTIL. CODE ANN . § 39.102(b) (Vernon 2007), and id. § 39.202(b),
with id. § 39.107(a) (Vernon 2007 & Supp. 2008) (“On introduction of customer
choice . . . .”), and id. § 39.154(a) (“[O]n the date of introduction of customer choice . . . .”),
and id. § 39.201(l) (“[A]fter customer choice is introduced . . . .”). By using the imprecise
phrase, “the date customer choice is introduced,” the legislature left interpreting section
39.202(c) to the Commission. Id. § 39.202(c); see generally Meno v. Kitchens, 873
10
See Trawalter v. Schaefer, 142 Tex. 521, 179 S.W .2d 765, 767 (Tex. 1944); Hartford Ins. Co. v.
Cain, 246 S.W .3d 374, 378 (Tex. App–Austin 2008, no pet.) (“In construing a statute, we m ust ascertain the
legislative intent by looking to the entire act, including the caption and body.”).
9
S.W.2d 789, 791 (Tex. App.–Austin1994, writ denied) (noting that, “if the meaning of the
section or statute in question is not clear,” deference to the Commission’s interpretation
is appropriate).
The Commission determined that, by requiring a “final” fuel reconciliation, the
legislature intended for each of the formerly-regulated utilities to reconcile all of its costs
and revenues for its bundled services, even those incurred or received after December 31,
2001. Surely the legislature did not intend for costs and revenues from a utility’s bundled
services to remain unreconciled after the final fuel reconciliation.11 Had the Commission
used the interpretation urged by TCC, the final fuel reconciliation would have left
unreconciled $43,429,462.00 in revenues billed in 2002 for energy consumption both
before and after December 31, 2001, and $10,591,133.00 in expenses incurred in 2002
for bundled, regulated service provided after December 31, 2001. The Commission’s
interpretation “protects the public interest” by ensuring that in the final fuel reconciliation,
all costs and revenues incurred during the reconciliation period and associated with rate-
regulated services were reconciled so that TCC did not receive a windfall by including costs
in its reconciliation but not revenues. See id. § 39.001(a). The Commission’s
interpretation is reasonable, does not contradict the plain meaning of the statute, and in
fact, promotes the statute’s purpose. See generally Tarrant Appraisal Dist., 845 S.W.2d
at 823; Steering Comms., 42 S.W.3d at 300. We overrule TCC’s first issue.
D. TCC’s Second Issue: Violation of the Fuel Rules
11
See generally State v. Shumake, 199 S.W .3d 279, 284 (Tex. 2006); CenterPoint Energy Houston
Elec., LLC v. Gulf Coast Coalition of Cities, No. 03-06-00285-CV, 2008 W L 2852336, at *9 (Tex. App.–Austin
July 25, 2008, pet. filed) (“Our prim ary objective in statutory construction is to give effect to the legislature's
intent.”).
10
Similarly, TCC argues that the Commission erroneously interpreted its own rules to
extend the reconciliation period beyond December 31, 2001. Utilities were required by rule
to account for revenues and expenses incurred “during the reconciliation period.” 16 TEX .
ADMIN . CODE § 25.236(d)(1). TCC complains that in prior reconciliations, the Commission
defined the reconciliation period as a single month. According to TCC, the change in
methodology allowed the Commission to reconcile expenses incurred in December 2001
with revenues billed in December 2001 and revenues billed in a subsequent month. TCC
asserts that this action resulted in a mismatch “between the items reconciled, resulting in
a longer time period of revenues than expenses being ‘reconciled.’”
TCC concedes, as it must, that the “the reconciliation period” is not defined by the
rule. Thus, we must determine whether the Commission reasonably interpreted its fuel
rule. See 16 TEX . ADMIN . CODE § 25.236; Gulf States Util. Co., 809 S.W.2d at 207
(requiring deference to the Commission’s construction of its own rules, so long as its
construction is reasonable). Without designating a specific date for the end of the
reconciliation period, the legislature required final fuel reconciliations for the period ending
the day before customer choice was introduced. See TEX . UTIL. CODE ANN . § 39.202(c).
As we held in deciding TCC’s first issue, the Commission reasonably interpreted section
39.202(c) to include the period during which TCC’s customers were switched to retail
providers. Likewise, the Commission’s interpretation of its own rule is reasonable.
The Commission recognized not only that “[n]ormal billing lag occurs between when
a cost is incurred and when that cost is billed and collected,” but also that the legislature
directed it to conduct a final fuel reconciliation. Id. In prior reconciliations, costs incurred
in the final month of the reconciliation period and billed in the first months of the next
11
reconciliation were accounted for in the subsequent reconciliation. Because there are no
more reconciliations, the Commission reasonably interpreted the legislature’s command
to conduct a final reconciliation by accounting for all revenues associated with the costs
of providing service during the reconciliation period. See id. TCC’s second issue is
overruled.
III. TCC ISSUE NO . 3: OFF-SYSTEM SALES MARGINS
In TCC’s third issue, it argues that the Commission erred when resolving an issue
related to sharing off-system sales margins with retail customers. “Off-system margins”
are sales margins arising from a utility’s sale of excess energy, generated beyond what its
retail customers needed, that the utility sold to other customers. TCC argues: (1) the
Commission exceeded its authority because, by requiring the margin sharing to account
for months beyond the date of the final fuel reconciliation, the Commission extended the
date of the final fuel reconciliation; and (2) the Commission’s order contravenes an
“Integrated Stipulations and Agreement” (“ISA”). We disagree with both contentions.
A. Factual Background
Prior to deregulation, utilities would produce electricity to satisfy the needs of their
retail customers. When the utility generated more electricity than its customers needed,
it would sell the excess to other customers in a off-system sale. As a general rule, utilities
were required to share ninety percent of their off-system sales margins with their retail
customers through fuel reconciliations. 16 TEX . ADMIN . CODE § 25.236(a)(8).
12
As part of the AEP and Central and South West Corporation (“CSW”)12 merger, the
Commission adopted the ISA, a settlement agreement entered into by TCC’s predecessor
and several other parties. The ISA required TCC to share the off-system margins with its
retail customers for five years from the effective date of the merger. These margins were
to be credited to the customers in the form of revenue credits in fuel reconciliation
proceedings.
Subsection G of the ISA provides, in pertinent part:
3.G. Off-System Sales Margins
(1) [TCC] off-system sales margins up to $1.75 million shall be
credited to customers. For any [TCC] off-system sales
margins between $1.75 million and $2.62 million, 85% shall be
credited to customers and 15% of such margin shall be
retained by the shareholders. For any [TCC] off-system sales
margins above $2.62 million, 50% of such margins shall be
credited to customers and 50% of such margins shall be
retained by the shareholders.
....
(4) The provisions as to off-system sales margins shall be in effect
for a period of five years from the effective date of the merger.
....
(6) Off-system sales margins to be credited to customers under
this subsection shall be made in the form of revenue credits in
fuel reconciliation proceedings.
The merger was effective in July 2000, and this appeal involves the final fuel
reconciliation for TCC that was filed in 2002. To account for the five-year period of margin-
sharing under the ISA, the Commission took the total margin of off-system sales for the 18
12
CSW was the holding com pany of CP&L, TCC’s predecessor. In a stock transaction, CSW m erged
into AEP, and as part of the m erger process, the parties adopted the ISA as a comprom ise on m any issues
including the present, contested issue.
13
months before TCC’s final fuel reconciliation, when the margin-sharing was in effect under
the ISA, divided that total by 18 to get a monthly average or proxy, and multiplied that proxy
by 60 months to represent the full five years of sharing required by the ISA. The total dollar
figure of off-system margins owed by TCC, according to this formula, was approximately
$52.8 million, the amount the Commission concluded was reconcilable.
B. Did the Commission Properly Construe the ISA?
TCC raises the issue of whether the Commission may include, in the present fuel
reconciliation, expenses incurred beyond December 31, 2001. TCC argues that by
requiring it to fulfill the five-year margin sharing in the ISA, the Commission is improperly
extending the reconciliation period by 42 months. As we noted supra Part II, the legislature
tasked the Commission with conducting a final fuel reconciliation. The Commission
properly interpreted this mandate by insisting that TCC reconcile the margin-sharing it
committed to in the ISA.
Additionally, section 39.108, commands that chapter 39 of the utility code may not
“interfere with or abrogate the rights or obligations of any party, including a retail or
wholesale customer, to a contract with an investor-owned utility . . . .” TEX . UTIL. CODE ANN .
§ 39.108(1) (Vernon 2007). Thus, section 39.108 required the Commission to give effect
to the parties’ agreement embodied in the ISA, regardless of chapter 39's final fuel
reconciliation proceedings. The question before us, then, is one of contract interpretation.
1. Standard of Review: Contract Interpretation
Determining whether an agreement is ambiguous is a question of law which we
review de novo. Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd., 940 S.W.2d
14
587, 589 (Tex. 1996). The interpretation of an unambiguous agreement is also a question
of law reviewed de novo. Weslaco Fed’n of Teachers v. Tex. Educ. Agency, 27 S.W.3d
258, 263-64 (Tex. App.–Austin 2000, no pet.). If the agreement is ambiguous, a fact issue
is created regarding the parties’ intent. See Cities of Abilene v. Pub. Util. Comm’n of Tex.,
146 S.W.3d 742, 748 (Tex. App.–Austin 2004, no pet.). If the agreement is ambiguous,
we will affirm the Commission’s interpretation of it, so long as the interpretation is
supported by substantial evidence. Id.
The Commission may resolve a dispute arising from the interpretation of a
settlement agreement adopted into a final order in a previous administrative proceeding.
In re Entergy Corp., 142 S.W.3d 316, 324 (Tex. 2004). The Commission may not,
however, use this power to amend the prior order that adopted the agreement. Cities of
Abilene, 146 S.W.3d at 747 n.7 (citing R.R. Comm’n v. Home Transp. Co., 670 S.W.2d
319, 325 (Tex. App.–Austin 1984, no writ)). The Commission must use the rules of
contract interpretation to interpret a settlement agreement previously adopted. Id. at 747.
Under the rules of contract interpretation, the primary duty of the Commission is to
“ascertain and give effect to the parties’ intentions as expressed in the document.” Frost
Nat’l Bank v. L&F Distribs., Ltd., 165 S.W.3d 310, 311 (Tex. 2005). The Commission
should attempt to “harmonize and give effect to all the provisions of the contract by
analyzing the provisions with reference to the whole agreement.” Id. An oppressive,
unreasonable, and inequitable construction should be avoided, if possible. Id. The
agreement should be construed from “‘a utilitarian standpoint bearing in mind the particular
business activity sought to be served.’” Id. (quoting Reilly v. Rangers Mgmt., Inc., 727
15
S.W.2d 527, 530 (Tex.1987)). After applying the rules of interpretation, if the agreement
can be given a certain or definite legal meaning, it should be construed as a matter of law
because it is unambiguous. Id. If the agreement can reasonably be interpreted in more
than one way, it is ambiguous. Id.
2. Analysis
TCC argues that the agreement is ambiguous on the post-deregulation effect of
subsection G(6), which requires that margins be shared with the utility’s customers through
fuel reconciliations. TCC argues that after deregulation, there is no way to fulfill the
express provision of G(6) because post-deregulation, fuel reconciliations do not exist. On
the other hand, the Commission and the Cities allege that the intent of the parties to the
ISA is clear and unambiguous: the ISA contemplated a sharing of off-system sales
margins for five years. They also assert that this commitment to margin-sharing is
independent of the method by which the margins would be shared. TCC counters by
arguing that subsections 3(G)(1) and 3(G)(6) cannot be independent of each other
because off-system sales margins have always been shared through fuel reconciliations.
We find, as did the Commission in Docket No. 26000,13 that the ISA is unambiguous
as a matter of law. See generally Cities of Abilene, 146 S.W.3d at 748. The mere fact that
there are two or more interpretations advanced does not lead automatically to the
conclusion that the agreement is ambiguous. AT&T Corp. v. Rylander, 2 S.W.3d 546, 560
(Tex. App.–Austin 1999, pet. denied) (“Not every difference in the interpretation of a
13
Application of W est Texas Utilities for Authority to Reconcile Fuel Costs, Docket No. 26000, Order
on Rehearing at 7 (10/18/2004) (affirm ing, in a fuel reconciliation involving TCC's sister com pany, that the ISA
is unam biguous) available at http://interchange.puc.state.tx.us (last visited 12/15/2008).
16
contract creates an ambiguity. The mere disagreement over the meaning of a particular
provision in a contract does not make it ambiguous.”). We look at the circumstances
present at the time the agreement was made when determining whether the agreement
is ambiguous. Weslaco Fed’n of Teachers, 27 S.W.3d at 264.
The intent of the parties to share off-system sales margins for five years is clear and
subject to only one reasonable interpretation. Subsection 3(G)(4) clearly requires five
years of sharing: “[t]he provisions as to off-system sales margins shall be in effect for a
period of five years from the effective date of the merger.” The off-system sales margins
are shared through a fuel reconciliation, and that is what occurred in this case through the
use of the proxy. The interpretation urged by TCC, that because there are no more fuel
reconciliations, there should be no more off-system margin sharing, leads to an
unreasonable result that is contrary to the plainly expressed intent of the parties.14 We
overrule TCC’s third issue.
IV. TCC’S FOURTH ISSUE: THE DOCKET NUMBER 25755 LOAD -FORECASTING SETTLEMENT
In its fourth issue, TCC asserts error in the Commission including, as a reduction
to TCC’s fuel expenses, a distribution received under Docket No. 25755.15 TCC alleges
that the Commission treated TCC and its sister company, AEP-Texas North Company
(“TNC”), differently, thereby acting arbitrarily and capriciously. See TEX . GOV’T CODE ANN .
§ 2001.174(2)(F) (2008).
14
See W est Texas Utilities, Docket No. 26000 at 7 ("The fact that m argin-sharing credits are to be
m ade in the form of revenue credits in fuel reconciliation proceedings does not lim it the requirem ent to share
five years of off-system sales m argins.").
15
See PUC Investigations of Overscheduling in ERCOT in August, 2001, Docket No. 25755 available
at http://interchange.puc.state.tx.us (last visited 12/15/2008).
17
A. Factual Background
The Electric Reliability Council of Texas (“ERCOT”) operates Texas’s electric
production and transmission grid. BP Chemicals, Inc. v. AEP Texas Central Company, 198
S.W.3d 449, 451 (Tex. App.–Corpus Christi 2006, no pet.); see TEX . UTIL. CODE ANN . §
39.151 (Vernon 2007). The ERCOT grid is divided into different zones with different
utilities being responsible for serving loads in the different zones. “Load” is the amount of
power being used by consumers at any given time. This grid system ensures that there
is an even amount of power being distributed to a specific zone to meet the demand of
consumers in that zone.
Using a variety of data, a Qualified Scheduling Entity (“QSE”)16 would submit a
“balanced schedule” for each of the utilities servicing ERCOT. A “balanced schedule” is
one where the total amount of power supplied to the grid equals the total amount of power
required by end-users for the same time period. TCC’s QSE is named “AEPSC.” When
the amount of power actually consumed was more than the amount scheduled in that
zone, ERCOT would buy power from another supplier to fill the need. ERCOT would then
charge the under-forecasting utility the amount paid to cover the shortfall.
Docket No. 25755 resulted from the Commission’s investigation into potential load
over-scheduling in ERCOT. In Docket No. 25755, the Commission determined that costs
among the utilities serving ERCOT had been inaccurately allocated. The QSEs settled
with ERCOT and agreed to remit to ERCOT amounts that had been over-allocated.
16
“A m arket participant that is qualified by the Electric Reliability Council of Texas (ERCOT) in
accordance with Section 16, Registration and Qualification of Market Participants of ERCOT's Protocols, to
subm it balanced schedules and ancillary services bids and settle paym ents with ERCOT.” 16 T EX . A D M IN .
C OD E § 25.5(95).
18
ERCOT would then allocate the funds properly and distribute the appropriate amounts
back to the utilities. A remittance to ERCOT represented a return of previously-collected
revenues, and a distribution from ERCOT was crediting already-incurred expenses.17
On behalf of the AEP ERCOT operating companies—TCC and TNC— AEPSC was
required to remit over $3 million to ERCOT. TNC remitted over $2 million to ERCOT.
Then in TNC’s final fuel reconciliation, the Commission did not require TNC to recognize
the remittance it made to ERCOT, which should have resulted in a decrease in TNC’s
revenues.
In contrast, in recognition of Docket No. 25755, TCC received a distribution of over
$1 million. The Comission required this distribution to be credited against TCC’s fuel
expenses in the present reconciliation. TCC alleges that the Commission has acted
arbitrarily and capriciously by requiring TCC to reconcile the amount received from the
ERCOT distribution, which decreases the amount of expenses TCC may recognize. TCC
argues that this disparate treatment—requiring TCC to reduce its expenses but not
requiring TNC to decrease revenues—is an arbitrary and capricious action by the
Commission causing an unreasonable result.
B. Standard of Review: Arbitrary and Capricious
An agency acts in an arbitrary and capricious manner when it (1) fails to consider
a factor the legislature required it to consider; (2) considers an irrelevant factor; or (3)
considers only relevant factors, yet reaches an unreasonable result. See City of El Paso
17
The term inology in this process m ay be confusing, so for the sake of clarity, we will use “rem ittance”
to reflect m oney returned to ERCOT by the QSEs and “distribution” when discussing m oney sent from ERCOT
to the utilities. Therefore, a “distribution” is the proper allocation of the m oney rem itted to ERCOT by the
QSEs.
19
v. Pub. Util. Comm'n of Texas, 883 S.W.2d 179, 184 (Tex. 1994). Additionally, when the
agency fails “to follow the clear, unambiguous language of its own regulation,” it acts
arbitrarily and capriciously. Office of Pub. Util. Counsel v. Pub. Util. Comm'n of Tex., 185
S.W.3d at 564.
C. Analysis
TCC claims that Docket No. 25755 either created obligations or it did not. TCC
asserts Docket No. 25755 did not create them in one company while creating them in the
other. The Commission counters by demonstrating that the difference results from the
different treatment of expenses and revenues in a fuel reconciliation. In a fuel
reconciliation, revenues are counted upon receipt, but expenses must be proven necessary
and reasonable. 16 TEX . ADMIN . CODE § 25.236(d)(1)(A), (C). In TNC’s final reconciliation,
the Commission determined that TNC “failed to meet its burden of proving $2,704,246 [ ]
in expenses associated with ERCOT over-scheduling, arising from the settlement in Docket
No. 25755, were reasonable and necessary expenses incurred to provide reliable electric
service to retail customers.”18 The Commission disallowed TNC’s request to reconcile as
expenses the remittance to ERCOT. In contrast, in TCC’s final reconciliation, the
Commission held that the distribution from ERCOT must be included in TCC’s fuel
reconciliation. We hold that the Commission did not act arbitrarily by treating the revenues
and expenses differently. The Commission, pursuant to its fuel rules, reached a
reasonable result in the present case by requiring TCC to include in its fuel reconciliation
the distribution it received from Docket No. 25755. We overrule TCC’s fourth issue.
18
See W est Texas Utilities, Docket No. 26000, Order on Rehearing at 26, Conclusion of Law No. 16.
20
VI. TCC’S FIFTH ISSUE: REPLACEMENT POWER COSTS
In its fifth issue, TCC challenges the Commission’s decision to disallow the inclusion
of replacement power costs incurred during a shut-down of TCC’s South Texas Project
(“STP”), a nuclear power plant.
A. Background
Westinghouse, a third party vendor, sold generators to STP that were placed into
service beginning in 1988. According to TCC, Westinghouse claimed the generators were
supposed to perform for 40 years. In 2000, TCC shut down STP to replace four of the
steam generators manufactured by Westinghouse. The replacement occurred 12 years
after they were placed into service.
Deteriorating tubes caused the need for replacement. According to William R.
Jacobs, the Cities' witness, a leak in a steam generator tube is "a serious problem because
it allows the high pressure, radioactive reactor coolant from the primary side to enter the
non-radioactive secondary side of the plant." TCC, and the other owners of STP, sued
Westinghouse, alleging that Westinghouse had “acted knowingly or recklessly, without due
regard for the rights of others.”19
The STP shut down caused an outage during the replacement period, and TCC
purchased additional power to cover that lost during the shut-down. According to the
Commission, TCC did not act imprudently. However, the Commission determined that
Westinghouse acted imprudently, and it imputed Westinghouse’s imprudence to TCC. The
Commission found that “Westinghouse’s sale of highly defective critical equipment that did
19
TCC and W estinghouse reached an undisclosed settlem ent.
21
not achieve a reasonable level of performance, coupled with what TCC asserts were
knowing or reckless misrepresentations, constituted imprudence.” The Commission
decreased TCC’s eligible fuel expenses by $7.8 million, “a reasonable estimate of the
portion of the total replacement-power costs for this outage attributable to the replacement
of the steam generators.”
TCC attacks the Commission’s decision in three ways. First, TCC argues that the
Commission improperly considered TCC’s allegations in its lawsuit against Westinghouse
as admissions in the present case. Second, TCC asserts that there is no evidence that
Westinghouse was imprudent. Third, TCC alleges that the Commission failed to follow its
enabling statute and rules by placing the burden of the expense onto TCC through
standards applicable to base-rate proceedings and not to fuel reconciliation proceedings.
B. Standard of Review: Substantial Evidence
Generally, we review the Commission’s final orders under the substantial evidence
rule. TEX . UTIL. CODE ANN . § 15.001 (Vernon 2007); TEX . GOVT . CODE ANN . § 2001.174
(Vernon 2008); see Nucor Steel v. Pub. Util. Comm’n of Tex., 168 S.W.3d 260, 267 (Tex.
App.–Austin 2005, no pet.). Under the substantial evidence rule, we must uphold the
Commission’s decision if a reasonable basis exists in the record for the decision, even if
the evidence preponderates against the decision. See Tex. Health Facilities Comm’n v.
Charter Med.-Dallas Inc., 665 S.W.2d 446, 453 (Tex. 1984). While presuming that the
Commission’s order is valid and that “its findings, inferences, conclusions, and decisions
are supported by substantial evidence,” we also “give significant deference to the
[Commission] in its field of expertise.” State v. Pub. Util. Comm’n of Tex., 246 S.W.3d 324,
22
331 (Tex. App.–Austin 2008, pet. filed). As the complaining parties, TCC and the Cities
have the burden of overcoming our presumptions regarding the Commission’s order. Id.
at 332.
On questions falling under the Commission’s discretion, we will not substitute our
judgment on the weight of the evidence. Id. at 332. We will, however, consider the entire
record to determine whether the evidence is such that reasonable minds could have
reached the same conclusion that the Commission, to issue its order, must have reached.
Id. at 332. If that is the case, we will affirm the Commission’s decision. Id. at 332. “[I]f the
decision is not reasonably supported by substantial evidence, in violation of a constitutional
or statutory provision, in excess of the [Commission’s] statutory authority, made through
unlawful procedure, affected by other error of law, arbitrary or capricious, or characterized
by an abuse of discretion,” we will reverse the Commission’s Final Order. Id. at 332 (citing
TEX . GOV’T CODE ANN . § 2001.174(2)(A)-(F).
C. The Commission’s Rules and Precedent
A utility is permitted to recover its reasonable and necessary expenses. See 16
TEX . ADMIN . CODE § 25.236(d)(1)(A); Cities of Abilene, 146 S.W.3d at 746. To be a
reasonable and necessary expense, the cost must have been prudently incurred. See Gulf
States Utils. Co. v. Pub. Util. Comm'n of Tex., 841 S.W.2d 459, 466 (Tex. App.–Austin
1992, writ denied). Under Commission precedent, costs incurred due to the imprudence
of a third-party vendor are not reasonable and necessary.20 The imprudence of a third-
20
See Application of Texas Utilities Electric Company for Authority to Change Rates, Docket No.
9300, 17 P.U.C. Bull. 2057, 1991 W L 790285, at *473, Conclusion of Law No. 34 (Sept. 27, 1991).
23
party vendor may be imputed to the utility, even if the utility has not acted imprudently.21
“By virtue of the fact that they paid [TCC’s] base rate costs during the reconciliation period,
[TCC’s] ratepayers are entitled to a reasonable level of performance from the resources
that gave rise to those base rate costs.”22
D. Analysis
1. Admissions
The Commission considered TCC’s pleadings from its suit against Westinghouse
as evidence of Westinghouse’s imprudence. “Pleadings in another case that are
inconsistent with a party’s position in a present action are quasi-admissions, which are
treated as some evidence.” Daimler-Benz Aktiengesellschaft v. Olson, 21 S.W.3d 707, 718
(Tex. App.–Austin 2000, pet. dism’d w.o.j.) (citing Dowelanco v. Benitez, 4 S.W.3d 866,
871 (Tex. App.–Corpus Christi 1999, no pet. h.)). However, when certain conditions are
met, quasi-admissions can become formal judicial admissions.23 Id. at 719. The
Commission argues that TCC’s pleadings in the suit against Westinghouse amount to
21
Id.
22
Application of Texas Utilities Electric Company for the Reconciliation of Fuel Costs, Docket No.
15195, Final Order at 10 (Aug. 26, 1997)available at http://interchange.puc.state.tx.us (last visited
12/15/2008).
23
The conditions are as follows:
(1) the statem ents relied on were m ade during the course of a judicial proceeding; (2) the
statem ents are contrary to an essential fact em braced in the theory of recovery or defense
asserted by the person m aking the statem ents; (3) the statem ents were deliberate, clear, and
unequivocal; (4) giving conclusive effect to the statem ents will be consistent with the policy
on which the rule is based; and (5) the statem ents are not also destructive of the opposing
party's theory of recovery.
Daimler-Benz Aktiengesellschaft v. Olson, 21 S.W .3d 707, 718 (Tex. App.–Austin 2000, pet. dism 'd w.o.j.).
24
formal judicial admissions.24 Under the substantial evidence standard of review, we do not
need to decide whether TCC made a formal judicial admission via its pleadings in its
lawsuit against Westinghouse. It is enough that TCC’s pleadings in the lawsuit against
STP—where TCC claimed Westinghouse acted recklessly—amount to some evidence,
forming a reasonable basis in the record for the Commission’s conclusion that
Westinghouse acted imprudently. See generally Charter Med.-Dallas Inc., 665 S.W.2d at
453.
2. Westinghouse’s Imprudence
TCC asserts that there is no evidence that Westinghouse was imprudent.
Prudence, in this context, means
[T]he exercise of that judgment and the choosing of one of that select range
of options which a reasonable utility manager would exercise or choose in
the same or similar circumstances given the information or alternatives
available at the point in time such judgment is exercised or option is chosen.
Entergy Gulf States, Inc. v. Pub. Util. Comm’n of Tex., 112 S.W.3d 208, 210 n.2 (Tex.
App.–Austin 2003, pet. denied). TCC claims that the Commission, contrary to the
prudence standard, evaluated Westinghouse’s actions using hindsight. See id. The
Commission responds that it based its finding of imprudence on the specific
representations and warranties Westinghouse made when it sold the generators to STP
and that by doing so, it did not make its findings using hindsight. In adopting the ALJs’
decision, the Commission concurred with their findings that “Westinghouse designed and
24
A form al judicial adm ission is binding on the party adm itting it, and he m ay not introduce
contradictory evidence. See Cameron County v. Velasquez, 668 S.W .2d 776, 782 (Tex. App–Corpus Christi
1984, writ ref’d n.r.e.) (discussing the differences between form al judicial adm issions and quasi-judicial
adm issions).
25
supplied steam generators so defective they performed for only a fraction of their
anticipated duration” and that “Westinghouse seriously misrepresented the performance
that could have been expected from the steam generator tubes.” Dr. William R. Jacobs,
a witness for the Cities, testified that “[t]he steam generators supplied to STP were flawed
and lasted only a fraction of their intended life.” This provides a reasonable basis in the
record upon which the Commission based its determination that Westinghouse, and thus
TCC, was imprudent. See generally Charter Med.-Dallas, Inc., 665 S.W.2d at 453 (setting
forth the substantial evidence rule).
3. Base-Rate Standards vs. Fuel Reconciliation Standards
The crux of TCC’s third argument is that the Commission erred as a matter of law
by following factors applicable to base-rate proceedings25 —risk allocation and equity—and
not the fuel reconciliation standard26 applicable to this proceeding. However, the
Commission followed its fuel rule as it determined that the expenses were not “reasonable
and necessary.” See 16 TEX . ADMIN . CODE § 25.236(d)(1)(A).
Docket No. 15195 is instructive.27 In that fuel reconciliation, the Commission had
to determine who bears the fuel replacement costs associated with an extraordinary outage
at a generation plant. The Commission determined that because the ratepayers continued
to pay the utility’s base rates during the extraordinary outage, the ratepayers should not
bear the burden of the fuel replacement costs, even absent a finding of utility imprudence.28
25
See T EX . U TIL . C OD E A N N . §§ 36.051-.052 (Vernon 2007).
26
See 16 T EX . A D M IN . C OD E § 25.236(d)(1)(A).
27
See Texas Utilities Electric Company, Docket No. 15195, Final Order at 10 (Aug. 26, 1997).
28
Id. at 9.
26
Significantly, to make this determination, the Commission used the risk allocation and
equity factors.29 In the present case, the Commission properly followed its enabling
statute, its rules, and its precedent. See Nucor Steel v. Pub. Util. Comm'n of Texas, 26
S.W.3d 742, 748 (Tex. App.–Austin 2000, pet. denied) (noting that reviewing courts defer
to the agency’s interpretation of its own rule unless the interpretation is inconsistent with
the rule or plainly erroneous, and affirming that the “‘prudence’ standard explicitly
incorporates a utility’s reasonableness and, by speaking in terms of available alternatives,
implicitly recognizes that an expense must be necessary”). Accordingly, we overrule TCC’s
fifth issue.
VII. TCC’S SIXTH ISSUE AND THE CITIES’ FIRST ISSUE: CAPACITY COSTS IN ENERGY
PURCHASES
In its sixth issue, TCC challenges the Commission’s decision to disallow
approximately $1.96 million of the costs of certain block energy contracts—also known as
“purchased-power contracts.”30 The Commission determined that the costs were implicit
“capacity” costs that are typically not included as fuel expenses and are not recoverable
under the Commission’s fuel rule. See 16 TEX . ADMIN . CODE § 25.236(a)(4). Capacity
29
Id. ("[F]rom an equity and risk allocation standpoint, the Com m ission concludes that the increased
fuel costs associated with the extraordinary 19-m onth outage at MOSES Unit N o. 3 should fall upon the
shareholders of TUEC, even in the absence of a finding of im prudence.").
30
Block energy purchases provide for a fixed am ount of energy in specific, daily on-peak or off-peak
hours to be delivered over a certain num ber of days. As an exam ple,
[I]n a typical “5x16 purchase,” a specified num ber of m egawatts (“MW ”) is to be delivered
during each 16-hour on-peak period on each of five weekdays. The buyer under such a
contract pays for the energy over the entire period specified, regardless of whether or not the
buyer actually takes possession of the full block of energy. These contracts are typically
“financially firm ” in that they include liquidated dam ages provisions.
Order on Rehearing at 26, Finding of Fact No. R7.
27
costs, generally, are those “costs associated with providing the capability to deliver energy
(primarily the capital costs of facilities).” Gulf States Utils. Co., 841 S.W.2d at 461; City of
El Paso, 851 S.W.2d at 898 (“‘Capacity costs’ refer to one element of the price charged
by a seller of electric power—an element that represents the seller’s fixed costs in
generating the power.” Energy-only charges reflect “the seller’s variable costs in
generating the power—the cost of fuel, for example.”). TCC asserts there is not substantial
evidence to support this decision and that the Commission acted arbitrarily and
capriciously.
Conversely, in their first issue, the Cities complain that the Commission did not go
far enough in disallowing TCC’s capacity costs. The Cities allege that the Commission
erred by (1) failing to find certain purchases to contain capacity; (2) using an inaccurate
method of quantifying the approximately $1.96 million of costs the Commission disallowed;
and, in the alternative, (3) allowing an unreasonable price to be paid for the summer 2001
purchases, if those purchases are considered energy purchases without embedded
capacity.
A. TCC’s Sixth Issue: Whether the Commission Properly Included Capacity Costs
in its Final Fuel Reconciliation
1. Factual and Procedural Background
a. Original Proceeding
TCC requested that more than $75 million in purchased-power contracts be
reconciled. The purchases at issue did not contain an explicit, separate charge for
capacity. The ALJs originally concluded that $29.6 million of these expenses were implicit
capacity costs and recommended their exclusion. The ALJs’ original recommendation
28
quantified the implicit capacity costs using a method the Commission had rejected in El
Paso Electric Company’s fuel reconciliation.31 The Commission declined to adopt the
portion of the original proposal for decision recommending the exclusions and remanded
this issue back to the ALJs.
b. Remand Proceedings
The order on remand stated that the Commission could not determine whether
“specific contracts or other documents contain language indicating that [TCC] was
purchasing capacity” in any of its purchased-power contracts. On remand, the
Commission instructed the ALJs to take additional evidence to determine whether TCC’s
purchased-power contracts contained implicit capacity, and if so, to quantify the costs so
that they could be excluded from the final reconciliation.
i. The Evidence on Remand
On remand, the ALJ received evidence primarily from three witnesses: Naim Hakimi,
who at the time was the Director of Power Cost Recovery with AEPSC; Scott Norwood, on
behalf of Cities; and Randall Falkenberg, for the Office of Public Utility Council. To
evaluate this additional evidence, the ALJ was guided by the Commission’s order on
remand that directed the ALJ to Docket 2619432 and alluded to the Commission’s decision
in Entergy.33 As enunciated by the ALJ on remand, the factors she was to follow were:
31
See Petition of El Paso Electric Company to Reconcile Fuel Costs, Docket No. 26194, Final Order
(May 5, 2004) (finding im proper a m ethod of quantifying im plicit energy costs that involved com paring firm
energy contracts with the cost of providing power from a utility’s least efficient generating plants) available at
http://interchange.puc.state.tx.us (last visited 12/15/2008).
32
El Paso, Docket No. 26194, Final Order (May 5, 2004).
33
Application of Entergy Gulf States, Inc. for the Authority to Reconcile Fuel Costs, Docket No. 23550,
Final Order (Aug. 2, 2002) available at http://interchange.puc.state.tx.us (last visited 12/15/2008).
29
(1) in El Paso, a contractual definition of “firm power service” as including
“firm capacity with reserves” and “capacity purchases”;
(2) in El Paso, that the utility purchased the power to serve native load
and purchased additional power during the peak summer months of
the contract;
(3) in Entergy, internal meeting notes that state that the utility should
“[l]ock in ‘No Capacity Cost’ options” and “[a]ttempt to restructure
some proposals [for purchased power] to shift capacity costs to
energy costs”;
(4) in Entergy, that the contracts at issue were found to contain a
capacity component by the Louisiana Public Service Commission;
and
(5) in Entergy, the utility’s admission that its more recent “energy-only”
purchases contained a capacity component.
The ALJ summarized these factors by stating, “The Order on Remand . . . seems to focus
primarily on the language used by the utility, and in particular whether the language of the
contracts themselves or of other company documents mentions capacity.”
ii. Identifying the Contracts Containing Capacity Costs in 1999, 2000,
and 2001
Hakimi asserted that the disputed purchases during 1999, 2000, and 2001 did not
contain capacity costs and that when TCC purchased capacity during the reconciliation
period, those costs were separated from energy-only purchases. Norwood and
Falkenberg, on the other hand, discussed contracts by TCC they believed contained
characteristics meeting some of the factors laid out by the Commission. They also
provided TCC documents they claimed satisfied some of the factors as well.
Ultimately, Norwood made two alternate recommendations. First, he recommended
a disallowance of $22.73 million, and in the alternative, he recommended a disallowance
of $14.57 million. Both recommendations were quantified using a method in which he took
30
the explicit capacity charge—$11.625/kilowatt (“kW”) month—under one of TCC’s capacity
contracts and used it as a proxy to determine the total embedded capacity costs in the
contracts he urged contained capacity costs. The ALJ rejected Norwood’s first proposal
because it followed the same identification procedure previously rejected by the
Commission. Norwood’s second proposal identified seventeen contracts that contained
capacity according to company documentation, one of the factors mentioned by the
Commission.
Falkenberg’s recommendations included three contracts for the summer of 1999.
The ALJ found that the evidence presented by Falkenberg and Norwood, while disputed
by Hakimi, supported the conclusion that these three contracts included implicit capacity
costs.
Falkenberg then identified nine transactions in the spring of 2000, which he
contended contained capacity costs. The ALJ rejected this characterization, as the
evidence did not support a finding of embedded capacity and because many of the
transactions were to replace power lost during the steam generator replacement at STP
that had already been excluded by the Commission.
For the summer of 2000, Falkenberg identified two contracts, and Norwood
recommended the same. However, on one of the contracts, Falkenberg and Norwood
disagreed as to the amount of capacity purchased for TCC. The ALJ agreed with
Norwood’s identification of 100 MW as capacity purchased for TCC. With that adjustment,
the ALJ found that both summer 2000 contracts contained embedded capacity costs.
For the summer of 2001, the ALJ did not agree wholesale with either Falkenberg’s
or Norwood’s recommendations. However, the ALJ did find that four purchases, identified
31
by Hakimi, included capacity costs. In summary, the ALJ identified three contracts for the
summer of 1999, two for summer 2000, and four for summer 2001 that included embedded
capacity costs.
iii. Quantifying the Capacity Costs
To quantify these capacity costs, the ALJ determined that the order on remand
directed her to quantify the costs by following El Paso.34 In El Paso, capacity costs were
quantified using the Western Systems Power Pool price cap along with a general
recommendation of a market-based approach.35 In the instant case, there was no price
cap, so the ALJ relied on Norwood’s and Hakimi’s recommendations which were both
market-based—they looked at TCC’s contracts that contained capacity in order to
determine proxies by which to quantify capacity costs in the nine identified transactions.
The ALJ ultimately followed, and the Commission adopted, Hakimi’s proposed proxies of
$1.53/kW month, $2.31/kW month, and $2.15/kW month for the years 1999, 2000, and
2001 respectively. The total disallowance adopted by the ALJ based on these proxies was
$1,619,750. The Commission, in its order on rehearing, adopted these recommendations
but amended the final tally to correct a “math error” asserted by TIEC. The amendments
resulted in a proxy of $2.50/kW month for 1999 and $2.57/kW month for 2000, with
$2.15/kW month for 2001 remaining the same. The resulting amount disallowed by the
Commission was $1,962,750. TCC asserts that the findings of capacity and the
quantification of the capacity are not supported by substantial evidence and are arbitrary
34
See El Paso, Docket No. 26194, Final Order (May 5, 2004).
35
Id. at 5, 29, Finding of Fact No. 17B (May 5, 2004).
32
and capricious. We disagree.
2. Standards of Review: Substantial Evidence & Arbitrary and Capricious
Under the substantial evidence rule, we must uphold the Commission’s decision if
a reasonable basis exists in the record for the decision, even if the evidence preponderates
against the decision. See Charter Med.-Dallas Inc., 665 S.W.2d at 453. An agency acts
in an arbitrary and capricious manner when it (1) fails to consider a factor the legislature
required it to consider; (2) considers an irrelevant factor; or (3) considers only relevant
factors, yet reaches an unreasonable result. See City of El Paso, 883 S.W.2d at 184.
Additionally, when the agency fails “to follow the clear, unambiguous language of its own
regulation,” it acts arbitrarily and capriciously. Office of Pub. Util. Counsel v. Pub. Util.
Comm'n of Tex., 185 S.W.3d at 564.
In a fuel reconciliation, a utility is prohibited from recovering capacity costs. 16 TEX .
ADMIN . CODE § 25.236(a)(4). The Commission is permitted to go beyond the express
language of purchased-power contracts to determine whether embedded capacity costs
are included in the expenses presented for reconciliation. See Entergy Gulf States, Inc.
v. Pub. Util. Comm’n of Tex., 173 S.W.3d 199, 211 (Tex. App.–Austin 2005, no pet.).
3. Analysis
Here, the Commission, through the proceeding on remand, received testimony
indicating that nine purchased-power contracts included capacity costs. The Commission
followed the ALJ’s acceptance of the majority of Falkenberg’s identification of capacity
costs in contracts. The Commission is the sole judge of the weight and credibility of the
witnesses, and we will not interfere with that role here. See Reliant Energy, Inc. v. Pub.
33
Util. Comm’n of Tex., 153 S.W.3d 174, 203 (Tex. App.–Austin 2004, pet. denied); TEX .
GOV’T CODE ANN . § 2001.174. The evidence presented amounts to a reasonable basis in
the record for the Commission’s decision that the nine transactions included capacity costs
and that these costs amounted to approximately $1.96 million. See generally Charter
Med.-Dallas, Inc., 665 S.W.2d at 453 (setting forth the substantial evidence rule).
The legislature did not present the Commission with any factors for the Commission
to use in determining whether the transactions included capacity costs nor by which the
Commission could quantify those costs. See City of El Paso, 883 S.W.2d at 184 (noting
that an agency acts arbitrarily and capriciously by failing to follow factors the legislature
mandates, following irrelevant factors, or reaching an unreasonable result). The
Commission’s fuel rules do not contain a methodology by which capacity costs may be
identified and quantified. See 16 TEX . ADMIN . CODE § 25.236. The Commission reached
a reasonable result. See City of El Paso, 883 S.W.2d at 184. The Commission did not act
arbitrarily and capriciously.
B. The Cities’ First Issue: Whether the Commission Properly Included Certain
Capacity Costs in TCC’s Final Fuel Reconciliation
The Cities’ first issue is essentially TCC’s sixth issue in reverse. The Cities argue
that the Commission violated Commission rule 25.236(a)(4) by including capacity costs in
TCC’s eligible fuel expense. See 16 TEX . ADMIN . CODE § 25.236(a)(4). The Cities claim
that the violation occurred by either of two actions, taken by the Commission, that allowed
capacity costs to be included in TCC’s fuel reconciliation: (1) the Commission deprived the
Cities of due process, or (2) the Commission’s decision was arbitrary and capricious.
Ultimately, the Cities identify nine contracts from summer 2001 that the Commission found
34
to not include capacity and claim the Commission erred by imputing only approximately
$1.96 million as capacity costs, none of which came from the nine contracts identified by
the Cities.
1. Standards of Review: Procedural Due Process & Arbitrary and
Capricious
In a contested-case hearing, a party’s due process rights are violated when the
agency fails to notify the parties of the grounds upon which the agency will rely in reaching
a final decision. Langford v. Employees Retirement Sys. of Tex., 73 S.W.3d 560, 566
(Tex. App.–Austin 2002, pet. denied). Also, “when an agency adopts new policy in the
course of a contested-case hearing without giving the parties pre-hearing notice, the
parties may be deprived of procedural due process.” Flores v. Employees Retirement Sys.
of Texas, 74 S.W.3d 532, 544 (Tex. App.–Austin 2002, pet. denied).
An agency acts in an arbitrary and capricious manner when it (1) fails to consider
a factor the legislature required it to consider; (2) considers an irrelevant factor; or (3)
considers only relevant factors, yet reaches an unreasonable result. See City of El Paso,
883 S.W.2d at 184. Additionally, when the agency fails “to follow the clear, unambiguous
language of its own regulation,” it acts arbitrarily and capriciously. Office of Pub. Util.
Counsel v. Pub. Util. Comm’n of Tex., 185 S.W.3d at 564.
2. The Cities’ Due Process Rights
First, the Cities challenge the Commission’s decision alleging it violated their due
process rights “by failing to provide notice of a comprehensible standard to be used in
identifying capacity purchases and abandoning, without explanation, prior Commission
precedent.” The Cities allege that, in its order on remand, the Commission failed to identify
35
a standard by which to identify capacity costs in a purchased-power contract.
The Commission, in its order on remand, set forth the grounds upon which the ALJ
should determine whether any of TCC’s purchased-power contracts contained embedded
capacity costs. See supra Part VII.A. The Commission did not violate the Cities’ due
process rights by failing to notify the parties of the grounds upon which it would rely in
determining whether any of TCC’s purchased-power contracts contained capacity costs.
The Cities further assert that their due process rights were violated because the
Commission did not “explain deviations from established policy or precedent.” See Flores,
74 S.W.3d at 544-45 (“Courts, however, frequently require that an agency explain its
reasoning when it ‘appears to the reviewing court that an agency has departed from its
earlier administrative policy or there exists an apparent inconsistency in agency
determinations.’”) (citing City of El Paso, 851 S.W.2d at 900). The Cities complain that the
Commission offered no explanation for not using the “reliability and firmness of supply”
standard the Cities allege was established in Entergy.36 In its order on remand, the
Commission referred the ALJ to El Paso, which was decided subsequent to Entergy.37 In
El Paso, the Commission found that a contract entered into by El Paso Electric Company
contained capacity costs because the “contract contained language indicating that there
was a capacity component,” and because the “contract was for a long-term purchase and
was made in advance as part of [El Paso Electric Company’s] planning process designed
36
See Entergy, Docket No. 23550, Order at 17-18, Finding of Fact 59A (Aug. 2, 2002).
37
Com pare El Paso, Docket No. 26194, Final Order (May 5, 2004); Entergy, Docket No. 23550, Order
(Aug. 2, 2002).
36
to meet [its] resource needs for reliability.”38 The Commission also specifically deleted the
ALJ’s Finding of Fact No. 27, which read, “A capacity, as opposed to an economic,
purchase is characterized by a purchase price in excess of the fuel cost for generation and
a need to ensure reliability or firmness of power to the utility’s base load.”39 By deleting
Finding of Fact No. 27 in El Paso, the Commission indicated that “reliability and firmness
of supply” is not the sole factor for determining whether a purchased power contract
contains capacity costs as the Cities now imply.
By referring to both Entergy and El Paso in its order on remand, the Commission
was not abandoning precedent or policy without explanation, as El Paso did not require a
showing of “reliability and firmness of supply” in order to find embedded capacity in the
purchased power contracts in that contested case. Additionally, by directing the ALJ on
remand to follow El Paso and Entergy, the Commission set forth the standard by which it
would determine whether purchased-power contracts contain capacity costs. The Cities’
due process rights were not violated.
3. Arbitrary and Capricious Action
Next, the Cities allege that the Commission acted arbitrarily and capriciously by
failing “to exclude capacity costs associated with [TCC’s] summer 2001 purchases.” The
Cities identify nine contracts for the summer of 2001 and assert that these nine contracts
took the place of contracts previously part of TCC’s 2001 Power Supply Plan that were
38
El Paso, Docket No. 26194, Final Order at 4.
39
Id. at 7; Proposal for Decision, Finding of Fact No. 27 (Sept. 22, 2003).
37
“booked out.”40 According to the Cities, the booked out contracts contained capacity costs,
so by replacing the booked out contracts with the nine other contracts, TCC was still
acquiring capacity. Additionally, the Cities claim that “[t]hese contracts had the same
characteristics, same terms and provided the same reliability and firmness of supply as the
purchases considered to be capacity by the Commission.”
In its order on remand, the Commission listed the factors by which the ALJ should
determine whether TCC’s purchased power contracts contained capacity. The Cities
complain that the Commission reached an unreasonable result. Here, the Commission
and the ALJ on remand evaluated the summer 2001 contracts identified by the Cities and
determined that, based on the grounds listed in the order on remand, the contracts did not
contain capacity. As the ALJ on remand noted:
Norwood and Falkenberg both relied on [TCC’s] communication with the
Commission as the relevant documentary evidence that the 425 MW were
purchased in part as “capacity.” However, while the purchases selected by
Mr. Norwood were much like those booked out, it appears there is no direct
link between that documentation and most of the 2001 contracts identified
in Mr. Norwood’s recommendation. Based on this evidentiary record, the
ALJ is unable to find that the corporate documents indicate the transactions
at issue were executed for “capacity” purposes.41
Because the evidence before the Commission did not indicate embedded capacity in the
nine contracts identified by the Cities, as measured on the grounds laid out in the order on
40
A “booked out” transaction occurs when there are opposing buy-sell transactions. For exam ple,
A sells 100 MW to B and B sells 90 MW to A. Instead of A delivering all 100 MW to B and B delivering all 90
MW to A, the transactions are booked out, resulting in the transactions being treated as a sale of 10 MW from
A to B. Revised Public Utility Filing Requirements, 67 F ED . R EG . 31,044; 31,062-63.
41
Application of Central Power and Light Company for Authority to Reconcile Fuel Costs, Docket No.
27035, Proposal for Decision on Rem and at 26 (Jan. 12, 2005).
38
remand, the Commission did not reach an unreasonable result.42 The Commission did not
act arbitrarily and capriciously. The Cities’ first issue is overruled.
VIII. THE CITIES’ SECOND ISSUE: THE AMOUNT OF IMPUTED CAPACITY
The Cities argue, in their second issue, that the Commission erred in quantifying the
amount of imputed capacity found in the purchased-power contracts. See supra, Part VII.
A. Background
The Commission adopted proxy capacity charges based on recommendations
provided by TCC. The Commission used $2.50/kW month for 1999, $2.57/kW month for
2000, and $2.15/kW month for 2001. The Cities claim these proxies are inappropriate
because they represented an average capacity charge over the course of each respective
year and not capacity charges for summer peak capacity that is more expensive. The
Cities recommended using as a proxy a single, summer of 1999 contract wherein TCC paid
$11.625/kW month for capacity. The ALJ on remand rejected this approach because it
reflected only one contract over the three year reconciliation period. The ALJ decided that
even though the Cities’ and TCC’s approaches had “serious flaws,” TCC’s “represents the
most defensible approach, in that it reflects more than just a single contract from the three-
year period.”
42
U nderlying the Cities’ argum ents in their first issue is a disagreem ent with the grounds for
determ ining capacity costs identified in the Com m ission’s order on rem and. W e note that even the
Com m ission has com m ented on the lack of clarity and variety of definitions surrounding “capacity.” See El
Paso, Docket No. 26194, Final Order at 4 (May 5, 2004). Here, the Com m ission set forth the grounds it
considered im portant in identifying capacity, and it followed those grounds in deciding to include or exclude
certain costs. “[The substantial evidence] standard affords great deference to the Com m ission's decisions
on topics that the legislature has determ ined are within the agency's discretion. . . .” Nucor Steel, 168 S.W .3d
at 267. “‘T EX . U TIL . C OD E A N N . generally confers authority upon the Com m ission to regulate and supervise
public utilities, to fix and regulate rates of public utilities, and to insure rates, operations, and services [ ] are
just and reasonable to the consum ers and to the utilities.’” Id. (citing Pub. Util. Comm'n v. GTE-Sw, Inc., 901
S.W .2d 401, 407 (Tex.1995)).
39
B. Standard of Review: Substantial Evidence
Under the substantial evidence rule, we must uphold the Commission’s decision if
a reasonable basis exists in the record for the decision, even if the evidence preponderates
against the decision. See Charter Med.-Dallas Inc., 665 S.W.2d at 453.
C. Analysis
In the order on remand, the Commission directed the ALJ to quantify any capacity
costs she found by using a method consistent with El Paso.43 In El Paso, the Commission
adopted a proxy based on a price cap in place with WSPP and general market-based
principles.44 All parties involved in this reconciliation agree that there is no ERCOT price
cap in place similar to the WSPP price cap. The ALJ on remand took a market-based
approach in considering what proxy to use to quantify capacity costs.
Hakimi recommended the proxy numbers upon with the ALJ based her decision.
He noted that the proxies reflect average capacity contract prices paid by TCC during the
reconciliation period on contracts that expressly stated capacity costs. Such evidence
presents a reasonable basis in the record upon which the Commission could base its
decision to use TCC’s recommended proxies. See generally Collins v. Tex. Nat. Res.
Conservation Comm’n, 94 S.W.3d 876, 881 (Tex. App.–Austin 2002, no pet.) (discussing
the substantial evidence rule).
The Cities, however, argue that the mere existence of substantial evidence is not
enough, and they cite cases reflecting that some courts require a rationale between the
43
See El Paso, Docket No. 26194, Final Order (May 5, 2004).
44
Id. Final Order at 5, 29, Finding of Fact 17B.
40
agency’s decision and the fact.45 The rationale provided by the ALJ on remand and
adopted by the Commission is that the proxies chosen by the Commission reflect capacity
prices during the entire three years of the reconciliation period. The ALJ and the
Commission chose not to follow the Cities’ recommended proxy as it reflected only one
contract from 1999 and not any capacity prices during the rest of the reconciliation period.
Here, as the Cities requested, the Commission demonstrated a “rationale between the
facts and the agency’s decision.” The Cities’ second issue is overruled.
X. THE CITIES’ THIRD ISSUE: THE PRICE PAID FOR PURCHASED -POWER CONTRACTS NOT
CONTAINING CAPACITY
By their third issue, the Cities make two arguments. First, the Cities contend that
the Commission failed to determine whether TCC paid a reasonable price for the
purchased-power contracts not found to contain capacity. See supra, Part VII. Second,
because some of the purchased-power contracts did not contain capacity costs, the Cities
argue that the prices paid for the energy were unreasonable and unnecessary per se. The
Cities base this argument in the fact that the price paid for the energy in some of the
contracts was higher than the cost of TCC generating that energy itself.
A. Did the Commission Fail to Rule on this Issue?
After the ALJs completed the original proposal for decision, the Commission
remanded the case back for a determination on the capacity issue. The ALJ on remand
presented a proposal for decision on the remanded issues as those issues were
45
In support of this proposition, the Cities cite the following cases: City of El Paso, 883 S.W .2d at
184; Flores, 74 S.W .3d at 544-45; Nat'l Assoc. of Indep. Insurers v. Tex. Dep't of Ins., 888 S.W .2d 198, 207
(Tex. App.–Austin 1992), rev'd on other grounds, 925 S.W .2d 667 (Tex. 1996); Gulf States Utils. Co., 841
S.W .2d at 474-75; Starr County v. Starr Indus. Svcs., Inc., 584 S.W .2d 352, 356 (Tex. App.–Austin 1979, writ
ref'd n.r.e.)).
41
designated in the Commission’s order on remand. The Commission adopted the ALJ’s
proposal for decision on remand with modifications not relevant to this issue.
In the Commission’s order on rehearing, in which the Commission adopted the
ALJ’s decision on remand, Finding of Fact R13 lists the transactions in which the ALJ and
the Commission found embedded capacity. The purchases about which the Cities
complain were not on that list. In Finding of Fact R12 in the order on rehearing, the
Commission also determined that most of “TCC’s on-peak block purchases were made to
supply system load and operating reserve requirements.” Additionally, for these remaining
transactions—included in eligible expenses—that the Cities argue are unreasonable, the
Commission made Conclusion of Law 37: “During the reconciliation period, TCC’s eligible
fuel expenses, as modified by the findings of fact and conclusions of law, are reasonable
and necessary expenses that were incurred to provide reliable electric service to retail
customers pursuant to P.U.C. SUBST . R. 25.236(d).” Thus, contrary to the Cities’ argument,
the Commission has ruled on this issue.
B. Were the Prices Paid Unreasonable?
The Cities’ argument that the prices paid were unreasonable and unnecessary per
se is also unavailing. The basis of this argument is that a utility, acting reasonably, would
not pay more for energy-only purchases than it would cost the utility to produce that energy
itself. In El Paso, the Commission rejected such an argument.46 In that contested case,
the Commission noted such a “construct fails to account for [the utility] buying a pure
46
See El Paso, Docket No. 26194, Final Order at 6 (May 5, 2004).
42
energy contract.”47 The Commission also stated that “the mere possibility of a pure energy
purchase destroys [such a] construct, and thus undermines” the conclusion that a
reasonable utility would not pay more for purchased energy than it would cost to produce
that energy itself.48
The Cities also argue that if the Commission has determined that the prices paid
were reasonable and necessary, it did so without any rationale or justification. The Cities
cite to City of El Paso, in which the Austin Court of Appeals determined that through
providing for judicial review of contested cases, the legislature “implies a power [in the
reviewing court] to require the Commission to supply any reasons or explanations
necessary for the reviewing court to understand the Commission’s final order.” City of El
Paso, 851 S.W.2d at 900. In that case, the Austin Court of Appeals held that the
Commission was required to provide a justification for the definition it gave to a certain term
when that definition led to different results in two different proceedings before the
Commission. Id. at 901.
In the present case, we need not require the Commission to go to such lengths.
The Commission’s order on rehearing clearly determined that those purchases not
excluded for containing capacity costs were reasonable and necessary energy-only
purchases. The Cities’ third issue is overruled.
XI. THE CITIES’ FOURTH ISSUE: THE DEPARTMENT OF ENERGY OVERCHARGES
In their fourth issue, the Cities allege the Commission erred by not excluding
47
Id.
48
Id.
43
approximately $3.5 million in overcharges by the United States Department of Energy
(“DOE”).
A. Background
The DOE provided uranium enrichment services to the owners of STP, which
includes TCC. During the contested case hearing, it was revealed that DOE had
overcharged for these services. These overcharges occurred from 1986 through 1993 and
had been charged to TCC’s customers through the fuel factor in previous reconciliations.
Because these expenses were incurred outside the present reconciliation period, the
Commission reversed the ALJs’ recommendation that the $3.5 million should be excluded
from reconcileable expenses in TCC’s final fuel reconciliation. TCC has sued DOE to
recover the overcharges. Thus, the Commission also ordered that, should TCC recover
anything in the lawsuit, the recovery should be placed into the nuclear decommissioning
fund. See generally 10 C.F.R. § 50.75 (2008); TEX . UTIL. CODE ANN . § 39.205 (Vernon
2007); 16 TEX . ADMIN . CODE § 25.231(b)(1)(F); 16 TEX . ADMIN . CODE § 25.301.
The Cities argue that the expenses previously passed on to customers have now
been determined to be unreasonable and unnecessary and therefore are not recoverable
under the fuel rule. See 16 TEX . ADMIN . CODE § 25.236(d)(1)(A) (permitting recovery of
only those expenses that are necessary and reasonable). Additionally, the Cities claim that
the Commission acted without legal basis in deciding to require TCC to give any recovery
it may receive from its lawsuit against DOE to the nuclear decommissioning fund. TCC
counters by asserting that pending litigation should not be considered in a reconciliation
proceeding.
44
B. Should the Pending Litigation be Considered in This Reconciliation?
In Houston Lighting & Power Co., the Texas Supreme Court held that, in a rate
proceeding, pending litigation should not be considered. Pub. Util. Comm’n of Tex. v.
Houston Lighting & Power Co., 748 S.W.2d 439, 442 (Tex. 1987). The Commission
followed this precedent in other reconciliation proceedings.49 The Commission was
required by law to not include pending litigation in this fuel reconciliation.
C. Are the Expenses Now Unreasonable and Unnecessary?
The Cities assert that the expenses previously found to be reasonable and
necessary are now acknowledged to be unreasonable and unnecessary. The
Commission’s rules dictate that only those expenses incurred during the reconciliation
period are reconcilable in a fuel reconciliation proceeding. 16 TEX . ADMIN . CODE §
25.236(d)(2). The fact that these expenses occurred before the present reconciliation
period is undisputed. Additionally, the Commission has previously ruled that issues
reviewed and resolved in a prior proceeding cannot be revisited in a later proceeding.50
Here, the Commission followed its precedent and refused to litigate expenses subject to
review during a prior reconciliation period.
49
See Application of Gulf States Utils. Co. To Reconcile Its Fuel Costs, Establish New Fixed Fuel
Factors, and Recover Its Underrecovered Fuel Costs, P.U.C. Docket No. 10894, 19 P.U.C. Bull.1401, 1993
W L 655241 at *124, Finding of Fact No. 23 (Tex. P.U.C., Aug. 19, 1993) (Final Order) (deferring a decision
on certain issues until concurrent litigation was concluded); Entergy, Docket No. 23550, Order at 15, 28,
Finding of Fact No. 42, Conclusion of Law No. 7 (Aug. 2, 2002) (postponing a decision on certain issues until
the outcom es of an insurance claim and a warranty claim were finalized).
50
See Application of Houston Lighting & Power Co. for Reconciliation of Fuel Costs, P.U.C. Docket
No. 10092, 1992 W L 814024, at *20, 39, Finding of Fact No. 12 (Tex. P.U.C., Feb. 18, 1992) (Exam iner's
Report) ("Having previously determ ined that the choice of the flam e scanner design used in Parish and
Lim estone was prudent, the Com m ission is precluded by res judicata from reconsidering that issue in this
case."); Petition of General C ounsel for a Fuel Reconciliation for Southwestern Public Service Co., P.U.C.
Docket No. 9030, 1991 W L 790253, at *40, 42, Finding of Fact No. 16, Conclusion of Law No. 9 (Tex. P.U.C.,
June 3, 1991).
45
D. Should Lawsuit Proceeds be Turned Over to the Nuclear Decommissioning
Fund?
Recognizing that, should TCC recover any amount in its lawsuit against DOE, that
amount would represent overcharges already passed on to its customers, the Commission
decided to require TCC to pass any recovery from the lawsuit over to the nuclear
decommissioning fund. The Commission was correct in deciding, as mentioned above,
that the present reconciliation is not the place for addressing whether such a still unrealized
recovery should be credited to TCC’s customers. The Cities counter, however, that the
Commission should have, in this fuel reconciliation, credited to TCC’s customers the
amount it seeks in its lawsuit. The Cities argue that since this is the final fuel reconciliation
for TCC, all fuel-related expenses should be reconciled. We agree with the Cities to the
extent that the expenses were incurred during the reconciliation period. Here, however,
the expenses were incurred prior to the reconciliation period. Additionally, the Commission
was left with the decision of what to do should TCC recover in the lawsuit against the DOE.
The Commission decided to order TCC to pass any recovery into the decommissioning
trust fund. We agree with the Commission that this decision properly respects Commission
precedent relating to reviewing matters that were the subject of prior proceedings and is
a reasonable resolution to the potential double-recovery TCC would get should TCC win
its lawsuit. See Texaco Producing, Inc. v. Fortson Oil Co., 798 S.W.2d 622, 626 (Tex.
App.–Austin 1990, no writ) (holding that under the substantial evidence doctrine, “[t]he
reviewing court is concerned not with the correctness of the administrative order, but with
its reasonableness.”) (citing Firemen's and Policemen's Civil Svc. Comm'n v. Brinkmeyer,
662 S.W.2d 953, 956 (Tex.1984)). The Cities’ fourth issue is overruled.
46
XII. THE CITIES’ FIFTH ISSUE: COSTS ASSOCIATED WITH AN OUTAGE AT STP
In their fifth issue, the Cities object to the Commission including, in reconcilable fuel
expenses, the replacement costs associated with an outage at STP during May 2001.
A. Factual and Procedural Background
The outage at issue occurred when STP personnel connected a laptop to a “Hart
adapter” used to monitor Feedwater Regulating Valves. The personnel used the laptop
to record data concerning the operation of these valves. Before connecting the laptop, the
personnel asked the vendor whether the adapter was polarity sensitive, and the vendor
stated that polarity did not matter. Initially, the personnel connected a laptop with a two-
prong, AC adapter and successfully tested the adapter. Then, the personnel connected
a laptop with a three-prong AC adapter to perform the actual monitoring. Essentially, the
third prong shorted signal wires which then started a process culminating in the valve
closing and the reactor tripping. TCC incurred replacement power costs to cover the costs
associated with this outage, and the ALJs recommended that TCC not recover these
expenses, asserting that the approximately $800,000 was imprudently incurred. The
Commission overruled the ALJs, stating: “TCC STP personnel exhibited appropriate
caution in asking the vendor about the polarity sensitivity of the Hart adapter and in running
a test of the monitoring equipment.” The Cities allege that the Commission failed to
properly apply the prudence standard. Additionally, the Cities assert that the Commission
acted arbitrarily and capriciously by failing to apply the Commission’s standard, mentioned
in Conclusion of Law No. 29, that “human error rarely shields the utility from responsibility.”
47
B. Analysis
A utility is permitted to recover its reasonable and necessary expenses. See 16
TEX . ADMIN . CODE § 25.236(d)(1)(A); Cities of Abilene, 146 S.W.3d at 746. To be a
reasonable and necessary expense, the cost must have been prudently incurred. See
Gulf States Utilities Co., 841 S.W.2d at 466. Again, in this context, “prudence” means
the exercise of that judgment and the choosing of one of that select range
of options which a reasonable utility manager would exercise or choose in
the same or similar circumstances given the information or alternatives
available at the point in time such judgment is exercised or option is chosen.
Entergy Gulf States, Inc., 112 S.W.3d at 210 n.2. The prudence standard also
contemplates that
[t]here may be more than one prudent option within the range available to a
utility in any given context. Any choice within the select range of reasonable
options is prudent, and the Commission should not substitute its judgment
for that of the utility. The reasonableness of an action or decision must be
judged in light of the circumstances, information, and available options
existing at the time, without benefit of hindsight.
Nucor Steel, 26 S.W.3d at 752 (citing with approval the Commission’s prudence standard
prohibiting reliance on hindsight).
As evidence of imprudence, the Cities point to reports prepared by TCC and filed
with the Nuclear Regulatory Commission (“NRC”). “In response to the reactor trip, an
Event Review Team was formed” that drafted the STP Condition Report 01-8043
(“Condition Report”). The Condition Report, dated June 7, 2001 and submitted by TCC to
NRC, noted two root causes of the event. One root cause was inadequate management
oversight and the other was that “[p]ersonnel did not recognize the laptop PC and Hart
adapter as test equipment with the potential to introduce a ground path” and “testing was
48
insufficient to detect the ground path.” Significantly, the Condition Report noted that
“[o]perating experience reviews did not find any cases where use of a laptop computer
contributed to plant events.” And, while “there have been numerous occasions where
grounded test equipment has caused plant events,” “[t]he use of a laptop was not
considered as test equipment in regards to previous operating experience.” The Condition
Report also commented:
The feedwater control valves are designated in the Master Equipment
Database as non-safety related/not risk significant (NRS). 0PG03-ZA-0090
(Work Process Program) has minimal requirements for working on non risk
significant Structures, Systems, and Components (SSC). Because of this,
planning for the job did not require detailed research. Also, because this
was classified as “not risk significant”, the job did not require a heightened
level of management involvement.
(emphasis added). Finally, the Condition Report also stated, “Operator actions were
prudent and timely.”
In the order on rehearing, the Commission noted that the use of documents, such
as the Condition Report, to judge the prudence of STP personnel does not amount to an
improper use of hindsight. This conclusion applied generally to all six power outages and
one power reduction at STP that the Commission was evaluating under the prudence
standard. See Order on Rehearing at 30, Conclusion of Law No. 28; but see Order on
Rehearing at 22, Finding of Fact No. 76(c) (finding that “[n]o disallowance should be made
in connection with [the outage caused by the laptop]”). However, regarding this specific
outage, we believe the Condition Report does use improper hindsight in the manner the
Cities use it to support their contentions. Based on the above-quoted statements, the
Condition Report establishes that the STP personnel prudently consulted with the vendor
regarding whether the adapter was polarity sensitive. The designation of the feedwater
49
control valves as “non-safety related/not risk significant” meant that “planning for the job
did not require detailed research” and “did not require a heightened level of management
involvement.” In “light of the circumstances, information, and available options existing at
the time,” STP personnel and management acted prudently. See Nucor Steel, 26 S.W.3d
at 752. As was also indicated in the quoted statements from the Condition Report, the
outage was not caused by mere human error. The Cities’ fifth issue is overruled.
XIII. THE CITIES’ SIXTH ISSUE: SPOT MARKET COAL PURCHASES
In their sixth issue, the Cities allege the Commission erred by allowing TCC to
reconcile spot market coal purchases made in response to conditions at the Coleto Creek
coal plant.
A. Factual Background
Coleto Creek historically burned bituminous coal from South America and Colorado.
In the 1990s, TCC constructed a facility at Coleto Creek, allowing it to burn coal from the
Powder River Basin blended with the Colorado or South American coal. TCC purchased
the bituminous coal under a long-term contract with Kennecott Energy Company
(“Kennecott”). During late 2000 and early 2001, Coleto Creek experienced an operational
condition that caused the plant to consume more Colorado coal than had been expected.
Under the Kennecott contract, to purchase coal for 2001, TCC was required to specify the
amount it would purchase in 2001 by April 1, 2000. The need to purchase additional coal
was discovered after April 1, 2000, so TCC could not purchase additional coal under the
Kennecott contract and was forced to seek additional coal on the spot market. Of the
competitive bids TCC received, Oxbow Minings, Inc. provided the lowest delivered cost per
50
unit of power, and TCC acquired the needed coal from Oxbow.
B. Analysis
The Cities argue that TCC’s customers should not be held responsible when
operational conditions result in increased expenses.51 We agree with the Cities that
ratepayers are entitled to a reasonable level of performance from the generation resources
whose costs are included in the rates paid by the customers.52 We disagree with the Cities’
assertion that we must go outside the prudence and substantial evidence standards when
reviewing the Commission’s decision in this instance. The Cities cite three cases in
support of their contention, and all three utilized the prudence standard.53
According to the Commission’s order on rehearing, based on confidential testimony,
the Commission found that TCC exceeded its targeted blend of 50% Colorado coal in total
burning, lending credibility to TCC’s assertion that the plant conditions necessitated
additional use of Colorado coal. TCC also experienced an unanticipated reduction in coal
51
See Texas Utilities Electric Company, Docket No. 15195, Final Order at 9 (Aug. 26, 1997) (holding
that due to the nature of the extraordinary 19-m onth outage, the utility's shareholders bear the burden of the
expenses even absent a showing of im prudence).
52
See id. at 10.
53
See id. at 9-10 (noting that costs associated a 19-m onth outage caused by a chim ney collapse were
im prudent, but even if they were not, the Com m ission would still hold the utility's shareholders responsible for
the costs of the "extraordinary" outage under an "equity and risk allocation standpoint"); but see Application
of Gulf States Utils. Co. To Reconcile ifs Fuel Costs, for Permission to Delay Requesting a Surcharge, or in
the Alternative, for a Surcharge to Recover Under-Recovered Fuel Expense, Docket No. 15102, Order at
Rehearing at 4 (June 26, 1997) ("W hile the traditional application of the prudence standard is appropriate in
this case, circum stances m ay dictate otherwise in the future, as long as the utility is given proper notice of
what standard the Com m ission will em ploy.") available at http://interchange.puc.state.tx.us (last visited
12/15/2008).; Application of Entergy Texas for Approval of its Transition to Competition Plan and the Tariffs
Implementing the Plan, and for Authority to Reconcile Fuel Costs, to Set Revised Fuel Factors, and to
Recover a Surcharge for Under-Recovered Fuel Costs, Docket No. 16705, Second Order on Rehearing at
55, Finding of Facts 10-13 (Oct. 14, 1998) (holding that the utility had not shown the additional expenses were
the "reasonable and necessary result of prudent changes" and therefore disallowing the increased expenses)
available at http://interchange.puc.state.tx.us (last visited 12/15/2008).
51
inventory coinciding with its increased need for Colorado coal. As a result of these
circumstances, TCC sought competitive bids and chose the one giving TCC the lowest
cost. Marguerite C. Mills, Director, Regulated Oil & Gas Administration for AEPSC,
testified that the conversion of the plant to burn the blended coal resulted in significant
savings for the ratepayers. This evidence supports the Commission’s conclusion that the
Oxbow purchases were prudent, reasonable, and necessary. The Commission decided
what testimony to credit and not credit, and we will not substitute our judgment for its
judgment. See TEX . GOV’T CODE ANN . § 2001.174 (Vernon 2008). The Cities’ sixth issue
is overruled.
XIV. Conclusion
Having overruled all of the issues presented by both TCC and the Cities, we affirm
the ruling of the district court affirming the Commission’s Order on Rehearing.
___________________________
GINA M. BENAVIDES,
Justice
Opinion delivered and filed this
the 22nd day of December, 2008.
52