USA for u v.

USCA1 Opinion






November 29, 1993 [NOT FOR PUBLICATION]

UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT



____________________

No. 93-1541

UNITED STATES OF AMERICA, for
u/b/o LUIS A. CABRERA, S.E.
A SPECIAL PARTNERSHIP,

Plaintiff, Appellee,

v.

SUN ENGINEERING ENTERPRISES, INC.,
AND CNA CASUALTY OF PUERTO RICO,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF PUERTO RICO

[Hon. Jos Antonio Fust , U.S. District Judge]
___________________

____________________

Before

Breyer, Chief Judge,
___________

Coffin, Senior Circuit Judge,
____________________

and Torruella, Circuit Judge.
_____________

_____________________

Federico Lora-L pez for appellants.
___________________
Thomas Doran-Gelabert, with whom Eduardo Castillo-Blanco was
_____________________ _______________________
on brief for appellee.



____________________


____________________

















Per Curiam. This case concerns an action brought under
__________

the Miller Act, 40 U.S.C. 270a-f (1986), in the name of the

United States for the use and benefit of Luis A. Cabrera, S.E.

("Cabrera"), a subcontractor, against Sun Engineering

Enterprises, Inc. ("Sun Engineering"), a general contractor, and

its surety, CNA Casualty of Puerto Rico ("CNA"). In the

complaint, Cabrera claimed money it was due under a subcontract

with Sun Engineering. After a non-jury trial, the United States

District Court for the District of Puerto Rico awarded Cabrera

$44,769.25. Sun Engineering then filed this appeal claiming that

the district court improperly amended the pre-trial order at

trial, and that there was insufficient evidence to support the

court's findings of fact. For the reasons stated herein, we

affirm.

I. BACKGROUND
I. BACKGROUND

We review the facts in favor of the prevailing party at

trial, Cabrera. See American Title Ins. Co. v. East West
___ __________________________ __________

Financial Corp., 959 F.2d 345, 346 (1st Cir. 1992). Sun
________________

Engineering is a construction company which was the prime

contractor for a federal project involving partially renovating

the United States General Post Offices in San Juan, Puerto Rico

("the Project"). Cabrera was a subcontractor on the Project. On

December 21, l989, Mr. Luis Cabrera submitted a price quotation

to Mr. Francisco Jim nez, the president of Sun Engineering, which

detailed, item by item, the work which the Project blueprints and

specifications required with respect to supplying and installing


-2-














vinyl floors, dry wall partitions, and acoustical ceilings. The

quotation estimated the cost of the work to be $106,707.35.1

Mr. Cabrera and Mr. Jim nez then discussed the precise terms of

the quotation. On January 8, l990, Sun Engineering sent a letter

to Cabrera accepting Cabrera's December 21, l989 quotation.

Although the parties had negotiated some changes to the work

specified in the quotation, and a reduced "estimated" contract

price of $80,000, an absolute price for the contract was never

agreed upon. Rather, Cabrera and Sun Engineering informally

agreed that Sun Engineering would pay Cabrera based on the work

Cabrera actually performed.

After the contract was formed, Cabrera commenced work.

During the course of the Project, Mr. Jim nez verbally requested

that Cabrera perform additional work not encompassed by the

original contract. This work involved floor underlays. Mr.

Ismael El as, the designer of the Project who also served as the

Project inspector for the Post Office, also verbally requested

Cabrera to make changes with respect to some partitions it was

installing. Cabrera completed all work required on the Project

by June 5, l99l.

Cabrera billed Sun Engineering $105,495.39 for the work

it performed. Sun Engineering made progress payments to Cabrera

totalling $60,726.14. Sun Engineering refused to pay Cabrera the

____________________

1 At trial, there was some dispute regarding the precise dollar
figure of this initial quotation. The present appeal does not in
any way turn upon the exact figure of this initial quotation, and
for the purposes of this opinion, we will assume that $l06,707.35
was the correct figure.

-3-














balance of $44,769.25.

Cabrera then filed suit. As its defense, Sun

Engineering claimed that the contract was for a total price of

$80,000, and therefore, Sun Engineering only owed Cabrera

$l9,273.86. Sun Engineering also claimed that Cabrera

negligently performed its work, and delayed the completion of the

Project.

After trial, the district court found that the parties

entered into an informal contract. In accordance with the

contract, Cabrera was entitled to be paid $105,495.39 for the

work it had performed on the Project. The court found that

Cabrera was not responsible for any Project delays. Because Sun

Engineering had only paid Cabrera $60,726.14, the court entered

judgment in Cabrera's favor in the amount of $44,769.25.

Sun Engineering then filed this appeal. Sun

Engineering makes three arguments on appeal. Sun Engineering

contends that 1) by allowing a modification of the pre-trial

order at trial, the district court permitted Cabrera to introduce

evidence with respect to the cost of the contract that

contradicted a stipulated fact, and changed Cabrera's theory of

its case, in violation of Fed. R. Civ. P. 16(e); 2) the evidence

presented at trial did not support the district court's

conclusion that valid change orders were issued to Cabrera; and

3) the record does not support the district court's finding that

Cabrera was not responsible for Project delays. Sun

Engineering's arguments are meritless.


-4-














II. THE RULE 16 CHALLENGE
II. THE RULE 16 CHALLENGE

In the final pre-trial order, the parties stipulated

that "the agreed price on said subcontract was $80,000." At

trial, Cabrera introduced its December 21, l989 quotation for

$106,707.35 as an exhibit. Sun Engineering objected to the

introduction of this exhibit on the ground that the parties had

stipulated that there was a contract for $80,000, and that this

evidence, which suggested a different price for the contract,

contradicted that stipulation. The court overruled Sun

Engineering's objection and permitted Cabrera to introduce the

exhibit because the court believed that the quotation was

relevant to the negotiations between the parties, and what the

parties intended to be the terms of the contract. On appeal,

Sun Engineering argues that the court violated Fed. R. Civ. P.

16(e)2 by effectively amending the pre-trial order at trial and

permitting Cabrera to introduce evidence which contradicted a

stipulated fact, and which changed Cabrera's theory of its case.

A trial court has broad discretion to preserve the

integrity and purpose of the pre-trial order. Roland M. v.
_________

Concord School Comm., 910 F.2d 983, 999 (lst Cir. l990), cert.
_____________________ _____

denied, 499 U.S. 912 (1991). An appellate court should exercise
______

____________________

2 Federal Rule of Civil Procedure l6(e) provides in pertinent
part:

[A pre-trial order] shall control the
subsequent course of the action unless
modified by a subsequent order. The
order following a final pretrial
conference shall be modified only to
prevent manifest injustice.

-5-














minimal interference with a trial court's interpretation of a

pre-trial order and a court's decision to permit the introduction

of evidence, or exclude evidence, based on that interpretation.

See Ram rez Pomales v. Becton Dickinson & Co., S.A., 839 F.2d 1,
___ _______________ ____________________________

3 (1st Cir. l988); Geremia v. First Nat'l Bank of Boston, 653
_______ ___________________________

F.2d 1, 5 (lst Cir. l981); 6 Charles A. Wright, Arthur R. Miller

& Mary K. Kane, Federal Practice & Procedure 1527, at 279-286
_____________________________

(1990). "Unless there is manifest injustice or the district

court has abused its discretion to the point of being arbitrary,"

the court's ruling will not be disturbed. Nickerson v. G.D.
_________ ____

Searle & Co., 900 F.2d 412, 422 (lst Cir. l990); Ram rez Pomales,
____________ _______________

839 F.2d at 3.

Federal Rule of Civil Procedure l6 provides that at the

final pre-trial conference the participants shall formulate a

plan for trial. Ram rez Pomales, 839 F.2d at 3. After the pre-
_______________

trial conference, an order shall be entered reciting the action

taken, and this order then controls the subsequent course of the

action, unless modified by a subsequent order. Fed. R. Civ. P.

l6(d),(e); Ram rez Pomales, 839 F.2d at 3. The interpretation of
_______________

a pre-trial order is the responsibility of the trial court. A

trial court should construe the pre-trial order liberally so that

it covers any of the possible legal or factual theories that

might be embraced by its language. Geremia, 653 F.2d at 5
_______

(quoting Rodr gues v. Ripley Indus., Inc., 507 F.2d 782, 787 (lst
_________ ___________________

Cir. l974) (citing 6 C. Wright & A. Miller, Federal Practice &
___________________

Procedure l527, at 609 & n.47 (l971))).
_________


-6-














Contrary to Sun Engineering's contention, the district

court did not amend the pre-trial order. Rather, the court

reviewed the pre-trial order, and based on its interpretation of

that order, found that the exhibit Cabrera proposed to introduce

was admissible. The district court's actions were not an abuse

of discretion. After Sun Engineering objected to the

introduction of the exhibit, the court reviewed the factual

stipulation in the context of Cabrera's legal theory, which was

also set out in the pre-trial order. The court found that the

introduction of the exhibit by Cabrera was consistent with its

theory of the case. Pursuant to the contract, Cabrera was

entitled to be paid on the basis of the work it actually

performed. The December 21, l989 quotation and the subsequent

change orders established the work that Cabrera was to perform.

While the factual stipulation did provide that the agreed cost of

the contract was $80,000, the court stated that it would simply

defy logic to find that Cabrera stipulated that the absolute

price of the contract was $80,000, in light of its theory of the

case. Rather, the court found that the only reasonable

interpretation of the stipulation was that it referred to an

agreed "estimated" contract cost of $80,000. The court acted

within its discretion in interpreting the stipulation and pre-

trial order in this manner, and we will not disturb its ruling.

III. THE CHANGE ORDERS
III. THE CHANGE ORDERS

Sun Engineering argues that in light of federal

regulations which purportedly require all change orders on


-7-














government projects to be in writing, the evidence was

insufficient to support a finding that valid change orders were

issued to Cabrera.

An appellate court will review a district court's

findings of fact in a bench trial for clear error. Dedham Water
____________

Co. v. Cumberland Farms Dairy, Inc., 972 F.2d 453, 457 (lst Cir.
___ ____________________________

l992); Fed. R. Civ. P. 52(a).3 A finding is clearly erroneous

when the reviewing court is left with the definite and firm

conviction that a mistake has been committed. See Dedham Water,
___ ____________

972 F.2d at 457. Mixed questions of fact and law, which require

a court to determine if certain facts possess, or lack, legal

significance in a given case, are also reviewed for clear error.

Roland M., 910 F.2d at 990. Absent a showing that the court made
_________

a mistake of law, we will give effect to the trial's courts

findings. Id. at 990-91.
___

The record supports the district court's factual

findings that change orders were issued to Cabrera. Mr. Cabrera

and Mr. Jim nez testified that after Cabrera submitted the

____________________

3 Federal Rule of Civil Procedure 52(a) provides in pertinent
part:

In all actions tried upon the facts
without a jury . . . the court shall find
the facts specially and state separately
its conclusions of law thereon, and
judgment shall be entered pursuant to
Rule 58 . . . . Findings of fact,
whether based on oral or documentary
evidence, shall not be set aside unless
clearly erroneous, and due regard shall
be given to the opportunity of the trial
court to judge of the credibility of
witnesses.

-8-














original quotation to Mr. Jim nez detailing the work Cabrera

proposed to do, Mr. Jim nez requested that Cabrera make certain

changes to the quotation. Mr. Cabrera also offered undisputed

testimony that after the parties entered into the original

contract, Mr. Jim nez orally requested that Cabrera perform work

beyond that encompassed in the contract with respect to floor

underlays. Mr. Jim nez and Mr. El as both testified that Mr.

El as also orally requested Cabrera to do additional work with

respect to partitions, that Mr. Jim nez was aware of this

request, and that Cabrera made those requested changes.

Cabrera claims that even if oral changes were issued to

Cabrera, they were of no legal consequence. There is no

requirement, however, that change orders to subcontractors on

government projects be in writing and approved by the government

to be legally binding. Despite Sun Engineering's contention to

the contrary, 48 C.F.R. 43.201 (1992) does not impose such a

requirement.4 Part 43 of the Code of Federal Regulations

generally addresses government policies and procedures for

preparing and processing contract modifications. 48 C.F.R.

43.000 et seq. (1992). The regulations are directed to
__ ____

____________________

4 48 C.F.R. 43.201(a) (1992) provides in pertinent part:

Generally, Government contracts contain a
changes clause that permits the
contracting officer to make unilateral
changes, in designated areas, within the
general scope of the contract. These are
accomplished by issuing written change
orders on Standard Form 30, Amendment of
Solicitation/Modification of Contract
(SF 30), unless otherwise provided.

-9-














government contracting officers and those parties who contract

directly with them. Section 43.20l is specifically directed at

the procedures which the government's contracting officer should

follow when issuing a change order to its contracting partner.

Generally, the relationship covered by the regulation is that

between the officer and the prime contractor on a government

project. The regulation does not apply to more remote parties,

such as subcontractors, who contract solely with the prime

contractor. We have been unable to find any other statutory or

regulatory requirement which purports to control the prime

contractor's relationship with its subcontractors with respect to

the logistics of contract modifications, such as change orders.5

The prime contractor/subcontractor relationship is

governed by the terms of the contract between the parties. See,
___

e.g., United States for Control Systems, Inc. v. Arundel Corp.,
____ ________________________________________ _____________

814 F.2d 193, 196-97 (5th Cir.), modified on other grounds, 826
__________________________

F.2d 298 (5th Cir. 1987). In the present case, the court found

that the contractual dealings between Cabrera and Sun Engineering

were informal at best. The parties never signed a final written

contract. Moreover, there was no oral or written contractual

provision which required that any change orders issued to Cabrera

had to be in writing, or approved by the contracting officer, in


____________________

5 In its brief, Sun Engineering points to the testimony of
Mr. El as and Mr. Delgado, an architect who worked for the Post
Office, who both stated that change orders were generally
accomplished through written directives. Their testimony,
however, also referred to the relationship between the government
and the prime contractor.

-10-














order to be valid. Therefore, the oral change orders at issue

were legally binding, and the district court properly found that

Cabrera was entitled to be paid for the work performed pursuant

to those orders. This finding is in accord with the general

purpose of the Miller Act, 40 U.S.C. 270a-f (1986), a remedial

statute, enacted to assure that all workers and subcontractors on

government projects received compensation for their efforts. See
___

F.D. Rich Co. v. United States for Use of Indus. Lumber Co., 417
_____________ __________________________________________

U.S. 116, 124 (l974).

IV. DELAY CLAIM
IV. DELAY CLAIM

Sun Engineering contends that the district court's

finding that Cabrera was not responsible for Project delays is

unsupported by the record. We disagree and find that the

evidence amply supports the court's findings. Mr. Cabrera, Mr.

Delgado and Mr. El as all offered uncontradicted testimony that

Cabrera completed all required work on the Project. There was

evidence that Cabrera did correct some deficiencies in its work

after the scheduled completion date of the Project. With the

exception of the testimony of Mr. Jim nez, however, the record is

void of any evidence that this "delay" translated into any

financial penalty to Sun Engineering. While Mr. Jim nez

testified that Sun Engineering was financially penalized for

delays which were in fact caused by Cabrera, Mr. El as offered

conflicting testimony to the effect that Sun Engineering was

solely responsible for the delays. The trial court refused to

credit Mr. Jim nez' testimony. It was well within the court's


-11-














discretion to determine whether or not it found Mr. Jim nez to be

a credible witness. See Dedham Water Co., Inc., 972 F.2d at 461.
___ ______________________

There was no error in the court's findings.

V. DOUBLE COSTS
V. DOUBLE COSTS

Because Sun Engineering filed a frivolous appeal, we

find it appropriate to assess a monetary penalty of double costs

against it. Federal Rule of Appellate Procedure 38 provides that

"[i]f a court of appeals shall determine that an appeal is

frivolous, it may award just damages and single or double costs

to the appellee." Westcott Constr. Corp. v. Firemen's Fund of
_______________________ __________________

New Jersey, 996 F.2d 14, 17 (lst Cir. l993). An appeal is
__________

frivolous if the "result was obvious" or the arguments are

"wholly without merit." Id. "[I]t is enough that the appellants
___

and their attorney should have been aware that the appeal had no

chance of success." E.H. Ashley & Co. v. Wells Fargo Alarm
__________________ __________________

Servs., 907 F.2d 1274, 1280 (lst Cir. l990). Sun Engineering's
______

arguments on appeal are wholly without merit. There is no legal

support for Sun Engineering's Fed. R. Civ. P. 16(e) challenge, or

its contention that change orders issued to Cabrera had to be in

writing to be legally binding. The record also amply supports

the trial judge's factual findings, and there are simply no

reasonable grounds to challenge the sufficiency of the evidence.

We therefore award Cabrera double costs.








-12-