Hewlett-Packard v. Berg

USCA1 Opinion











UNITED STATES COURT OF APPEALS UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT FOR THE FIRST CIRCUIT
____________________

No. 94-2251

HEWLETT-PACKARD COMPANY, INC.,

Plaintiff, Appellant,

v.

HELGE BERG, ETC., ET AL.

Defendants, Appellees.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Joseph L. Tauro, U.S. District Judge] ___________________

____________________

Before

Boudin, Circuit Judge, _____________

Bownes, Senior Circuit Judge, ____________________

and Stahl, Circuit Judge. _____________

____________________

Richard Allan Horning with whom Horning, Janin & Harvey, Kevin P. _____________________ ________________________ ________
Light, Choate, Hall & Stewart and Robert W. Sutis were on brief for _____ _______________________ _______________
appellant.
David A. Burman for appellees. _______________


____________________

August 3, 1995
____________________


















BOUDIN, Circuit Judge. Hewlett-Packard appeals from an _____________

order of the district court confirming an arbitration award

rendered in a business dispute with appellees Helge Berg and

Lars Skoog and rejecting Hewlett-Packard's requests for a

stay of the confirmation proceeding or a declaration that it

is entitled to a set-off for the award. The case presents

several difficult legal issues which can be understood only

after a brief description of the facts and prior proceedings.

I. BACKGROUND I. BACKGROUND

In March 1982, Apollo Computer, now owned by Hewlett-

Packard, entered into a two-year distributorship contract

with a Swedish company called Dicoscan Distributed Computer

Scandinavia to sell Hewlett-Packard products in several

Nordic countries. The 1982 contract included an agreement to

submit any dispute under the contract to binding arbitration.

In March 1984, the parties executed a new distributorship

contract, which also contained an arbitration clause.

In the meantime, during 1983 and 1984, Dicoscan

experienced financial problems. In mid-1984, Apollo claimed

that Dicoscan was far behind in its payments. In September,

Apollo terminated the 1984 agreement. The following month,

Dicoscan filed for bankruptcy. The bankruptcy court assigned

to Berg and Skoog, directors and officers of Dicoscan, the

right to bring claims against Apollo based on the contracts.





-2- -2-













Berg and Skoog filed a request for arbitration with the

International Chamber of Commerce Court of Arbitration,

claiming millions of dollars of damages arising out of

Apollo's unilateral termination of the 1984 agreement.

Apollo counterclaimed in the arbitration by asserting that

the Swedish company had failed to pay about $10,000 due on

the 1984 contract and about $207,000 due under the 1982

contract. After a dispute about Berg and Skoog's right to

invoke arbitration, see Apollo Computer, Inc. v. Berg, 886 ___ _____________________ ____

F.2d 469, 473 (1st Cir. 1989), an arbitration proceeding was

begun.

The arbitrators were required by the parties' contracts

to apply Massachusetts law. Ultimately, the arbitrators

awarded around $700,000 plus interest to Berg and Skoog, but

allowed a set-off for the $10,000 that Dicoscan still owed

Apollo under the 1984 contract. To both parties' surprise,

the tribunal held that it was without jurisdiction to decide

Apollo's more substantial claim based on the 1982 contract,

ruling that the 1982 contract was not within the Terms of

Reference issued by the arbitrators at the beginning of the

proceeding.

As a result, Apollo was left with a sizable obligation

to Berg and Skoog on the 1984 contract without a

determination of its claim for more than $207,000 on the 1982

contract. Apollo unilaterally decided to pay the arbitration



-3- -3-













award amount but subtracted the $207,000 plus interest

(together, about $300,000) as a "setoff in recoupment,"

which, it said, is a time-honored common law doctrine

embraced in Massachusetts courts. Apollo also filed a

request with the tribunal for a second arbitration regarding

the 1982 contract. That tribunal has indicated that it will

hear the arbitration.

In January 1993, Apollo (later succeeded as the

plaintiff by Hewlett-Packard) filed the complaint in this

action with the Massachusetts district court. Hewlett-

Packard requested that the district court (1) declare that

Hewlett-Packard was entitled to the $207,000 set-off and that

the arbitration award is fully satisfied, and (2) vacate the

tribunal's award and correct it. Hewlett-Packard later

withdrew its second claim for relief.

Berg and Skoog moved to dismiss the complaint, arguing

that such declaratory relief is unavailable as to foreign

arbitration awards. Later, Berg and Skoog moved for

confirmation of the arbitration award. Hewlett-Packard

opposed confirmation of the award on the ground that, by

failing to include its 1982 set-off, the award was contrary

to public policy. In the alternative, Hewlett-Packard moved

to stay confirmation, pending the outcome of the second

arbitration. Hewlett-Packard also asked the court to compel

arbitration as to its 1982 claim.



-4- -4-













On November 7, 1994, the district judge filed a

memorandum, together with a separate order, disposing of all

of these motions. The court's order compelled arbitration

under the 1982 contract but it confirmed the award previously

made by the tribunal on the 1984 contract. The court said

that it was without power to stay the confirmation

proceeding, as Hewlett-Packard had requested, and that the

request for a set-off was an improper attempt to modify the

tribunal's award.

Apparently ready to enforce the now-confirmed

arbitration award, Berg and Skoog moved the court for entry

of final judgment, and proffered a detailed judgment

specifying the award, interest and attorney's fees. Four

days later, Hewlett-Packard filed its notice of appeal and

thereafter filed a response disputing certain aspects of the

proposed judgment. The district court has not acted on the

motion for entry of final judgment; and no such judgment has

been entered.

II. DISCUSSION II. DISCUSSION

Hewlett-Packard purports to appeal all three of the

district court's adverse actions: the confirmation of the

arbitration award, the refusal to stay that confirmation

proceeding pending the outcome of the second arbitration; and

the rejection of Hewlett-Packard's set-off claim declaration.

Commendably, Hewlett-Packard has alerted us to a possible



-5- -5-













jurisdiction problem, which this court is obliged to

consider. We do so but caution future panels that the

jurisdictional problems have not been briefed in this case.

Nothing in the record in this case purports to be a

"final judgment," set forth in a separate document as

required by Fed. R. Civ. P. 58, disposing of all claims.

Thus, in formal terms there is no basis for appeal of a

"final decision" under 28 U.S.C. 1291, even if the court

actually resolved all of the claims before it. Indeed, as

already noted, the defendants have pending a motion that

requests entry of a "final judgment."

Nevertheless, the November 7 order, insofar as it

confirms the arbitration award, is appealable now because

Congress directed in the statute governing arbitration-

related appeals that such an "order" confirming an award

should be immediately appealable. 9 U.S.C. 16(a)(1)(D).

The reason is a pro-arbitration policy designed to expedite

confirmation of arbitration awards. This is clear from

precedent and scholarly commentary. See, e.g., 15B C. __________

Wright, A. Miller & E. Cooper, Federal Practice and Procedure ______________________________

3914.17, at 9-12, 32-34 (2d ed. 1992).

There is one technical hitch. Seemingly, the order

confirming the award is not itself a judgment that can be

collected through court processes until it is entered on the

docket as a judgment. See 9 U.S.C. 13. This has nothing ___



-6- -6-













to do with the final judgment rule; rather, the statute that

governs confirmations provides that after a confirmation is

ordered, a separate "entry of judgment" must be made pursuant

to that order, and it is only at that stage that "[t]he

judgment so entered . . . may be enforced as if it had been

rendered in an action in the court in which it is entered."

Id. ___

Nevertheless, the Federal Rules of Civil Procedure do

not say that appeals can only be taken from judgments; on the

contrary, they contemplate that, subject to the complex rules

that determine what is immediately appealable, there may be

such a thing as an "appealable order" that is not a judgment.

Fed. R. Civ. P. 79(b). And, as already noted, Congress has

designated as immediately appealable "an order . . .

confirming . . . an [arbitration] award." 9 U.S.C.

16(a)(1)(D).

Our position is not at odds with Middleby Corp. v. _______________

Hussmann Corp., 962 F.2d 614 (7th Cir. 1992). Middleby held _______________ ________

that no immediate appeal could be taken where the district

court issued an order of confirmation but declined to enter

judgment after making a specific determination to delay

giving effect to the confirmation order until further

proceedings were concluded. Here, by contrast, the district

court denied the requested stay, and the confirmation order

is immediately effective, requiring only the filing of



-7- -7-













specified papers with the clerk to permit "the entry of

judgment thereon." 9 U.S.C. 13.

Because the confirmation order is appealable, we think

that there is also before us Hewlett-Packard's claim that the

confirmation proceeding should have been stayed. The reason

is simply that the underlying argument for a stay is also an

objection to the confirmation order itself. To this extent,

it is effectively an interlocutory ruling made in the process

of approving the confirmation request and like any other such

interlocutory ruling it is reviewable at the time that the

confirmation order itself is brought up on appeal. Cf. ___

Stringfellow v. Concerned Neighbors in Action, 480 U.S. 370, ____________ ______________________________

375 (1987); 15A Wright, Miller & Cooper, supra, 3905.1, at _____

249-63.

A similar argument might also be made to justify an

appeal now based on the district court's refusal to declare

Hewlett-Packard's right to the set-off it asserted. The

problem is complicated, but we see no need to resolve the

complexities. Whether or not the refusal to allow the set-

off is an appealable issue, the refusal at this time turns

out not to be a legal error, so the jurisdictional issue need

not be decided. See Norton v. Matthews, 427 U.S. 524, 530-32 ___ ______ ________

(1976); In re Pioneer Ford Sales, 729 F.2d 27, 31 (1st Cir. ________________________

1984).





-8- -8-













We turn now to the merits. Hewlett-Packard does not

object to the confirmation of the award in all respects; it

says it has paid the award except the disputed amount

including interest. But Hewlett-Packard says that the

district court erred by confirming the award in full instead

of either allowing a set-off or granting a stay of the

confirmation pending the results of the new arbitration.

We agree with the district court's rejection at this

time of the first alternative. Whether Hewlett-Packard has a

valid claim under the 1982 contract is subject to

arbitration; we agree with the district court--and Hewlett-

Packard--that the tribunal has never resolved the merits of

that claim. Whatever the Massachusetts law on set-offs, the

district court could not allow the set-off at present without

determining that Hewlett-Packard had a valid claim, which is

the very subject of the arbitration.

It is hard to imagine a step that would be more

offensive to the pro-arbitration policies reflected in

Congress' endorsement of the 1958 Convention on the

Recognition and Enforcement of Foreign Arbitral Awards, often

called the New York Convention. The New York Convention was

approved by Congress, and implementing legislation was

codified at 9 U.S.C. 201-08. The statute enlists the aid

of federal courts to compel arbitration. 9 U.S.C. 206. By

contrast, the judicial set-off requested here would



-9- -9-













circumvent the 1982 contract to arbitrate and the now-pending

arbitration under that contract.

The request to defer confirmation of the award under the

1984 contract stands on a different footing. However the

case might stand absent the bankruptcy, Dicoscan's bankruptcy

gives Hewlett-Packard a very substantial prudential argument.

If the existing award were confirmed in full and reduced to

judgment, Hewlett-Packard would have to pay the full award to

the defendants as successors-in-interest of an insolvent

company. If in due course Hewlett-Packard then prevailed on

its claims against the insolvent company on a closely related

transaction, it would have no assurance of collecting

anything.

Further, Hewlett-Packard cannot be blamed for the

discrepant timing in the resolution of its claim, or at least

no argument to that effect has been made. After it was told

that the defendants did have arbitration rights despite an

anti-assignment clause in the contracts, Hewlett-Packard

apparently made a reasonable effort to have both the

defendants' claim and its own counterclaim resolved in one

proceeding at the same time. Only the arbitrators'

surprising interpretation of their mandate frustrated this

attempt.

Under these circumstances, the seemingly fair solution

would be to confirm the award in its uncontested part,



-10- -10-













reserving confirmation of the balance until the 1982 contract

dispute is arbitrated. The district court refused to

consider a stay of confirmation on the ground that it was

without power to do so. We fully understand the basis for

the district court's doubt about its authority, but we

conclude that it does have the power to issue a stay in the

peculiar circumstances of this case.

Ordinarily there could be no doubt that a court,

although obliged to decide a claim, would retain discretion

to defer proceedings for prudential reasons. Indeed, a

typical reason is the pendency of a related proceeding in

another tribunal. "[T]he power to stay proceedings is

incidental to the power inherent in every court to control

the disposition of the causes on its docket with economy of

time and effort for itself, for counsel, and for litigants."

Landis v. North Amer. Co., 299 U.S. 248, 254 (1936). ______ _______________

The question here is whether this traditional authority

is curtailed by the New York Convention and its implementing

legislation. The statute provides that, upon a petition for

confirmation, a district court "shall confirm the award _____

unless it finds one of the grounds for refusal or deferral of

recognition or enforcement of the award specified in the said

Convention." 9 U.S.C. 207 (emphasis added). Article VI of

the Convention is the only provision that deals with staying

confirmation. Article VI states:



-11- -11-













If an application for the setting aside or
suspension of the award has been made to a
competent authority [in the country where the award
has been made], the authority before which the
award is sought to be relied upon may, if it
considers it proper, adjourn the decision on the
enforcement of the award [and require a security].

The circumstances outlined in Article VI do not appear to

exist in this case. The question is whether a district court

may grant a stay in circumstances other than those authorized

in Article VI.

The fact that section 207 uses the word "shall" is not

decisive, because a stay is a deferral rather than refusal.

But the fact that the statute refers to the Convention and

the Convention lists a single ground for a stay could be

taken to exclude all other grounds under the principle of

expressio unius est exclusio alterius. That was, in __________________________________________

substance, the reasoning of the district court. However,

expressio unius is an aid to construction and not an ________________

inflexible rule. See, e.g., United States v. Massachusetts _________ ______________ _____________

Bay Transport. Auth., 614 F.2d 27, 28 (1st Cir. 1980). ______________________

Whatever we might think if the question were entirely open,

precedent informs our decision in this case. Domestic

arbitrations are governed by the United States Arbitration

Act (chapter 1 of Title 9) but not by the Convention (chapter

2 of Title 9). The Act states that, upon application, "the

court must grant [a confirmation] order unless the award is ____

vacated, modified, or corrected as prescribed in sections 10



-12- -12-













and 11 of this title." 9 U.S.C. 9 (emphasis added). But

courts routinely grant stays in such cases for prudential

reasons not listed in sections 10 and 11. E.g., Middleby, ____ ________

962 F.2d at 615-16.

Similarly, this court has held that district courts have

discretion to stay an action to compel arbitration pending ______

the outcome of related litigation, even though the Act states

that on a motion to compel the court "shall hear the parties"

and "shall proceed summarily to trial." 9 U.S.C. 4; see ___

Acton Corp. v. Borden, Inc., 670 F.2d 377, 383 (1st Cir. ____________ ____________

1982). In Acton, then-Judge Breyer held that, in drafting _____

the statute, Congress did not "intend[] a major departure

from the ordinary rule allowing one federal court to stay

litigation when another federal court is on the process of

deciding the same issue." We take the same view of Congress'

intentions in implementing the Convention.

Of course, a stay of confirmation should not be lightly

granted. A central purpose of the Convention--an

international agreement to which the United States is only

one of approximately one hundred signatories--was to expedite

the recognition of foreign arbitral awards with a minimum of

judicial interference. But the risk that the power to stay

could be abused by disgruntled litigants--real though that

risk is, see Spier v. Calzaturificio, 663 F. Supp. 871, 875 ___ _____ ______________





-13- -13-













(S.D.N.Y. 1987)--argues more for a cautious and prudent

exercise of the power than for its elimination.

Because the district court acted under a misapprehension

of its authority, we vacate the confirmation order and remand

for further proceedings. Whether confirmation or collection

of the award should be partially deferred pending the

resolution of the 1982 contract arbitration is a matter for

the district court to determine in the first instance.

Still, we think it would require some explanation if, in the

face of the equities of this case, the district court

concluded that the full award should be confirmed and

collected now.

The confirmation order is vacated and the matter is _______

remanded to the district court for further proceedings ________

consistent with this opinion.























-14- -14-