Hope Furnace Assoc. v. FDIC

USCA1 Opinion











UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________

No. 95-1505

HOPE FURNACE ASSOCIATES, INC.,
Plaintiff - Appellant,

v.

FEDERAL DEPOSIT INSURANCE CORPORATION,
as Receiver of Eastland Bank & Eastland Savings Bank,
Defendant - Appellee.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF RHODE ISLAND

[Hon. Raymond J. Pettine, Senior U.S. District Judge] __________________________

____________________

Before

Torruella, Chief Judge, ___________
Lynch, Circuit Judge, _____________
and Stearns,* District Judge. ______________

_____________________

Karen A. Pelczarski, with whom John H. Blish and Blish & ___________________ _____________ ________
Cavanagh were on brief for appellant. ________
Kathleen V. Gunning, Appellate Litigation Section, Federal ____________________
Deposit Insurance Corporation, with whom Ann S. DuRoss, Assistant _____________
General Counsel, Colleen B. Bombardier, Senior Counsel, John P. _____________________ _______
Parker, Senior Attorney, Federal Deposit Insurance Corporation, ______
Christopher M. Neronha, Hinckley, Allen & Snyder and John P. _______________________ __________________________ _______
Parker were on brief for appellee. ______



____________________

December 6, 1995
____________________

____________________

* Of the District of Massachusetts, sitting by designation.












STEARNS, District Judge. The plaintiff-appellant, Hope STEARNS, District Judge. ______________

Furnace Associates, Inc. ("Hope"), appeals from the entry of

summary judgment against it, claiming that Eastland Savings Bank

("Eastland"), the FDIC's predecessor in interest, reneged on a

binding commitment to finance a Hope real estate development. We

disagree and affirm the judgment of the district court, although

on a different ground than the one articulated by that court.

BACKGROUND BACKGROUND __________

Hope originally brought suit in Rhode Island Superior

Court. Eastland was afterwards declared insolvent by the Rhode

Island Director of Business Regulation. The FDIC, appointed as

Eastland's receiver, removed the case to the federal district

court in Rhode Island where, in due course, cross-motions for

summary judgment were heard.

Hope accused Eastland of defaulting on its obligations

under a loan commitment letter by pretextually demanding that

Hope obtain an unobtainable state environmental approval. The

FDIC argued that because Hope was not designated as the borrower

in the commitment letter, it was barred from maintaining the

action by the D'Oench, Duhme doctrine and 12 U.S.C. 1823(e). _______ _____

The FDIC also contended that Hope had defaulted on several

conditions precedent of the agreement, thus relieving Eastland of

any duty to perform.

The district court adopted the D'Oench, Duhme argument _______ _____

proffered by the FDIC and granted it summary judgment. The

district judge reasoned that the loan commitment had been


-2-












expressly extended to ENDA Associates, Inc., a partnership

affiliated with, but juridically independent from Hope. Hope

pointed unavailingly to bank records and to written admissions by

bank officials that should have alerted the FDIC to the fact that

the insertion of ENDA's name in the letter was the result of a

clerical blunder. The district court did not find it necessary

to address the contract issue, although it had been fully

briefed.

In light of the contemporaneous verification in

Eastland's records of Hope as the actual borrower, the FDIC no

longer relies on the D'Oench, Duhme argument. In its brief, the _______ _____

FDIC candidly and commendably makes the following concession.

The FDIC does not contend on appeal that
section 1823(e) [or D'Oench, Duhme] applies _______ _____
to bar Hope Furnace's assertion that it,
rather than ENDA, was the true borrower under
[the] Commitment Letter, or that it is the
proper party to contend that the Bank
breached its obligations thereunder. Here,
the record appears to reveal the clear intent
of the parties that Hope Furnace, rather than
ENDA, was the intended borrower despite the
Commitment Letter's express provisions to the
contrary.

Appellee's Brief, at 13-14.

The sole issue on appeal, therefore, is whether the

alternative ground for summary judgment urged by the FDIC before

the district court is valid. See Mesnick v. General Electric _______ _________________

Co., 950 F.2d 816, 822 (1st Cir. 1991). ___

FACTS FACTS _____

The commitment letter was signed on April 4, 1989.

Eastland promised to lend $1.5 million to finance a planned

-3-












development in Scituate, Rhode Island, if Hope succeeded in

fulfilling certain conditions by June 5, 1989. On July 26, 1989,

Eastland extended the compliance date to August 31, 1989. Ender

Ozsezen and David Verardo, the joint principals of Hope and ENDA,

agreed to personally guarantee the loan. The commitment letter

required that the loan be cross-collateralized and cross-

defaulted with an outstanding loan to an ENDA condominium project

(the Tamarac loan) on which a balance was then owing of $572,195.

Hope planned to subdivide a 125 acre parcel of

undeveloped land into fifty-six single family lots. At least

sixteen of the lots were to have municipal water. The remaining

lots would require more expensive groundwater wells.

Approximately $300,000 of the loan proceeds were to be used to

install the municipal water connections. This entailed laying

two pipelines, each extending some 3,000 feet from the parcel.

At the time the commitment letter was signed, it was unclear

whether construction of the connectors would impact an adjacent

wetlands, a matter of no small concern to Eastland.1

The commitment letter imposed two pertinent conditions.

First, that Hope obtain a letter from the Rhode Island Department

of Environmental Management ("DEM") "indicating that a Request

for Applicability Determination has been filed with said
____________________

1 Eastland made clear this concern in the opening paragraph of
the loan commitment letter by including municipal water access in
its definition of the subject parcel. "It is our understanding
that the property securing this loan consists of a parcel of land
containing approximately 125 acres and that it will be developed
into 16 buildable lots ranging in size from 1 1/2 to 2 1/2 acres
each with adequate road frontage and municipal water service."

-4-












department and that the subject parcel of land does not require a

Permit to Alter Wetlands." (Paragraph 37). And second, that

Hope provide Eastland with a certificate of a registered engineer

verifying the availability of utility service, storm drainage

facilities, sewerage connections and "such other facilities as

may be deemed necessary by the bank." (Paragraph 27).2

The commitment letter also contained several clauses

giving Eastland discretion to determine whether or not these

conditions had been met. Paragraph 39 provided that:

[t]he Bank shall reserve the right to cancel
and to terminate its obligations under this
commitment if any of the following occur:

a. Failure of the borrowers to comply, or
cause to be complied within the time
specified with any of the provisions or
conditions applicable to this commitment.

. . .

f. Any change subsequent to this commitment
deemed by the Bank to be material or
substantial in the assets, net worth or
credit standing of any borrower or other
person who shall become obligated to the Bank
under this commitment, or the taking of a
judgment against any said person which, in
the sole discretion of the Bank, materially
affect his credit standing . . . .

Finally, the letter stated that "[t]his commitment cannot be

changed, discharged, or terminated orally but only by an

____________________

2 The FDIC also claims that Hope breached Paragraph 38 of the
letter which required that Hope maintain any property in which
Eastland had a security interest (including Tamarac) free of
liens over the life of the loan. Hope argues, not implausibly,
that it was never in breach of Paragraph 38 because the loan was
never made. Moreover, Hope alleges that it had filed releases on
all liens on the Tamarac property on or before July 28, 1989.

-5-












instrument in writing signed by the party against whom

endorsement of any change, discharge or termination is sought."

(Paragraph 46).

Eastland's attorney, Robert Branca, provided Hope with

a draft of an engineer's certificate that Eastland would deem to

satisfy Paragraph 27 (and by implication, Paragraph 37) of the

commitment letter, namely

[t]hat construction and operation of the
Improvements will not involve the filling or
alteration of any stream, brook or other body
of water or any wetlands area nor the
discharge of any fill or other material into
the ground water . . . .

Hope's engineer meanwhile determined that installation of the

municipal water connectors would in fact have a disruptive impact

on the neighboring wetlands. Consequently, he refused to sign a

certificate in the form dictated by Eastland. On May 31, 1989,

Branca, having been made aware of the engineer's refusal,

provided Hope with a second, more flexibly worded draft. It

stated, in pertinent part,

[t]hat construction and operation of the
Improvements will not involve the filling or
alteration of any . . . wetlands area nor the
discharge of any fill or other material into
the ground water, except as hereinafter set
forth. The construction of the portion of
the Improvements involving construction of
the water line along Hope Furnace Road from
Route 116 to the Premises will require stream
crossings, and as such, come under the
jurisdiction of the [DEM]. In our
professional opinion, we and the Borrower can
work with DEM incorporating any suggestions
it may make (without unusual measures being
taken or unusual costs being incurred) in
order for DEM to make a determination that
such construction involves an insignificant

-6-












alteration of freshwater wetlands. There is
presently pending with DEM an application for
a determination of the impact on freshwater
wetlands of such construction and in our
experience, the same should be granted in 90
days . . . .

While the language of an acceptable certificate was being

negotiated, Hope's engineer declared bankruptcy. Before Hope's

new engineer (Gerhard Graf) could complete his investigation,

Eastland resolved to reject any engineer's certificate that

contemplated even an "insignificant" wetlands alteration unless

Hope obtained prior DEM approval.

On August 17, 1989, Eastland warned Verardo that

payments on the cross-collateralized Tamarac loan were past due

and reaffirmed the August 31, 1984 deadline for compliance with

the conditions of the commitment letter. Eastland also demanded

that Verardo "respond by August 25, 1989 as to how you plan to

resolve these issues." On August 19, 1989, DEM notified Verardo

that "[b]ased upon our observations and review, it is our

conclusion that Fresh Water Wetlands, as described by Section 2-

1-20 of the Fresh Water Wetlands Act, are present on or adjacent

to the subject property. These wetlands do fall under the

protection of the Department. . . . The approval of this

Department is required for any alteration proposed within the

above described wetland(s)."

The parties were unable to close on the loan by August

31, 1989, the date on which the loan agreement, by its terms,

expired. Four months later, on December 15, 1989, DEM reversed

itself. In a letter to Graf, DEM announced that "[i]t is the

-7-












determination of this Department that this [project] can be

approved as an INSIGNIFICANT ALTERATION of a freshwater wetland

. . . ." Hope was unable to secure alternative financing and

lost the Scituate property to foreclosure.

STANDARD OF REVIEW STANDARD OF REVIEW __________________

As with all questions of law, this court conducts a de

novo review of a district court's entry of summary judgment. Inn ___

Foods, Inc. v. Equitable Co-operative Bank, 45 F.3d 594, 596 (1st ___________ ___________________________

Cir. 1995). Accordingly, an appellate court is not restricted by

the district court's rulings of law, but is "free, on appeal, to

affirm [the] judgment on any independently sufficient ground."

Polyplastics, Inc. v. Transconex, Inc., 827 F.2d 859, 860-61 (1st __________________ ________________

Cir. 1987). See also Massachusetts Mutual Life Ins. Co. v. _________ _____________________________________

Ludwig, 426 U.S. 479, 480-81 (1976). ______

Summary judgment is appropriate when, based upon the

pleadings, affidavits, and depositions, "there is no genuine

issue as to any material fact, and [where] the moving party is

entitled to judgment as a matter of law." Fed. R. Civ. P. 56(c);

Gaskell v. Harvard Co-op Society, 3 F.3d 495, 497 (1st. Cir. _______ ______________________

1993). To succeed, "the moving party must show that there is an

absence of evidence to support the nonmoving party's position."

Rogers v. Fair, 902 F.2d 140, 143 (1st. Cir. 1990). "An issue is ______ ____

only 'genuine' if there is sufficient evidence to permit a

reasonable jury to resolve the point in the nonmoving party's

favor." NASCO, Inc. v. Public Storage, Inc., 29 F.3d 28, 32 (1st ___________ ____________________

Cir. 1994).


-8-












DISCUSSION DISCUSSION __________

The FDIC's main argument on appeal is that Hope's

failure to fulfill the wetlands conditions of the loan agreement

discharged Eastland from any duty to perform. "A condition

precedent is an act which must occur before performance by the

other party is due." Wood v. Roy Lapidus, Inc. 10 Mass. App. Ct. ____ _________________

761, 763 n.5 (1980). As Professor Corbin explains, "[c]onditions

precedent . . . are those facts and events, occurring

subsequently to the making of a valid contract, that must exist ____________

or occur before there is a right to immediate performance, before

there is a breach of contract, before the usual judicial remedies

are available." 3 A. L. Corbin, Corbin on Contracts 628 (1960) ___________________

(emphasis added). Because of the confusion engendered by the

often subtle distinctions between conditions subsequent and

conditions precedent, the American Law Institute (ALI) prefers

the more catholic term "conditions." See Restatement (Second) of ___

Contracts, Ch. 9, Topic 5, Conditions and Similar Events, at 159

(1981). The ALI defines a condition as "an event, not certain to

occur, which must occur, unless its non-occurrence is excused,

before performance under a contract becomes due." Id. 224, at __

160.

Although the FDIC claims that Hope failed to fulfill at

least three conditions of the agreement, its focus is on

Paragraph 37. Hope argues that Paragraph 37 did not obligate it

to obtain prior DEM approval of any wetlands alteration. Hope _____

points out that it fulfilled the first requirement of Paragraph


-9-












37 when it provided Eastland with the DEM letter of August 19,

1989, confirming Hope's petition for an Applicability

Determination. Hope gamely contends that this same letter

fulfilled the second requirement of Paragraph 37, namely that it

obtain a determination by DEM that "the subject parcel of land

does not require a Permit to Alter Wetlands." The essence of

Hope's argument is that the clause cannot mean what it says.

Hope argues that it was "inartfully drafted," and that

"technically, there is no DEM regulation or applicable law

pursuant to which one may obtain a letter from the DEM that a

parcel of land does not require a permit to alter wetlands."

A more plausible reading of Paragraph 37 is that it

reflected Eastland's unwillingness to extend the Scituate loan

without the protection of a comfort letter from DEM. Eastland's

circumspection in this regard was not unreasonable. Regulatory

entanglement can be the deathknell of even the most carefully

conceived development, particularly if its backers (as evidenced

by their irresolute performance on the Tamarac loan) are in a

parlous financial state. Perhaps more significant, the premise

of Hope's argument, impossibility, is fatally compromised by

DEM's December 15, 1989 letter. While Hope argues that DEM's

ultimate change of heart lends credence to its supposition that

Eastland seized on DEM'S August demurrer as a pretext for

scuttling the agreement, the December DEM letter appears to be

precisely the type of assurance that Eastland was looking for,




-10-












and which Hope contradictorily maintains was impossible to

obtain.

Hope next argues that the engineer's certificate

contemplated by Paragraph 27 sufficiently addressed Eastland's

concerns regarding the water connections, including any interim

difficulties with DEM. In other words, Hope contends that

Paragraph 27 impliedly waived the requirement of prior DEM

approval of the alterations, so long as Hope could produce an

engineer who would promise that DEM would ultimately relent.

Hope also pounces on the fact that Paragraph 37 speaks of

wetlands alterations "on" the subject parcel, while the

alterations that Hope was to undertake would affect wetlands

adjacent to the site. This purported distinction is somewhat

beside the point. The clear intent of the disputed Paragraphs,

when they are read as a contextual whole rather than as

grammatical shards, was to protect Eastland from the eventuality

that disapproval by DEM would force the entire project into

default. That the construction of the two 3,000 foot pipelines

would occur in wetlands adjacent to rather than "on" the site

does not alter the fact that DEM opposition to the connectors

would impact directly on the project's viability.

The fact that Eastland's second draft of the engineer's

certificate would have tolerated "an insignificant alteration" of

the wetlands on the assurance that it would be ultimately

acceptable to DEM makes no difference. It still remained for

Hope to produce such a certificate in a timely fashion (it did


-11-












not). Moreover, the draft did not commit Eastland to accept the

certificate of any engineer, particularly one that was bankrupt. ___

Even to the extent that Eastland's second draft certificate could

be seen as an offer to compromise the terms of Paragraph 37, the

offer was never effectively accepted by Hope. That Eastland

chose to withdraw the draft and revert to the more stringent

terms of Paragraph 37 is not under the circumstances surprising

or the least bit objectionable.3

As a last resort, Hope cites the deposition testimony

of two Eastland officers, Lenssen, and his supervisor, Fournier,

both of whom participated in the decision to allow the loan

commitment to lapse. Lenssen's testimony can be read to suggest

that, in his opinion, the lack of DEM approval of the connector

project would not ordinarily have been a deal breaker. Fournier

testified more or less to the same effect. Hope argues that this

evidence is sufficiently material to preclude summary judgment.

The opinion of a loan officer that a breach of a particular

condition might not in the ordinary course have caused the bank

to cancel a loan agreement does not alter the fact that material

conditions of this agreement were never fulfilled. Eastland's ____
____________________

3 So too with regard to ENDA's default on the cross-
collateralized Tamarac loan. Hope argued below that "Eastland
waived any ability to rely on any default' of the Tamarac
loan . . . [because p]rior to August 1, 1989, Eastland entered
into negotiations with ENDA for an extension of the Tamarac loan
. . . and Eastland previously had . . . not required ENDA to
repay [similar] loans on the due date." That Eastland had been
forced to renegotiate payment with Verardo and Ozsezen after
three successive defaults supports the inference that the
decision to withdraw the Hope loan was primarily motivated by
prudential concerns.

-12-












motives in insisting on the letter of the agreement in refusing

to perform are not a matter with which the law is concerned.

CONCLUSION CONCLUSION __________

For the foregoing reasons, the judgment of the district

court is AFFIRMED. ________












































-13-