United States v. George Hyman

USCA1 Opinion









UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT

____________________

No. 97-1577

UNITED STATES OF AMERICA FOR THE USE AND,
BENEFIT OF WATER WORKS SUPPLY CORPORATION,

Plaintiff, Appellee,

v.

GEORGE HYMAN CONSTRUCTION COMPANY,
NATIONAL UNION FIRE INSURANCE COMPANY OF
PITTSBURGH, P.A., FEDERAL INSURANCE COMPANY
AND SEABOARD SURETY COMPANY,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Patti B. Saris, U.S. District Judge] ___________________

____________________

Before

Torruella, Chief Judge, ___________

Campbell, Senior Circuit Judge, ____________________

and Boudin, Circuit Judge. _____________

____________________

Steven J. Comen, with whom Jeremy M. Sternberg, Dori C. ________________ ____________________ ________
Gouin, Howard J. Hirsch and Goodwin, Procter & Hoar LLP were on _____ ________________ ____________________________
brief for appellant, The George Hyman Construction Company.
Bert J. Capone, with whom CharCretia V. DiBartolo and _______________ _________________________
Cetrulo & Capone were on brief for appellant, National Union Fire ________________
Insurance Company of Pittsburgh, PA; Federal Insurance Company
and Seaboard Surety Company.
Gary H. Kreppel for appellee. _______________
____________________
December 10, 1997
____________________















CAMPBELL, Senior Circuit Judge. Defendant- _______________________

appellant George Hyman Construction Company ("Hyman") appeals

from the district court's judgment awarding recovery to the

Water Works Supply Corporation ("Water Works") under the

Miller Act, 40 U.S.C. 270a-270d (1986) (the "Miller Act"

or the "Act"). Hyman makes a number of arguments as to why

the district court erred in allowing recovery. In this

opinion we concentrate particularly on Hyman's contentions:

(1) that Water Works did not satisfy the Act's ninety-day

notice requirement; and (2) that Water Works did not have a

sufficiently close relationship to Hyman to qualify for

recovery under the Miller Act. Finding no merit in these or

in the other arguments that Hyman advances, we affirm.



I. BACKGROUND.

The facts are largely undisputed. Hyman was the

general contractor on a $70 million federal construction

project to build a mail processing center in Waltham,

Massachusetts (the "Post Office Project" or the "Project").

Pursuant to the requirements of the Miller Act, Hyman

obtained a payment bond from National Union Fire Insurance

Company of Pittsburgh, PA, Federal Insurance Company, and

Seaboard Surety Company (collectively, the "Sureties"). On

or about September 16, 1994, Hyman entered into an oral

agreement with Calvesco, Inc. ("Calvesco"), wherein Calvesco



-2-













promised to serve as demolition, excavation and site work

subcontractor for the Post Office Project.

On September 16, 1994, the same day that Hyman

hired Calvesco, Calvesco submitted an application for credit

to Water Works, a purveyor of pipe and piping materials.

Water Works extended an unlimited line of credit to Calvesco.

Calvesco was working on at least three projects at that time,

and the credit application did not indicate whether it was

for a particular project.

Subsequently, Calvesco informed Hyman that it could

not legally serve as subcontractor on the Post Office Project

because it was a non-union shop. On September 27, 1994,

Hyman and Calvesco agreed to replace Calvesco with Iron

Holdings, Inc. d/b/a Charles A. Jackson Co. ("Jackson"), a

unionized company created by the principals of Calvesco.

On October 11, 1994, Jackson notified Water Works

that it had replaced Calvesco as subcontractor on the Post

Office Project. Jackson requested that it, rather than

Calvesco, receive Water Works's invoices. Because Water

Works had extended credit only to Calvesco and not to

Jackson, Water Works refused to supply Jackson unless

Calvesco executed a corporate guarantee. Until the corporate

guarantee could be signed, Water Works agreed to ship piping

materials to the Post Office Project site at Jackson's

request and to send the invoices to Calvesco. That same day,



-3-













Jackson placed an order for pipe. Water Works shipped the

material to "Charles A. Jackson Co., c/o Calvesco." Water

Works sent the invoice to "Calvesco, Inc. Attn: Jackson

Gateman, Treas." ("Gateman").

From early October through December 29, 1994, Water

Works filled seven purchase orders relating to the Post

Office Project. Water Works continued to ship materials to

the Post Office Project site and to send the invoices to

Gateman at Calvesco. Jackson paid for five of the seven

shipments; the other two invoices remain unpaid and are the

subject of this action. The first unpaid invoice, for

$53,493.83 and dated November 30, 1994, corresponded to an

order placed on November 1, 1994 by Lou Ingegneri, the Post

Office Project manager for Jackson. The second unpaid

invoice, for $157.76 and dated January 12, 1995, related to

the last delivery made by Water Works to the Project, which

occurred on December 29, 1994. This second invoice does not

indicate the name of the person placing the order.

During January and February of 1995, Water Works's

credit manager Stanley Wernick ("Wernick") conversed on the

telephone with several employees of Hyman about the

outstanding November and December invoices. On March 7,

Wernick sent a demand letter to Calvesco. Wernick also sent

a copy of this letter to Hyman and the Sureties. Hyman

responded to Wernick's communications in writing on March 22



-4-













by indicating that it had turned the matter over to its

attorneys and was not paying any claims until it had a clear

picture of its options.

On April 5, 1995, Water Works filed suit in

Middlesex County Superior Court against Calvesco and its

personal guarantor for monies owed on several jobs, including

the Post Office Project. This state court suit resulted in a

settlement in which Calvesco agreed to pay Water Works for

the cost of its materials. Calvesco has not satisfied this

judgment.

On the same day that Water Works filed its state

action, it also filed a one-count Miller Act complaint

against Hyman and the Sureties in the United States District

Court for the District of Massachusetts. The district court

consolidated Water Works's federal action with twenty-five

other actions brought against Hyman arising from the Post

Office Project in order to determine issues of fact and law

common to all the claimants. The district court found that

Calvesco and Jackson were separate corporate entities, and

that Calvesco was Hyman's subcontractor from September 16,

1994 through September 27, 1994, with Jackson serving as

subcontractor thereafter.

Water Works argued to the district court that it

was in a direct contractual relationship with Calvesco during

the period of time when Calvesco was Hyman's direct



-5-













subcontractor. The district court rejected this argument,

finding that the credit application between Water Works and

Calvesco did not constitute a contract.

Nevertheless, the court held that Water Works could

recover under the Miller Act. Finding that Water Works had

satisfied the 90-day notice requirement in the Miller Act,

the court held that Water Works could recover from the

payment bond on the amount owed for its November order under

two alternative theories. First, Jackson had an open account

with Water Works. Second, Water Works could recover under

the doctrine of quantum meruit.

The district court allowed Water Works to recover

the amount of its November shipment -- $53,493.83, plus costs

and interest -- but not the amount of its December shipment -

- $157.76. The key distinction between the two orders, in

the court's view, was that the November order was signed by

Jackson's project manager, whereas the December order, being

unsigned, could not be plainly attributed to Jackson.



II. STANDARD OF REVIEW.

We review de novo questions of statutory __ ____

interpretation that present pure questions of law. See Riva ___ ____

v. Commissioner of Mass., 61 F.3d 1003, 1007 (1st Cir. 1995). _____________________

The sufficiency of notice under the Miller Act, to the extent

based on undisputed facts, is commonly reviewed de novo. __ ____



-6-













See United States ex rel. Consol. Elec. Distribs., Inc. v. ___ ______________________________________________________

Altech, Inc., 929 F.2d 1089, 1092 (5th Cir. 1991); United ____________ ______

States ex rel. Moody v. American Ins. Co., 835 F.2d 745, 748 ____________________ _________________

(10th Cir. 1987). We uphold a district court's factual

findings unless they are clearly erroneous. See Fed. R. Civ. ___

P. 52(a); United States ex rel. Calderon & Oyarzun, Inc. v. ________________________________________________

MSI Corp., 408 F.2d 1348, 1348 (1st Cir. 1969). _________



III. DISCUSSION.

A. The Statutory Scheme of the Miller Act. ______________________________________

The Miller Act requires a general contractor

performing a contract valued at over $25,000 on any public

construction project to obtain a performance bond for the

protection of persons supplying labor and material in the

prosecution of the work on the project. See 40 U.S.C. ___

270a(a)(2). The Act provides that persons who have

"furnished labor or material" to a public project may sue to

recover from the payment bond any amount owed to them. Id. ___

270b(a).

The purpose of the Miller Act is "to protect

persons supplying labor and material for the construction of

federal public buildings in lieu of the protection they might

receive under state statutes with respect to the construction

of nonfederal buildings." United States ex rel. Sherman v. ______________________________

Carter, 353 U.S. 210, 216 (1957); see also United States ex ______ ___ ____ ________________



-7-













rel. Pittsburgh Tank & Tower, Inc. v. G&C Enters., Inc., 62 ___________________________________ __________________

F.3d 35, 35 (1st Cir. 1995) (same). Courts give the Act a

liberal interpretation to achieve that purpose. See, e.g., _________

Carter, 353 U.S. at 216; Clifford F. MacEvoy Co. v. United ______ _______________________ ______

States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107 (1944). _________________________________

Despite the "highly remedial" nature of the Act,

MacEvoy, 322 U.S. at 107, there are two important limitations _______

on who can recover from the payment bond. First, the Miller

Act allows recovery from the bond by persons who have a

"direct contractual relationship" with either the general

contractor or a first-tier subcontractor of the general

contractor. 40 U.S.C. 270b(a). The Supreme Court has

interpreted this provision to preclude recovery on the

payment bond by anyone whose relationship to the general

contractor is more remote than a second-tier subcontractor.

See J.W. Bateson Co. v. United States ex rel. Bd. of Trustees ___ ________________ _____________________________________

of the Nat'l Automatic Sprinkler Indus. Pension Fund, 434 _______________________________________________________

U.S. 586, 590-91 (1977); MacEvoy, 322 U.S. at 107. _______

Second, the Act imposes a strict notice requirement

upon suppliers who have a direct contractual relationship

with a first-tier subcontractor, but no relationship with the

general contractor. In order to recover from the payment

bond, such suppliers must send written notice of their claim

on the payment bond to the general contractor within ninety

days from the date that they supply the last of the materials



-8-













for which they make a claim. 40 U.S.C. 270b(a); see also ___ ____

United States ex rel. John D. Ahern Co. v. J.F. White _____________________________________________ ___________

Contracting Co., 649 F.2d 29, 31 (1st Cir. 1981).1 _______________

B. Notice under the Miller Act. ___________________________

Fulfilling the Act's notice provision is a strict

condition precedent to recovery by suppliers of first-tier

subcontractors. See Ahern, 649 F.2d at 31. The notice ___ _____

provision serves an important purpose: it establishes a firm

date after which the general contractor may pay its

subcontractors without fear of further liability to the

materialmen or suppliers of those subcontractors. See id.; ___ ___

Noland Co. v. Allied Contractors, Inc., 273 F.2d 917, 920-21 __________ ________________________

(4th Cir. 1959).

____________________

1. The relevant statutory language concerning notice reads
as follows:

Every person who has furnished labor or material in
the prosecution of the work provided for [a federal
project] . . . and who has not been paid in full
therefor . . . shall have the right to sue on such
payment bond . . . Provided, however, That any person ________ _______
having direct contractual relationship with a
subcontractor but no contractual relationship express or
implied with the contractor furnishing said payment bond
shall have a right of action upon the said payment bond
upon giving written notice to said contractor within
ninety days from the date on which such person . . .
furnished or supplied the last of the material for which
such claim is made, stating with substantial accuracy
the amount claimed and the name of the party to whom the
material was furnished or supplied. . . . Such notice
shall be served by mailing the same by registered mail,
postage prepaid, in an envelop addressed to the
contractor . . . .

40 U.S.C. 270b(a).

-9-













1. Substance of Water Work's Notice. ________________________________

While adherence to the notice requirement is

mandatory, courts have allowed some informality in complying

with the terms of the Miller Act regarding the method by

which notice must be served. See, e.g., Fleisher Eng'g & __________ _________________

Constr. Co. v. United States ex rel. Hallenbeck, 311 U.S. 15, ___________ ________________________________

18 (1940) (holding written notice sufficient although it was

not sent via registered mail as statute provides); Coffee v. ______

United States ex rel. Gordon, 157 F.2d 968, 969 (5th Cir. ______________________________

1946) (holding that a writing exhibited to the general

contractor in the course of a discussion served as adequate

notice under the Act). Courts have also been somewhat

forgiving of deviations from the statutory requirement that

the notice be in writing. See, e.g., Altech, 929 F.2d at __________ ______

1092 (holding that the "only reasonable inference" from a

meeting was that the subcontractor sought payment from the

general contractor).

The language of the Miller Act requires notice to

the general contractor of the amount of the claim and name of

the party to whom the material was furnished; it does not

expressly require a demand that the general contractor pay.

40 U.S.C. 270b(a); see also McWaters & Bartlett v. United ___ ____ ____________________ ______

States ex rel. Wilson, 272 F.2d 291, 295 (10th Cir. 1959). ______________________

Nevertheless, courts have consistently, and we think

correctly, held that "the written notice and accompanying



-10-













oral statements must inform the general contractor, expressly

or impliedly, that the supplier is looking to the general

contractor for payment so that it plainly appears that the

nature and state of the indebtedness was brought home to the

general contractor." United States ex rel. Kinlau Sheet _____________________________________

Metal Works, Inc. v. Great Am. Ins. Co., 537 F.2d 222, 223 __________________ ___________________

(5th Cir. 1976) (internal quotation marks omitted); see ___

also United States ex rel. Bailey v Freethy, 469 F.2d 1348, ____ _____________________________ _______

1350-51 (9th Cir. 1972).

Hyman argues that such notice as Water Works was

shown to have provided to Hyman did not indicate that Water

Works was looking to it for payment because the only "formal

notice" that it received was a copy of Water Works's demand ____

letter to Calvesco. Hyman points to court decisions holding

that the mere forwarding to the general contractor of a copy

of a demand sent to a subcontractor does not satisfy the

Miller Act's notice requirement. See Maccaferri Gabions, ___ ____________________

Inc. v. Dynateria, Inc., 91 F.3d 1431, 1437 (11th Cir. 1996) ____ _______________

(denying recovery under the Miller Act because sending to the

general contractor a copy of a collection letter that was

sent to the subcontractor, even when combined with a joint

payment plan and invoices, was insufficient notice); United ______

States ex rel. Jinks Lumber Co. v. Federal Ins. Co., 452 F.2d _______________________________ ________________

485, 488 (5th Cir. 1971).





-11-













But while adequate notice requires bringing home to

the general contractor that the supplier is looking to it for

payment, courts have not required formalistic proof of this.

Communications sent to the general contractor detailing the

supplier's claim against the subcontractor may, for example,

be supplemented by oral and other written exchanges if these

make it unambiguously clear that the supplier is seeking

payment from the general contractor. See Altech, 929 F.2d at ___ ______

1093; Coffee, 157 F.2d at 970; Kinlau, 537 F.2d at 223. ______ ______

The record here shows not only that Water Works

sent Hyman the amount and details of Water Works's claims

against the subcontractor, but that these were accompanied by

further oral and written communications that could only be

perceived, and were in fact perceived, as looking to Hyman

itself for payment. Water Works's credit manager, Wernick,

initiated matters on February 3, 1995, by speaking on the

telephone with two Hyman employees who were handling the Post

Office Project account. During the course of several calls

on that day, Wernick informed them that Water Works had not

been paid by the subcontractor for its materials. Wernick

thereupon faxed copies of Water Works's unpaid invoices and

proofs of delivery to Hyman, thus informing Hyman of the

amount Water Works claimed from the subcontractor. The

district court found that, in these calls, Wernick also asked

to obtain a copy of Hyman's payment bond for "the express



-12-













purpose of filing a bond claim." Hyman's personnel refused

to release the requested bonding information, but, as the

district court found, they countered with a promise that

Hyman would issue joint checks payable to Jackson and Water

Works, a device to ensure payment for Water Works's

materials. Wernick continued to communicate about the unpaid

claims with Hyman throughout the month of February. On

February 9, Wernick spoke again with the same Hyman

employees, who informed him that they were attempting to meet

with the subcontractor to discuss the issue of the unpaid

invoices. Finally on March 7, after more phone calls, Water

Works sent to Hyman a copy of a demand letter it had written

to Calvesco.2 The copy reflected at the bottom not only that

a copy had gone to Hyman but that copies had been sent to

Hyman's three Miller Act Sureties. Finally, on March 22,

1995, Hyman wrote Water Works thanking it for its patience,

indicating that it had already paid Jackson, expressing its

____________________

2. Hyman argues that "the facts of the present case are even
more persuasive than Maccaferri or Kinlau since Water Works __________ ______
purported demand letter . . . was not made to Hyman's ___
subcontractor Jackson, but rather to Calvesco." However, the
names "Calvesco" and "Jackson" seem to have been used
interchangeably on various occasions, and there is absolutely
no evidence that Hyman was confused over the identity of the
subcontractor identified by Water Works. Calvesco and
Jackson were owned in common and Hyman had been a party to
the agreement that substituted Jackson for Calvesco as
subcontractor for the Project. While Hyman personnel, like
Water Works, sometimes referred to "Calvesco," the name
"Jackson" was correctly used by Hyman in its March 22 letter
to Water Works declining to pay its claim, showing that Hyman
was fully aware of thecorrect identity of the subcontractor.

-13-













reluctance to pay the same bill twice, and informing Water

Works that it had "turned the entire matter over to our

attorneys and, on their advi[c]e, we are not paying anyone

until we have a clear picture of our options."

The above evidence provides clear indication that

Hyman understood that Water Works was looking to it for

payment, having received, as the district court found "actual

notice." Wernick's initial request for a copy of the bond,

following his faxing of the unpaid invoices and his telephone

calls to Hyman about the debt, suggested that Water Works was

looking to it for payment. Hyman's comprehension of this can

be inferred from Hyman's promise to issue joint checks in

substitute for information about the bond. But we need not

decide whether these actions by themselves sufficed to

constitute notice. Following these and other exchanges,

Water Works sent Hyman on March 7 a copy of Water Works's

demand upon the subcontractor. Unlike the copy in

Maccaferri, this indicated at the bottom that copies were __________

also being sent to Hyman's three Sureties on the Miller Act

bond, each of which was designated by name. It is not easy

to think of a reason to notify the Sureties unless Water

Works was looking to the bond for payment.

In Maccaferri, the Eleventh Circuit held that __________

merely sending the general contractor a copy of the demand to

the subcontractor did not suffice to show that the supplier



-14-













was looking for payment to the general, but the surrounding

circumstances were far less indicative that payment was

sought, and there was no indication that the Sureties were

being sent copies. Here, upon receipt of a copy of Water

Works's demand upon the subcontractor showing plainly that

other copies had been sent to Hyman's Sureties, Hyman could

have had no illusion that it was not being asked to pay.

Hyman's letter of March 22, 1995 fully confirms our

interpretation. In the letter, Hyman thanked Water Works

"for being so patient with us while we are trying to sort out

the problems" relative to the Jackson claims. The letter

went on to speak of Hyman's difficulties with Jackson,

Hyman's strong reluctance to pay the same bill twice, and

that it had "turned the entire matter over to our attorneys

and, on their advice, we are not paying anyone until we have _________________

a clear picture of our options" (emphasis added). "In the

end," the letter went on, "we may, in fact, be held

responsible for paying these invoices. But we will exhaust

every legal remedy before we do." The district court

inferred, and we entirely agree, that this letter must have

been in response to what Hyman believed was a request for

payment by Water Works. See Altech, 929 F.2d at 1093 ___ ______

(general contractor's letter held to provide evidence of

notice).





-15-













We, therefore, agree with the district court that

in this period Hyman received notice sufficient to meet the

requirements of the Miller Act.

2. Timing of Water Works's Notice. ______________________________

The district court found that the ninety-day period

began to run on December 29, 1994, the day that Water Works

made its final delivery of materials to the Post Office

Project. Thus, by the court's calculations, Water Works's

letter of March 7, 1995, a copy of which was sent to Hyman

and the Sureties, and which in combination with the earlier

invoices constituted the written portion of the notice, fit

within the ninety-day limit.

In support of its assertion that the court should

have used the date of the November order, November 1, 1994,

rather than the date of the December order when calculating

the ninety-day time limit, Hyman suggests that each order

under an open account represents a separate contract with an

individual ninety-day limit. See United States ex rel. ___ _______________________

Robert DeFilippis Crane Serv., Inc. v. William L. Crow _______________________________________ _________________

Constr. Co., 826 F. Supp. 647, 655 (E.D.N.Y. 1993) _____________

(concluding that "[w]here claims are based on a series of

contracts, a claim must be made within 90 days from the date

on which the supplier 'furnished or supplied the last of the

material' for each underlying contract"); United States ex _________________

rel. I. Burack, Inc. v. Sovereign Constr. Co., 338 F. Supp. ____________________ ______________________



-16-













657, 661 (S.D.N.Y. 1972). Under this reasoning, Hyman

argues, the limit on the November order had run by the time

that Water Works sent notice to Hyman.

While several district courts have held that Miller

Act notice runs from each order on an open contract, the

weight of authority contradicts that position. See United ___ ______

States ex rel. A&M Petroleum, Inc. v. Santa Fe Eng'rs, Inc., __________________________________ ______________________

822 F.2d 547 (5th Cir. 1987) (collecting cases from the

Second, Fourth, and Tenth Circuits that have held, either

implicitly or explicitly, that notice on an open account runs

from the last delivery of materials); Noland, 273 F.2d at ______

920-21. In Noland, the Fourth Circuit reasoned that, ______

although a strict reading might fulfill the purpose of the

notice provision by offering more protection to the general

contractor, the goal of a specific statutory provision must

take a back seat to the purpose of the overall statute, which

is to provide recovery for suppliers who have provided

materials but not received compensation. See Noland, 273 ___ ______

F.2d at 920-21.

We agree with the reasoning in Noland. Where ______

claims are based on an open account theory, the ninety-day

notice period for all of the deliveries begins on the date of

the last delivery to the project. The parties to this action

agree that Water Works delivered the last of its materials to

the Post Office Project on December 29, 1994. We therefore



-17-













conclude that the district court correctly refused to deny

recovery on the November order merely because it was part of

an open account.

Hyman also argues that, since the district court

denied recovery to Water Works for the December order of

$157.76, it should not have used the date of that order for

purposes of calculating the timeliness of notice. We are not

persuaded.

As an initial matter, we note that the statute

states that the time limit runs from the date of the last

delivery of material "for which a claim is made." 40 U.S.C.

270b(a). The statute does not start the time limit on the

last claim for which the plaintiff eventually recovers; such

a provision might prove unworkable.

But even if the statute runs from the last

recoverable claim, we see little problem. In denying Water

Works recovery on the December order, the district court

wrote a footnote explaining its reasoning for distinguishing

between the November and December orders: the November order

form contained the name of a Jackson employee while there was

no name on the December order. The district court concluded

that there was "no evidence as to whether Calvesco or Jackson

placed the [December] order." Accordingly, the court limited

Water Works's recovery to the amount of the November order

($53,493.83) plus costs and interest.



-18-













The undisputed facts are as follows. First, Water

Works provided materials that were incorporated into the Post

Office Project. Second, Water Works did not begin shipping

these materials until after Jackson became the subcontractor

on the Project. Third, although Water Works insisted upon

sending its invoices to Calvesco, Jackson paid for the first

five shipments by Water Works. Fourth, Calvesco was not a

subcontractor on the Project during the time that Water Works

shipped materials to the Project. Fifth, the last date that

Water Works delivered materials to the Project was December

29, 1994.

On these facts, we see no reason for the court to

have questioned if Calvesco rather than Jackson placed the

December order. Calvesco, having been replaced by Jackson as

the subcontractor on the Post Office Project, had no reason

to order materials for this job. The only reasonable

inference is that Jackson placed this order, as it did

earlier ones. While in the absence of a cross appeal, the

court's denial of the $157.76 stands, we see no reason to

reject the court's determination that the December 29, 1994

date triggered the notice period.

As the notice was adequate and as the district

court did not err in beginning the notice period from

December 29, 1994, Water Works satisfied the notice

requirements of the Miller Act.



-19-













C. Water Works's Relationship to Hyman. ___________________________________

In order to recover from the payment bond, a person

must have a "direct contractual relationship" either with the

general contractor or with a direct subcontractor. 40 U.S.C.

270b(a); see also Bateson, 434 U.S. at 590-91. Hyman and ___ ____ _______

Water Works agree that they had no direct relationship.

Hyman argues further that Water Works did not have a direct

contractual relationship with any of Hyman's subcontractors.

Hyman relies upon the undisputed fact that Water Works

consistently refused to extend credit to Jackson and regarded

Calvesco as its customer.

As the district court correctly noted, courts have

allowed recovery under the Miller Act by suppliers who

furnish materials to a subcontractor "from time to time on

open account . . . without formal contract." Noland, 273 ______

F.2d at 919; see also Apache Powder Co. v. Ashton Co., 264 ___ ____ _________________ ___________

F.2d 417, 422-23 (9th Cir. 1959). It is undisputed that

Water Works supplied materials to the Project and that

Jackson was the demolition, excavation and site work

subcontractor on the Post Office Project after September 27,

1994. In addition, Jackson, rather than Calvesco, paid Water

Works's first five invoices. This evidence clearly supports

the district court's finding of the existence of an open

account between Jackson and Water Works. Since Jackson was





-20-













Hyman's direct subcontractor, the Act's tiering requirements

are satisfied.

Since we find that the district court correctly

allowed Water Works to recover under an open account theory,

we need not address the propriety of its alternative holding,

which allowed recovery on the basis of quantum meruit.

We have carefully considered Hyman's other

arguments; none of them persuade us that the district court

erred in its determination.

Affirmed. ________

































-21-