J-S55031-15
NON-PRECEDENTIAL DECISION – SEE SUPERIOR COURT I.O.P 65.37
VICTOR P. AMRHEIN AND KAREN L. : IN THE SUPERIOR COURT OF
AMRHEIN, : PENNSYLVANIA
:
Appellees :
:
v. :
:
JAN J. GARVEY AND ROSEMARY :
GARVEY, :
:
Appellants : No. 418 WDA 2015
Appeal from the Order Entered February 12, 2015
in the Court of Common Pleas of Beaver County,
Civil Division, at No(s): 11934 of 2010
BEFORE: FORD ELLIOTT, P.J.E., BENDER, P.J.E, and STRASSBURGER,* J.
MEMORANDUM BY STRASSBURGER, J.: FILED SEPTEMBER 28, 2015
Jan J. and Rosemary Garvey (the Garveys) appeal from the February
12, 2015 order which granted in part and denied in part the petition to
enforce settlement agreement filed by Victor P. and Karen L. Amrhein (the
Amrheins). Upon review, we quash this appeal.
The relevant history of this case is as follows. In 2010, the Amrheins
filed a complaint and an amended complaint alleging that the Garveys
breached covenants to which their land was subject concerning use and
maintenance of a paved 50-foot right-of-way which provided access to the
public road for both parties. Specifically, the Amrheins asked the trial court
for the following relief:
*Retired Senior Judge assigned to the Superior Court.
J-S55031-15
A. Enjoin [the Garveys’] use of the 50’ private right-of-way
until such time as [the Garveys] comply with the terms of
Note “C” [of the plan, which provides that the property
owners share maintenance costs equally];
B. Declare the 50’ private right-of-way terminated due to [the
Garveys’] failure to abide by the terms of the grant of use
of the 50’ private right-of-way;
C. Order [the Garveys] to pay one-half of the maintenance
cost pursuant to Note “C”…;
D. Order [the Garveys] to escrow one-half of estimated repair
costs;
E. Order [the Garveys] to utilize only that portion of the
[Amrheins’] land that has the 50’ right-of-way; and
F. Grant such other relief as the [c]ourt deems proper.
Amended Complaint, 11/1/2010, at unnumbered page 3.
By order of October 4, 2011, the trial court scheduled a non-jury trial
of the matter to commence on January 30, 2012. Between January 2012
and June 2014, the trial court entertained 12 motions to postpone the trial,
11 of which were filed by the Garveys. By order of June 12, 2014, the trial
court denied the final continuance motion. The parties appeared before the
trial court on June 23, 2014.
The trial court had the Amrheins’ counsel state on the record the terms
of an agreement, purportedly reached by the parties that day, which covered
numerous issues including, but not limited to, the following: (1) termination
of the existing right-of-way and the creation of “recordable easement
-2-
J-S55031-15
agreement” which would implement a different arrangement for
maintenance and costs, N.T., 6/23/2014, at 3-9; and (2) payment by the
Garveys to the Amrheins of $5,332.65, which was half of the maintenance
expenses the Amrheins paid between February 2008 and February 2014, id.
at 10. The trial court indicated that Amrheins’ counsel was to draft, within
30 days of the completion of a new survey, “the different documents that
will need to be put together in order to give a final effect to the agreement
that we’ve reached here today.” Id. at 3, 32.
On November 25, 2014, the Amrheins presented a petition to enforce
settlement agreement, alleging therein that the Garveys had neither
complied with the terms of the settlement nor submitted a revised proposal.
The trial court entered a rule to show cause and scheduled a hearing. The
Garveys filed a response in which they alleged that they never entered into a
binding agreement; rather, counsel for the Amrheins stated proposed terms
to which the Garveys never agreed. Response to Rule to Show Cause,
1/8/2015, at 2. The Garveys also contended that even if there had been an
oral agreement regarding the parties’ interests in the real estate, it is
unenforceable under the statute of frauds. Id. at 5-6.
At the hearing on January 22, 2015, counsel presented arguments, but
the parties offered no testimony. Counsel for the Amrheins noted that the
Garveys, earlier that day, finally filed an answer to the Amrheins’ 2010
-3-
J-S55031-15
amended complaint, as well as a new matter and counterclaim, and
indicated that their position was that the settlement be enforced as stated or
that they proceed to trial. The trial court ultimately concluded: “I don’t think
we need a trial. I think their case has already been settled.” N.T.,
1/22/2015, at 19. Accordingly, it indicated that it would enter an order
“pursuant to a settlement agreement reached on the record with the
transcript….” Id. at 20.
However, the trial court thereafter entered an order which granted the
Amrheins’ enforcement motion only in part. While it granted the motion
with respect to the claim for monetary damages, the trial court denied the
motion “[w]ith respect to the newly[-]negotiated easement agreement,”
determining that the statute of frauds precluded it from enforcing the new
easement agreement and thus concluding that “the existing easement
agreement between the parties shall remain in full force and effect.” Order,
2/12/2015. The Garveys timely filed a notice of appeal.
While no party has questioned the appealability of the February 12,
2015 order, “[w]e may examine the issue of appealability sua sponte
because it affects the Court’s jurisdiction over the case. An appeal must be
taken from a final order.” In re Miscin, 885 A.2d 558, 561 (Pa. Super.
2005) (citations omitted). The definition of a final order is provided in Rule
341 of the Pennsylvania Rules of Appellate Procedure. “Rule 341 is
-4-
J-S55031-15
fundamental to the exercise of jurisdiction by this court.” Prelude, Inc. v.
Jorcyk, 695 A.2d 422, 424 (Pa. Super. 1997) (en banc).
Rule 341 provides in relevant part as follows:
(b) Definition of final order. A final order is any order that:
(1) disposes of all claims and of all parties; or
(2) is expressly defined as a final order by statute; or
(3) is entered as a final order pursuant to subdivision (c)
of this rule[ (i.e., upon the trial court’s express
determination that an immediate appeal as to fewer
than all claims and/or parties would facilitate
resolution of the entire case.)].
Pa.R.A.P. 341. See also 42 Pa.C.S. § 742 (“The Superior Court shall have
exclusive appellate jurisdiction of all appeals from final orders of the courts
of common pleas….”).1
No statute defines the trial court’s February 12, 2015 order as a final
order, and the trial court did not add the language required to satisfy
subdivision (c). Thus, the order is final only if it disposes of all claims and all
parties.
Because the trial court determined that there was no enforceable
settlement of any issue other than the Garvey’s share of past maintenance
and that the original covenant remains in place, there has been no resolution
of the majority of the Amrheins’ original claims (e.g., to terminate the
1
The Garveys cite 42 Pa.C.S. § 742 as the basis for this Court’s jurisdiction
over the instant appeal. Garveys’ Brief at 1.
-5-
J-S55031-15
existing easement, to enjoin the Garveys from using the right of way until
they comply with the original agreement, to require the Garveys to escrow
half of the estimated repair costs, and to order the Garveys to use only that
portion of the Amrheins’ land that is within the 50-foot right-of-way).2 There
is no indication in the record that the Amrheins have dismissed those claims;
to the contrary, counsel expressly demanded a trial in the absence of
enforcement of the entire agreement. N.T., 1/22/2015, at 19.
Accordingly, the trial court’s February 12, 2015 order does not dispose
of all of the Amrheins’ claims. Because this Court has no jurisdiction over
the interlocutory order granting in part but denying in part the Amrhein’s
petition to enforce settlement, we must quash the appeal. See, e.g., Levitt
v. Patrick, 976 A.2d 581, 588 (Pa. Super. 2009) (“If any claim remains
outstanding and has not been disposed of by the trial court, then … this
Court lacks jurisdiction to entertain the appeal….”).
Appeal quashed.
2
Although the propriety of the trial court’s determination that the statute of
frauds precludes enforcement of the new easement agreement is not before
us, we note that there is precedent to the contrary. See Aetna
Electroplating Co. v. Jenkins, 484 A.2d 134, 136 (Pa. Super. 1984)
(“[A]greements made before the court need not be in writing. … Counsel
cannot play fast and loose with the court. If he enters an agreement as part
of a proceeding before the court, he cannot assert the statute of frauds as a
defense to an action to enforce the same. The statute of frauds was
intended to prevent fraud; it cannot be used as a vehicle to avoid
agreements entered in open court.”).
-6-
J-S55031-15
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 9/28/2015
-7-