FOR PUBLICATION
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
TOYO TIRE HOLDINGS OF AMERICAS
INC., as successor in interest to
TOYO TIRE INTERNATIONAL, INC.,
Plaintiff-Appellant,
No. 10-55145
v.
CONTINENTAL TIRE NORTH AMERICA, D.C. No.
8:10-CV-00052-JVS
INC., as successor in interest to
OPINION
GENERAL TIRE INC.; YOKOHAMA
CORPORATION OF AMERICA; GTY
TIRE CO.; and DOES 1-100,
Defendants-Appellees.
Appeal from the United States District Court
for the Central District of California
James V. Selna, District Judge, Presiding
Argued and Submitted
June 10, 2010—Pasadena, California
Filed June 17, 2010
Before: Dorothy W. Nelson and Ronald M. Gould,
Circuit Judges, and James S. Gwin* District Judge.
Opinion by Judge Gwin
*The Honorable James S. Gwin, United States District Judge for the
Northern District of Ohio, sitting by designation.
9231
TOYO TIRE v. CONTINENTAL TIRE 9233
COUNSEL
Steven B. Kinnaird and Joseph R. Profaizer, Paul, Hastings,
Janofsky & Walker LLP, Washington, DC, and Donna M.
D’Angelo Melby and Daniel Prince, Paul, Hastings, Janofsky
& Walker LLP, Los Angeles, California, for the plaintiff-
appellant.
9234 TOYO TIRE v. CONTINENTAL TIRE
Leslie M. Werlin and Sidney K. Kanazawa, McGuire Woods
LLP, Los Angeles, California, and Mitchell G. Blair and
Maura L. Hughes, Calfee Halter & Griswold LLP, Cleveland,
Ohio, for defendant-appellee Continental Tire North America,
Inc.
Richard W. Lasater II, Leila Nourani, and Michael B. McCol-
lum, Foley & Lardner LLP, Los Angeles, California, for
defendant-appellee Yokohama Corporation of America.
OPINION
GWIN, District Judge:
Appellant Toyo Tire Holdings of Americas, Inc. (“Toyo”)
appeals the district court’s denial of its motion to enjoin
Appellees Continental Tire North America, Inc.
(“Continental”) and Yokohama Corporation of America
(“Yokohama”) from dissolving the parties’ joint venture and
from distributing the partnership assets until an arbitration
panel can consider Toyo’s claims. In denying Toyo’s motion
for a preliminary injunction, the district court reasoned that
our holding in Simula, Inc. v. Autoliv, Inc., 175 F.3d 716 (9th
Cir. 1999), precluded granting injunctive relief when the par-
ties have agreed to arbitrate and the arbitration panel has the
power to issue injunctive relief. Because we believe that the
district court incorrectly concluded that Simula controls in the
present circumstances, we reverse and remand for the district
court to consider the merits of Toyo’s request for a prelimi-
nary injunction.
I
Toyo, Continental, and Yokohama all manufacture and dis-
tribute tires. In 1988, Continental’s predecessor General Tire,
Inc., Toyo, and Yokohama formed a general partnership,
TOYO TIRE v. CONTINENTAL TIRE 9235
Appellee GTY Tire Co. (“GTY”). GTY manufactures truck
and bus radial tires (“TBR tires”) for each of the partners to
distribute.
The 1998 Partnership Agreement contains an arbitration
clause that says in pertinent part: “Failing . . . amicable reso-
lution all disputes arising in connection with this Partnership
Agreement or any other Basic Document shall be finally set-
tled by arbitration. . . . All arbitration shall be conducted . . .
in accordance with the Rules of Conciliation and Arbitration
of the International Chamber of Commerce by three arbitra-
tors appointed in accordance with such Rules.” As hereafter
described, those International Chamber of Commerce Rules
allow judicially imposed interim relief, including injunctive
relief.
On December 22, 2009, Continental and Yokohama sent
Toyo a letter saying they would dissolve the partnership at the
end of 2009. In the letter, Continental and Yokohama said that
Toyo had agreed to a collaboration agreement with Bridge-
stone Corporation, a competitor. Continental and Yokohama
said Toyo’s relationship with Bridgestone gave them the right
to dissolve the joint venture under the Partnership Agreement
and a 1990 Amendment thereto. Continental and Yokohama
indicated that, pursuant to the Partnership Agreement, they
could acquire Toyo’s 2010 share of TBR tires and could
enforce a non-competition clause that would prohibit Toyo
from selling non-GTY TBR tires in North America for five
years.
At Toyo’s request, Continental and Yokohama agreed to a
January 8, 2010, meeting of the general partners and tempo-
rarily suspended the notice of dissolution. At the meeting,
Continental and Yokohama said they intended to dissolve the
partnership, effective January 13, 2010, and that they planned
to take Toyo’s entire allocation of GTY tires. On January 9,
2010, Toyo wrote to Continental and Yokohama, stating that
it believed it had a right to purchase TBR tries from GTY for
9236 TOYO TIRE v. CONTINENTAL TIRE
the current and two following fiscal years, even if the partner-
ship was dissolved. Neither Continental nor Yokohama
responded.
On January 11, 2010, Toyo requested arbitration with the
International Chamber of Commerce (“ICC”) International
Court of Arbitration. Within its Request for Arbitration, Toyo
requested interim injunctive relief.
On the same day, Toyo sued Continental, Yokohama, and
GTY.1 With its Complaint, Toyo brings claims for breach of
contract, breach of fiduciary duty, breach of the duty of loy-
alty, breach of the covenant of good faith and fair dealing,
violation of California’s fair business practices law, tortious
interference with business relations, and slander.
On January 14, 2010, Toyo asked the district court for a
preliminary injunction to prevent the Appellees from: (1) ter-
minating Toyo’s status as a partner in GTY, (2) disrupting
GTY’s supply of TBR tires to Toyo, and (3) making false,
disparaging, inflammatory, or other defamatory statements to
Toyo’s customers or other third parties regarding Toyo’s
assets, the partnership, or Toyo’s ability to supply tires. Toyo
also moved for a temporary restraining order.
On January 25, 2010, the district court heard argument and
orally denied Toyo’s motion for a preliminary injunction. At
that hearing, the district court gave clear indication that
injunctive relief should be given unless Simula foreclosed
such relief.2 The district court concluded that our opinion in
1
Toyo initially sued the Defendants-Appellees in the Orange County
Superior Court. On January 13, 2010, the Defendants removed the case to
the U.S. District Court for the Central District of California.
2
At the hearing, the district court described its views regarding the mer-
its of Toyo’s application for injunctive relief:
[I]t seems to me at a minimum there is a serious question with
regard to the legal claims that Toyo puts forward with respect to
TOYO TIRE v. CONTINENTAL TIRE 9237
Simula created a “blanket judgment” that a district court may
not grant a preliminary injunction when the parties have
agreed to arbitrate and the arbitrator has the power to grant
interim injunctive relief. Finding that Simula controlled this
case, the district court denied Toyo’s motion.
Toyo now appeals that denial. We have jurisdiction under
28 U.S.C. § 1292(a)(1) and we reverse.
II
We review the district court’s denial of a preliminary
injunction for an abuse of discretion. N.D. ex rel. Parents Act-
ing as Guardians Ad Litem v. Hawaii Dep’t of Educ., 600
F.3d 1104, 1111 (9th Cir. 2010). Under this standard, we first
determine de novo whether the trial court identified the cor-
rect legal rule to apply to the relief requested. United States
v. Hinkson, 585 F.3d 1247, 1261-62 (9th Cir. 2009) (en banc).
If the trial court applied an incorrect legal standard, we must
conclude that it abused its discretion. Id. at 1262. If the trial
court applied the correct legal standard, we reverse only when
the district court reaches a result that is illogical, implausible,
or without support in the record. N.D., 600 F.3d at 1111.
its breach of contract, breach of the covenant of good faith and
fair dealing, breach of the duty of loyalty, and the interference
claims. It seems to me that the disruption of a 290,000 unit sup-
ply agreement is serious and causes the balance of hardships to
tip substantially in favor of plaintiff Toyo. I’m less convinced
that there is an equally serious question with regard to the defa-
mation claim, but it seems to me that the expulsion from the part-
nership and termination of the distribution arrangement seriously
tips the balance of hardships in favor of Toyo. I believe that the
termination of the distribution also presents an adequate showing
of irreparable harm for the present purposes. Given those facts,
I think that the public interest would be served by issuing an
injunction. My big stumbling block is to whether under Simula
[ ] the Court has any room to issue an injunction.
9238 TOYO TIRE v. CONTINENTAL TIRE
Because we find that the district court incorrectly applied
Simula, we conclude that the district court abused its discre-
tion in denying the Appellant’s motion for a preliminary
injunction, and we reverse and remand.
III
The Appellant argues that the district court abused its dis-
cretion by erroneously reading our decision in Simula, Inc. v.
Autoliv, Inc., 175 F.3d 716 (9th Cir. 1999), to deprive it of the
authority to grant injunctive relief to maintain the status quo
pending arbitration. We agree.
[1] In both Simula and in the case before us, the parties
agreed to arbitrate in accordance with the Rules of Arbitration
of the International Chamber of Commerce (“ICC Rules”).
The ICC Rules provide in relevant part:
Article 23 Conservatory and Interim Measures
(1) Unless the parties have otherwise agreed, as soon
as the file has been transmitted to it, the Arbitral Tri-
bunal may, at the request of a party, order any
interim or conservatory measure it deems appropri-
ate. . . .
(2) Before the file is transmitted to the Arbitral Tri-
bunal, and in appropriate circumstances even there-
after, the parties may apply to any competent
judicial authority for interim or conservatory mea-
sures. The application of a party to a judicial author-
ity for such measures or for the implementation of
any such measures ordered by an Arbitral Tribunal
shall not be deemed to be an infringement or a
waiver of the arbitration agreement and shall not
affect the relevant powers reserved to the Arbitral
Tribunal. Any such application and any measures
taken by the judicial authority must be notified with-
TOYO TIRE v. CONTINENTAL TIRE 9239
out delay to the Secretariat. The Secretariat shall
inform the Arbitral Tribunal thereof.
ICC Rules Article 23 (emphasis added). On its face, Article
23 of the ICC Rules provides that (1) once the file has been
transmitted to it, an arbitral panel may order interim injunc-
tive relief at the request of a party and (2) “any competent
judicial authority” may order interim injunctive relief before
the file is transmitted to the panel and “in appropriate circum-
stances even thereafter.”
Despite Article 23(2) of the ICC Rules, the district court
concluded that Simula foreclosed its ability to grant injunctive
relief in this case. However, in Simula we did not discuss
whether a court may grant interim relief to maintain the status
quo while the parties are waiting for the arbitration panel to
be formed and for the arbitration panel to consider whether to
grant interim relief. Instead, in Simula, the appellant argued
that the arbitral forum would be unable to provide it meaning-
ful relief and attempted to avoid arbitration by seeking injunc-
tive relief in the district court. After considering Article 23(1)
of the ICC Rules, we determined that Simula was wrong
when it argued that the arbitrators could not grant preliminary
relief. We thus concluded that the district court did not abuse
its discretion when it denied preliminary injunctive relief after
finding that all of Simula’s claims were arbitrable and the
arbitral tribunal had the power to grant the injunctive relief
that Simula sought. 175 F.3d at 725-26.
Importantly, Simula involved claims completely different
from the claims in this case. Simula concerned a developer of
safety technologies that claimed that an auto parts supplier
stole its ideas, violated its trademark, and restrained trade in
violation of the Sherman Act, 15 U.S.C. §§ 1, 2. Id. at 719.
Simula argued “that preliminary injunctive relief should have
been granted by the district court because the arbitrators can-
not grant such relief.” Id. at 725. Against this backdrop, we
held that the district court did not err in denying injunctive
9240 TOYO TIRE v. CONTINENTAL TIRE
relief. First, and contrary to Simula’s position, the arbitration
panel did have power to afford the interim relief Simula
sought. Second, nothing suggested any imminent need for
injunctive relief to maintain the status quo until an arbitration
panel could address Simula’s request for interim relief.
Here, by contrast, Appellant Toyo says the district court
should afford injunctive relief because the Appellees are
denying Toyo its right to purchase nearly 290,000 tires, or
60% of its North American supply of TBR tires, after Toyo
had purchased tires from GTY for over twenty years. In addi-
tion, Toyo says the Appellees are attempting to stop Toyo
from purchasing tires from other suppliers for distribution in
North America.
[2] In contrast to Simula, Toyo seeks an injunction to pre-
serve the status quo until the arbitral panel can consider and
rule upon Toyo’s application for interim relief pending the
arbitration panel’s final decision. Allowing a district court to
grant this type of relief is not contrary to the “emphatic fed-
eral policy in favor of arbitral dispute resolution” of primary
concern in Simula. See 175 F.3d at 726. To the contrary, in
cases such as this, judicial interim relief may be necessary to
preserve the meaningfulness of the arbitral process. See Sec-
tion IV, infra.
[3] Thus, in Simula we did not decide the question pres-
ented here—whether a court may grant interim relief pursuant
to Article 23(2) of the ICC Rules to maintain the status quo
while the parties are awaiting the creation of an arbitration
panel and a decision by that panel with respect to injunctive
relief. Therefore, the holding of Simula is not binding in this
case.
IV
[4] In PMS Distributing Co. v. Huber & Suhner, A.G., we
recognized that “the congressional desire to enforce arbitra-
TOYO TIRE v. CONTINENTAL TIRE 9241
tion agreements would frequently be frustrated if the courts
were precluded from issuing preliminary injunctive relief to
preserve the status quo pending arbitration and, ipso facto, the
meaningfulness of the arbitration process.” 863 F.2d 639,
641-42 (9th Cir. 1988) (quoting Teradyne, Inc. v. Mostek
Corp., 797 F.2d 43, 51 (1st Cir. 1986)). We thus held in PMS
that a district court has authority to issue equitable relief in
aid of arbitration. Id. at 642.
The importance of the courts’ ability to issue interim
injunctive relief is even more apparent now than when we
decided PMS twenty-two years ago. We assume that parties
ordinarily choose to arbitrate, inter alia, to lower costs and
increase efficiency and speed. See Stolt-Nielsen S.A. v. Ani-
malFeeds Int’l Corp., 130 S. Ct. 1758, 1775 (2010). However,
arbitration’s promised speed and efficiency frequently do not
materialize in practice. See Bruce M. Selya, Arbitration
Unbound?: The Legacy of McMahon, 62 Brook. L. Rev.
1433, 1446-47 (1996) (describing arbitration process as
becoming “increasingly litigious,” resulting in shrinking mar-
gins of savings in time and cost between arbitration and litiga-
tion).
Moreover, one party to the arbitration often has an incen-
tive to delay arbitration proceedings to its own advantage.
See, e.g., Int’l Union of Petroleum & Indus. Workers v. W.
Indus. Maint., Inc., 707 F.2d 425, 428 (9th Cir. 1983)
(upholding award of attorney’s fees against party who refused
to abide by arbitrator’s award to deter “frivolous dilatory tac-
tics [which] not only den[y] the individual prompt redress,
[but also] threaten[ ] the goal of industrial peace”); Engalla v.
Permanente Med. Group, Inc., 938 P.2d 903, 969 (Cal. 1997)
(finding evidence that defendant insurance company delayed
appointment of neutral arbitrator until after plaintiff’s death,
resulting in merger of surviving spouse’s loss of consortium
and malpractice claims and reducing defendant’s potential lia-
bility).
9242 TOYO TIRE v. CONTINENTAL TIRE
Even without bad faith by either party, the selection of arbi-
trators and the constitution of the arbitral panel necessarily
takes time. Under the district court’s interpretation of Simula,
parties would be without remedy when, as here, the delay
associated with securing an arbitration panel’s ruling on
interim relief could defeat any ultimate award. If Toyo loses
its customers before interim relief is possible, any subsequent
relief could be useless. As recognized in PMS, the unavaila-
bility of interim conservatory measures can frustrate the arbi-
tration process. See 863 F.2d at 641-42.
[5] Moreover, Article 23(2) of the ICC Rules provides that
“[b]efore the file is transmitted to the Arbitral Tribunal, and
in appropriate circumstances even thereafter, the parties may
apply to any competent judicial authority for interim or con-
servatory measures.” ICC Rules, Article 23(2). Thus, the very
rules that the parties agreed would govern their arbitration
proceedings allow a party to request the relief that Appellant
Toyo seeks in this case. And the same rules allow a party to
seek interim or conservatory relief before the file is transmit-
ted to the Arbitral Tribunal, “and in appropriate circumstances
even thereafter.”
[6] Accordingly, we conclude that a district court may
issue interim injunctive relief on arbitrable claims if interim
relief is necessary to preserve the status quo and the meaning-
fulness of the arbitration process—provided, of course, that
the requirements for granting injunctive relief are otherwise
satisfied. This holding is consistent with our rulings in PMS
and Simula, as well as the holdings of a majority of our sister
circuits. See Performance Unlimited, Inc. v. Questar Publish-
ers, Inc., 52 F.3d 1373, 1377-80 (6th Cir. 1995) (reversing
district court’s denial of preliminary injunction and joining
other circuits in holding that district courts have subject mat-
ter jurisdiction under the Federal Arbitration Act (“FAA”) to
grant preliminary injunctive relief pending arbitration); Blu-
menthal v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 910
F.2d 1049, 1052-54 (2d Cir. 1990) (federal district court has
TOYO TIRE v. CONTINENTAL TIRE 9243
power to issue injunction pending arbitration, even absent
express contractual language so providing); Ortho Pharm.
Corp. v. Amgen, Inc., 882 F.2d 806, 813-14 (3d Cir. 1989)
(district court has jurisdiction to issue injunctive relief pend-
ing arbitration, provided movant satisfies traditional four-
pronged test); Merrill Lynch, Pierce, Fenner & Smith, Inc. v.
Dutton, 844 F.2d 726, 726-28 (10th Cir. 1988) (affirming dis-
trict court’s grant of preliminary injunction to preserve status
quo until arbitration panel takes jurisdiction); Teradyne, Inc.
v. Mostek Corp., 797 F.2d 43, 47-51 (1st Cir. 1986) (“We
hold, therefore, that a district court can grant injunctive relief
in an arbitrable dispute pending arbitration, provided the pre-
requisites for injunctive relief are satisfied. We believe this
approach reinforces rather than detracts from the policy of the
Arbitration Act . . . .”); Merrill Lynch, Pierce, Fenner &
Smith, Inc. v. Bradley, 756 F.2d 1048, 1050-55 (4th Cir.
1985) (“We do not believe that Congress would have enacted
a statute intended to have the sweeping effect of stripping the
federal judiciary of its equitable powers in all arbitrable com-
mercial disputes without undertaking a comprehensive discus-
sion and evaluation of the statute’s effect. Accordingly, we
conclude that the language of § 3 [of the FAA] does not pre-
clude a district court from granting one party a preliminary
injunction to preserve the status quo pending arbitration.”);
Sauer-Getriebe KG v. White Hydraulics, Inc., 715 F.2d 348,
351-52 (7th Cir. 1983) (reversing district court’s denial of
injunctive relief pending arbitration pursuant to ICC Rules).
But see Peabody Coalsales Co. v. Tampa Elec. Co., 36 F.3d
46, 47-48 (8th Cir. 1994) (district court may issue injunctive
relief in arbitrable dispute only if contract contains “qualify-
ing language” that permits such relief and only if such relief
can be granted without addressing merits).
[7] We therefore hold that the district court erred by find-
ing as a matter of law that it lacked the power to grant injunc-
tive relief in this case.
9244 TOYO TIRE v. CONTINENTAL TIRE
V
A plaintiff seeking a preliminary injunction must establish
(1) that he is likely to succeed on the merits, (2) that he is
likely to suffer irreparable harm in the absence of preliminary
relief, (3) that the balance of equities tips in his favor, and (4)
that an injunction is in the public interest. Winter v. Nat’l Res.
Def. Council, Inc., 129 S. Ct. 365, 374 (2008). In denying
Toyo’s motion for a preliminary injunction, the district court
only considered “whether under the existing Ninth Circuit
authority, the Court has the power to grant a preliminary
injunction on the facts of this case.” While the district court
made some comments regarding the Winter factors, it explic-
itly declined to make findings with respect to any of these fac-
tors.
While we are concerned that Toyo faces an increasing
chance of suffering irreparable injury as time passes, and have
considered granting temporary injunctive relief ourselves, we
conclude that the proper course in this case is to remand. The
district court intimated but did not make specific findings
with respect to any of the Winter factors. We thus could not
grant Toyo’s requested injunctive relief without conducting a
de novo assessment of the factors on the limited evidentiary
record before us. In such a situation, we believe the more
appropriate course is to remand the case to the district court
to consider Toyo’s preliminary injunction request under the
Winter standard. See Sierra Forest Legacy v. Rey, 577 F.3d
1015, 1023 (9th Cir. 2009) (concluding that district court
applied wrong legal standard and remanding case to district
court to “exercise its discretion” in light of correct standard).
However, in light of Toyo’s repeated assertions that it will
suffer an irreparable harm if injunctive relief is not quickly
provided, we direct the district court to consider Toyo’s
motion for injunctive relief as expeditiously as possible.
VI
Finally, we note that the Appellees have moved this Court
to dismiss this appeal, arguing that this case has become moot
TOYO TIRE v. CONTINENTAL TIRE 9245
because the ICC has now constituted the arbitral panel. “In
general a case becomes moot when the issues presented are no
longer ‘live’ or the parties lack a legally cognizable interest
in the outcome.” Murphy v. Hunt, 455 U.S. 478, 481 (1982)
(per curiam) (quotation marks and citations omitted). “This
court has an obligation to determine whether a case presents
a live controversy, and is precluded from entering judgment
in an appeal that has been rendered moot.” Granados-
Oseguera v. Mukasey, 546 F.3d 1011, 1014 (9th Cir. 2008)
(per curiam).
[8] We conclude that we continue to have subject matter
jurisdiction over the case for the following reasons: Article
23(2) provides that parties may seek interim relief from a
court “[b]efore the file is transmitted to the Arbitral Tribunal,
and in appropriate circumstances even thereafter” (emphasis
added). The arbitrators have not yet issued a ruling on Toyo’s
request for injunctive relief. Toyo at this time still has a need
for interim relief pending the arbitrators’ ruling on the issue.
Accordingly, we hold that the appeal is not moot.
VII
[9] We conclude that the district court’s denial of the pre-
liminary injunction was based on application of an incorrect
legal standard, and therefore an abuse of discretion. Accord-
ingly, we reverse and remand for the district court to properly
weigh the appropriate factors.
The mandate shall issue forthwith. Petitions for rehearing
and rehearing en banc will be received and treated in the ordi-
nary course. The panel reserves jurisdiction to review further
emergency motions or appeals on this subject.
REVERSED and REMANDED.