[Cite as Schlaegel v. Howell, 2015-Ohio-4296.]
IN THE COURT OF APPEALS OF OHIO
SECOND APPELLATE DISTRICT
CHAMPAIGN COUNTY
JERRY SCHLAEGEL, et al. :
:
Plaintiffs-Appellants : Appellate Case No. 2014-CA-37
:
v. : Trial Court Case No. 13-CV-36
:
TERRY HOWELL, et al. : (Civil Appeal from
: Common Pleas Court)
Defendants-Appellees :
:
...........
OPINION
Rendered on the 16th day of October, 2015.
...........
JAMES M. HILL, Atty. Reg. No. 0030633, James M. Hill Co., L.P.A., 2365 Lakeview Drive,
Suite A, Beavercreek, Ohio 45431-3639
Attorney for Plaintiffs-Appellants
RICK BRUNNER, Atty. Reg. No. 0012998, and PETER CONTRERAS, Atty. Reg.
No. 0087530, 35 North Fourth Street, Suite 200, Columbus, Ohio 43215
Attorneys for Defendants-Appellees
.............
HALL, J.
{¶ 1} The plaintiffs, Jerry Schlaegel; J&J Champaign, LLC; and J&J Schlaegel,
Inc., appeal the entry of summary judgment for the defendants, Terry Howell and Howell
-2-
Land Development, LLC, on the plaintiffs’ claims for breach of joint venture, breach of
fiduciary duty, quantum meruit, unjust enrichment, conversion, and tortious interference.
Finding no error, we affirm.
I. Background
{¶ 2} Jerry Schlaegel owns J&J Schlaegel—a construction company that does site
development, underground utilities, bridges, roads, and the like—and also owns J&J
Champaign, a holding company. Terry Howell owns Howell Land Development, LLC, a
general contracting company that does business under the name Howell Buildings
Company.
{¶ 3} Schlaegel alleges that in December 2011 he and Howell entered into a joint
venture to build and lease a research facility for Pioneer Hi-Bred International.
Specifically, Schlaegel claims, they agreed that
they would prepare and submit a proposal for the Pioneer project;
J&J Schlaegel would provide the bid for the site-preparation work;
Howell Land Development would provide the bid to construct the facility;
J&J Schlaegel would do the site-preparation work and Howell Land Development
would construct the facility, if the proposal was accepted;
they would jointly obtain financing for the project;
at the end of the joint venture, J&J Champaign and Howell Land Development
would form a limited-liability company that would own and lease the facility.
{¶ 4} In January 2012, Howell Buildings Company submitted a proposal to Pioneer
to build and lease the facility. The proposal’s cover letter states in part that “Howell
Buildings Company will build the project, and will partner with J&J Schlaegel to form an
-3-
ownership LLC for a partnership with Pioneer in this venture.” The letter also says:
Your site, as I explained does not have municipal or county water or
sewer readily available. However we have consulted a local Professional
Civil Engineer, who has worked locally in the Champaign County area for
over thirty years, and he has extensive experience with EPA and local
health department regulations. Both we and he are extremely confident of
obtaining local permits for on-site septic and/or mound treatment.
Our partners in this venture, J&J Schlaegel, have extensive
experience in on-site treatment installation. They are also ODOT
contractors in site, roadway, and bridge construction in addition to
installation and maintenance of such sewage treatment installations.
{¶ 5} The proposal gives the total cost to build the facility as $1,766,432 plus the
cost of the land on which the facility would be built ($85,000). The cost breakdown shows
the site-work cost as $339,650, which includes installing a storm water detention area,
paving the parking area, and an $85,000 allowance for utilities to service the site. J&J
Schlaegel had given Howell a bid for the site work, but according to Howell, the site-work
cost included in the proposal to Pioneer is not based on J&J’s bid but on a bid from
another company. Howell says that he did not use J&J’s bid because it was too high.
J&J’s bid was $329,999, but that did not include the $85,000 site-utility allowance or the
cost of paving the parking area, which Howell estimated would be $35,000. Consequently,
J&J’s bid would have increased the site-work cost (and the entire proposal) by $110,349
($329,999 + $85,000 + $35,000 – $339,650).
{¶ 6} Pioneer accepted Howell’s proposal. In February, Howell filed articles of
-4-
organization for A&C Land Development LLC (named for Howell’s and Schlaegel’s sons,
Andy Howell and Chris Schlaegel). (The articles bear only Howell’s name and signature.)
A&C and Pioneer then executed a lease agreement for the facility. (Only Howell signed
for A&C.) One provision of the lease (Article XVI) pertinently provides that “Lessor [A&C]
hereby represents and warrants that it is the owner of the Property and that it has the
right and authority to enter into this Agreement without the joinder or approval of any other
person.” Pioneer owned an option to purchase the land on which the facility was to be
built, and in early March, it assigned A&C its interest in the option. The option expired on
March 31, however, so A&C had to purchase and close on the property by then or seek
an extension of time. Howell and Schlaegel received an email in mid-March telling them
that their joint application for lease financing had been approved. But the approval notice
states that the lease will not close if certain conditions are not satisfied. The conditions
include a “[s]igned copy of lease/rent agreement with Pioneer Hy-Bred [sic] International,
Inc.” and “[s]atisfactory entity documents.”
{¶ 7} On March 14, Howell emailed Schlaegel asking for input on what their
respective roles would be in A&C. Schlaegel responded with his thoughts for an operating
agreement, which he said should include a provision that J&J Schlaegel would perform
all site work except paving, as identified in J&J’s bid. Howell responded with a draft
operating agreement, dated March 15, 2012. Among the provisions in Howell’s draft
agreement is one stating that Howell Land Development will serve as general contractor
for the Pioneer project “and have the full discretion to hire whoever it makes the most
economical sense to provide those construction services.” Another provision states in part
that “J&J Champaign LLC shall have the site work responsibility for the execution and risk
-5-
associated with such projects and pledges to provide the most economical pricing to be
competitive with all functions associated.” On March 19, Schlaegel sent Howell an email
in which he proposed several revisions to the draft agreement. One change Schlaegel
wanted was the phrase “most economical” removed from the just-quoted provision.
Schlaegel also notes in the email that they “still need an agreement between J&J
Champaign or J&J Schlaegel for site work and Howell Buildings as general contractor.”
On the same day, Schlaegel sent Howell another email that sets forth numerous “action
items” that he thought needed to be done for A&C. Among these were completing the
operating and buy-sell agreements and writing up the Pioneer agreement between Howell
Land Development and J&J Schlaegel.
{¶ 8} Howell never responded to Schlaegel’s proposed revisions or “action items.”
Instead, sometime before the end of March, Howell told Schlaegel that he (Schlaegel)
would no longer be part of the Pioneer project. According to Howell, the problem was his
and Schlaegel’s inability to agree on who would do the site work. The expiration of A&C’s
unexercised land-purchase option, on March 31, says Howell, violated Article XVI of
A&C’s lease agreement with Pioneer, so Pioneer terminated the agreement. With no
signed leased agreement and no operating agreement, the lease financing would not
close. Moreover, without the land on which the facility was to be built, the project could
not move forward. For these reasons, Howell decided to continue with the Pioneer project
without Schlaegel doing the site work. Howell hired the other company, whose site work
costs had been included in the Pioneer proposal, and he formed Howell Bros.
Development, LLC, to own and lease the facility.
{¶ 9} In February 2013, Schlaegel (and his companies) filed suit against Howell
-6-
(and his company). The amended complaint asserts six claims for relief. The first claim
alleges the breach of joint venture and/or partnership agreements. The second claim
alleges that the defendants breached their fiduciary duty to the plaintiffs by negotiating
with Pioneer and others to exclude the plaintiffs from the Pioneer project. The third claim
for relief alleges that the defendants breached their contract with the plaintiffs by not hiring
J&J Schlaegel to perform the site work for the Pioneer facility. The fourth claim is for
quantum meruit and unjust enrichment, alleging that the plaintiffs expended considerable
time, money, and goodwill in support of the Pioneer project and that the defendants have
been unjustly enriched as a result of the plaintiffs’ expenditures. The fifth and sixth claims
are for conversion and tortious interference. These two claims allege that the defendants
wrongly interfered with or exercised control over the plaintiffs’ business relationships with
A&C, Pioneer, and the defendants.
{¶ 10} The defendants moved for summary judgment on all of the claims. They
contended that the parties never entered into an enforceable joint-venture contract.
Howell contended that he never agreed to hire J&J Schlaegel to perform the site work on
the Pioneer project. The trial court sustained the motion. The court concluded, based on
the evidentiary material presented, that there was no “meeting of the minds” on the two
essential terms of the alleged joint-venture contract—who would do the site work and the
ownership of the facility. The parties, said the court, agreed only to a framework for further
negotiation, which is an unenforceable “agreement to make an agreement.”
{¶ 11} The plaintiffs appealed.
II. Analysis
{¶ 12} The plaintiffs assign seven errors to the trial court’s entry of summary
-7-
judgment. The first six challenge summary judgment on the claim for breach of the alleged
joint-venture agreement. The seventh assignment of error challenges summary judgment
on the claims for breach of fiduciary duty, quantum meruit, unjust enrichment, conversion,
and tortious interference.1
{¶ 13} “Summary judgment will be granted only when there remains no genuine
issue of material fact and, when construing the evidence most strongly in favor of the
nonmoving party, reasonable minds can only conclude that the moving party is entitled to
judgment as a matter of law.” Byrd v. Smith, 110 Ohio St.3d 24, 2006-Ohio-3455, 850
N.E.2d 47, ¶ 10, citing Civ.R. 56(C). The initial burden of showing that no genuine issue
of material fact exists is on the moving party. Dresher v. Burt, 75 Ohio St.3d 280, 294,
662 N.E.2d 264 (1996). If the movant satisfies this burden, the nonmoving party “may not
rest upon mere allegations or denials of the party’s pleadings, but the party’s response,
by affidavit or as otherwise provided in this rule [Civ.R. 56], must set forth specific facts
showing that there is a genuine issue for trial.” Civ.R. 56(E).
A. The existence of a joint venture
{¶ 14} “A joint venture is ‘* * * an association of persons with intent, by way of
contract, express or implied, to engage in and carry out a single business adventure for
joint profit, for which purpose they combine their efforts, property, money, skill and
knowledge, without creating a partnership, and agree that there shall be a community of
interest among them as to the purpose of the undertaking, and that each coadventurer
shall stand in the relation of principal, as well as agent, as to each of the other
1 The appellants do not challenge the entry of summary judgment on the breach-of-
contract claim.
-8-
coadventurers * * *.’ ” Al Johnson Const. Co. v. Kosydar, 42 Ohio St.2d 29, 325 N.E.2d
549 (1975), paragraph one of the syllabus, quoting Ford v. McCue, 163 Ohio St. 498, 127
N.E.2d 209 (1955), paragraph one of the syllabus. “[T]he elements of a joint venture are:
(1) a contract, express or implied; (2) the intent to associate as joint venturers; (3)
contributions from each co-venturer to the common enterprise; (4) equal control or
authority of the co-venturers over the enterprise, (5) an agreement to share profits and a
sharing of losses, (6) a single enterprise as opposed to a continuing business.” (Citation
omitted) Carey v. Seeley’s Ceramic Serv., Inc., 2d Dist. Miami No. 93-CA-30, 1994 WL
124849, *2 (Apr. 13, 1994).
{¶ 15} Fundamentally, “[a] joint venture is a contractual association in which the
parties intend to carry out a common business purpose.” (Citation omitted.) Nilavar v.
Osborn, 127 Ohio App.3d 1, 20, 711 N.E.2d 726 (2d Dist.1998). “ ‘[J]oint venture
agreements may be oral, [but] they are, nonetheless, still contracts, and thus subject to
all of the applicable requirements of contract law.” Olympic Holding Co. LLC v. ACE Ltd.,
122 Ohio St.3d 89, 2009-Ohio-2057, 909 N.E.2d 93, ¶ 46, quoting Garg v. Venkataraman,
54 Ohio App.3d 171, 172, 561 N.E.2d 1005 (9th Dist.1988). “A contract of joint adventure
need not be established by showing an express agreement between the parties, but it
may be implied or inferred, in whole or in part, from their acts and conduct.” Bennett v.
Sinclair Refining Co., 144 Ohio St. 139, 57 N.E.2d 776 (1944), paragraph five of the
syllabus.
{¶ 16} Here, the trial court concluded that the plaintiffs failed to produce sufficient
evidence to show that a joint venture exists. Specifically, the court concluded that there
is no enforceable joint-venture contract, because there was no “meeting of the minds” on
-9-
two essential terms—site-work and ownership. The evidentiary materials, said the court,
show that Howell understood the site-work agreement to be that J&J Schlaegel would do
the work if its bid was competitive with other bidders, not like the plaintiffs assert, that J&J
would do the work regardless of how much it charged. Also, pointing to the failure to
execute an operating agreement for A&C Land Development, the trial court said that the
evidentiary materials show that the parties failed to reach an agreement as to the
ownership of the Pioneer facility. At best, said the court, the evidence shows that the
parties made only an unenforceable “agreement to make an agreement.” We think that
the trial court got it right.
{¶ 17} A requirement to enforcing a contract is “ ‘[a] meeting of the minds as to the
essential terms of the contract.’ ” Minster Farmers Coop. Exchange Co. v. Meyer, 117
Ohio St.3d 459, 2008-Ohio-1259, 884 N.E.2d 1056, ¶ 28, quoting Kostelnik v. Helper, 96
Ohio St.3d 1, 2002-Ohio-2985, 770 N.E.2d 58, ¶ 16. And as to the essential terms, the
contract must be specific. Scotts Co. v. Cent. Garden & Pet Co., 403 F.3d 781, 788 (6th
Cir.2005) (saying that “an agreement lacking terms specific enough to be enforced falls
short of the Ohio standard for a valid contract”). In Ohio case law, the “meeting of the
minds” concept is used interchangeably with the concept of “mutual assent.” Advance
Sign Group, LLC v. Optec Displays, Inc., 722 F.3d 778, 784 (6th Cir.2013). Under either
concept, the standard is objective. 216 Jamaica Ave., LLC v. S & R Playhouse Realty
Co., 540 F.3d 433, 440 (6th Cir.2008), citing Nilavar, 127 Ohio App.3d 1, 711 N.E.2d 726.
Put in mutual-assent language, for a contract to be enforceable, there must be a
manifestation of mutual assent—generally, offer and acceptance—to the contract’s
essential terms. Nilavar at 11. “ ‘[W]hile mutual assent is usually manifested by offer and
-10-
acceptance, in oral contracts, mutual assent may be manifested by other acts or failures
to act.’ ” KeyBank Natl. Assn. v. Mazer Corp., 188 Ohio App.3d 278, 2010-Ohio-1508,
935 N.E.2d 428, ¶ 33 (2d Dist.), quoting LaPoint v. Templeton, 6th Dist. Fulton No. F-07-
014, 2008-Ohio-1792, ¶ 25. “ ‘ “It is sufficient if the intent is disclosed by word, deed, act,
or even silence.” ’ ” Id., quoting LaPoint at ¶ 25, quoting Rutledge v. Hoffman, 81 Ohio
App. 85, 86, 75 N.E.2d 608 (1st Dist.1947).
{¶ 18} Here, the evidentiary materials submitted by the defendants do not raise a
genuine issue of material fact that Howell agreed to use J&J Schlaegel’s site-work bid
regardless of the amount. The materials show that Howell was quite concerned about the
cost of the Pioneer project.
{¶ 19} Howell states in his affidavits that he did not use J&J’s site-work bid
because it was too high. Affidavit of Terry Howell, ¶ 5 (Mar. 25, 2013); Affidavit of Terry
Howell, ¶ 10 (Aug. 18, 2014). And he told Schlaegel this in two different emails. In a
February 15, 2012 email, Howell told Schlaegel: “Right now we (Chief, J&J, Geuy, etcc)
are too high, and I did not use those numbers in the bid I gave Pioneer.” Howell told
Schlaegel that he wanted to use J&J but doing so would cost too much: “I want to use
J&J for the excavation but cannot if that makes our total costs in excess of the $1,766,432
quoted. I added a small profit, not very much, but it certainly cannot absorb those
differences in cost.” In a March 19, 2012 email, Howell told Schlaegel: “As I have stated
repeatedly, I could not use our (your site number was at first glance $190K higher and
Chief's was $14K higher) numbers including your site work number when I developed the
$1,851,432 proposal.” Howell states in an affidavit that the proposal’s site-work cost is
based on a bid from another company “plus additional estimated costs for storm draining.”
-11-
Affidavit of Terry Howell, ¶ 23 (Aug. 18, 2014). He told Schlaegel this in the February 15,
2012 email: “When I submitted the bid their numbers plus what I added for the storm
drainage to their numbers was used.” Using J&J Schlaegel for the site work, says Howell,
would have cost significantly more money: “The total bid and the site-work line item
estimation in the proposal would have been substantially higher if J&J Schlaegel’s bid
had been used because it does not include certain significant items or expenses that were
included.” Id. at ¶ 14. In particular, J&J’s bid includes neither the required site-utility
allowance nor the cost of paving, so it would have cost around $110,000 more for J&J to
do the site work. Id. at ¶ 20.
{¶ 20} Howell’s draft operating agreement for A&C also shows that Howell was
cost conscious and not willing to hire J&J Schlaegel at any price. In response to Howell’s
query about managing A&C, Schlaegel sent Howell an email on March 14, 2012,
containing a number of suggestions. In particular, Schlaegel wanted a provision saying
that “J&J Schlaegel, Inc. will partner with the GC [Howell Buildings] to perform all site
work except paving as [i]dentified to GC at time of bid in amount of 329,999.48 as a lump
sum.” Howell incorporated many of Schlaegel’s suggestions in the draft operating
agreement. But as to site work on the Pioneer project, Howell’s provision in the draft
agreement states that Schlaegel “pledges to provide the most economical pricing to be
competitive with all functions associated.” (Emphasis added.). Schlaegel’s response to
the draft agreement tells Howell to remove the phrase “most economical.”
{¶ 21} Construing the evidence in the plaintiffs’ favor, the evidentiary materials
presented by the defendants do not demonstrate a genuine issue of material fact that
Howell agreed to hire J&J Schlaegel to do the site work regardless of what Schlaegel
-12-
charged. There was no “meeting of the minds” on this essential term of the purported
joint-venture contract.
{¶ 22} None of Schlaegel’s arguments in the first six assignments of error convince
us otherwise. The first assignment of error argues that Schlaegel’s 2014 affidavit by itself
is sufficient to show a genuine issue of material fact as to the existence of a joint venture.
Schlaegel’s 248-page deposition, taken on April 4, 2014, was among the material
submitted in support of the defendants’ motion for summary judgment. The deposition
covers, in painstaking detail, the plaintiffs’ claim that there was a joint-venture agreement,
including Schlaegel’s assertion that he and Howell agreed that Schlaegel’s company
would perform the site work. Viewed as a whole, Schlaegel’s largely narrative 7-page
affidavit, dated July 28, 2014, attempts to rewrite critical aspects of the deposition. For
instance, in the affidavit, Schlaegel states that in December 2011 he and Howell explicitly
agreed that J&J Schlaegel would do the site work: “We agreed that J&J Schlaegel, would
provide a bid for all the site preparation and utilities that the project required, and his
company, Howell Land Development would provide a bid to complete the rest of the
project which included the building itself. We agreed those two numbers combined, as
Howell and I had always done in the past, would serve as the total price of the bid.”
Affidavit of Jerry Schlaegel, ¶ 12 (July 28, 2014). But in the deposition, Schlaegel testified
that their agreement was implicit:
Q. He specifically agreed that he personally was hiring J&J Schlaegel?
Not opposed to his role with Howell Land Development, but he personally?
A. He never had to say it. We were a partnership. It had already been
established what our rules were. So Terry didn’t have a say whether Jerry–
-13-
J&J Schlaegel did the excavating. It was already determined that J&J
Schlaegel would do the excavating.
Q. Okay. When was this determined?
A. Back in 2009.
Q. Okay. In 2009, how was that contract created?
A. Terry and I worked together. We came up with a plan and agreed on
how it was going to be followed and we followed it to a tee.
(Schlaegel dep. 34-35). This exchange shows that Schlaegel believed that their
“agreement” was somehow formed in 2009 through either a partnership or a
course-of-dealing rather than by a specific agreement at the time of the 2012
Pioneer proposal, as his affidavit states.
{¶ 23} We have previously recognized that an “affidavit of a party opposing
summary judgment that contradicts former deposition testimony of that party may not,
without sufficient explanation, create a genuine issue of material fact to defeat the motion
for summary judgment.” Gessner v. Schroeder, 2d Dist. Montgomery No. 21498, 2007-
Ohio-570, ¶ 53, citing Byrd, 110 Ohio St.3d 24, 2006-Ohio-3455, 850 N.E.2d 47,
paragraph three of the syllabus. Schlaegel’s 2014 affidavit does not explain its
contradictions with the deposition. Furthermore, “a non-movant’s own self-serving
assertions, whether made in an affidavit, deposition or interrogatory responses, cannot
defeat a well-supported summary judgment when not corroborated by any outside
evidence.” White v. Sears, Roebuck & Co., 10th Dist. Franklin No. 10AP-294, 2011-Ohio-
204, ¶ 9. In that case, the plaintiff had worked for the defendant for 17 years when his
employment was terminated. The plaintiff claimed that the defendant had an unwritten
-14-
policy of giving a terminated employee two weeks of severance pay for every year of
employment. The defendant denied any such policy. The only evidence in opposition was
the plaintiff’s own assertions in discovery and by affidavit that such a policy existed. That,
held the court of appeals, was insufficient to avoid summary judgment. Applying either of
the foregoing concepts to Schlaegel’s affidavit assertion that there was an agreement that
his company would do the site work, we conclude that the materials submitted fail to
create a genuine issue of material fact as to the use of J&J Schlaegel for the site work.
{¶ 24} The second assignment of error argues that the parties’ conduct shows that
there is a genuine issue as to the existence of a joint venture. The argument here cites
plenty of evidentiary material that shows an intent to associate as joint venturers but cites
nothing that shows a meeting of the minds on who would do the site work. The third
assignment of error argues that the lack of a final written operating agreement for A&C is
not dispositive to the existence of a joint venture. We agree. But this, along with other
material, does not create a genuine issue of fact as to whether the parties’ December
2011 “agreement” was specific enough as to its essential terms to be enforceable. The
fourth assignment of error argues that there is a genuine issue as to whether Howell
agreed to use J&J Schlaegel’s bid in the Pioneer proposal, and the fifth assignment of
error argues that there is a genuine issue as to whether Howell used J&J Schlaegel’s bid
in the proposal. We have already dealt with the lack of a genuine issue as to the use of
J&J Schlaegel’s bid at any cost. In addition, the arguments in these assignments of error
do not point to any evidentiary material, other than Schlaegel’s own assertions in his
affidavits and deposition, that raise a genuine issue as to either fact. Only the sixth
assignment of error directly addresses the “meeting of the minds” contract element and
-15-
the trial court’s conclusion that there was none. That assignment argues that there are
genuine issues as to whether there was a “meeting of the minds” and contends that there
are genuine issues as to whether Schlaegel and Howell’s agreement was merely an
agreement to make an agreement. But the argument adds nothing new and merely cites
the arguments in previous assignments of error, all of which we have rejected.
{¶ 25} “Where an agreement contemplates further action toward formalization or if
an obligation to become binding rests on a future agreement to be reached by the parties,
so that either party may refuse to agree, there is no contract.” (Citations omitted.) Weston,
Inc. v. Brush Wellman, Inc., 8th Dist. Cuyahoga No. 65793, 1994 WL 393685, *5 (July 28,
1994), citing Smith v. Kissell Co., 2d Dist. Montgomery No. 10012, 1987 WL 10163, *2
(Apr. 10, 1987) (saying that “where an agreement contemplates further action toward
formalization, there is no binding contract”). Here, the evidentiary material shows that
Schlaegel and Howell’s December 2011 agreement contemplated further action. And for
three months, they tried to reach final agreement on the terms of their joint venture.
Because they were unsuccessful, no joint-venture contract ever arose. Schlaegel and
Howell’s agreement to work towards an agreement on the Pioneer project is not per se
unenforceable. Champion Gym & Fitness, Inc. v. Crotty, 178 Ohio App.3d 739, 2008-
Ohio-5642, 900 N.E.2d 231, ¶ 13 (2d Dist.). But to be enforced, Schlaegel and Howell
must have “manifested an intention to be bound” by the terms of their agreement to agree
and their intentions must be “sufficiently definite to be specifically enforced,” M.J.
DiCorpo, Inc. v. Sweeney, 69 Ohio St.3d 497, 503, 634 N.E.2d 203 (1994), quoting
Normandy Place Assoc. v. Beyer, 2 Ohio St.3d 102, 105, 443 N.E.2d 161 (1982). If they
“merely negotiated toward a formal contract without ever reaching it,” the agreement to
-16-
agree is not binding. Borkey v. J.F. Glaze Cleveland L.L.C., 2014-Ohio-3727, 18 N.E.3d
820, ¶ 7 (8th Dist.), citing Oglebay Norton Co. v. Armco, 52 Ohio St.3d 232, 236, 556
N.E.2d 515 (1990). We agree with the trial court’s observation that the parties “were
talking past each other on this project.” Journal Entry Granting Defendants’ Motion for
Summary Judgment, 15 (Nov. 18, 2014). The evidentiary material presented here does
not show a sufficiently definite intention to be bound. Instead, the material shows that
Schlaegel and Howell negotiated toward a final agreement, getting stuck on who would
do the site work and on the nature of terms that would govern their relationship. Ultimately,
they never reached final agreement on either issue.
{¶ 26} The defendants satisfied their initial burden to show that no genuine issue
of material fact exists. But the plaintiffs failed to satisfy their reciprocal burden to present
evidence that sets forth specific facts showing that a genuine issue exists for trial.
Construing the evidence most strongly in favor of the plaintiffs, reasonable minds can
only conclude that there was no joint-venture contract binding the parties. Therefore
summary judgment for the defendants is proper on the breach-of-joint-venture claim.
{¶ 27} The first, second, third, fourth, fifth, and sixth assignments of error are
overruled.
B. The claims for breach of fiduciary duty, quantum meruit, unjust enrichment,
conversion, and tortious interference
{¶ 28} The seventh assignment of error alleges that the trial court erred by entering
summary judgment for the defendants on the claims for breach of fiduciary duty, quantum
meruit, unjust enrichment, conversion, and tortious interference. Summary judgment is
proper on these claims too.
-17-
{¶ 29} “[P]arties to a joint venture, like those in a partnership, owe each other the
duties of fiduciaries.” Nilavar, 127 Ohio App.3d at 20, 711 N.E.2d 726. Here, the plaintiffs
claim that the defendants breached this duty when they excluded the plaintiffs from the
Pioneer project. But if there is no enforceable joint-venture agreement, no fiduciary duty
is imposed. See Olympic Holding, 122 Ohio St.3d 89, 2009-Ohio-2057, 909 N.E.2d 93,
at ¶ 46 (holding that a joint-venture agreement unenforceable under the statute of frauds
imposes no fiduciary duty). Because there is no enforceable joint-venture agreement
here, the defendants are entitled to summary judgment on the claim for breach of fiduciary
duty.
{¶ 30} “Unjust enrichment and quantum meruit are doctrines ‘derived from the
natural law of equity’ and share the same essential elements[:] * * * (1) the plaintiff
conferred a benefit on the defendant, (2) the defendant knew of the benefit, and (3) it
would be unjust to permit the defendant to retain the benefit without payment.” Meyer v.
Chieffo, 193 Ohio App.3d 51, 2011-Ohio-1670, 950 N.E.2d 1027, ¶ 37 (10th Dist.),
quoting Maghie & Savage, Inc. v. P.J. Dick, Inc., 10th Dist. Franklin No. 08AP-487, 2009-
Ohio-2164, ¶ 33. “The plaintiff must confer the benefit as a response to fraud,
misrepresentation, or bad faith on behalf of the defendant.” (Citation omitted.) Superior
Piping Contrs., Inc. v. Reilly Industries, Inc., 8th Dist. Cuyahoga No. 90751, 2008-Ohio-
4858, ¶ 28. Here, there is no evidence of fraud, misrepresentation, or bad faith by the
defendants. We note too that work done during negotiations that fail to result in a final
agreement is not a circumstance in which it can be deemed unjust to retain a benefit
without compensation. See id. at ¶ 29-30. The defendants are entitled to summary
-18-
judgment on the claims for quantum meruit and unjust enrichment.
{¶ 31} “ ‘The elements essential to recovery for a tortious interference with a
business relationship are: (1) a business relationship; (2) the wrongdoer’s knowledge
thereof; (3) an intentional interference causing a breach or termination of the relationship;
and (4) damages resulting therefrom.’ ” Kademian v. Marger, 2d Dist. Montgomery No.
24256, 2012-Ohio-962, ¶ 93, quoting Wolf v. McCullough-Hyde Memorial Hosp., 67 Ohio
App.3d 349, 355, 586 N.E.2d 1204 (12th Dist.1990). Here, the plaintiffs do not allege that
the defendants induced or otherwise caused A&C or Pioneer to terminate a relationship
with them. Instead, the plaintiffs allege that the defendants wrongfully excluded them from
the Pioneer project after the parties agreed to build the facility and to form a new entity
that would purchase, own, and lease the facility. This agreement, however, was
contingent on further negotiations and agreements. The parties’ inability to reach further
agreements does not constitute tortious interference. “Otherwise, a tortious interference
claim could be brought whenever parties engage in business negotiations that ultimately
prove unfruitful.” Journal Entry Granting Defendants’ Motion for Summary Judgment, 23
(Nov. 18, 2014). The defendants are entitled to summary judgment on the claim for
tortious interference.
{¶ 32} “[C]onversion is the wrongful exercise of dominion over property to the
exclusion of the rights of the owner * * *.” Joyce v. Gen. Motors Corp., 49 Ohio St.3d 93,
96, 551 N.E.2d 172 (1990). Here, the plaintiffs allege that the defendants wrongfully
exercised dominion and control over the plaintiffs’ business interests. But the parties’
inability to reach a final agreement does not constitute any kind of wrongful exercise of
dominion. “Otherwise, this claim like the one for tortious interference, could be brought
-19-
whenever parties engage in business negotiations that ultimately prove unfruitful.” Journal
Entry Granting Defendants’ Motion for Summary Judgment, 23-24 (Nov. 18, 2014). The
defendants are entitled to summary judgment on the claim for conversion.
{¶ 33} The seventh assignment of error is overruled.
III. Conclusion
{¶ 34} We have overruled all of the assignments of error. The trial court’s judgment
is affirmed.
.............
DONOVAN, J., and WELBAUM J., concur.
Copies mailed to:
James Hill
Rick Brunner
Peter Contreras
Hon. James A. Brogan
(sitting for Judge Nick A. Selvaggio)