15-20
Allco Finance v. Klee
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
_______________
August Term, 2015
(Submitted: September 2, 2015 Decided: November 6, 2015)
Docket No. 15‐20
_______________
ALLCO FINANCE LIMITED,
Plaintiff‐Appellant,
—v.—
ROBERT J. KLEE, in his official capacity as Commissioner of the Connecticut
Department of Energy and Environmental Protection,
Defendant‐Appellee,
OFFICE OF CONSUMER COUNSEL, FUSION SOLAR LLC, NUMBER NINE WIND FARM
LLC, GREENSKIES RENEWABLE ENERGY, LLC,
Intervenors‐Appellees.
_______________
1
B e f o r e:
KATZMANN, Chief Judge, HALL and LIVINGSTON, Circuit Judges.
_______________
Appeal from a district court judgment (Arterton, J.), which dismissed the
plaintiff’s complaint. We hold that: (1) the plaintiff cannot bring claims under 42
U.S.C. §§ 1983 and 1988 to vindicate any rights conferred by the Public Utility
Regulatory Policies Act (“PURPA”) because PURPA’s private right of action
forecloses such a remedy; (2) the plaintiff failed to exhaust administrative
remedies, a prerequisite to bringing an equitable action seeking to vindicate any
rights conferred by PURPA; and (3) the plaintiff lacks standing to bring a
preemption action seeking solely to void the contracts awarded to the intervenors.
Accordingly, we AFFIRM the district court’s judgment on alternative grounds.
_______________
Thomas Melone, Allco Renewable Energy Limited, New York, New
York, for Plaintiff‐Appellant.
Robert D. Snook, Assistant Attorney General, for George Jepsen,
Attorney General of the State of Connecticut, Hartford,
Connecticut, for Defendant‐Appellee.
Bradford S. Babbitt and James R. Nault, Robinson & Cole LLP,
Hartford, Connecticut, for Intervenors‐Appellees Fusion Solar LLC
and Number Nine Wind Farm LLC.
Joseph A. Rosenthal, Principal Attorney, for Elin Swanson Katz,
Consumer Counsel of the State of Connecticut, New Britain,
Connecticut, for Intervenor‐Appellee Office of Consumer Counsel.
_______________
2
KATZMANN, Chief Judge:
Plaintiff‐Appellant Allco Finance Limited (“Allco”) appeals from a final
judgment entered on December 11, 2014 by the United States District Court for
the District of Connecticut (Arterton, J.), which dismissed Allco’s complaint. Allco
brought this action against Defendant‐Appellee Robert Klee (“Commissioner”), in
his official capacity as Commissioner of the Connecticut Department of Energy
and Environmental Protection. Allco alleges that the Commissioner’s actions,
which were taken pursuant to section 6 of Connecticut Public Act 13‐303 (“Section
6”) and include his awarding two power purchase agreements to Intervenors‐
Appellees Number Nine Wind Farm LLC (“Number Nine”) and Fusion Solar LLC
(“Fusion Solar”), are preempted by the Federal Power Act and the Public Utility
Regulatory Policies Act (“PURPA”).1 In addition to seeking damages and fees
under 42 U.S.C. §§ 1983 and 1988, Allco sought equitable relief in the form of
voiding the intervenors’ contracts and enjoining the Commissioner from violating
1 Technically, PURPA is one of several amendments to the Federal Power
Act. See Federal Power Act, 16 U.S.C. §§ 791–828; PURPA, Pub. L. No. 95‐617, 92
Stat. 3117 (1978) (codified in part at 16 U.S.C. § 824a‐3). For ease of reference in
this opinion, however, any reference to the “Federal Power Act” excludes the
sections of the Act enacted under PURPA.
3
the Federal Power Act and PURPA in any future Section 6 procurement process.
The district court dismissed Allco’s complaint, concluding that Allco lacked
standing to sue and, in the alternative, that Allco failed to state a claim. Allco
contests both determinations on appeal.
We AFFIRM the district court’s judgment on alternative grounds.
Specifically, we hold that: (1) Allco cannot bring claims under §§ 1983 and 1988 to
vindicate any rights conferred by PURPA because PURPA’s private right of
action forecloses these remedies; (2) Allco failed to exhaust its administrative
remedies, a prerequisite for any qualified facility to bring an equitable action
seeking to vindicate specific rights conferred by PURPA; and (3) Allco lacks
standing to bring a preemption action seeking solely to void the contracts
awarded to Intervenors Fusion Solar and Number Nine.
BACKGROUND
A. The Federal Power Act and PURPA Statutory Schemes
We begin with some background on the Federal Power Act and PURPA
statutory schemes. The Federal Power Act gives the Federal Energy Regulatory
Commission (“FERC”) exclusive authority to regulate sales of electricity at
4
wholesale in interstate commerce. See 16 U.S.C. § 824(b)(1). States may not act in
this area unless Congress creates an exception. Id. § 824(b). PURPA contains one
such exception that permits states to foster electric generation by certain power
production facilities (“qualifying facilities”) that have no more than 80 megawatts
of capacity and use renewable generation technology. Id. § 824a‐3; see also id.
§ 796(17)(A). A state may regulate wholesale sales by qualifying facilities, but
those facilities must generally receive a price for their electricity equal to the
buying utility’s “avoided costs”—that is, those costs that the utility would have
otherwise incurred in procuring the same quantity of electricity from another
source. 18 C.F.R. § 292.304(b)(2); 16 U.S.C. § 824a‐3(b). PURPA imposes
obligations on each state regulatory authority to implement FERC’s PURPA
regulations. See 16 U.S.C. § 824a‐3(f)(1) (“[E]ach State regulatory authority shall,
after notice and opportunity for public hearing, implement [a new FERC] rule (or
revised rule) for each electric utility for which it has ratemaking authority.”).
PURPA also provides FERC and certain private parties with the ability to enforce
the requirement that states implement PURPA. See id. § 824a‐3(h). Relevant to this
appeal, PURPA provides a private right of action to “qualifying cogenerator[s]” to
5
enforce a state’s obligations under PURPA. Id. § 824a‐3(h)(2)(B).
Even though Allco concedes that it “does not rely on the private right of
action under” 16 U.S.C. § 824a‐3(h)(2)(B), Appellant’s Supp. Br. 1, this private
right of action is relevant to several aspects of this appeal, so we briefly describe
its structure. First, “qualifying cogenerator[s],” such as Allco, “may petition
[FERC] to enforce” a state’s requirements to comply with PURPA.
§ 824a‐3(h)(2)(B). Then, “[i]f the Commission does not initiate an enforcement
action . . . against a State regulatory authority,” such as the Connecticut
Department of Energy and Environmental Protection, “within 60 days following
the date on which a petition is filed . . . , the petitioner may bring an action in the
appropriate United States district court to require such State regulatory
authority . . . to comply with such requirements.” Id. The district court may then
“issue such injunctive or other relief as may be appropriate.” Id. Additionally,
FERC “may intervene as a matter of right in any such action.” Id.2
2 Allco argues that § 824a‐3(h)(2) is unconstitutional because it permits “an
action commandeering a State to implement federal law.” Appellant’s Supp. Br. 2.
Because Allco does not bring its claims under that section, we need not decide the
constitutional validity of the provision.
6
B. Factual Background
This case centers on Connecticut’s implementation of a 2013 state statute
that empowered the Commissioner of Connecticut’s Department of Energy and
Environmental Protection to solicit proposals for renewable energy, select
winners of the solicitation, and direct Connecticut’s utilities to enter into
wholesale energy contracts with the chosen winners. See Act Concerning
Connecticut’s Clean Energy Goals, 2013 Conn. Acts 303, § 6.
Implementing this statute, the Commissioner solicited Section 6 proposals
in July 2013. Allco submitted proposals for five solar projects, each of which was
no more than 80 megawatts and satisfied PURPA’s criteria for a qualifying
facility.
In September 2013, the Commissioner selected Number Nine as one of the
recipients of a contract with the utilities. Number Nine received a fifteen‐year
contract at a fixed price. According to Allco, Number Nine is too large to be a
qualifying facility under PURPA, so its selection prevented the selection of at least
one of Allco’s projects. The Commissioner also directed the utilities to enter into a
separate fixed‐price contract with Fusion Solar, a generator that was a qualifying
7
facility. According to Allco, Fusion Solar’s fixed price will differ from the price
that Number Nine otherwise would have received from selling its electricity into
the FERC‐approved energy market, thereby also violating the Federal Power Act
and PURPA regulatory schemes.
In a determination accompanying its selection of Number Nine and Fusion
Solar, the Connecticut Department of Energy and Environmental Protection
“describ[ed] the basis for its selection of [these] two renewable energy projects to
enter into long‐term power purchase agreements pursuant to Section 6.” J.A. 55.
In so doing, the Department set forth a ranked list of proposals. Allco’s
Harwinton Solar project appeared fourth on that list. Other Allco projects ranked
seventh, tenth, and thirteenth. Additionally, Allco bid a project at a lower price
than Fusion Solar, but that project was excluded, without explanation, from the
ranked list.
After failing to receive a Section 6 contract, Allco filed a complaint in the
U.S. District Court for the District of Connecticut, alleging that the
Commissioner’s implementation of Section 6 was preempted by the Federal
Power Act. The complaint alleged that Number Nine was too large to be a
8
qualifying facility and that the Commissioner’s action in compelling a wholesale
electricity transaction could be lawful only with respect to a qualifying facility
under PURPA. Additionally, the complaint asserted that the Commissioner
violated PURPA by selecting a higher bid from the qualifying facility Fusion Solar
instead of one of Allco’s lower‐priced bids.
The Commissioner moved to dismiss this complaint, and the district court
granted that motion for two independent reasons. The district court first
concluded that Allco lacked standing, both because its injuries were not within
the Federal Power Act and PURPA’s “zone of interests” and because its injuries
were not likely to be redressed by a favorable judgment. Allco Fin. Ltd. v. Klee, No.
13‐cv‐1874, 2014 WL 7004024, at *3–6 (D. Conn. Dec. 10, 2014). In the alternative,
the district court concluded that Allco failed to state a claim, both because the
Commissioner’s actions were not preempted and because there was no right of
action available to Allco under 42 U.S.C. § 1983. Id. at *6–10. On appeal, Allco
contests both sets of determinations.
9
DISCUSSION
We review de novo a district court’s dismissal of a complaint both for lack
of standing and for failure to state a claim. See Selevan v. N.Y. Thruway Auth., 584
F.3d 82, 88 (2d Cir. 2009). “[W]e are entitled to affirm the judgment on any basis
that is supported by the record.” Crawford v. Franklin Credit Mgmt. Corp., 758 F.3d
473, 482 (2d Cir. 2014).
To establish Article III standing, Allco must demonstrate: “(1) injury‐in‐fact,
which is a ‘concrete and particularized’ harm to a ‘legally protected interest’; (2)
causation in the form of a ‘fairly traceable’ connection between the asserted
injury‐in‐fact and the alleged actions of the defendant; and (3) redressability, or a
non‐speculative likelihood that the injury can be remedied by the requested
relief.” W.R. Huff Asset Mgmt. Co., LLC v. Deloitte & Touche LLP, 549 F.3d 100, 106–
07 (2d Cir. 2008) (emphases omitted) (quoting Lujan v. Defenders of Wildlife, 504
U.S. 555, 560–61 (1992)). In determining whether an injury is redressable, we
examine whether each aspect of the relief requested by Allco would redress its
asserted injury. See, e.g., Steel Co. v. Citizens for Better Env’t, 523 U.S. 83, 105–09
(1998).
10
In this case, Allco asserts as its primary injury its not being selected for a
Section 6 contract.3 To redress this injury, Allco seeks to: (1) invalidate the
Commissioner’s actions and void the Section 6 contracts awarded to Fusion Solar
and Number Nine; (2) enjoin the Commissioner from conducting any future
procurement that violates the Federal Power Act or PURPA; and (3) receive
money damages and fees resulting from the lost contract and the Commissioner’s
failure to comply with PURPA.
The crux of Allco’s challenge to the power‐purchase agreements is that the
Commissioner failed to conduct the challenged procurement in compliance with
the Federal Power Act and PURPA. Allco seeks to invalidate the results of the
first procurement so that the Commissioner can award Allco a Section 6 contract
3 Allco asserts as an alternative theory of injury that it will “earn lower
profit from future energy sales under PURPA” because “the [challenged]
procurement will affect the utilities’ cost structure.” Appellant’s Br. 33–34. For an
injury to be cognizable as an injury‐in‐fact, the plaintiff must have suffered the
injury at the time of the complaint’s filing, Lujan, 504 U.S. at 570 n.5, or the injury
must at least have been “imminent,” id. at 564. Neither is true with respect to this
asserted injury. The PURPA sales that Allco fears it would make at a lower price
clearly did not occur at the time that the complaint was filed, as they are future
sales. There is also no indication in the record that these future sales were
imminent when the complaint was filed. As such, this alternative theory of injury
is far too speculative to serve as the basis for an Article III injury‐in‐fact.
11
based either on the original procurement’s bidding results or on the results of a
new procurement process. Because the only way in which Allco may obtain a
Section 6 contract is for the Commissioner to conduct a PURPA‐compliant
bidding process, Allco is in effect seeking to enforce PURPA’s requirements.4
But, as noted earlier, Allco does not seek to enforce PURPA’s requirements
through the private right of action contained within PURPA itself. Allco concedes
that it “does not rely on the private right of action under” 16 U.S.C.
§ 824a‐3(h)(2)(B), Appellant’s Supp. Br. 1, and that it “has not petitioned [FERC]
to enforce the requirements of 16 U.S.C. § 824a‐3(f) against [the Commissioner],”
4
The district court also held that Allco lacks standing to assert a violation of
the FPA because the interest Allco asserts is not “within the zone of interests to be
protected or regulated by the statute that it says was violated.” Allco Fin. Ltd.,
2014 WL 7004024, at *4 (quoting Match‐E‐Be‐Nash‐She‐Wish Band of Pottawatomi
Indians v. Patchak, 132 S. Ct. 2199, 2210 (2012)). The parties do not address the
effect, if any, of Lexmark International, Inc. v. Static Control Components, Inc., 134 S.
Ct. 1377 (2014), on the district court’s standing analysis. But even assuming that
Allco comes within the FPA’s zone of interests, we conclude that its claims fail for
alternative reasons, as discussed in the text, so we need not decide Lexmark’s
effect on the district court’s zone‐of‐interests analysis. Cf. Lerner v. Fleet Bank, N.A.,
318 F.3d 113, 127 (2d Cir. 2003) (“[C]ourts may determine whether a cause of
action exists under a given statute, an issue of statutory construction that goes to
the merits of the action, before addressing the zone‐of‐interests prudential
dimension of standing . . . .”).
12
id. at 2. Instead, Allco brings two other claims—“a claim under 42 U.S.C. § 1983”
and “a straightforward pre‐emption claim for regulating wholesale sales.”
Appellant’s Supp. Br. 2. We address each of these claims in turn.
A. Allco’s Claims Under 42 U.S.C. §§ 1983 and 1988
Allco has Article III standing to bring a claim for money damages and fees
under §§ 1983 and 1988 because it suffered a monetary loss that is fairly traceable
to the challenged conduct and would be redressable through a monetary
judgment. See, e.g., Steel Co., 523 U.S. at 96. But to establish its entitlement to
money damages for its loss of contract, Allco must show that PURPA provides a
non‐preempted way in which the Commissioner could have conducted the
Section 6 procurement and awarded the contract to Allco. Allco therefore seeks to
enforce PURPA indirectly, even if it styles its claim differently and brings it under
another right of action.
Because Allco is in effect seeking to enforce PURPA when it requests
money damages for its lost Section 6 contract, we must decide whether § 1983
provides a private right of action to enforce PURPA. We undertake a two‐part
inquiry to determine whether Congress intended to foreclose a § 1983 remedy.
First, we ask whether PURPA provides “an unambiguously conferred right to
13
support a cause of action brought under § 1983.” Gonzaga Univ. v. Doe, 536 U.S.
273, 283 (2002); see also Albright v. Oliver, 510 U.S. 266, 271 (1994). Second, we must
determine whether there is “indication, express or implicit, that the remedy
[provided in PURPA] is to complement, rather than supplant, § 1983,” thereby
overcoming the “ordinary inference that the remedy provided in the statute is
exclusive.” City of Rancho Palos Verdes v. Abrams, 544 U.S. 113, 122 (2005).
We need not consider the first question because the answer to the second
question clearly forecloses the availability of relief under § 1983. PURPA’s
conferral of a private right of action requiring compliance with specific pre‐
lawsuit procedures strongly indicates Congress’s intent to foreclose a separate
remedy under § 1983. See, e.g., id. at 121 (“The provision of an express, private
means of redress in the statute itself is ordinarily an indication that Congress did
not intend to leave open a more expansive remedy under § 1983.”). As the Rancho
Palos Verdes Court recognized, multiple Supreme Court decisions have foreclosed
§ 1983 remedies due to “the existence of more restrictive remedies provided in the
violated statute itself.” Id. (citing Smith v. Robinson, 468 U.S. 992, 1011 (1984)
(concluding that the recognition of a § 1983 action would “render superfluous
14
most of the detailed procedural protections outlined in the statute”); Middlesex
Cty. Sewerage Auth. v. Nat’l Sea Clammers Ass’n, 453 U.S. 1, 20 (1981) (“[W]hen ‘a
state official is alleged to have violated a federal statute which provides its own
comprehensive enforcement scheme, the requirements of that enforcement
procedure may not be bypassed by bringing suit directly under § 1983.’”)). The
existence of PURPA’s private right of action forecloses Allco’s ability to bring a
§ 1983 claim for money damages based on the Commissioner’s failure to award
Allco a PURPA‐compliant Section 6 contract.
Additionally, because no § 1983 claim is available to enforce PURPA, Allco
also cannot bring a § 1988 claim for attorneys’ fees predicated on the
Commissioner’s failure to comply with PURPA. See 42 U.S.C. § 1988(b) (limiting
the award of attorneys’ fees to certain actions, including “any action or
proceeding to enforce a provision of [§ 1983]”).
B. Allco’s Preemption Claim
Allco also seeks equitable relief through what it describes as “a
straightforward pre‐emption claim for regulating wholesale sales.” Appellant’s
Supp. Br. 2. This preemption claim requests two forms of relief: (1) enjoining the
Commissioner from conducting future procurements that violate the Federal
15
Power Act or PURPA and (2) voiding the Section 6 contract awards to Fusion
Solar and Number Nine. We analyze each form of relief separately.
1. Injunction Related to Future Procurements
First, we affirm the district court’s dismissal of Allco’s claims seeking
equitable relief regarding future procurements conducted by the Commissioner.
For such relief to redress Allco’s injury, it must be “likely, as opposed to merely
speculative,” that Allco receive the Section 6 contract that it seeks. Friends of the
Earth, Inc. v. Laidlaw Envtl Servs. (TOC), Inc., 528 U.S. 167, 181 (2000). Based on the
record before us, the only way in which the Commissioner can issue a Section 6
contract that is not preempted by the Federal Power Act is if that contract meets
the requirements of the PURPA exception. As Allco acknowledges, its “status as a
small power producer” under PURPA “is relevant to [its] Article III standing and
to explain[ing] why [its] injury is redressable.” Appellant’s Supp. Br. 2. As such,
any equitable relief relating to future contracts awarded under Section 6
necessarily implicates PURPA; otherwise, such relief would provide no path by
which Allco could eventually obtain a non‐preempted Section 6 contract.
16
To the extent that Allco seeks to enforce PURPA’s requirements through a
“straightforward pre‐emption claim,” Appellant’s Supp. Br. 2, it “cannot avoid
the administrative exhaustion requirement of [§ 824a‐3(h)(2)(B)] simply by
restating its PURPA claim under a different heading,” Niagara Mohawk Power
Corp. v. FERC, 306 F.3d 1264, 1270 (2d Cir. 2002). This Court has held that a party
cannot evade PURPA’s administrative exhaustion requirement by characterizing
an otherwise covered PURPA‐related equitable claim as a Supremacy Clause
claim. Id. Therefore, if Allco’s preemption claim—regardless of how it is
characterized—is covered by § 824a‐3(h)(2)(B)’s administrative exhaustion
requirement, then Allco’s claim must be dismissed.
PURPA requires administrative exhaustion for claims brought by qualified
facilities5 that are attempting to enforce the requirements of § 824a‐3(f). See § 824a‐
3(h)(2)(B). Section 824a‐3(f) requires states to “implement” FERC’s rules
promulgated under 16 U.S.C. § 824a‐3(a)6 by “issuing regulations, by resolving
5 It is undisputed that Allco is a qualified facility under § 824a‐3(h)(2)(B).
See J.A. 9.
6 Section 824a‐3(a) empowers FERC to promulgate rules to encourage
cogeneration and small power production. Allco’s claim can be characterized as
an attempt to enforce § 210(a) rules, including 18 C.F.R. § 292.304(d), that require
17
disputes on a case‐by‐case basis, or by taking any other action reasonably
designed to give effect to FERC’s rules.” FERC v. Mississippi, 456 U.S. 742, 751
(1982). In Niagara Mohawk, we dismissed a preemption claim for failure to exhaust
PURPA’s administrative remedies because the claim challenged “a state rate‐
setting regulation promulgated pursuant to [§ 824a‐3(f)], the provision that
[§ 824a‐3(h)(2)(B)] petitions are intended to enforce.” 306 F.3d at 1270. Niagara
Mohawk is an example of a straightforward application of § 824a‐3(h)(2)(B)’s
administrative exhaustion requirement—a qualified‐facility plaintiff brought a
preemption claim challenging a state regulation promulgated under § 824a‐3(f). See
id.
Allco’s preemption claim presents us with a novel application of PURPA’s
administrative exhaustion requirement. Allco’s attempt to enforce PURPA’s
requirements stems not from a challenge to a state regulation promulgated under
§ 824a‐3(f) but from a challenge to a state procurement law—Section 6. This
distinction, however, does not relieve Allco of its obligation to exhaust its
administrative remedies under § 824a‐3(h)(2)(B) because its claim is still an
utilities to buy power from Allco at a rate at or below the avoided cost.
18
attempt to enforce § 824a‐3(f). A state’s ongoing obligation under § 824a‐3(f) to
“implement” PURPA regulations can be accomplished in a variety of ways, but,
at a minimum, § 824a‐3(f) undoubtedly prevents states from violating § 824a‐3(a).
See Mississippi, 456 U.S. at 751; see also POLICY STATEMENT REGARDING COMM’N’S
ENF’T ROLE UNDER SECTION 210 OF [PURPA], 23 FERC P 61,304, 61,644 (1983). The
heart of Allco’s claim is that the Commissioner failed to follow § 824a‐3(a)
regulations when conducting the Section 6 procurement and the procurement is
therefore preempted. Allco’s characterization of its cause of action “under a
different heading” does not transform its claim into something other than what it
is: an action to compel a state to implement § 824a‐3(a). Niagara Mohawk, 306 F.3d
at 1270.
Our reading of §§ 824a‐3(f) and 824a‐3(a) comports with our holding in
Niagara Mohawk. In Niagara Mohawk, we distinguished our holding from Freehold
Cogeneration Ass’n L.P. v. Board of Regulatory Commissioners, 44 F.3d 1183 (3d Cir.
1995), on the grounds that the claim in Freehold was not a challenge to a state
regulation promulgated under § 824a‐3(f). 306 F.3d at 1270. We now distinguish
our holding from Freehold on similar, yet distinct, grounds. The preemption claim
19
in Freehold did not require § 824a‐3(h)(2)(B) exhaustion because the claim was an
attempt to enforce the exemption provisions contained in § 824a‐3(e), not an
attempt to enforce the qualified‐facility regulations in § 824a‐3(a). See Freehold, 44
F.3d at 1184–85. Allco’s preemption claim is subject to § 824a‐3(h)(2)(B)’s
administrative exhaustion requirement because Allco’s claim is an attempt to
enforce § 824a‐3(f), which requires Connecticut to implement FERC’s rules
promulgated under § 824a‐3(a).
This Court has also held that the administrative exhaustion requirement is
jurisdictional.7 See Niagara Mohawk Power, 306 F.3d at 1270 (“We hold that the
District Court correctly dismissed [the plaintiff’s] PURPA claim as against the
[defendants] for lack of subject matter jurisdiction because of [the plaintiff’s]
failure to exhaust its administrative remedy by petitioning FERC to bring an
7 Allco argues that, in light of more recent Supreme Court decisions in
Sebelius v. Auburn Regional Medical Center, 133 S. Ct. 817, 824 (2013), and Arbaugh v.
Y&H Corp., 546 U.S. 500, 516 (2006), PURPA’s administrative exhaustion
requirement is not actually a jurisdictional bar. We need not determine whether
these Supreme Court decisions call into question that part of the holding in
Niagara Mohawk Power because Allco’s claims would be dismissed for failure to
exhaust administrative remedies regardless of whether the requirement is
jurisdictional.
20
enforcement action against the [state regulatory agency] in the first instance.”); see
also id. (“[B]ecause [the plaintiff] has not satisfied this [exhaustion] requirement,
its [Supremacy Clause] claims against the [defendants] should have been
dismissed for lack of subject matter jurisdiction.”). Accordingly, Allco’s attempts
to characterize its PURPA‐enforcement efforts as preemption or Supremacy
Clause claims are unavailing, and we affirm the dismissal of those claims on the
alternative grounds that Allco failed to comply with the administrative
exhaustion requirement.
2. Equitable Relief Voiding Fusion Solar and Number Nine’s Contracts
Having disposed of Allco’s claims seeking equitable relief regarding future
procurements, we must finally resolve Allco’s claims that seek solely to invalidate
the results of the challenged procurement and void its competitors’ contracts. To
the extent that these claims seek only to invalidate the results of the prior
procurement—and not also to require the Commissioner to conduct future
procurements in compliance with PURPA—Allco lacks standing because that
requested relief does not redress its injury, i.e., its not being selected for a Section
6 contract.
21
Allco contends that its preemption claim should be permitted because it can
redress its injuries simply by invalidating the Commissioner’s prior selections and
voiding the contracts given to Fusion Solar and Number Nine. But those forms of
relief, standing alone, fail to redress Allco’s injuries, as they do not make it
“likely, as opposed to merely speculative,” that Allco will eventually receive a
Section 6 contract. Friends of the Earth, 528 U.S. at 181. Allco must show, at a
minimum, that the requested relief provides a path for Allco to eventually obtain
a Section 6 contract. But invalidating the Section 6 contracts awarded to Fusion
Solar and Number Nine would simply deny Allco’s competitors a contractual
benefit without redressing Allco’s injury— its not being selected for a Section 6
contract. Because merely voiding its competitors’ contracts would not redress
Allco’s injury, Allco also lacks standing to seek such equitable relief.
CONCLUSION
For the reasons stated herein, we AFFIRM the district court’s judgment.
22