STATE OF MICHIGAN
COURT OF APPEALS
RAVE’S CONSTRUCTION AND UNPUBLISHED
DEMOLITION, INC., and NORA SHEENA, January 7, 2016
Plaintiffs/Counter-Defendants-
Appellees/Cross-Appellants,
v No. 323908
Oakland Circuit Court
RANDY MERRILL, JAMES MERRILL, LC No. 2012-129781-CZ
ANGELO PALETTA, CHRISTOPHER
ROTHROCK, and TONY & SONS, INC.,
Defendants/Counter-Plaintiffs-
Appellants/Cross-Appellees.
Before: TALBOT, C.J., and CAVANAGH and K. F. KELLY, JJ.
PER CURIAM.
After a bench trial, the trial court entered a final judgment in the amount of $84,356.53
plus statutory interest against Randy Merrill (Randy) and James Merrill (James), and in favor of
Rave’s Construction and Demolition, Inc. (Rave’s). The trial court entered a judgment of no
cause of action with regard to claims raised by the Merrills against Rave’s, as well as with
respect to claims raised by Rave’s against Angelo Paletta (Paletta), Christopher Rothrock
(Rothrock), and Tony & Sons, Inc. The Merrills appeal the trial court’s judgment as of right, and
Rave’s has filed a cross-appeal. We affirm in part, vacate in part, and remand for further
proceedings.
I. FACTS
This case arises out of the Merrills’ employment with Rave’s. Prior to their employment
with Rave’s, the Merrills owned their own construction companies. The Merrills completed
several large-scale projects for Kroger, generally involving remodeling entire stores. Rave’s,
itself a construction company, is owned by Nora Sheena (Nora). Its vice president and treasurer
is Robert Sowles (Sowles), and Nora’s husband, Ramiz Sheena (Ramiz), is Rave’s chief
financial officer. Before hiring the Merrills, Rave’s completed small-scale projects for Kroger.
But Kroger did not have confidence that Rave’s could complete whole-store remodeling projects,
and would not allow Rave’s to bid on these larger projects without the Merrills’ involvment.
-1-
On January 1, 2010, Rave’s hired the Merrills to head a newly-established division, the
General Contracting Division. This division’s primary purpose was to bid and complete large-
scale remodeling projects for Kroger, although the division also bid and completed some small-
scale projects. Pursuant to a written employment agreement, the Merrills were to receive a base
salary of $65,000. They were also to receive a commission of 1.5% of the gross revenues
received by Rave’s from Kroger, so long as the Merrills were “a procuring cause” of the
contract. Each month, the Merrills also each received $850 in the form of an allowance for
health insurance, and an additional $850 as a vehicle allowance.
The Merrills were responsible for tracking the division’s profits, and provided monthly
profit and loss statements to Rave’s. In 2010, the division was profitable, at least according to
the Merrills’ calculations. In January, 2011, the parties agreed to share the division’s profits,
with half going to the Merrills and the other half to Rave’s. Randy provided a proposal to
Rave’s. Using the division’s year-end profit and loss statement as a starting point, Randy
determined that he and James were each entitled to an additional $26,629.63. Rave’s accepted
this determination. However, rather than pay this amount in a lump sum, Rave’s divided it into
equal weekly payments, which were added to the Merrills’ weekly paychecks throughout 2011.
The parties’ arrangement broke down in 2012, after the Merrills refused Rave’s request
that they invest their commissions in the company. On April 6, 2012, the parties entered into an
agreement, titled “Employment Agreement.” Under this agreement, the Merrills’ responsibilities
were described as the “[c]ompletion of all general contracting work, through receipt of final
payment for Kroger store #622.” The Merrills were to receive their base salary through June 9,
2012, and health and vehicle allowances in May and June, 2012.1 The Merrills were also to
receive additional compensation in the form of commissions and a share of the General
Contracting Division’s monetary assets after its debts were paid.
Much of the instant dispute centers on the profit-sharing arrangement reached in 2011
and the Merrills’ entitlement to additional compensation under the April 6, 2012 agreement.
After a bench trial, the trial court concluded that the Merrills had failed to include certain
expenses when calculating the General Contracting Division’s profits. It added the expenses it
found were not included and then awarded half of this amount to Rave’s. Relying on a
restriction contained in the January 1, 2010 employment agreement, the trial court concluded that
the Merrills were not entitled to any additional commissions or profits beyond those already
received.
The trial court also concluded that the Merrills had failed to timely return certain
documents and records to Rave’s, and that the delay in providing these documents and records
caused $1,500 in damages to Rave’s. The trial court found that the Merrills had wrongfully
retained certain laptop computers that were purchased by Rave’s for the Merrills’ use, and
awarded $2,220 in damages to compensate Rave’s for these computers. The trial court rejected
1
At the time of this agreement, three projects were in various stages of completion. Store 622
was the farthest from completion. According to Randy, June 9, 2012 was selected because this
was the date this store was scheduled to be completed.
-2-
the remaining claims raised by the parties. The Merrills appeal from this judgment, and Rave’s
has filed a cross-appeal.
II. COUNT V OF RAVE’S AMENDED COMPLAINT2
Both parties contest the trial court’s conclusion with regard to Count V of the complaint.
In this count, Rave’s asserted that the Merrills failed to include certain expenses when
calculating the General Contracting Division’s profits, and thus, overstated the division’s profits.
We agree that the trial court clearly erred with regard to this count. We vacate the trial court’s
decision with regard to Count V of the amended complaint and remand for further proceedings.
“Following a bench trial, we review for clear error the trial court’s factual findings and
review de novo its conclusions of law.”3 “This Court [also] reviews the trial court’s
determination of damages following a bench trial for clear error.”4 “[F]actual findings are
clearly erroneous where there is no evidentiary support for them or where there is supporting
evidence but the reviewing court is nevertheless left with a definite and firm conviction that the
trial court made a mistake.”5 We review de novo “questions involving the proper interpretation
of a contract or the legal effect of a contractual clause . . . .”6
A. THE MERRILLS’ ARGUMENTS
In their appeal, the Merrills raise five individual reasons why they believe the trial court
erred with respect to this count. First, the Merrills argue that because the January 1, 2010
agreement contains an integration clause, the parol evidence rule bars this Court from looking
beyond the terms of this agreement. The January 1, 2010 employment agreement contains an
integration clause, and no party contests the validity of this clause.7 It is well-established in our
jurisprudence that a “valid integration clause nullifie[s] all prior and contemporaneous
2
The Merrills briefly argue that the trial court abused its discretion by failing to allow them to
file an answer to Rave’s motion for reconsideration. No such issue is raised in the Merrills’
statement of the questions presented. As such, we will not address the question. See Bouverette
v Westinghouse Elec Corp, 245 Mich App 391, 404; 628 NW2d 86 (2001) (“Independent issues
not raised in the statement of questions presented are not properly presented for appellate
review.”).
3
Ligon v Detroit, 276 Mich App 120, 124; 739 NW2d 900 (2007).
4
Alan Custom Homes, Inc v Krol, 256 Mich App 505, 513; 667 NW2d 379 (2003).
5
Hill v City of Warren, 276 Mich App 299, 308; 740 NW2d 706 (2007).
6
Rory v Continental Ins Co, 473 Mich 457, 464; 703 NW2d 23 (2005).
7
The agreement states, “[t]his Agreement constitutes the entire agreement among the parties
hereto with respect to the subject matter hereof. All prior correspondence and proposals . . . are
merged herein and superseded hereby.”
-3-
agreements, understandings, representations, and warranties . . . .”8 It is equally well-established
that evidence of subsequent agreements is not barred by the parol evidence rule.9 This is because
“the parties possess, and never cease to possess, the freedom to contract even after the original
contract has been executed.”10 Thus, while agreements reached prior to or contemporaneously
with the January 1, 2010 agreement were nullified, this Court is not prohibited in any way from
considering the effect of agreements reached by the parties after January 1, 2010. And as the
trial court found, the agreement at issue was reached in January, 2011.11
Second, the Merrills contend that the additional sums they received in 2011 were wages,
and thus, are not refundable under the Michigan Payment of Wages and Fringe Benefits Act.12
We find no merit to this argument. The statute relied upon by the Merrills, MCL 408.477,
regulates when and under what conditions an employer may make deductions from wages paid in
an employee’s regular paycheck.13 Through its lawsuit, Rave’s did not seek to make a deduction
from a regular paycheck. Rave’s sought to recover an amount it believed it wrongfully paid to
the Merrills because, according to Rave’s, the Merrills misrepresented the true financial state of
the General Contracting Division. The statute is of no relevance to this matter.
Third, the Merrills argue that because Rave’s voluntarily approved the additional
compensation received by the Merrills in 2011, Rave’s cannot now recover those payments. The
Merrills rely on Montgomery Ward & Co v Williams, where our Supreme Court stated:
8
Hamade v Sunoco Inc (R & M), 271 Mich App 145, 171; 721 NW2d 233 (2006) (emphasis
supplied). See also UAW-GM Human Resource Ctr v KSL Recreation Corp, 228 Mich App 486,
499; 579 NW2d 411 (1998) (“[A]n integration clause nullifies all antecedent agreements.”).
9
See Michigan Nat’l Bank of Detroit v Holland-Dozier-Holland Sound Studios, 73 Mich App
12, 14; 250 NW2d 532 (1976) (“[W]e must . . . disabuse the lower court of the notion that the
parol evidence rule will bar proof of oral modifications occurring after the parties have reduced
their obligations to writing. The swath of the parol evidence rule is not so broad as to prevent a
showing of subsequent oral modifications.”).
10
Quality Prods and Concepts Co v Nagel Precision, Inc, 469 Mich 362, 372; 666 NW2d 251
(2003).
11
Specifically, the trial court found that “[i]n January 2011 the parties agreed that the Merrills
would receive additional compensation for their work, i.e., a portion of the profits realized from
the General Contracting Division in 2010 . . . .” The Merrills do not contest this finding.
12
MCL 408.471 et seq.
13
The specific provision relied on by the Merrills, MCL 408.477(4), provides:
Within 6 months after making an overpayment of wages or fringe benefits that are
paid directly to an employee, an employer may deduct the overpayment from the
employee’s regularly scheduled wage payment without the written consent of the
employee if all of the following conditions are met:” (emphasis supplied).
-4-
“It is well settled that a voluntary payment cannot be recovered back, but a
voluntary payment is one made with full knowledge of all the circumstances upon
which it is demanded, and without artifice, fraud, or deception on the part of the
payer, or duress of the person, or goods of the person making the payment.”[14]
The trial court concluded that because the Merrills had incorrectly reported the General
Contracting Division’s profits to Rave’s, Rave’s lacked full knowledge of all the relevant
circumstances, and thus, Rave’s payments could not be considered voluntary under Montgomery
Ward & Co. The Merrills contend that because Rave’s had the necessary information to perform
its own profit calculation, and thus, discover any discrepancies, it cannot now claim that it was
defrauded or deceived into making these payments. It is true that in Montgomery Ward & Co,
the Court held that “fraud is not perpetrated upon one who has full knowledge to the contrary of
a representation.”15 But as our Supreme Court has recently explained, it is unnecessary for a
party “to have performed an investigation of all assertions and representations made by its
contracting partner as a prerequisite to establishing fraud.”16 Moreover, our Supreme Court also
recognized in Montgomery Ward & Co that “a payment, although voluntarily made, if made
under a mistake of a material fact, may be recovered, even if the mistake be due to a lack of
investigation.”17 Thus, regardless of whether Rave’s had the means to discover that the Merrills’
accounting of the division was erroneous, Montgomery Ward & Co presents no bar to Rave’s
recovery in this matter.
The Merrills’ fourth contention is that the trial court erred by including in its calculation
of damages expenses not attributable to the year 2010. In this regard, we agree that the trial
court clearly erred. The trial court found that the agreement between the parties was to share the
2010 profits of the General Contracting Division.18 Both before and after trial, the parties
similarly couched the issue as pertaining only to the division’s 2010 profits. And even at the
present stage of the proceedings, Rave’s states, “Rave’s is contending that the profit for 2010,
14
Montgomery Ward & Co v Williams, 330 Mich 275, 284-285; 47 NW2d 607 (1951), quoting
Pingree v Mutual Gas Co, 107 Mich 156, 157; 65 NW 6 (1895).
15
Id. at 284.
16
Titan Ins Co v Hyten, 491 Mich 547, 557; 817 NW2d 562 (2012).
17
Montgomery Ward & Co, 330 Mich at 284.
18
Specifically, the trial court found that “[i]n January[,] 2011[,] the parties agreed that the
Merrills would receive additional compensation for their work, i.e., a portion of the profits
realized from the General Contracting Division in 2010, to be paid out weekly throughout
2011.” When describing the count of the complaint at issue, the court explained that “[t]his
count is based on the parties’ agreement that the Merrills would receive 50% of the 2010 profits
from the General Contracting Division, and the manner in which the Merrills calculated that
amount . . . .”
-5-
not 2011[,] was overstated . . . .”19 Thus, the pertinent issue is whether the Merrills failed to take
into account certain expenses when calculating the General Contracting Division’s profits for the
year 2010.
But when it calculated the damages owed to Rave’s, the trial court accepted the
determinations stated in Exhibit 32.20 This exhibit, prepared by Nora, was an accounting of the
division’s finances over its entire existence. It included expenses incurred21 both before and
after 2010.22 Including expenses from years other than 2010 cannot be reconciled with Rave’s
description of its claim or with trial court’s conclusion that the count at issue “was based on the
parties’ agreement that the Merrills would receive 50% of the 2010 profits from the General
Contracting Division . . . .” Indeed, by relying on this exhibit, the trial court eventually awarded
over $80,000 in damages to Rave’s on this count of the complaint, even though Rave’s had only
paid the Merrills approximately $53,000 under the agreement at issue. The award is clearly
erroneous.
On reconsideration, the trial court rejected this challenge to its calculations, stating that
“the parties’ agreement clearly called for the sharing of expenses whenever they were incurred.”
This conclusion was in error. The agreement, as found by the trial court, was not one
contemplating the sharing of profits or expenses over the entire course of the parties’
relationship. It was simply an agreement that the Merrills would receive a portion of the
division’s 2010 profits. Indeed, our review of the record established in the trial court does not
disclose a single agreement to share expenses.23 Accordingly, we vacate the trial court’s award
of damages on Count V of the complaint and remand for further proceedings. Before it may
award damages on this count, the trial court must determine what expenses are attributable to the
year 2010, and then, whether these expenses were omitted by the Merrills when calculating the
division’s 2010 profits.
19
Rave’s similarly states in its cross-appeal that the parties had an agreement for the “split of
profit realized from the General Contracting Division . . . which agreement was made in January,
2011 for the profit realized for the calendar year 2010.”
20
Nora testified that her approach to preparing this exhibit was to show “the actual bank balance
in the bank as of September 1, 2012. The G[eneral Contracting] bank account.”
21
The Merrills utilized an accrual method of accounting, as opposed to a cash-basis accounting
method. The accrual method is “[a]n accounting method that records entries of debits and credits
when the revenue or liability arises, rather than when the income is received or an expense paid.”
Black’s Law Dictionary (10th ed), p 24.
22
As examples, Nora included “supervision fees” incurred in 2012 and 2013, payroll processing
fees for “January 2010 thr[ough] last checks paid in June 2012,” payroll taxes for 2010, 2011,
and 2012, legal fees incurred in 2008 and 2009, and insurance expenses for 2011 and 2012.
23
Of course, those expenses attributable to the year 2010 would be shared by the parties, as those
expenses form a necessary component of the profit calculation. But there exists no evidence of
an agreement that required the Merrills to bear a portion of losses if the General Contracting
Division was not profitable, whether in 2010 or in any other year.
-6-
The Merrills raise a fifth contention of error, arguing that certain amounts awarded by the
trial court represent items that were not actually expenses of the General Contracting Division.
For example, the Merrills argue that what the trial court described as automobile and insurance
expenses for Ramiz and Sowles should not be the responsibility of the division. The Merrills
assert that these “expenses” actually represented a profit distribution to Ramiz and Sowles. The
Merrills argue that the loans addressed in the trial court’s award were not actually loans, but
represented the capital used to fund the work done by the division. The Merrills argue that
payroll taxes were, in fact, accounted for in Randy’s calculations. They also argue that they
never agreed to pay attorney fees, and that in any case, many of these fees were unrelated to the
division.
While the trial court found that these amounts were not included in Randy’s calculations,
it did not specifically address a more fundamental question – whether these amounts should have
been included in Randy’s calculations as expenses. And ultimately, it appears that this question
is the one truly disputed by the parties. Given that we must vacate the trial court’s decision with
respect to this count, the parties may address the issue in the trial court on remand. Nor is this
Court the correct forum to resolve disputed factual questions such as these. Rather, such factual
determinations, many of which would seem to turn on a determination of credibility, are properly
left to the finder of fact.24
B. RAVE’S ARGUMENTS
Rave’s contends that the trial court clearly erred by failing to include insurance expenses
when it calculated damages owed to Rave’s under Count V of its amended complaint. The trial
court found that these expenses had not been presented to the Merrills, and thus, were not
improperly omitted when the Merrills calculated the General Contracting Division’s profits.
Relying on certain communications and invoices, Rave’s contends that these expenses were, in
fact, presented to the Merrills. Rave’s also contends that whether the Merrills were aware of
these expenses is irrelevant because pursuant to the April 6, 2012 agreement, the parties agreed
that these expenses would be paid before any of the division’s monetary assets were distributed.
Because we must vacate the trial court’s decision with respect to this count of the amended
complaint, we decline to address this issue. The trial court may revisit the question of whether
the Merrills should have included insurance expenses in their calculation of the division’s 2010
profit on remand.
III. COUNT I OF THE AMENDED COMPLAINT
The Merrills argue that the trial court erred with respect to Count I of Rave’s amended
complaint. The trial court concluded that the Merrills were responsible for damages in the
amount of $3,720, representing $1,500 in expenses for Rave’s to reproduce documents the
24
“The question of credibility is generally for the fact-finder to decide.” Taylor v Mobley, 279
Mich App 309, 314 n 5; 760 NW2d 234 (2008). To facilitate any potential further appellate
review, we encourage the trial court to provide clear and specific findings in this regard.
-7-
Merrills refused to provide, and $2,220 for three computers purchased by Rave’s but retained by
the Merrills. We find no clear error in the trial court’s decision with regard to this count.
Rave’s complaint alleged that the Merrills retained several boxes of documents, including
contracts, invoices, and other information, after their employment was terminated. Sowles
testified that as a result, he spent 200 hours reconstructing these records. Rave’s sought $15,000
in damages, representing a rate of $75 an hour for this work. In response to a motion, the trial
court ordered the Merrills to turn over the documents at issue, and the Merrills complied. The
trial court concluded:
The Court finds that Rave[’]s is entitled to recover for these expenses, but
not to the extent sought. Specifically, the evidence indicates that Rave[’s] need
for immediate reproduction of the documents related only to the jobs that were
still outstanding at the time Rave[’]s terminated the Merrills. This represents
approximately ten percent of the documents at issue. Thus, Rave[’]s is entitled to
recover only that portion of its claim, i.e, $1,500 . . . .
The Merrills first argue that this award was improper because the Merrills did provide the
requested records to Rave’s. The Merrills’ argument does not address the basis of the trial
court’s decision. The trial court did not award damages because the documents were never
provided; it did so on the basis that the delay in providing the documents caused harm to Rave’s.
Because the Merrills’ argument fails to address the basis of the trial court’s decision, this Court
need not even consider granting relief.25
In their reply brief, the Merrills assert that Rave’s produced no “credible evidence” of
damages, pointing out that Sowles did not produce any records to substantiate the number of
hours he claimed to have spent reproducing the documents. This argument simply disputes the
trial court’s finding that Sowles’s testimony was credible, and is no basis for reversing the trial
court’s decision.26
The Merrills also argue that Rave’s failed to mitigate its damages because it could have
allowed the Merrills to remain employed and to finish the projects that were not yet complete.
“Mitigation of damages is a legal doctrine that seeks to minimize the economic harm arising
from wrongdoing.”27 “Specifically, when one has committed a legal wrong against another, the
latter has an obligation to use reasonable means under the circumstances to avoid or minimize
his or her damages and cannot recover for damages that could thus have been avoided.”28 It is
25
Derderian v Genesys Health Care Sys, 263 Mich App 364, 381; 689 NW2d 145 (2004).
26
See In re Miller, 433 Mich 331, 337; 445 NW2d 161 (1989) (under the clear error standard of
review, “regard is to be given to the special opportunity of the trial court to judge the credibility
of the witnesses who appeared before it.”); Taylor, 279 Mich App at 314 n 5 (“The question of
credibility is generally for the fact-finder to decide.”).
27
Landin v Healthsource Saginaw, Inc, 305 Mich App 519, 538; 854 NW2d 152 (2014).
28
Id.
-8-
clear from the record that the parties’ relationship deteriorated to a point of being unworkable.
Randy testified at trial that the parties’ relationship had become adversarial. Indeed, before they
were terminated, the Merrills refused to provide the records requested by Raves, demanded
payment of commissions, and threatened legal action if a compromise could not be reached.
Under the circumstances, we decline to hold that continuing the Merrills’ employment would
have been a reasonable means to avoid the damages found by the trial court.
The Merrills also make cursory arguments regarding the laptop computers, with no
citation to authority supporting their arguments. By failing to support their position with any
legal authority, the Merrills have abandoned their arguments.29 Nor do the arguments have any
merit. The Merrills suggest that the trial court should not have considered any award of damages
with respect to the computers because the computers were not specifically mentioned in the
complaint. However, in a joint final pretrial statement signed by the Merrills’ counsel, the
Merrills acknowledged that one of Rave’s claims was “[w]hether [d]efendants, [the] Merrills[,]
have retained computers owned by Rave’s and refuse to return the same to Rave’s.” “A party
may not take a position in the trial court and subsequently seek redress in an appellate court that
is based on a position contrary to that taken in the trial court.”30 The Merrills also state that
Rave’s was not entitled to recover damages because the computers were purchased to replace
computers owned by the Merrills. The trial court found the contrary, concluding that the parties
did not intend for the Merrills to retain these computers. As this factual determination turned on
a credibility determination, we find no clear error.31 Accordingly, we affirm the trial court’s
award of damages with respect to Count I of the complaint.
IV. THE MERRILLS’ CROSS-CLAIMS
The Merrills contend that the trial court erred when it found that the Merrills were not
entitled to recover any amount under the April 6, 2012 agreement. They also argue that the trial
court erred by finding no cause of action with regard to their claim of conversion. While we find
no error with regard to claim of conversion, we agree that the trial court erred with respect to the
Merrills’ claims arising from the April 6, 2012 agreement.
In the trial court, the Merrills claimed that Rave’s failed to pay all of the commissions
and other sums due to them under the April 6, 2012 agreement. Relying on a portion of the
January 1, 2010 agreement, the trial court found the Merrills were not entitled to recover any
amount from Rave’s. The January 1, 2010 employment agreement provided:
Employee shall be eligible for a commission, over and above his Base Salary, if
he is a procuring cause of any general contracting work obtained by [Rave’s] for
29
Magee v Magee, 218 Mich App 158, 161; 553 NW2d 363 (1996) (“A party may not leave it to
this Court to search for authority to sustain or reject its position.”).
30
Czymbor’s Timber, Inc v Saginaw, 269 Mich App 551, 556; 711 NW2d 442 (2006) (quotation
marks and citation omitted).
31
See Miller, 433 Mich at, 337; Taylor, 279 Mich App at 314 n 5.
-9-
The Kroger Company. In the event Employee is a procuring cause of a general
contracting contract obtained by [Rave’s] for The Kroger Company, Company
shall pay the employee a commission equal to 1.5% of the gross revenues
received by [Rave’s] from The Kroger Company on that contract. The timing of
[Rave’s] payment to Employee of the commission, in whole or periodically, shall
be at [Rave’s] sole discretion but in no event shall Employee receive the balance
of the commission owed any later than thirty (30) days subsequent to the
Company’s receipt of final payment from The Kroger Company. Employee shall
forfeit any commission to which it was otherwise entitled if he is not employed
with [Rave’s] at the time [Rave’s] would be making the commission payment.
The trial court concluded that this final sentence was “fully enforceable . . . and that it
bars the Merrills’ claims . . . .” The trial court’s analysis does not, however, specifically address
the fact that on April 6, 2012, the parties entered into a different agreement pertaining to
Merrills’ compensation. This document stated that the Merrills would each receive their base
salary, insurance and automobile allowances, and:
ADDITIONAL COMPENSATION: 3% of the gross revenues (1.5% each to
Randy Merrill and Jim Merrill) from Kroger on all general contracting jobs with
the exception of store #622. When final payment is received from all Kroger
general contracting jobs including store #622, all money owed to Rave’s
Construction from the general contracting division will be paid first, including but
not limited to taxes and insurance liabilities. Whatever money is left will be
divided equally (25% each to Randy Merrill and Jim Merrill).
“[T]he freedom to contract . . . permits parties to enter into new contracts or modify their
existing agreements.”32 And if a “later contract covers the same subject matter as the earlier
contract and contains terms that are inconsistent with the terms of the earlier contract, the later
contract may supersede the earlier contract, unless it appears that this is not what the parties
intended.”33 The April 6, 2012 agreement explicitly refers to the Merrills’ compensation, and
even more specifically, commissions. Thus, it clearly covers the same subject matter as
contained in the January 1, 2010 agreement. And while some of its terms are consistent with the
January 1, 2010 agreement, many are not. Most significantly, the April 6, 2012 agreement
contains no language conditioning the Merrills’ entitlement to commissions on their employment
status. The April 6, 2012 agreement also contains a provision for the sharing of the division’s
monetary assets, a provision that did not exist in the January 1, 2010 agreement.
Nor does it appear that the parties intended for the Merrills’ entitlement to commissions
to remain conditioned on the Merrills’ continued employment. Rather than being titled as an
32
Quality Prods and Concepts Co, 469 Mich at 370-371. See also Grosse Pointe Park v Mich
Municipal Liability and Prop Pool, 473 Mich 188, 219-220; 702 NW2d 106 (2005)
(“[C]ontracting parties are always entitled mutually to modify the underlying contract . . . .”).
33
Archambo v Lawyers Title Ins Corp, 466 Mich 402, 414 n 16; 646 NW2d 170 (2002).
-10-
amendment to the prior agreement, as the parties had done with a document executed just a
month before, the parties titled the April 6, 2012 agreement as an “Employment Agreement.”
The agreement contains no references to the former agreement. By relying on the terms of the
January 1, 2010 agreement, the trial court essentially rewrote the April 6, 2012 agreement to
create a condition that the parties had omitted. “Clear, unambiguous, and definite contract
language must be enforced as written and courts may not write a different contract for the parties
. . . .”34 Under the April 6, 2012 agreement, the Merrills’ entitlement to commissions was not
conditioned on their continued employment with Rave’s, and the trial court erred by holding to
the contrary.35
However, the question remains: precisely what amount in commissions are the Merrills
entitled to receive? The April 6, 2012 agreement states that the Merrills are entitled to a
commission “from all Kroger general contracting jobs with the exception of store #622.” Thus,
it is clear that the Merrills are not entitled to a commission for the project at store 622. But the
contract does not define the term “Kroger general contracting job.” Given the circumstances
leading to the April 6, 2012 agreement, it may well be that the parties meant to refer only to the
three projects that were underway at the time. But the language could also be read as referring to
any and all general contracting jobs undertaken by Rave’s for Kroger, a definition that, for
obvious reasons, is preferred by the Merrills. The Merrills also now seek commissions on the
smaller, “minor capital” projects, all but one of which were completed prior to April 6, 2012.
The Merrills did not seek commissions on these projects until after signing the April 6, 2012
agreement, even though the prior agreement used similar language, “any general contracting
work obtained by [Rave’s] for” Kroger. “Where the contract language is unclear or susceptible
to multiple meanings, interpretation becomes a question of fact.”36 Because the issue is a factual
one that has yet to be addressed, we remand the matter to the trial court to determine what
commissions the Merrills are entitled to receive under the April 6, 2012 agreement.
The Merrills also contend that the trial court erred when it failed to award damages the
Merrills believe they are entitled to receive pursuant to the language of the April 6, 2012
agreement concerning the distribution of the division’s monetary assets. The trial court did not
34
Wausau Underwriters Ins Co v Ajax Paving Indus, Inc, 256 Mich App 646, 650; 671 NW2d
539 (2003).
35
The Merrills also argue that the trial court erred by finding no cause of action with respect to
Count IV of their counterclaim, which alleged that Rave’s breached an implied covenant of good
faith and fair dealing by terminating their employment in an effort to avoid paying the
commissions. While the issue is irrelevant in light of our conclusion that the Merrills’
entitlement to commissions was no longer conditioned upon their employment status, we note
that “this Court has refused to recognize a cause of action for breach of an implied covenant of
good faith and fair dealing in the employment context.” Barber v SMH (US), Inc, 202 Mich App
366, 373; 509 NW2d 791 (1993).
36
Port Huron Educ Ass’n, MEA/NEA v Port Huron Area Sch Dist, 452 Mich 309, 323; 550
NW2d 228 (1996).
-11-
separately address this claim. It would seem that the trial court concluded that any sums
potentially due under this language were also subsumed within the forfeiture clause of the
January 1, 2010 agreement. As discussed, that clause was of no effect after the parties signed the
April 6, 2012 agreement.37 However, the amount of damages due on this claim depends on a
determination of the amount of money left in the General Contracting Division, if any, after its
debts are paid. The parties submitted conflicting evidence on this point, and the conflict was not
resolved by the trial court. Thus, the trial court must determine what additional sums, if any, are
due to the Merrills under this provision of the April 6, 2012 agreement.
We find no error, however, in the trial court’s determination that the Merrills had not
proven their claim of conversion. “Common law conversion . . . consists of any distinct act of
domain wrongfully exerted over another’s personal property in denial of or inconsistent with the
rights therein.”38 The Merrills claimed that Rave’s committed the tort of conversion by retaining
certain equipment and furniture after their employment ended. The trial court concluded that the
Merrills failed to satisfy the elements of this claim because the Merrills had not sought the return
of this property from Rave’s. On appeal, the Merrills do not address the trial court’s reasoning.
Because the Merrills do not address the basis of the trial court’s decision, this Court need not
consider granting any relief with regard to this claim.39 Nor does the evidentiary record support
the Merrills’ claim of conversion. It is undisputed that the Merrills voluntarily brought these
items to the office space established for them when they began working for Rave’s. There is no
evidence that the Merrills were ever denied the return of these items. Rather, as Randy testified,
the Merrills never asked for the items to be returned, nor did they attempt to retrieve them.40 The
record contains no evidence of “any distinct act of domain wrongfully exerted [by Rave’s] over
[the Merrills’] personal property in denial of or inconsistent with the rights therein.”41
V. COUNTS IX AND X OF RAVE’S AMENDED COMPLAINT
Rave’s contends that the trial court erred when it dismissed its claims against Paletta and
Rothrock. These counts sought damages for violations of noncompetition provisions contained
within the employment agreements between Rave’s and these two individuals. We find no error
with respect to these counts.
37
Moreover, even if we were to find that the forfeiture language of the January 1, 2010
agreement survived the April 6, 2012 agreement, that language clearly applies only to the 1.5%
commissions that the Merrills were entitled to receive. It would have no effect whatsoever on
the portion of the April 6, 2012 agreement regarding a division of the sums remaining in the
General Contracting Division after its debts were paid.
38
Dep’t of Agriculture v Appletree Marketing, LLC, 485 Mich 1, 13-14; 779 NW2d 237 (2010)
(quotation omitted).
39
Derderian 263 Mich App at 381.
40
Randy testified that “[d]ue to the adversarial environment, we just left them in the office.”
41
Dep’t of Agriculture, 485 Mich at 13-14 (quotation omitted).
-12-
Paletta and Rothrock were hired by Rave’s in 2011 and worked for the General
Contracting Division. Rave’s laid off the two in 2012. Shortly after, the Merrills, Paletta, and
Rothrock began working for Paletta’s company, Tony & Sons, Inc. This company bid on and
was awarded several Kroger projects. In the trial court, Rave’s contended that it was entitled to
approximately $86,000 from each individual based on “the profit realized by the Merrills,”
Paletta, and Rothrock as a result of their work for Kroger.42 The trial court found no cause of
action with regard to these counts because even assuming Paletta and Rothrock breached the
covenants, Rave’s had not proven that the damages they claimed were the result of the breaches
alleged. The trial court concluded that the reason Rave’s was not awarded these projects “was
attributable solely to its dissociation of itself from the Merrills, and not to these defendants’
failure to continue working for Rave[’]s.”
“The party asserting a breach of contract has the burden of proving its damages with
reasonable certainty, and may recover only those damages that are the direct, natural, and
proximate result of the breach.”43 Rave’s argues that Paletta and Rothrock benefitted from their
alleged breaches of their employment agreements. Rave’s does not, however, explain how
Paletta’s and Rothrock’s alleged breaches caused it to lose these same profits. And more
specifically, Rave’s fails to contest the trial court’s finding that the reason Rave’s did not procure
the contracts awarded to Tony & Sons, Inc. was because without the Merrills, Kroger would not
hire Rave’s. Rave’s has not demonstrated that this conclusion was clearly erroneous.
Rave’s also argues that, at a minimum, it is entitled to nominal damages with respect to
this claim. Rave’s did not seek nominal damages at any stage of the trial court proceedings.
Because the issue was not raised in the trial court, we consider it waived.44
Affirmed in part, vacated in part, and remanded for further proceedings. We do not
retain jurisdiction.
/s/ Michael J. Talbot
/s/ Mark J. Cavanagh
/s/ Kirsten Frank Kelly
42
On appeal, Rave’s now argues for damages of approximately $29,000, the amount Paletta
earned from these projects.
43
Alan Custom Homes, Inc, 256 Mich App at 512.
44
See Walters v Nadell, 481 Mich 377, 387; 751 NW2d 431 (2008) (although appellate courts
may consider issues not raised in the trial court in order to prevent a miscarriage of justice,
generally, the failure to raise an issue in the trial court waives appellate review of the issue).